HomeMy WebLinkAboutPeters Construction - CO #1 - Hangar No. 4 Mold Remediation - 4.15.2024CHANGE ORDER NO. 1
Owner: Waterloo Regional Airport, City of Waterloo, Iowa
Project: Hangar No. 4 (Mold Remediation)
Owner's Contract No. FAA AIP Project No. 3-19-0094-048 (CARES)
Contractor: Peters Construction Corporation
Date of Contract Start: February 5, 2024
Date; March 20, 2024
You are directed to make the following changes in he Contract Documents. Description:
ITEM
NO.
DESCRIPTION
UNIT
UNIT BID
PRICE
CHANGE ORDER
NO. 1
CHANGE ORDER
AMOUNT
6
DRYWALL REPLACEMENT
SF
$ 15.58
-253.0
$
(3,941.74)
8
DRYWALL REMOVAL ONLY
SF
$ 12.11
1,489.0
$ 18,031.79
TOTALS
$ 14,090.05
Reason for Change Order:
Item 6 — Quantity adjusted based on field measurements.
Item 8 — Quantity added based on field conditions requiring additional drywall removal.
ALO FAA AIP 3-19-0094-048
CO-1 Project No — 60675091
1
CONTRACT PRICE
CONTRACT TIMES (Calendar Days)
To substantial To final
completion completion
Original: $ 98,942,10 Original:
Previous C,O.s (DEDUCT):$ 0.00 Previous C.O.s (ADD):
This C.O. (ADD): $ 14,090.05 This C.O. (ADD):
Contract Price with all REVISED:
approved Change Orders: $ 113,032.15
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By: ----
Engineer (Authorized Signature)
APPROVED:
By: Quertarz rrE
Owner (Authorized Signature)
ACCEPTED:
By: y ,•.,J{`1� L 1
Contractor (Authorized Signature)
Di60ALLV
SIGNED
March 21, 2024
Date
4/15/2024
Date
Date
ALO FAA AIP 3-19-0094-048
CO-1 Project No -- 60675091