HomeMy WebLinkAboutEntrust - Supplemental Agmnt No. 2 , Cont. No. 1088 - 1.21.2025ADDENDUM NO. 2
TO THE
EN COMMUNICATIONS CONTRACT - CITY OF WATERLOO IA — PROJECT MANAGEMENT,
CONSTRUCTION MANAGEMENT, CONSTRUCTION INSPECTION AND ENGINEERING SUPPORT
SERVICES 2024
CITY OF WATERLOO, IOWA
DATE: DECMBER 30, 2024
The following is a revision to the EN COMMUNICATIONS CONTRACT - CITY OF WATERLOO
IA — PROJECT MANAGEMENT, CONSTRUCTION MANAGEMENT, CONSTRUCTION
INSPECTION AND ENGINEERING SUPPORT SERVICES 2024:
o Due to long lead times with USACE permits for three (3) levee crossings in Task
Orders 9, 13 and 14, the City requested to go overhead and attach to
MidAmerican Energy poles.
o This Addendum has been created to account for labor towards the Make Ready
Engineering (MRE) services (make ready, pole loading analysis, pole applications,
and pole data collection) for the MidAmerican Energy pole attachment
applications..
o The following labor pricing is net new costs to the project:
Make Ready
Engineering
Services
Description
Quantity
Unit Price
Amount
Design Coordinator
20
$145.00
$2,900.00
Design Tech II
20
$130.00
$2,600.00
Construction Manager
8
$175.00
$1,400.00
Construction Inspector
8
$140.00
$1,120.00
Field Manager
2
$200.00
$400.00
TOTAL
$8,420.00
Any revisions to any of the Contract Documents made by this Addendum shall be
considered as the same revision to any and all related areas of the Contract Documents not
specifically called out in this Addendum.
62aert rz 9 z SIGNED
Quentin Hart
Mayor of Waterloo, Iowa
City of Waterloo
Mike Hawkins
Vice President Operations
EN Engineering, LLC
Andrew Van Fleet
Board Chair
Waterloo Fiber
Page 1 of 1