CEDAR VALLEY RIVERFRONT RENAISSANCE
WATERLOO VISION IOWA PROJECTS
FINAL DESIGN SERVICES FOR MARK'S PARK AND PERFORMANCE STRUCTURE
SUPPLEMENTAL AGREEMENT NO. 8
WHEREAS, a Professional Services Agreement was entered into between the City of Waterloo, Iowa
(Client), and AECOM Technical Services, Inc., formerly Earth Tech, Inc. (Consultant), of Waterloo, Iowa,
dated September 22, 2003, for the preliminary design, final design and construction-related services for the
Cedar Valley Riverfront Renaissance, Waterloo Vision Iowa Projects, including the three major projects
known as the Riverwalk Loop, Cedar River Dam Improvements and the Cedar River Plaza and
Amphitheatre in Waterloo, Iowa; and
WHEREAS, Supplemental Agreement No. 1 was entered into between the Client and the Consultant dated
January 24, 2005, for Phase II - Final Design Services of selected alternatives; and
WHEREAS, Supplemental Agreement No. 2 was entered into between the Client and the Consultant dated
October 10, 2005, for Phase III - Construction-Review Services for that portion of the project including
floodwall modifications at the Lower Plaza and Waterloo Center for the Arts Youth Pavilion; and
WHEREAS, Supplemental Agreement No. 3 was entered into between the Client and the Consultant dated
September 18, 2006, for Phase III — Construction-Review Services for that portion of the project including
the Riverwalk Loop Trail from East 6th Street to 18th Street; and
WHEREAS, Supplemental Agreement No. 4 was entered into between the Client and the Consultant dated
May 21, 2007, for Phase III — Construction Review Services for that portion of the project including the
Waterloo Dam Rehabilitation and River Wall Reconstruction; and
WHEREAS, Supplemental Agreement No. 5 was entered into between the Client and Consultant dated
June 15, 2007, for Phase III - Construction Review Services for that portion of the project including the
Riverwalk Loop Trail from Cedar Bend Park to Mullan Avenue; and
WHEREAS, Supplemental Agreement No. 6 was entered into between the Client and the Consultant dated
September 2, 2008, for Phase III - Construction Review Services for that portion of the project including the
Riverwalk Loop Trail Enhancements (Overlooks) along the north side of the Cedar River, from 6th Street to
the Cedar River Dam; and
WHEREAS, Supplemental Agreement No. 7 was entered into between the Client and the Consultant dated
October 20, 2008, for Phase III - Construction Review Services for repairs of damage to portions of the
project along the Cedar River caused by the flood of 2008; and
WHEREAS, the Client and the Consultant now desire to enter into Supplemental Agreement No. 8 for final
design services for Mark's Park and additional design services for a Performance Structure for the
amphitheatre area of the lower plaza.
NOW THEREFORE, it is mutually agreed to amend the original Professional Services Agreement as
follows:
Page 2
Project Description
The project consists of the construction of Mark's Park and a Performance Structure for the lower
plaza area, both to become significant elements of the River Renaissance project. The project
received funding from the Cedar Valley Gaming Association, in addition to private funding obtained
for Mark's Park. Mark's Park will include creating a space in the current plaza area for a children's
park that will include water features and other play equipment. The Performance Structure will be
constructed in the lower plaza area to be used by performers within the amphitheatre.
II. Scope of Services
The Scope of Services provided by the Consultant team (including InVision Architecture) will
encompass and include services, materials, equipment, personnel and supplies necessary to
provide all detailed work, services, materials, equipment, personnel and supplies necessary to
provide final design and construction documents for Mark's Park and the Performance Structure.
The Scope of Services is further defined as follows:
Mark's Park— Final Construction Plans and Specifications
Tasks 1 - 15. These tasks include developing final construction plans and specifications for Mark's
Park. These tasks will include work necessary to complete the grading, paving, retaining wall
design, utility design, play equipment design and selection, and final plans and specifications for
the improvements. Included in these tasks will be the typical cross-sections, tabulations and
quantities, final plan sheets, details, utility design and tabulations, retaining wall plans, construction
cost estimate and technical specifications. These tasks will include work necessary to complete
the final design, project plans and specifications, and the printing of the documents for a City of
Waterloo letting. The following specific tasks lead to the completion of the final grading, paving and
utility plans for the project.
Task 1 -Title and Legend Sheets
Task 2-Typical Sections and Details
Task 3- Bid Items, Estimate Reference Notes and General Notes
Task 4-Tabulations and Quantities
Task 5- Plan and Profile Sheets
Task 6- Geometric Layout Sheets
Task 7-Construction Staging
Task 8- Utility Design (Water and Sanitary)
Task 9- Earthwork
Task 10 - Design Cross Sections
Task 11 - Retaining Wall Design
Task 12 - Play Equipment Selection and Design, Including Splash Pad
Task 13 -Construction Cost Estimate
Task 14-Specifications
Task 15- Field Review
COS'
Page 3
Performance Structure-Final Construction Plans and Specifications
Tasks 16 - 24. These tasks include developing final construction plans and specifications for the
Performance Structure. These tasks will include work necessary to complete the design of the
Performance Structure and associated footing design. Included in these tasks will be the typical
sections, final dimension sheets, footing details, construction cost estimate and technical
specifications. These tasks will include work necessary to complete the final design, project plans
and specifications, and the printing of the documents for a City of Waterloo letting. The following
specific tasks lead to the completion of the Performance Structure plans.
Task 16-Title and Legend Sheets
Task 17-Typical Sections and Details
Task 18- Bid Items, Estimate Reference Notes and General Notes
Task 19- Plan and Layout Sheets
Task 20- Structure Dimension Sheet
Task 21 - Footing Design and Dimension Sheets
Task 22-Construction Cost Estimate
Task 23-Specifications
Task 24- Field Review
Project Administration and Meetings
Tasks 25 - 27. These tasks include project administration, coordination and meetings throughout
the project development. These tasks also include pre-letting activities and general project
administration. The following identifies tasks leading to the completion of project administration,
meetings and coordination during the design phase of the project.
Task 25—Project Meetings
Task 26— Pre-Letting Activities
Task 27—Project Administration
Construction-Related Services
The scope of construction-related services will be determined at the time the services are needed
and defined under a future amendment to this agreement. Construction-related services include
construction staking, on-site field review, materials testing, contract administration during
construction and right-of-way staking, including new property pins.
III. Compensation
Compensation for the above services will be on any hourly basis in accordance with Part III of the
original agreement. Estimated fee for the services is One Hundred Four Thousand Dollars
($104,000.00)and shall be added to the fee in Supplemental Agreement No. 1.
AECOM
Page 4
IV. In all other respects, the obligations of the Client and the Consultant shall remain as specified in the
Professional Services Agreement dated September 22, 2003; and subsequent amendments.
IN WITNESS WHEREOF, the parties hereto have executed this Supplemental Agreement No. 8 as of the
dates shown below:
CITY OF WATERLOO, IOWA
By:
Date
Tim y . urley
ayor
ATTEST:
By: (cXLI
AECOM TECHNICAL RVICES, INC.
By
Date S) ICU I
Joe A. Becker
Vice President
LAwork\ADMI N\AGREE\SUPPLE\SA8-MarksParkPerformanceStructure.doc
AECOM
I AECOM
Letter of Transmittal
TO: City of Waterloo DATE: August 25, 2009 JOB ID NO.: 84050
715 Mulberry Street ATTENTION: Ms. Nancy Eckert
Waterloo, Iowa 50703 RE: Cedar Valley Riverfront Renaissance
Mark's Park and Performance Structure
Supplemental Agreement No. 8
WE ARE SENDING YOU:
❑ Attached ❑ Prints ❑ Under separate cover via the following items:
❑ Shop Drawings ❑ Change Order ❑ Plans ❑ Samples ❑ Specifications
❑ Copy of Letter ❑
COPIES DATE NO. DESCRIPTION
1 Original Executed Agreement for the Above-Referenced Project for your Files
THESE ARE TRANSMITTED AS CHECKED BELOW:
❑ For approval ❑ Approved as submitted ❑ Resubmit copies for approval
• For your use ❑ Approved as noted ❑ Submit copies for distribution
❑ As requested ❑ Returned for corrections ❑ Return corrected prints
❑ For review and comment ❑
❑ For Bids due 20 ❑ Prints returned after loan to us
REMARKS: Thanks Nancy!
COPY TO: Paul Hutinq (w/enclosure(copy) SIGNED: