HomeMy WebLinkAboutWoodruff Construction - CO #6 - Cont. No. 1076 - 1.16.2024CHANGE ORDER NO. 6
Owner City of Waterloo Date: 1/5/2024
Project Gates Park Improvements Project
Owner's Contract No.
1076 Contractor: Woodruff Construction
Date of Contact Start 5/30/2023
Contract Amount: $ 9,362,172.81
You are directed to make the following changes in the Contract Documents. Description:
6-1 Masonry Cold Weather Protection (Splash Pad) $ 100.00 /UNITS x
300 UNITS $ 30,000.00
TOTAL ADDITIONS $ 30,000.00
Reason for Change Order
6-1 Stage 1 Area - The Splash Pad (fencing, building, equipment, paving, utilities, and all work required to have the splash pad and buildings
properly functioning) and associated parking lot completed and open to the public for use by May 24, 2024.
A unit shall be measured and paid for to an equivelant for the time and material.
Contractor shall submit material invoices, hours worked, and employee hourly rates.
This work shall not exceed $30,000 .
CONTRACT PRICE
CONTRACT TIME
To Substantial To Final
Completion Completion
Original: $ 9,362,172.81 Original Working Days 2401 2401
Previous C.O.s (ADD/DEDUCT) $ (988,451.60)
This C.O. (ADD/DEDUCT) $ 30,000.00 Revised Working Days: I -
Contract Price with all approved
Change Orders: $ 8,403,721.21
it is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPROVED: BY: L �/
l`%LLe/2-1.(/Z J LGN °sicxio'
)
1 / 16/2024
Owner (Authorized Signature) Date
ACCEPTED:
BY: /5/Z`�
Cont t u orized Signature) Dat
1-5-23
AECOM Date
AECOM
60672429 I 6
Project No. C.O. No.
From: Nate Schmidt <nate@seehasemasonry.com>
Sent: Thursday, November 16, 2023 1:13 PM
To: Will McAllister <willm@woodruff.build>
Subject: RE: External: Gates Park Improvements Splash Pad Building
Will,
See list below for our billable rates associated with winter/shelter cost.
1
tem Total
Wood Lath Bundle
$35.38
2"x4"x12' Construction Lumber - Ea. $9.46
Tie Wire Coil - Ea.
$16.47
Wind Clip - Ea.
$1.59
40'x100' Reinforced Plastic- Ea. $305.00
2 1/4" Wood Screws - Ea. $0.31
400 BTU LP Heater - Per Week $225.70
LP - Per Gal. $1.98
Hoses - Per Ft./Per Week $2.14
LP Delivery, Set Lip & Pick Up $134.20
Northeast Iowa Labor - Per Hr. $90.00
Cedar Rapids Labor - Per Hr. $101.20
Tate Seismal
Estimating & Freconstruction Team
Seehase Masonry, Inc.
(319)404-3998
1018 W. 1 ' St.
Sumner, IA 50674