HomeMy WebLinkAboutWRH, Inc. - CO #4 FY 2023 WWTP Clairifer No. 3, Cont. No. 1067 - 10.21.202161:171 STRAND ASSOCIATES® Excellence in Engineerings" September 25, 2024 CHANGE ORDER NO. 4 PROJECT: OWNER: CONTRACT: 1067 CONTRACTOR: WRH, Inc. Strand Associates, Inc. 910 West Wingra Drive Madison, WI 53715 (P) 608.251.4843 www.strand.com F.Y 2023 Wastewater Treatment Plant Final Clarifier No. 3 Rehabilitation City of Waterloo, Iowa Description of Change • 4a Adjust the Contract price to account for the electrical usage associated with the bypass pumping in accordance with Request for Change No. 11 dated September 12, 2024. TOTAL VALUE OF THIS CHANGE ORDER: Contract Price Adjustment Original Contract Price Previous Change Order Adjustments Adjustment in Contract Price this Change Order Current Contract Price including this Change Order Contract Substantial Completion Date Adjustment (DEDUCT) (DEDUCT) Original Contract Substantial Completion Date Contract Substantial Completion Date Adjustments due to previous Change Orders Contract Substantial Completion Date Adjustments due to this Change Order Current Substantial Contract. Completion Dates including all Change Orders Contract Final Completion Date Adjustment Original Contract Final Completion Date Contract Final Completion Date Adjustments due to previous Change Orders Contract Final Completion Date Adjustments due to this Change Order Current Final Contract Completion Dates including all Change Orders KPB .nb2\S \rMAD\4400--4499\4463\016\Construction\Change Orders\CO 41CO 4.docx ($1,009.41) ($1,009.41) $842,000.00 $175,880.30 ($1,009.41) 1,016,870.89 / January 7, 2024 232 Days 0 Days August 16, 2024 February 6, 2024 230 Days 0 Days September 13, 2024 • Arizona j Illinois I Indiana 1 Iowa I Kentucky I Ohio I Tennessee 1 Texas I Wisconsin Strand Associates, Inc! City of Waterloo—WRH, Inc. Contract 1067, Change Order No. 4 Page 2 September 25, 2024 Q�oF�J .j°Nq��'This document shall become a supplement to the Contract and all provisions will apply hereto. •F: '/RANDALL A. c�kE / ENDED w: WIRTZ 1/Z.-SIZ-6Z({ =c1: 16137 'ins ::5%. r�.fONSULTANT—Stran As ciates, Inc." Date ,1/ iOWP���� `````APPR ittttt CONTRACTOR— WR1` , Dat APPROVED Quenifiz 914U'E DIGITALLY SIGNED CITY —City of Waterloo, Iowa SKH.nh2\S \MAD\4400-4499\4463\016\Construction\Change Orders\CO 4\CO 4 docx 10/21/2024 Date www.strand.com Request for Change (RFC) Project: FY 23 Watewater Treatment Plant Final Clarifier #3 Rehabilitation - Waterloo, Ia. RFC No. 11 Reference: Cost Proposal Request CPR # DATE 09/12/24 Job No. 1419 Location Clarifier #3 Contract No. 1067 A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this authorization is requested so that the material may be purchased and to prevent any delay in field operations. 1) Reason for Change: ( ) Design Request ( ) Field Condition ( ) Owner Request ( ) Suggested by Contractor (X ) Other ---- Explain Reimbursement of r owner supplied power Credit to reimburse city for electrical power used for de -watering system during the project. 2) It is requested that the completion date be; by 0 calendar days. ( ) extended ( ) decreased 3) Basis of Payment: a) ( x ) Firm price for performing this change along with attached supporting details is ( ) increased / ( X ) decreased by ($1,009.41) b) c) d) ( ( ( ) Unit Price $0.00 Change to be performed per unit prices in Contract $0.00 The time required to prepare and agree upon a detailed estimate prior to proceeding with the change would unduly delay job progress. The following is an approximate estimate to assist Owner in determining whether or not change should be made. If notified to proceed, a detailed estimate in the form agreed upon, with supporting details, will be submitted after receipt of said notice. Approximate Estimate is $0.00 ( ) CHANGE WILL NOT BE MADE PROCEED ON THE FOLLOWING BASIS: ( ) Firm Price ( ) Estimate of Price (x ) Unit Price in Contract Comments: ( ) Time and Material ( ) Change in Completion Date ( ) No Change Submitted by: WRH, Inc. Date: 9/12/2024 Date: 'DIGITALLY Approved by W %/Z si�o Tim hams Owner 10/21/2024 FY 23 Watewater Treatment Plant Final Clarifier #3 Rehabilitation - Waterloo, la. RFC Calculation Subcontractors Electrical power usage Material: Labor: General Labor Skilled Labor Safety Professional Foreman Superintendent Project Manager Equipment: Field Truck Skid loader Boom Truck Excavator (under 100 HP) Excavator (100 HP +) Welder Dump Truck Dozer (large) Sales Tax on Material Contractor's Fee (Self -performed) Contractor's Fee (Sub -contracts) Bond & insurance Total Proposed Change RFC #11 Quantity Unit 11,751.00 KW Sub -total Hr Hr Hr Hr Hr Hr Day Hr Hr Hr Hr Hr Hr Hr Unit Rate -$0.0859 $79.50 $96.08 111.09 $105.09 $111.09 $195.17 $93.60 $57.20 $168.30 $83 20 $135.20 $26.93 75.05 $130.00 0.00% 15.00% 5.00% 2 00% 09/12/24 Line Total ($1,0091 $0.00 $0.00 $0.00 $o.00 $0.00 $0.00 $o.00 $o.00 $0.00 $o.00 $0.00 $o.00 $o.00 $o.00 $o.00 $0.00 $0.00 $0.00 $0.00 ($ 1,009 41 1, $0.00 $0.00 $0.00 $0.00 ($ 1,009..41) $0.00 ($11OO9.41)