HomeMy WebLinkAboutPeterson Contractors CO #15 - Waterloo-Shaulis Rd, Cont. No. 1020 - 5.6.2024CITY OF WATERLOO, IOWA CHANGE ORDER NO. 15 RM-8155(772) — 9D-07 PROJECT: Shaulis Road Reconstruction Project CONTRACT NO. 1020 Date Prepared: 04-13-2024 AMOUNT: $61,254.50 Increase TO: Peterson Contractors Inc , Contractor You are hereby ordered to make the following changes to the plans and specifications or perform the following extra work on your contract dated 4-29-2021. A. Description of change to be made or extra work to be done: (1) Cold Weather (2) New Bid Item 0164 Winter 2023 Cold Weather Protection 6-12-23 (E&F Paving) B. Reason for ordering change or extra work: (1) Cold Weather protection of Concrete outside scoop of work. C. Settlement for cost of work to be made as follows: 1. $61,254.50 Participating Total Net Increase $61,254.50 CITY OF WATERLOO BY: 6ED 5/6/2024 Peterson Contractors, Inc. Mayor Date ATTEST: Kelley Fe[chlTe SIGNEDr„ . 5/6/2024 City Clerk Date CON TRACTOR Digitally signed by Chris D. Fleshner Chris D. Fleshner DN: C=US, E=cfleshner@pcius.com, CN=Chris D. Fleshner BY: Date: 2024.04.15 11:19:48-05'00' Date PRINTED NAME: Chris D. Fleshner TITLE: Project Manager APPROVED: SIGNED 5/6/2024 City Engineer Date This document was created by an application that isn't licensed to use novaPDF. Purchase a license to generate PDF files without this notice. HRGreen HR Green, Inc. 8710 Earhart Lane S.W. Cedar Rapids, IA 52404 (319) 841-4000 FAX (319)841-4012 CHANGE ORDER Distribution: Owner X Engineer X Contractor X Field Other PROJECT: RM-8155(772)-9D-07 Waterloo, IA Shaulis Road Reconstruction — Hess Road to US-218- Change Order No. 15 Date April 13, 2024 To Contractor: Peterson Contractors, Inc. 104 Black Hawk Street Reinbeck, IA 50669 Project No. 190428.04 Original Contract Date May 17, 2021 This Change Order includes the following: (1) The additional cost for Cold Weather Protection East Shaulis Rd. and Hess Road (Roundabout) at $61,254.50 SY . (New Bid line Item 0164) (2) Changes were requested on 4-12-24. The original Contract Sum was $8,842,011.38 Net change by previously authorized Change Orders $14,950.00 The Contract Sum prior to this Change Order was $8, 877,726.38 The Contract Sum will be increased by this Change Order in the amount of $61,254.50 The new Contract Sum including this Change order will be $8,938,980.88 The Contract Time will be (increased) by 0 The date of Substantial Completion as of the date of this Change Order therefore is September 21, 2021 The date of Final Completion as of the date of this Change Order therefore is April 13, 2024 NOT VALID UNTIL SIGNED BY THE CONTRACTOR, OWNER'S REPRESENTATIVE, if applicable, AND OWNER Contractor Peterson Contractors, Inc. Owner's Representative HR Green, Inc. Owner City By By Christopher Mon doff, /W�atte�rlloo,/IIA/ [ By lY ue to j l (fail L I fD By Date: Date: 4-13-2024 Date: 5/6/2024 Date: This document was created by an application that isn't licensed to use novaPDF. Purchase a license to generate PDF files without this notice. 1-F93 HRGreen HR Green, Inc. Contract Modification 4/13/2024 11:17 AM FieldManager 5.3c Contract: _190428, Shaulis Road Reconstruction- Hess Road to US-218 Cont. Mod. Number 15 Revision Number Cont. Mod. Date 4/13/2024 Net Change $61,254.50 Awarded Contract Amount $8,639,212.17 Route Entered By Chris Wion Contract Location City of Waterloo, Iowa Short Description 2023 Winter Cold Weather Protection Description of Changes Cold Weather protection of Concrete outside scoop of work. New Items Project: 190428, FY 2021 Shaulis Road Reconstruction Category: 1, Roadway And Bridge Item Description Item Code Prop.Ln. ItemType Unit Proposed Qty. Unit Price Dollar Value ('SQUARE YARDS' ITEM) 2023 Winter 2599-9999018 1640 SUPPLEMENT SY 9,238.990 Cold Weather Protection Reason: Cold Weather Protection outside of project scoup 6.63000 $61,254.50 Subtotal for Category 1: Subtotal for Project 190428: $61,254.50 $61,254.50 When authorized, the contractor agrees to perform the work outlined above in accordance with provisions of the contract documents. PETERSON CONTRACTORS INC. Recommended by Project Engineer Signature Date Signature Date Reviewed by Iowa DOT (if required) City of Waterloo Signature Date Signature Date FEDERAL PARTICIPATION - ACTION BY F.H.W.A. Approved Not Eligible See Letter Dated (Signature) (Date) Contract: _190428 Cont. Mod.: 15 Page 1 of 1 1:36% PETERSON CONTRACTORS, INC. t EXTRA WORK AUTHORIZATION N E I I B E C K IOWA PO Box A Phone: 319-345-2713 Reinbeck, Iowa 50669 Fax: 319-345-2991 O�¢Coj.., ..; AMhas neap:: < ..noarc� www.petersoncontractors.com Project Name: Date: PCI Job # Extra Work Autorization # Shaulis Road Reconstruction J9215 04/12/24 Remarks or Description of Extra Work: Below is the Cold Weather Protection cost for the work that was completed late in 2023. Please see the attached invoice for the from E&F for this work. Again I have cut the Mark-up cost to 2% to cover the bond cost that PCI will have to pay on the project only. Item # Description Quantity Units Base Unit Rate % Mark Up % Discount Adjusted Unit Rate Total Amount 1 Cold Weather Protection 9,238.99 SY $6.50 2.00% 0.00% $6.63 $61,254.50 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 0.00% 0.00% $0.00 $0.00 Total Amount: The work covered by this authorization shall be performed in accordance with the same terms and conditions as included in the original contract. $61,254.50 Work Authorized and Changes Approved by: Prime Contractor or Owner: Peterson Contractors, Inc. By: By: Chris Fleshner Title: Date: Date: 4/12/2024 'An Equal Opportunity Employer' Project: 235102 ! Shaulis Rd Waterloo REQUEST FOR PAYMENT DETAIL Invoice: 17735 Application #: 235102-00002 Period Ending Date: 11,30/2023 CONTRACTED PREVIOUS COMPLETED CURRENT TOTAL TO DATE Item ID Description Sid Quantity UOM Unit Price Amount Quantity Amount Quantity Amount Quantity Amount % Comp Retainage 35 10" PCC 36 10" PCC (Colored Truck Apron) 37 6" Colored Median (Splitter) 38 8" Median Sidewalk Crossing 39 Pavement Samples 8 Testing 77 Mobilization 80 Concrete Washout CO1 Cold Weather Protection 15,000.00 SY 416.70 SY 1,719.00 SY 190.40 SY 1.00 LS 1.00 LS 1.00 LS 9.238.99 6.50 60,053.43 0.00 0.00 9,238.99 60,053.44 Totals Detail Page 2 of 2 Pages