HomeMy WebLinkAboutWRH Inc - CO #3, Cont. No. 975 - 10.7.24AECOM
September 25, 2024
Mr. Jesse Gaherty
Waste Management Services
City of Waterloo
3505 Easton Avenue
Waterloo, Iowa, 50702
Subject: Titus Lift Station and Force Main
Change Order No. 3
City of Waterloo, Iowa
City Contract No. 975
AECOM #60726355
Dear Mr. Gaherty:
AECOM
501 Sycamore Street
Suite 222
Waterloo, Iowa 50703
www.aecom.com
Attached is Change Order No. 3 for the Titus Lift Station and Force Main project submitted by WRH, Inc.
319-232-6531 tel
319-232-0271 fax
The following are the details for the requested changes.
• Bid Item No. 8 — Lift Station and Wet Well — CAR No. 12 — The pump cable length needs to be
increased to mount the junction boxes on the electrical building wall. This will eliminate the need
for explosion proof junction boxes. This change is an addition of $11,654.00.
• Bid Item No. 8 — Lift Station and Wet Well and Bid Item No. 12 Air Release Manhole No. 1 —
CAR No. 13 — Changing from Knife Valves to Plug Valves because of availability and to stay on
schedule. This change is a deduction of ($18,880.00).
AECOM recommends the City approves Change Order No. 3 for the deduction of $(7,226.00) and a revised total contract
cost of $6,263,470.88. The increase is 1.28% % of the original contract including all change orders.
Yours sincerely,
Christopher G. Oelkers, PE
Enclosure: Change Order No. 3 dated 09/25/2024
WRH Inc Change Authorization Request Nos. 8 and 12
L:\DCS\Projects\WTR\60726355_Titus_LS_and_FM_CRS\600_Construction_Support\670_Change-Orders\CO 3\975 TITUS - CO 03 LTR.docx
CHANGE ORDER 3
A=COM
Owner City of Waterloo
Project TITUS LIFT STATION AND FORCE MAIN
Date: September 25, 2024
Owner's Contract No. 975
Contractor: WRH, INC.
SRF NON-SRF
Date of Contact Start
January 2, 2024
Contract Amount:
$6,184,087.00 $
You are directed to make the following changes in the Contract Documents. Description:
8
LIFT STATION WET WELL AND VALVE VAULT WRH CR 8
$ (2,506.00)
12
AIR RELEASE MANHOLE AT TITUS LIFT STATION WRH CR 10
$ (4,720.00)
TOTAL
$ (7,226.00)
DEDUCTION
Reason for Change Order
Bid Item No. 8 — Lift Station and Wet Well — CAR No. 12 — The pump cable length needs to be increased to mount the junction boxes on the
electrical building wall. This will eliminate the need for explosion proof junction boxes.
Bid Item No. 8 — Lift Station and Wet Well and Bid Item No. 12 Air Release Manhole No. 1— CAR No. 13 — Changing from Knife Valves to
Plug Valves because of availability and to stay on schedule
CONTRACT PRICE
SRF
NON- SRF
Original:
$ 6,184,087.00
$ 6,184,087.00
$ -
Previous C.O.s
This C.O.
$ 86,609.88
$ (7,226.00)
$ 86,609.88
$ (7,226.00)
$
$ -
Contract Price with all approved
$ 6,263,470.88
$ 6,263,470.88
$ -
Total Change Orders:
$ 79,383.88
1.28% Total CO %
TOTAL
$ 6,263,470.88
Original Completion Date:
Revised Completion Date:
CONTRACT TIME
To Substantial To Final
Completion Completion
11/30/2024
12/31/2024
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPROVbue/Wz
.
BY: 9-tar
IIICI1111V
SIGNED
Owner (Authorized Signature)
ACCEPTED:
BY:
10/7/2024
Date
September 25, 2024
Contractor (Authorized Signature) Date
ACCEPTED:
BY:
September 25, 2024
AECOM Date
AECOM
60726355 I 3
Project No. C.O. No.
Project:
CAR No. 12
Reference:
RFQ #
Change Autnorizatlon Request
(CAR)
DATE 09/24/24 Job No. 2401-00-1428
Location Waterloo, IA Contract No.
A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this
authorization is requested so that the material may be purchased and to prevent any delay in field operations.
Reason for Change:
( ) Design Request
( X ) Owner Request
( ) Other ---- Explain
( ) Field Condition
( ) Suggested by Contractor
1) Description of Change: (Refer to drawings, specification, addenda, bulletin if applicable)
Replace three originally specified pump cable lengths of 50-feet with three new 80-foot long cables
to reach new junction box location on exterior of electrcial building.
2) It is requested that the completion date be;
by 2 calendar days.
3) Basis of Payment:
a) ( X ) Firm price for performing this change
is ( X ) increased / ( ) decreased by
is ( ) increased / ( ) decreased by
is ( ) increased / ( ) decreased by
b)
c)
d)
(
(
(
) Unit Price
( X ) extended
( ) decreased
$11,654.00
$0.00
$0.00
$0.00
Change to be performed per unit prices in Contract $0.00
The time required to prepare and agree upon a detailed estimate prior to proceeding with
the change would unduly delay job progress. The following is an approximate estimate
to assist Owner in determining whether or not change should be made. If notified to proceed,
a detailed estimate in the form agreed upon, with supporting details, will be submitted
after receipt of said notice.
Approximate Estimate is $11,654.00
CHANGE WILL NOT BE MADE
PROCEED ON THE FOLLOWING BASIS:
Firm Price
Estimate of Price
Unit Price in Contract
Comments:
( ) Time and Material
( ) Change in Completion Date
( ) No Change
SIG
Submitted by: $u�l a Approved by I,CGf/Z'E(,/Z UM !ALLY
SIGNED
Brad Oja, Project Manager Owner
WRH, Inc.
Date: 9/24/2024 Date: 10/7/2024
Project:
CAR No. 13
Reference:
RFQ #
Change Autnorizatlon Request
(CAR)
DATE 09/24/24 Job No. 2401-00-1428
Location Waterloo, IA Contract No.
A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this
authorization is requested so that the material may be purchased and to prevent any delay in field operations.
Reason for Change:
( X ) Design Request
( ) Owner Request
( ) Other ---- Explain
( ) Field Condition
( ) Suggested by Contractor
1) Description of Change: (Refer to drawings, specification, addenda, bulletin if applicable)
Due to manufacturing delays of four approved Red Valve Series D knife gates, Electric Pump will
supply four ready -to -ship Dezurik plug vlaves (non-AIS).
2) It is requested that the completion date be;
by calendar days.
3) Basis of Payment:
a) ( X ) Firm price for performing this change
is ( ) increased / (X ) decreased by
is ( ) increased / ( ) decreased by
is ( ) increased / ( ) decreased by
b)
c)
d)
(
(
(
) Unit Price
( ) extended
( ) decreased
($18,880.00)
$0.00
$0.00
$0.00
Change to be performed per unit prices in Contract $0.00
The time required to prepare and agree upon a detailed estimate prior to proceeding with
the change would unduly delay job progress. The following is an approximate estimate
to assist Owner in determining whether or not change should be made. If notified to proceed,
a detailed estimate in the form agreed upon, with supporting details, will be submitted
after receipt of said notice.
Approximate Estimate is ($18,880.00)
CHANGE WILL NOT BE MADE
PROCEED ON THE FOLLOWING BASIS:
Firm Price
Estimate of Price
Unit Price in Contract
Comments:
( ) Time and Material
( ) Change in Completion Date
( ) No Change
Submitted by: $u4 a Approved by atetziUZ J l:att
UIUI IALLY
SIGNED
Brad Oja, Project Manager Owner
WRH, Inc.
10/7/2024
Date: 9/24/2024 Date: