December 29, 2023
CHANGE ORDER NO. 1
PROJECT:
OWNER:
CONTRACT:
CONTRACTOR:
Strand Associates, Inc
910 West Wingra Drive
Madison, WI 53715
(P) 608.251.4843
www.strand.com
F.Y. 2023 Wastewater Treatment Plant Final Clarifier No. 3 Rehabilitation
City of Waterloo, Iowa
1067
WRH, Inc.
Description of Change
la Remove Contractor -proposed motor replacement from
drive rebuild work in accordance with the Cost Proposal
Request (CPR) 001 dated October 20, 2023, and
Request for Change (RFC) 3 dated December 1, 2023.
lb Add replacement of Sluice Gate G-5-11-2 in accordance
with enclosed CPR 001 dated October 20, 2023, and
RFC 2A dated November 22, 2023.
TOTAL VALUE OF THIS CHANGE ORDER:
Contract Price Adjustment
Original Contract Price
Previous Change Order Adjustments
Adjustment in Contract Price this Change Order
Current Contract Price including this Change Order
Contract Substantial Completion Date Adjustment
(DEDUCT)
ADD
ADD
Original Contract Substantial Completion Date
Contract Substantial Completion Date Adjustments due to previous Change Orders
Contract Substantial Completion Date Adjustments due to this Change Order
Current Substantial Contract Completion Dates including all Change Orders
Contract Final Completion Date Adjustment
Original Contract Final Completion Date
Contract Final Completion Date Adjustments due to previous Change Orders
Contract Final Completion Date Adjustments due to this Change Order
Current Final Contract Completion Dates including all Change Orders
KPB:tll\S:\MAD\4400--4499\4463\016\Construction\Change Orders\CO 1\CO 1.docx
($7,553.47)
$44,159.31
$36,605.84
$842,000.00
$0.00
$36,605.84
$878,605.84
January 7, 2024
0 Days
173 Days
June 28, 2024
February 6, 2024
0 Days
171 Days
July 26, 2024
Arizona I Illinois I Indiana I Iowa I Kentucky I Ohio I Tennessee I Texas I Wisconsin
City of Waterloo—WRH, Inc.
Contract 1067, Change Order No. 1
Page 2
December 29, 2023
``�Q®.al')is document shall become a supplement to the Contract and all provisions will apply hereto.
%
RANDALL A. •
is WMRTZ
16137
�;.�� / INEER—Strand Associates, In Date
'������ IOWP\ APPROVEDD
/IIIEI!
Strand Associates, Inc.®
CONTRACTOR—WRH, Inc. Date
APPROVED
Quetz iiarE
sicaEo
/340 r.Lf
tL,ztA3
1/16/2024
OWNER —City of Waterloo, Iowa Date
KP13:III S: MAI) 4400- 4499 4463 016 CotstructiorChange Orders CO I CO I.docx
www.strand.com
Req u, U
-,=ncige (RFC)
Project: FY 23 Wastewater Treatment Plant Final Clairifier #3 Rehabilitation - Waterloo, la.
RFC No. 3
Reference:
RFQ #
DATE 12/01/23
Job No. 1419
Location Contract No.
A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this
authorization is requested so that the material may be purchased and to prevent any delay in field operations
Reason for Change
( ) Design Request
( X) Owner Request
( ) Other ---- Explain
1) Delete the motor replacement requirements
( ) Field Condition
( ) Suggested by Contractor
2) It is requested that the completion date be;
by 0 calendar days
( ) extended ( X ) decreased
3) Basis of Payment:
a) ( ) Firm price for performing this change along with attached supporting details
is ( ) increased / ( X ) decreased by $7,553.47
b) ( ) Unit Price $0.00
c)
d)
(
(
Change to be performed per unit prices in Contract $0.00
The time required to prepare and agree upon a detailed estimate prior to proceeding with
the change would unduly delay job progress. The following is an approximate estimate
to assist Owner in determining whether or not change should be made If notified to proceed,
a detailed estimate in the form agreed upon, with supporting details, will be submitted
after receipt of said notice.
Approximate Estimate is $0.00
( ) CHANGE WILL NOT BE MADE
PROCEED ON THE FOLLOWING BASIS
( ) Firm Price
( ) Estimate of Price
(x ) Unit Pr ce in Contract
Comments
( ) Time and Material
( ) Change in Completion Date
( ) No Change
Submitted.by. �.--.-.Appod__.by
Tim Williams Owner
WRH, Inc.
Date. 12/1/2023 Date:
L�J a V\\§
1
From:
Sant
Cc
S to ra cito
Tim,
Cory Sonner <csonner@vessco.com>
Tuesday November 28, 2023 6:48 PM
Tim Williams; kyle.kamerer@evoqua.com
Tim Hertel; Bud Maynard
RE° Evoqua Quote
Below is the breakout price of the carts you listed below:
Price
Part
Number/Description
Item
#
W2 ' 493`L
55
$2,030.00
50
MOTOR,GEAR;PARALLEL
L;1800
RPM
RPM
Reference
#: 303-70480-24
W3
21226
$523
47
51
BAS
RH,4.4
X
9
X
-DRIVE,
14.5",PNTD,STL
Reference
#:
503-81897-80
W3 T
ii
61i
3
5
$5,
000.
00
52
CF70
Gearmotor
W/
Drive
Base
'Best Reg
Cory Sonner I Sales Engineer
c: (515) 509-0470 I w: (515) 233-8599 I csonner@vessco.com
2740 Ford Street, Ames, IA. 50010
Vessco Inc. Celebrating Over 45 Years of Clean Water
VESSCO
„rye eatx1:5.
000
From: Tim Williams <twilliams@wendlerinc.com>
Sent: Tuesday, November 28, 2023 5:50 PM
To: kyle.kamerer@evoqua.com; Cory Sonner <csonner@vessco.com>
Cc: Tim Hertel <THertel@wendlerinc.com>, Bud Maynard <bmaynard@wendlerinc.com>
Subject: RE° Evoqua Quote
Kyle/Cory,
It has been a month since Bud inquired.
Have you come up with a credit for not replacing the Clarifier motor at the Waterloo WWTP?
Please advise.
Request for Change (RFC)
Project: FY 23 Wastewater Treatment Plant Final Clairifier #3 Rehabffltation - Waterbo9 la.
RFC No. 2-A DATE 11/22/23 Job No. 1419
Reference:
RFQ # Location Contract No.
A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this
authorization is requested so that the material may be purchased and to prevent any delay in field operations.
Reason for Change
( ) Design Request
( X ) Owner Request
( ) Other ---- Explain
( ) Field Condition
( ) Suggested by Contractor
1) Proposed replacement of the existing 24" x 24" Slide Gate, located in the adjacent open top aeration tank
structure, with a new 24" x 24" Stainless Steel Side Gate. Includes new gate, frame, stem, operator, and
mounting brackets Submittal lead time is approximately 10 weeks. Gate delivery is approximately 12 weeks
from submittal approval.
2) It is requested that the completion date be;
by 196.00 calendar days.
(X) extended ( ) decreased
3) Basis of Payment.
a) ( ) Firm price for performing this change along with attached supporting details
is ( X ) increased / ( ) decreased by $44,159.31
b)
c)
d)
(
(
(
Unit Price $0.00
Change to be performed per unit prices in Contract $0.00
The time required to prepare and agree upon a detailed estimate prior to proceeding with
the change would unduly delay job progress. The following is an approximate estimate
to assist Owner in determining whether or not change should be made If notified to proceed,
a detailed estimate in the form agreed upon, with supporting details, will be submitted
after receipt of said notice
Approximate Estimate is $0.00
( ) CHANGE WILL NOT BE MADE
PROCEED ON THE FOLLOWING BASIS
( ) Firm Price ( ) Time and Material
( ) Estimate of Price ( ) Change in Completion Date
(x ) Unit Pace in Contract ( ) No Change
Comments: r�
Submitted °�.` e' by-=ram Approved by
WRH, Inc.
Tim 17Clilliams Owner
Date. 11/22/2023 Date°
FY 23 Wastewater Treatment Plant Final Clairifier #3 Rehabilitation -
Waterloo, la.
RFC Calculation
Subcontractors
Material:
24" x 24" Stainless Steel Slide Gate
SS Mounting Hardware
Grout
Disposal of Materials
Labor:
General Labor
Skilled Labor
Truck Driver
Equipment Operator
Foreman
Superintendent
Project Manager
Equipment:
Field Truck
Med Duty Flatbed Truck
S kid loader
Scissor Lift
Excavator (under 100 HP)
Excavator (100 HP +)
Crane
Dozer (small)
Dozer (large)
S ales Tax on Material
Contractor's Fee (Self -performed)
Contractor's Fee (Sub -contracts)
Bond & Insurance
Total Proposed Change
RFC # 2-A
Quantity Unit
LS
1.00 EA
1.00 LS
1.00 LS
1.00 LS
30.0 Hr
0.0 Hr
4.0 Hr
60.0 Hr
30.0 Hr
6.0 Hr
2 0 Hr
3.0 Day
4.0 Hr.
30.0 Hr
30.0 Hr
Hr
Hr
30.0 Hr
Hr
Hr
Sub -total
1419
Unit Rate
$0.00
$12,810.59
$400.00
$200.00
$200.00
$79.50
$84.34
$87.35
$91.40
$95.40
$104.03
$182 75
$93.60
$61.20
$57.20
$41.60
$83.20
$135.20
$282.54
$98.80
$130.00
0.00%
15.00%
5.00%
11 /22/23
Line Total
$0.00
$0.00
$0.00
$0.00
$0.00
$12,810.59
$400.00
$200.00
$200.00
$0.00
$0.00
$2,385.00
$0.00
$349.40
$5,484.00
$2,862.00
$624.18
$365 50
$0.00
$280 80
$244.80
$1,716.00
$1,248.00
$0.00
$0.00
$8,476 20
$0.00
$0.00
$37,646 47
$0.00
$5,646.97
$0.00
$0.00
$43,293.44
$865 87
$44,159.31
P roposed replacement of the existing 24" x 24" Slide Gate, located in the adjacent open top aeration tank
structure, with a new 24" x 24" Stainless Steel Slide Gate. Includes new gate, frame, stem, operator, and
mounting brackets. Submittal lead time is approximately 10 weeks. Gate delivery is approximately 12 weeks
from submittal approval.
2of2
CD
LL.
1
Ct
CD
E
L
L
0)
CZ
G)
t/)
Ct
M
N
>-
LL
O
0
G)
0 .
vIma
Ca
.
•
as
a)
M
r
c
O
CO
U
RFC # 2 A
November 27, 2023
(6
T3
0
2
U)
1
U 0
CC E
o ~
c� ct
O O
a CD 0.
0_ c Q
Q Q
oto 06
N �
'> o >
a) .c a)
a) a) a)
O
mc
4—
O
0
2
l0ct
T
E
a)
J
a)
Weeks De
a)
rts
TNQ
c
a)
cn a)
C_ �+ -'
O al to
V1 -� 0 0
cn c c� L c
D — co as O
U cio tis _
a)- - a. a
- - a) co 0
a) a) c3 U
_c o — 0
U U as 7:3
(11Cn O =
Q)
SC - 1 O 0
a) a) a) O
O 0 0 0 0 0
O 0 0 0 0 0
r O r- N N (Ni
0 0
0 0
coo
N a)
Monday, June 10, 2024
ID
0
Task
Mode
Task Name
Duration
Start
Finish
Qtr 3, 2023
Jul
Aug
Sep
Qtr 4, 2023
Oct
Nov
Dec
Qtr 1, 2024
Jan
Feb
Mar
Qtr 2, 2024
Apr
Mav
Jun
Qtr 3, 2024
Jul
Aug
2
3
4
5
6
9
10
11
12
13
14
15
16
17
18
19
20
EP
61ieli11$11+11
41 41 41 A A.41.1AA
21
22
23
24
25
26
27
EP
EP
EP
EP
Contractual Items
Notice to Proceed
Substantial Completion
original Final Completion
Write Purchase Orders
Material Procurement
Presuure Relief Valves
Submittals
Product Delivery
Clarifier Submittals
product Delivery
Construction
Mobilization
Dewatering
remove drive/Motor
repairs to drive/reinstall
install new Unitube header,
recommision
pause dewatering
clean clarifier
concrete repairs/grout floor
blast and paint mechanism
cure time
final equipment install
end dewatering/start
equipment
SS Slide Gate
submittals
Fabrication of gate
installation
Punch out
129 days
1 day
107 days
1 day
11 days
110 days
30 days
80 days
30 days
80 days
179 days
2 days
177 days
3 days
30 days
9 days
16 days
1 day
14 days
14 days
5 days
6 days
145 days
65 days
60 days
15 days
5 days
Thu 8/10/23
Thu 8/10/23
Thu 8/10/23
Tue 2/6/24
Fri 8/11/23
Mon 8/28/23
Mon 8/28/23
Mon 10/9/23
Mon 8/28/23
Mon 10/9/23
Tue 9/12/23
Tue 9/12/23
Thu 9/14/23
Mon 11/6/23
Thu 11/9/23
Mon 1/29/24
Fri 2/9/24
Mon 3/25/24
Tue 3/26/24
Mon 4/15/24
Fri 5/3/24
Fri 5/10/24
Tue 2/6/24
Thu 8/10/23
Fri 1/5/24
Tue 2/6/24
Fri 8/25/23
Fri 1/26/24
Fri 10/6/23
Fri 1/26/24
Fri 10/6/23
Fri 1/26/24
Fri 5/17/24
Wed 9/13/23
Fri 5/17/24
Wed 11/8/23
Wed 12/20/23
Thu 2/8/24
Fri 3/1/24
Mon 3/25/24
Fri 4/12/24
Thu 5/2/24
Thu 5/9/24
Fri 5/17/24
Mon 12/18/23 Fri 7/5/24
Mon 12/18/23 Fri 3/15/24
Mon 3/18/24 Fri 6/7/24
Mon 6/10/24 Fri 6/28/24
Mon 7/1/24 Fri 7/5/24
spp 1/26
Project: Schedule with SS slide
Date: Wed 12/20/23
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
[ Manual Task
Duration -only
Manual Summary Rollup
Manual Summary
Start -only
Finish -only
External Tasks
External Milestone
7
Deadline
Progress
Manual Progress
Page 1