HomeMy WebLinkAboutPeters Construction - CO #2 - Ramp, Atrium, Skyewalk - 1.21.2025CHANGE ORDER NO. 2
Owner City of Waterloo Date: 1/10/2025
Project City of Waterloo Commercial Parking Ramp, Atrium, & Skywalk Update Comercial Street Parking Ramp
Owner's Contract No. Contractor: Peters Construction Corporation
Date of Contact Start 9/19/2024
Contract Amount: $ 94,728.00
You are directed to make the following changes in the Contract Documents. Description
1 Phase 1 $ 18,981.00 x 1 LS $ 18,981.00
2 Phase 2 $ 34,970.00 x 1 LS $ 34,970.00
TOTAL ADDITIONS $ 53,951.00
Reason for Change Order
1 This item is for Skywalk removals and window reset on the Commercial Street Skywalk.
2 This item is for cement board, fascia, painting on the Commercial Street Skywak.
CONTRACT PRICE
Original: $ 94,728.00 Original Completion Date:
Previous C.O.s (ADD/DEDUCT) $ 11,898.00
This C.O. (ADD/DEDUCT) $ 53,951.00 Revised Completion Date:
Contract Price with all approved
Change Orders: $ 160,577.00
CONTRACT TIME
To Substantial To Final
Completion Completion
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
APPROVED:
BY:
Quet itz 914,rt
DIGIrAI
SIGNED
Owner (Authorized Signature)
ACCEPTED:
BY:
1 /21 /2025
Date
Contractor (Authorized Signature) Date
ACCEPTED:
BY: M'fca,,,t ' 09,e4
1/17/2025
AECOM Date
AECOM
2
Project No. C.O. No.
PETERS
CONSTRUCTION CORPORATION
901 Black Hawk Rd., Waterloo, IA 50701 Phone: 319-236-2003 Fax: 319-236-2009
CITY OF WATERLOO PARKING RAMP, ATRIUM, & SKYWALK UPDATE
COMMERCIAL STREET PARKING RAMP
SKYWALK / PEDESTRIAN BRIDGE REPAIRS — PHASE 1
JANUARY 9TH, 2025
GENERAL PROJECT REQUIREMENTS
• Onsite field and office supervision and coordination.
• Electric and water service usage fees/costs to be provided by the City of Waterloo.
• Temporary interne and cell phone service.
• General and final project cleanup, including glass at reinstalled storefront units.
• Waste disposal fees.
• Subcontractor liability insurance.
• Equipment as required to perform work.
SELECTIVE DEMOLITION
• Remove and dispose of loose and/or damaged metal flashing, blocking and sheathing from
the area below the aluminum framing as noted for skywalk repair in the drawings.
• Remove and dispose damaged areas of plaster and sheathing to existing control joints.
ROUGH CARPENTRY
• Replace damaged framing, blocking, and nailers per detail 1/2 on sheet A200 in the area
below the aluminum framing as noted for skywalk repair in the drawings.
• Provide and install temporary plywood on horizontal and vertical surfaces below the
aluminum framing and horizontal areas under the skywalk to eliminate safety concerns and
allow for Commercial Street traffic.
GLAZING
• Remove and reset up to four (4) existing aluminum -framed storefront sections per side and
replace missing fascia pieces.
• Warranties on reinstalled glass are excluded.
PHASE 1 CONSTRUCTION TOTAL $18,981.00
NOTES AND CLARIFICATION
• Proposed work is based on drawings provided by AECOM (Project Number 60743948).
• Sales tax is excluded.
PETERS
CONSTRUCTION CORPORATION
901 Black Hawk Rd., Waterloo, IA 50701 Phone: 319-236-2003 Fax: 319-236-2009
• Building permit and plan review fees are excluded.
• Road closure permits and fees are excluded.
• Davis -Bacon wages are excluded.
• Builders risk insurance to be provided by the City of Waterloo.
• Barricades and traffic control shall be provided by the City of Waterloo.
• Please provide Notice to Proceed by 1/14 to allow for a tentative start date of 1/27/2025
with an expected duration of approximately one (1) week.
PETERS
CONSTRUCTION CORPORATION
901 Black Hawk Rd., Waterloo, IA 50701 Phone: 319-236-2003 Fax: 319-236-2009
CITY OF WATERLOO PARKING RAMP, ATRIUM, & SKYWALK UPDATE
COMMERCIAL STREET PARKING RAMP
SKYWALK / PEDESTRIAN BRIDGE REPAIRS — PHASE 2
JANUARY 9TH, 2025
GENERAL PROJECT REQUIREMENTS
• Onsite field and office supervision and coordination.
• Electric and water service usage fees/costs to be provided by the City of Waterloo.
• Temporary interne and cell phone service.
• General and final project cleanup.
• Waste disposal fees.
• Subcontractor liability insurance.
• Equipment as required to perform work.
SELECTIVE DEMOLITION
• Remove and dispose of protective plywood on horizontal and vertical surfaces below the
aluminum framing and horizontal areas under the skywalk.
PLASTER ASSEMBLIES
• Provide and install cement board, sub framing, and mesh under the skywalk to existing
control joints where previously damaged.
• Plaster new cement board to match adjacent surfaces (prior to painting).
SHEET METAL FLASHING AND TRIM
• Provide and install new 3-piece metal fascia below the aluminum framing in areas of
skywalk repair to match adjacent areas.
PAINTING
• Prepare and paint new and existing plaster under the entire skywalk (required for all paint
to match).
• Prepare and paint new and existing sheet metal flashing below the aluminum framing on
the entire skywalk (required for all metal to match).
PHASE 2 CONSTRUCTION TOTAL $34,970.00
PETERS
CONSTRUCTION CORPORATION
901 Black Hawk Rd., Waterloo, IA 50701 Phone: 319-236-2003 Fax: 319-236-2009
NOTES AND CLARIFICATION
• Proposed work is based on drawings provided by AECOM (Project Number 60743948).
• Sales tax is excluded.
• Building permit and plan review fees are excluded.
• Road closure permits and fees are excluded.
• Davis -Bacon wages are excluded.
• Builders risk insurance to be provided by the City of Waterloo.
• Barricades and traffic control shall be provided by the City of Waterloo.
Troy Phillips
From: AOL Mail! <hawkeyesm0000@aol.com>
Sent: Thursday, January 9, 2025 1:34 PM
To: Troy Phillips
Subject: Commercial st Bridge
We propose to furnish and install sheet metal as follows using 24 prefinished steel.
3 pc facia. Approx 40 If per side.
Note
Peters to do demo as needed
Peters to supply lift as needed
Color to match as close as possible. There will be variance do to age of existing metal.
Our Bid Is $3,900.00
Respectfully
Mike Lamb
Hawkeye Sheet Metal
Jason Adams, Mgr.
LINDGREN GLASS, LLC
511 Washington Street
WATERLOO, IOWA 50701
319/233-5291
FAX 319/235-54529
Quote
0107/2025
Waterloo Skywalk Repair
Peters Construction Troy
We propose to remove and reinstall (4) total pieces of glass. (2) on the East and (2) on the West side of the skywalk. Includes removing the framing that
holds the (4) pieces of glass in. Also includes new face pieces that are missing. All other infill and flashing by others. Lift machine by others. Any other
glass and framing that needs taken out will be at an additional cost. There will be no warranties on existing glass or framing. Lindgren Glass will not be
liable for any broken or damaged material from removal.
Quote:$2348.00 tax included
Fax Cover Sheet
Date: 1 /9/2025
Total Pages: 1
To:
Company: Peters Construction Co
Phone:
Fax:
From: Jim Hein
Company- Michael Painting & Decorating
1008 Jefferson St
Waterloo IA 50702
Phone' 319-232-3755
Fax: 319-232-4940
Message...
Fi E
TI L
Pricing for The Commerical Street Skywalk Repair.
Paint bottom side plaster complete after repairs are made by others, and
lift provided by others. $2500.00.
Paint new and existing flashing $1200.00.
Thanks, Jim