HomeMy WebLinkAboutPeters Construction - CO #6 WCC Restroom Renovation 8.5.24TAIA);' Document G701° — 2017
Change Order
PROJECT: (Name and address)
5 Sullivan Brothers Convention Center -
Restroom Renovation
233 W 4th Street
Waterloo, IA 50701
OWNER: (Name and address)
City of Waterloo
715 Mulberry Street
Waterloo, IA 50703
CONTRACT INFORMATION:
Contract For: General Construction
Date:
ARCHITECT: (Name and address)
l&S Group, Inc. (ISG)
314 East 4th Street
Waterloo, IA 50703
CHANGE ORDER INFORMATION:
Change Order Number: 006
Date: July 8, 2024
CONTRACTOR: (Name and address)
Peters Construction Corporation
901 Black Hawk Road
Waterloo, IA 50701
THE CONTRACT IS CHANGED AS FOLLOWS:
(Insert a detailed description of the clrange and, if applicable, attach or reference specific exhibits. Also include agreed upon adjustments
attributable to executed Construction Change Directives)
CR 11: Refrigerator for the family dressing room ADD $1,295.00
CR 12: Isolation ball valves on water lines ADD $3,030.00
REDUCE REFRIGERATOR ALLOWANCE FROM S1,200 TO ZERO.
REDUCE SPECIFIED GENERAL ALLOWANCE FROM S18,399.34 TO S15,274.34.
CONTRACT SUM REMAINS UNCHANGED.
The original Contract Sum was
The net change by previously authorized Change Orders
The Contract Sum prior to this Change Order was
The Contract Sum will be increased by this Change Order in the amount of
The new Contract Sum including this Change Order will be
The Contract Time will be increased by Zero (0) days.
The new date of Substantial Completiffl will be
995,697.00
$ 6,038.00
$ 1,001,735.00
0.00
$ 1,001,735.00
NOTE: This Change Order does not include adjustments to the Contract Sum or Guaranteed Maximum Price, or the Contract
Time, that have been authorized by Construction Change Directive until the cost and time have been agreed upon by both the
Owner and Contractor, in which case a Change Order is executed to supersede the Construction Change Directive.
NOT VALID UNTIL SIGNED SY THE ARCHITECT, CONTRACTOR AND OWNER,
1&S Group, Inc. (ISO)
ARCHITECT (Firm name)
SIGNATURE
Nathan Compton, Proj
Manager
PRINTED NAME AND TI11 E
July 8, 2024
DATE !
Bradley Best, President
ity of Waterloo
O E/R/ (Finn �naame)
UtG U L m�irauv
SIGNED
t'VItIn Hart, Mayor
PRINTED NAME AND TITLE p o 8q[LI AND TITLE
DATE
DATE
A!A Document G701
Architects,' "AIA," th
CT on 07/10/2024 u
accordance with Ih
User Notes:
2017. Copyright ®1979, 1967, 2000 , 2001 and 2017. All tights reserved. 'The American Institute of Architects,' American Institute of
AIA Logo, and `AIA Contract Documents" are trademarks of The American Institute of Architects. This document was produced at 10:55:36
er Order No.3104238596 which expires on 12/11/2024, is not for resale, is licensed for one-time use only, end may only be used in
IA Contract Documents° Terms of Service. To report copyright vlotations, e-mail docinfo@alacontracts.com.
(3139ADA4C)