July 23, 2024
CHANGE ORDER NO. 3
PROJECT:
OWNER:
CONTRACT:
CONTRACTOR:
Strand Associates, Inc.®
910 West Wingra Drive
Madison, WI 53715
(P) 608.251.4843
www.stra nd.com
F.Y. 2023 Wastewater Treatment Plant Final Clarifier No. 3 Rehabilitation
City of Waterloo, Iowa
1067
WRH, Inc.
Description of Change
3a Remove 1 1/2 inches of unitube header and cap the ADD
open end with a 1/4-inch-thick plate. These changes are
in accordance with the Cost Proposal
Request (CPR) 002 dated June 28, 2024, and Request
for Change (RFC) 8 dated July 3, 2024.
3b Provide a 1/4-inch-thick steel plate to cover the pitting ADD
and holes in the influent well (on both sides of pitting
and holes, welded all around). These changes are in
accordance with CPR 002 dated June 28, 2024, and
RFC 9R dated July 10, 2024.
3c Provide eight new floor pressure relief valves equally ADD
spaced at a radius of 32 feet 0 inches from the center of
the clarifier. These changes are in accordance with
CPR 003 dated July 10, 2024 and RFC 10 dated
July 15, 2024.
3d Extend Contract Substantial Completion and ADD
Final Completion dates by 14 calendar days in
accordance with RFC 9R dated July 10, 2024 and
RFC 10 dated July 15, 2024.
TOTAL VALUE OF THIS CHANGE ORDER:
Contract Price Adjustment
Original Contract Price
Previous Change Order Adjustments
Adjustment in Contract Price this Change Order
Current Contract Price including this Change Order
SKH:II\S:\MAD\4400--4499\4463\016\Construction \Change Orders\CO 3\CO 3.docx
ADD
$1,244.19
$7,375.12
$22,562.57
$0.00
$31,181.88
$842,000.00
$144,698.42
$31,181.88
$1,017,880.30
Arizona j Illinois I Indiana I Iowa I Kentucky I Ohio I Tennessee I Texas j Wisconsin
Strand Associates, Inc.'
City of Waterloo—WRH, Inc.
Contract 1067, Change Order No. 3
Page 2
July 23, 2024
Contract Substantial Completion Date Adjustment
Original Contract Substantial Completion Date
Contract Substantial Completion Date Adjustments due to previous Change Orders
Contract Substantial Completion Date Adjustments due to this Change Order
Current Substantial Contract Completion Dates including all Change Orders
Contract Final Completion Date Adjustment
Original Contract Final Completion Date
Contract Final Completion Date Adjustments due to previous Change Orders
Contract Final Completion Date Adjustments due to this Change Order
Current Final Contract Completion Dates including all Change Orders
January 7, 2024
208 Days
14 Days
August 16, 2024
February 6, 2024
206 Days
14 Days
September 13, 2024
```Q.�aS •••"'"'•. tiq jt. % document shall become a supplement to the Contract and all provisions will apply hereto.
c,•' RANDALL -i -=; r /4Ist,liED
=ZBw s WIRTZ'-,i. 72i Z•0 1
16137
w �i.
't• rZ. , SULTANT— nd Associates, Inc.® Date
'''* ,�legA,e� PPROV 1 ./.7
nit
iNTRACTI'—WR
APPROVED
atertun r�
CITY —City of Waterloo, Iowa
siV
SKI1II\SaMAD\4400--4499\4463\Ol6\Construction\Change Orders\CO 3\CO 3.docx
7
Date
8/5/2024
Date
www.strand.com
Request for Change (RFC)
Project: FY 23 Watewater Treatment Plant Final Clarifier #3 Rehabilitation - Waterloo, la.
RFC No. 8 DATE 07/03/24 Job No. 1419
Reference: Cost Proposal Request
CPR # 002-01 Location Clarifier #3 Contract No. 1067
A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this
authorization is requested so that the material may be purchased and to prevent any delay in field operations.
1)
Reason for Change:
( ) Design Request
(X ) Owner Request
( ) Other ---- Explain
( ) Field Condition
( ) Suggested by Contractor
The new Unitube header is rubbing the exterior wall at one location while having several inches of seperation on
the other. This RFC proposes to cut 1.5" off the end of the new UNITUBE and weld on
2) It is requested that the completion date be;
by 1 calendar days.
( X ) extended
3) Basis of Payment:
a) ( x ) Firm price for performing this change along with attached supporting details
is ( x ) increased / ( ) decreased by
b)
c)
d)
(
(
(
) Unit Price
( ) decreased
$1,244.19
$0.00
) Change to be performed per unit prices in Contract $0.00
) The time required to prepare and agree upon a detailed estimate prior to proceeding with
the change would unduly delay job progress. The following is an approximate estimate
to assist Owner in determining whether or not change should be made. If notified to proceed,
a detailed estimate in the form agreed upon, with supporting details, will be submitted
after receipt of said notice.
Approximate Estimate is $0.00
( ) CHANGE WILL NOT BE MADE
PROCEED ON THE FOLLOWING BASIS:
( ) Firm Price
( ) Estimate of Price
(x ) Unit Price in Conte
Comments:
( ) Time and Material
( ) Change in Completion Date
( ) No Change
Submitted by: //,fie _ Approved by
tie U z
DIGITALLY
SIGNED
Tim Williams Owner
WRH, Inc.
Date: 7/3/2024
Date:
FY 23 Watewater Treatment Plant Final Clarifier #3 Rehabilitation - Waterloo, lla.
RFC Calculation
Subcontractors
Material:
Additional Materials
Welding Materials
Labor:
General Labor
Skilled Labor
Safety Professional
Foreman
Superintendent
Project Manager
Equipment:
Field Truck
Skid loader
Scissor Lift
Excavator (under 100 HP)
Excavator (100 HP +)
Welder
Dozer (small)
Dozer (large)
Sales Tax on Material
Contractor's Fee (Self -performed)
Contractor's Fee (Sub -contracts)
Bond & Insurance
Total Proposed Change
RFC # 8
Quantity Unit
LS
Sub -total
1.00
1.00
30
3.0
1.0
1.0
20
LS
LS
Hr
Hr
Hr
Hr
Hr
Hr
Day
Hr
Hr
Hr
Hr
Hr
Hr
Hr
Unit Rate
$0.00
$75.00
$25.00
$79.50
$96 08
$111.09
$105.09
$111.09
$195.17
$93.60
$57.20
$41.60
$83.20
$135.20
$26.93
$98.80
$130.00
0.00%
15.00%
5.00%
2 00%
07/03/24
Line Total
$0.00
$0.00
$0.00
$75.00
$25.00
$0.00
$0.00
$0.00
$238.50
$0.00
$0.00
$315 27
$111.09
$195.17
$46.80
$0.00
$0.00
$0.00
$0.00
$53.86
$0.00
$0.00
$1,060.69
$0.00
$159.10
'$0.00
$0.00
$1,219.79
$24.40
$1,244.19
Request for Change (RFC)
Project: FY 23 Watewater Treatment Plant Final Clarifier #3 Rehabilitation - Waterloo, la.
RFC No. 9R
DATE 07/10/24 Job No. 1419
Reference: Cost Proposal Request
CPR # 002-02 Location Clarifier #3 Contract No. 1067
A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this
authorization is requested so that the material may be purchased and to prevent any delay in field operations.
1)
Reason for Change:
( ) Design Request
(X ) Owner Request
( ) Other ---- Explain
( ) Field Condition
( ) Suggested by Contractor
The paint preparation process exposed sections of rust holes in the Influent Well. This RFC includes providing
fabricated 1/4" plate steel as needed to cover both faces of the sections of rust holes. The plates will be welded
into place with a continual weld and painted to match the balance of the clarifier.
2) It is requested that the completion date be;
by 7 calendar days.
( X ) extended
( ) decreased
3) Basis of Payment:
a) ( x ) Firm price for performing this change along with attached supporting details
is ( x ) increased / ( ) decreased by $7,375.12
b) ( ) Unit Price
c)
d)
(
$0.00
) Change to be performed per unit prices in Contract $0.00
()
The time required to prepare and agree upon a detailed estimate prior to proceeding with
the change would unduly delay job progress. The following is an approximate estimate
to assist Owner in determining whether or not change should be made. If notified to proceed,
a detailed estimate in the form agreed upon, with supporting details, will be submitted
after receipt of said notice.
Approximate Estimate is
( ) CHANGE WILL NOT BE MADE
PROCEED ON THE FOLLOWING BASIS:
( ) Firm Price
( ) Estimate of Price
(x ) Unit Price in Contract
Comments:
$0.00
( ) Time and Material
( ) Change in Completion Date
( ) No Change
Submitted by: f� Approved by
Tim iliams Owner
WRH, Inc.
TREF
Date: 7/10/2024
Date:
8/5/2024
SIGNED
FY 23 Watewater Treatment Plan Final Clarifier #3 Rehabilitation - Waterloo, Ia.
RFC Calculation
Subcontractors
Touch -Up Paint
Material:
Additional Materials - 1/4" Plate Steel
Welding Materials
Labor:
General Labor
S killed Labor
Safety Professional
Foreman
S uperintendent
Project Manager
Equipment
Field Truck
S kid loader
Scissor Lift
Excavator (under 100 HP)
Excavator (100 HP +)
Welder
Dozer (small)
Dozer (large)
Sales Tax on Material
Contractor's Fee (Self performed)
Contractor's Fee (Sub -contracts)
Bond & Insurance
Total Proposed Change
RFC # 9R
Quantity
1.00
Sub -total
1.00
1.00
18.0
18.0
20
20
20
18.0
18.0
Unit
LS
LS
LS
Hr
Hr
Hr
Hr
Hr
Hr
Day
Hr
Hr
Hr
Hr
Hr
Hr
Hr
Unit Rate
$500.00
$350.00
$125.00
$79.50
$96.08
$111.09
$105.09
$111.09
$195.17
$93.60
$57.20
$41.60
$83 20
$135 20
$26.93
$98.80
$130.00
o.00%
15.00%
5.00%
2 00%
07/10/24
Line Total
$500.00
$0.00
$0.00
$350.00
$125.00
$0.00
$0.00
$0.00
$1,431.00
$0.00
$0.00
$1,891.62
$222 18
$390.34
$187 20
$0.00
$748.80
$0.00
$0.00
$484.74
$0.00
$0.00
$6,330 88
$0.00
$874 63
$25.00
$0.00
$7,230.51
$144.61
$7,375.12
Request for Change (RFC)
Project: FY 23 Watewater Treatment Plant Final Clarifier #3 Rehabilitation - Waterloo, la.
RFC No.
10
Reference: Cost Proposal Request
CPR # 3
DATE 07/15/24
Location Clarifier #3
Job No. 1419
Contract No. 1067
A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this
authorization is requested so that the material may be purchased and to prevent any delay in field operations.
1)
Reason for Change:
( ) Design Request
(X ) Owner Request
( ) Other ---- Explain
( ) Field Condition
( ) Suggested by Contractor
During construction, it was discovered that the clarifier's floor needs additional means to relieve ground water
pressure when the tank is empty. This RFC proposes to add an additonal Eight (8) Pressure releif valves within
the floor.
2) It is requested that the completion date be;
by 7 calendar days.
( X ) extended
( ) decreased
3) Basis of Payment:
a) ( x ) Firm price for performing this change along with attached supporting details
is ( x ) increased / ( ) decreased by $22,562.57
b) ( ) Unit Price
c)
d)
(
$0.00
) Change to be performed per unit prices in Contract $0.00
( )
The time required to prepare and agree upon a detailed estimate prior to proceeding with
the change would unduly delay job progress. The following is an approximate estimate
to assist Owner in determining whether or not change should be made. If notified to proceed,
a detailed estimate in the form agreed upon, with supporting details, will be submitted
after receipt of said notice.
Approximate Estimate is $0.00
( ) CHANGE WILL NOT BE MADE
PROCEED ON THE FOLLOWING BASIS:
( ) Firm Price
( ) Estimate of Price
(x ) Unit Price in Contract
Comments:
Submitted by.--
WRH, Inc.
Date: 7/15/2024
( ) Time and Material
( ) Change in Completion Date
( ) No Change
Tim Williams
IIIbIIRI IY
Approved by aten-an .1--Uri SIGNED
Owner
Date: 8/5/2024
FY 23 Watewater Treatment Plant Final Clarifier #3 Rehabilitation - Waterloo, la.
RFC Calculation
Subcontractors
Core Drill - Quote from Iowa Wall Sawing
Material:
PRV's
PRV Freight
Crushed Stone
Water Stop
Bonding Agent
Grout
Labor:
General Labor
Skilled Labor
Safety Professional
Foreman
Superintendent
Project Manager
Equipment:
F eld Truck
Skid loader
Boom Truck
Excavator (under 100 HP)
Excavator (100 HP +)
Welder
Dump Truck
Dozer (large)
Sales Tax on Material
Contractor's Fee (Self -performed)
Contractor's Fee (Sub -contracts)
Bond & Insurance
Total Proposed Change
RFC # 10
Quantity
8.00
Sub -total
8.00
1.00
1.00
1.00
1.00
1.00
35.0
35.0
20
20
3.0
10.0
Unit
Ea
Ea.
LS
LS
LS
LS
LS
Hr
Hr
Hr
Hr
Hr
Hr
Day
Hr
Hr
Hr
Hr
Hr
Hr
Hr
Unit Rate
$375.00
$784.71
$300.00
$70.00
$85.00
$50.00
$451.00
$79.50
$96.08
$111.09
$105.09
$111.09
$195.17
$93.60
$57.20
$168.30
$83.20
$135.20
$26 93
$75 05
$130.00
0.00%
15.00%
5 00%
2 00%
07/15/24
Line Total
$3, 000.00
$0.00
$0.00
$6,277 68
$300.00
$70.00
$85.00
$50.00
$451.00
$0.00
$2,782 50
$0.00
$0.00
$3,678.15
$222 18
$390.34
$280.80
$0.00
$1,683.00
$0.00
$0.00
$0.00
$225.15
$0.00
$19,495.80
$0.00
$2,474.37
$150.00
$0.00
$22,120.17
$442 40
$22,562.57