HomeMy WebLinkAboutPeters Construction - Terminal Canopy CO #1 - 1.21.2025CHANGE ORDER NO. 1
Owner: Waterloo Regional Airport, City of Waterloo, Iowa
Project: Terminal Parking Canopy Structure
Owner's Contract No. ICAIF Project No. 9I220AL0400
Contract No. 0004232
Contractor: Peters Construction Corporation
Date of Contract Start: November 6, 2023
Date: January 8, 2025
You are directed to make the following changes in the Contract Documents. Description:
Item
No.
Description
Unit
Unit Price
Contract
Quantity
Change
Percent
Change
Revised
Quantity
Amount
101
FOOTING, OVEREXCAVATE
AND ADD LEAN CONCRETE
LS
$ 4,820.10
-
1.0
-
1.0
$ 4,820.10
102
ENTRANCE/EXIT CANOPY
FOOTING OVEREXCAVATION
LS
$ 11,785.46
1.0
1.0
$ 11,785.46
103
STAGING AREA FENCE DEDUCT
LS
$ (2,210.00)
-
1.0
-
1.0
$ (2,210.00)
104
MOVE WIRELESS BRIDGES
LS
$ 1,622.98
-
1.0
-
1.0
$ 1,622.98
105
MOVE SW BARRIER GATE AND
TICKET SPITTER
LS
$ 3,923.38
1.0
1.0
$ 3,923.38
106
ADD FIVE (5) REMOVABLE
BOLLARDS
LS
$ 7,107.00
-
1.0
1.0
$ 7,107.00
Total Change Order $ 27,048.92
Reason for Change Order:
101— Item added due to poor soil bearing capacity determined after excavation. Applies to footings four and five
of the main canopy structure.
102 — Item added due to poor soil bearing capacity determined after excavation. Applies to the east exit canopy
footing and to both entrance canopy footings.
103 — Item added to remove approximately 560 LF of temporary fence around staging area from scope of work.
104 — Item added to move wireless communication bridges.
105 — Item added to move SW barrier gate and ticket spitter to new W entrance lane using existing circuit to
power relocated gate.
106 — Item added due to installation of five (5) removable bollards.
ICAIF Project No — 9I220AL0400
Contract No. 0004232
CO-1 Project No — 60723532
1
CONTRACT PRICE
Original: $ 2,382,854.00
Previous C.O.s (DEDUCT):$
This C.O. (ADD): $ 27,048.92
Contract Price with all
approved Change Orders: $ 2,409,902.92
CONTRACT TIMES (Calendar Days)
To substantial To final
completion completion
Original:
0.00 Previous C.O.s (ADD):
This C.O. (ADD):
REVISED:
380
0
10
390
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
By: 3
Engineer (Authorized Signature)
APPROVED:
Qaertiuz 9-tar
SIGNED
By: •/
Owner (Authorized Signature)
ACCEPTED:
By: 2J r;Ft
Contractor (Authorized Signature)
January 8, 2025
Date
1 /21 /2025
1/81209-5-
Date
Date
ICAIF Project No — 9I220AL0400
Contract No. 0004232
CO-1 Project No — 60723532
2