HomeMy WebLinkAboutWoodruff Construction - Contract No. 1076, CO #7 - 6.17.2024Owner
Project
Owner's Contract No.
Date of Contact Start
City of Waterloo
Gates Park Improvements Project
1076
5/30/2023
CHANGE ORDER NO. 7
Date: 6/13/2024
Contractor: Woodruff Construction
Contract Amount: $ 9,362,172.81
You are directed to make the following changes in the Contract Documents. Description.
45 PCC Pavement, Class C, 51N. Sidewalk
73 Construction Entrance Maintenance
94 AISC Steel Fabricator
97 Epoxy Flooring
97 Steel Countertop Support Detail
100 Metal Arch Signs and Columns for Gateways
100 Metal Arch Signs and Columns for Gateways
101 Monument Entry Signs
102 Splash Pad Wall Slgnage
103 Donor Recognition Sign
105 Amphitheater Wood Roof Finish
107 Monument Entry 4th & tester
108 Playground Fence
109 Playground 4' X 8' Double Gate - Wireworks
111 Concrete Curb Around Play Surface
114 Playground and Spray Park Railings
115 Basketball Goals
116 Basketball Court Coating
129 Amphitheater Restroom Building MFPT
130 Splash Pad Restroom Building MEPT
142 Updated Security Cameras
143 Chemical Controller and Equipment
143 Added Activation Bollard and Wiring
147 Dual Tot Slide - Children's Slide
6-1 Masonry Cold Weather Protection (Splash Pad)
7-1 Water Service Winterization
7-2 4'H Black Vinyl Chain Link Fence
7-3 Water Service Adjust for Flow Through
7-4 Storm Sewer Overflow
7-5 Winterization (4" Valve/Check Valve) 1/2 Freight
7.6 Bypass of Surge Tank (Filtration System) 1/2 Freight
7-7 Splash Pad Retaining Wail Changes
7-8 Weir Re-Plumbing/Reinstall Play Eq labor Only
7-9 Surge Tank Adjust for Flow Through
7-10 Splash Pad Concrete Modifications
TOTAI. ADDITIONS
43.15 /5Y
23.97 /SY
(35,103.00) /LS
1,463.00 /LS
2,884.20 /LS
(5,605.00) /LS
(379.20) /Ls
(454.00)/LS
(1,987.50) /LS
636.50 /LS
(225,826.82) AS
(7,111.00) /LS
7.60 /LF
(914.00) /EA
37.16 /LF
292.80 /LF
(6,466.24) /LS
2.18 /SF
803.00 /LS
2,805.00 /LS
4,240.00 /LS
(9,836.76) /LS
4,235.00 /LS
(11,460.00)/LS
100.00 /UNITS
11,000.00 /LS
55.00 /LF
100.00 /UNITS
100.00 /UNITS
100.00 /UNITS
100.00 /UNITS
100.00 /UNITS
100.00 /UNITS
100.00 /UNITS
100.00 /UNITS
25 SY
30 5Y
1 LS
1 LS
1 LS
1 LS
1 LS
1LS
1 LS
1 LS
1 LS
1 LS
1045.000 LF
2.000 EA
206 LF
-28.000 LF
1LS
14250 SF
1 LS
1L5
1 LS
1 LS
1 IS
1 LS
-167.21 UNITS
1 LS
104.000 LF
111.023 UNITS
20.657 UNITS
12.081 UNITS
35.647 UNITS
21.810 UNITS
1.262 UNITS
17.398 UNITS
74.638 UNITS
1,078.75
719.10
(35,103.00)
1,463.00
2,884.20
(5,605.00)
(379.20)
(454.00)
(1,987.50)
636.50
(225,826.82)
(7,111.00)
7,942.00
(1,828.00)
7,654.96
(8,198.40)
(6,466.24)
31,065.00
803.00
2,805.00
4,240.00
(9,836.76)
4,235.00
(11,460.00)
(16,720.66)
11,000.00
5,720.00
11,102.30
2,065.68
1,208.05
3,564.66
7,181.00
126.15
1,739.78
7,463.77
(214,278.68)
Rea
0
nge urger
45
Quantity added for additional 5" sidewalk around upper splash pad.
73
Quantity added to maintain installed construction entrance.
94
Reduction in unit price to remove requirement far AISC certified steel fabricator. Contractor able to use Grosse Steel.
97
Increase In unit price to add In epoxy flooring In chemical room closets.
97
Increase in unit price for added angles to the back of the frames, diagonal brace angles under each end, and expoxy anchors for additional support to countertops.
100
Reduction in unit price to eliminate all masonry from bid item. Reduce SPRAY and PLAY lettering to 3/8" thick material. Change Steel columns tol0"and
take to grade to match up with concrete foundation. Increase in amount of exposed steel that needs painted and paint exposed form lined concrete.
100
Decrease in unit price to eliminate the fence posts embedded In the concrete by adding mounting brackets to the metal signage posts, pier size was
able to be reduced.
101
Reduction in unit price to eliminate masonry from the item. Reduced lettering thickness to 3/8" material. Concrete -scope change to include C1P concrete footings,
walls, and cap. Walls to Include smooth finish and chamfered edges.
102
Reduction In unit price to reduce lettering thickness t03/8" material on Splash Pad Building. Also includes lettering on Amphitheater masonry wall.
103
Reduction in unit cost to eliminate masonry from item. Reduced lettering thickness to 3/8" material. Concrete scope change to Include CIP concrete footings,
walls, and cap. Walls to include smooth finish and chamfered edges.
105
Remove woad -looking soffit In its entirety on the job.
107
Design change per attached drawing. (PC018)
108
Increase in unit price to change all standard 2" vinyl coated fencing to 1-1/4" mesh polyolefin coated chain link fencing.
109
Decrease In unit price to change gates to 1-1/4" mesh polyelefin coated chain link fencing and utilizing the 10" steel columns of the gateway posts.
111
Quantity added for concrete playground curb.
114
Quantity removed from Splash Pad Retaining Wall.
115
Removing bid item since Woodruff is donating back cost for basketball goals.
116
Increase to unit price for change product for basketball court coating from a concrete stain to a Streetbond product. See attached product data.
129
Increase to unit price to add in bath fans to each restroom. Electrical only.
130
Increase to unit price to add in bath fans to each restroorn. Electric al only.
142
Increase In unit price to upgraded securitycameras to mast current AXIS model.
143
Decrease in unit price since chemical controller equipment was originaly provided by Select DBC through contract. Leisure Services will now provide the
material and equipment through their chemical provider.
143
Increase in unit price for added activation bollard to upper splash pad to activate upper splash features. Bollard to be provided by Leisure Services. Pricing
includes Installation of the bollard and mount as well es conduit and wiring from the splash pad controller.
147
Quantity deduct for slide return.
6-1
Reduction in quantity to match finalized winterization casts.
7-1
New item includes installation of48" 11DPE manhole, 6"x1"Tee, 1" shut off valve, 1" copper line, and 1" double check valve inside the manhole.
This Item is to allow the Splash Pad building water service line to drain empty prior to Winter Shutdown to prevent freezing.
7-2
4' H black vinyl chain link fence to be Installed around upper splash bad in lieu of railing.
7 3 A unit shall be measured and paid for to an equivelant for the time and material.
thru Contractor shall submit material invoices, hours worked, and employee hourly rates.
7 10 Work under these items shall not exceed the listed dollar amount for each item.
See attached revised drawings.
CONTRACT PRICE
Original:
Previous C.O.s {ADD/DEDUCT)
This C.O. (ADD/DEDUCT}
Contract Price with all approved
Change Orders:
9,362,172.81 Original Working Days
(958,451.61X
(714,278.68) Revised Working Days:
$ 8,189,442.53
CONTRACT TIME
To Substantial
Completion
2401
To final
Completion
2401
It Is agreed by the Contractor that this Change order includes any and all casts associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHAH. APPLY HERETO.
APPROVE rdth
BY: r�
Owner (Authorized Si
ACCEPTED:
BY:
6/17/2024
Date
Date )/��
6/13/24
AECOM s- Date
AECOM
60672429
Project No.
C.O. No.