You are directed to make the following changes in the Contract Documents. Description:
8-1 Lower Gates Electrical Feeder Relocate $ 5,265.70 /LS
TOTAL ADDITIONS
x
1 UNITS $ 5,265.70
$ 5,265.70
Reason for Change Order
8-1 The existing electrical feeder for the Lower Gates restroom shelter is too shallow for the proposed water detention area. The existing
feeder was also directed buried. The new feeder will be encased in PVC conduit and placed under the detention area.
CONTRACT PRICE
CONTRACT TIME
To Substantial To Final
Completion Completion
Original: $ 9,362,172.81 Original Working Days 2401 2401
Previous C.O.s (ADD/DEDUCT) $ (1,172,730.28)
This C.O. (ADD/DEDUCT) $ 5,265.70 Revised Working Days:
Contract Price with all approved
Change Orders:
$ 8,194,708.23
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPROVED: /�(
BY: ui.� / (/ e 9-tar
DIGITALLY
SIGNED
10/21/2024
Owner (Authorized Si •:ture) Date
ACCEPTED: 9/24/24
BY:
PTED:
BY:
AECOM
or (Authorized Signature) Date
9/26/24
Date
AECOM
60672429 8
Project No. C.O. No.
WOODRUFF CONSTRUCTION
100% Employee Owned
Anthony Hemann
AECOM
501 Sycamore St. #222
Waterloo, IA 50703
RE: FY 2023 Gates Park Improvements
820 E Donald St. Waterloo, IA 50703
SUBJ: Potential Change Order #039 - Lower Gates Electrical Feeder Relocate
Dear Mr. Hemann,
1717 Falls Avenue I Waterloo, IA 50701
Ph: [319] 233-3349 Fax: [319] 233-3369
08/23/24
Per onsite observations, it has been discovered that the existing electrical feeder for the south restroom is too shallow
for the installation of a water detention area. Rerouting of the electrical feeder will be required to place feeder under
detention area.
Updated plumbing & mechanical (quote attached) = $ 4,787.00
GC Markup (10%) = $ 478.70
Total = $ 5,265.70
Your written approval is required by (8/30/2024)
When this potential change order is signed by the Owner and a copy is returned to the contractor, approval of
change(s) is effective IMMEDIATELY and we will proceed with the change(s) described above. Approved changes
will be included in a future contract change order. If you require additional clarification, please contact me. Thank
you for your prompt response.
Sincerely,
WOODRUFF CONSTRUCTION, INC.
Will McAllister
Project Manager
cc: File
Owner Approval / Date
Architect Approval / Date
rECT r lC9 lll ca
1127 Lincoln St.
PO Box 967
CedarFalls,IA50613
0: 319.277.0415
C: 319.269.3844
E: bdevries@k-welectric.com
W: www.k-welectric.com
Date: August 23, 2024
Company: Woodruff Construction
Attention: Will
RE: Gate Park
Will,
It has been discovered that the existing electrical feeder for the south restroom is too shallow for the
installation of the retention pond. We propose to relocate the feeder for $4,787.00
If you have any questions, please call.
Brian DeVries
Estimator/Project Manager