HomeMy WebLinkAboutWRH, Inc. - Titus Lift Station, CO #6 Cont. No. 975 - 1.21.2025AECOM January 8, 2025 Mr. Jesse Gaherty Waste Management Services City of Waterloo 3505 Easton Avenue Waterloo, Iowa, 50702 Subject: Titus Lift Station and Force Main Change Order No. 6 City of Waterloo, Iowa City Contract No. 975 AECOM #60726355 Dear Mr. Gaherty: AECOM 501 Sycamore Street Suite 222 Waterloo, Iowa 50703 www.aecom.com 319-232-6531 tel 319-232-0271 fax Attached is Change Order No. 6 for the Titus Lift Station and Force Main project submitted by WRH, Inc. The following are the Change Order Requests (CAR) submitted by WRH, Inc. CAR 15 is to extend the final completion date to 05/30/2025 due to unforeseen delays. The delay is time for MidAmerican Energy to move an existing gas main that was in the way to connect to the existing sanitary sewer. The location of the gas main was not correct in the plans and was unknown till August. It took 4 months for MidAmerican Energy to disconnect that gas main. Work is on schedule to have the lift station operational by 01/31/2025. The remaining work is cosmetic. CAR 16 is a deduction for reduced demolition of the existing lift station. WRH will complete the task as previously described except the existing wet will be abandoned in place below 10 feet instead of full removal. A full description is provided on the attached CAR 16 from WRH, Inc. Pay Item No. 4 CAR 17 is an addition to extend the existing 6-IN force main to provide additional overflow relief. Pay Item No. 52 CAR 18 is an addition to provide additional bollards to protect the building and generator pad. Pay Item No. 53 Car 19 is an addition to increase the size of the magnetic meter from 10-IN to 12-IN. Pay Item No. 54 AECOM and City Staff recommends the City approves Change Order No. 6 for the Final Completion Date of 05/30/2025. and for the addition of $10,527.01. The revised total contract cost is $6,294,296.30. The increase is 1.78% of the original contract including all change orders. \\` ,,,ilo tIII111 lf///// �OESSf0Nq` �a may% z :CHRISTOPHER G.'. G) w : OELKERS : Z 22053 m %, ' I hereby certify that this engineering document was prepared by me or under my direct personal supervision and that I am a duly licensed Professional Engineer under the laws of the state of Iowa. 01/08/2025 CHRISTOPHER G. OELKERS, P.E. Date License No. 22053 My license renewal date is December 31, 2025. Pages or sheets covered by this seal: All Pages Enclosure: Change Order No. 6 dated 01/08/2025 WRH CAR No. 15, 16, 17, 18 and 19 L:\DCS\Projects\WTR\60726355_Titus_LS_and_FM_CRS\600_Construction_Support\670_Change-Orders\CO 6\975 TITUS - CO 06.docx CHANGE ORDER 6 AECOM Owner City of Waterloo Project TITUS LIFT STATION AND FORCE MAIN Date: January 8, 2025 Owner's Contract No. 975 Contractor: WRH, INC. SRF NON-SRF Date of Contact Start January 2, 2024 Contract Amount: $6,184,087.00 $ You are directed to make the following changes in the Contract Documents. Description: FINAL COMPLETION TIME EXTENSION WRH CAR 15 $ - 4 DEMOLISION ADJUSTMENT WRH CAR 16 $ (28,553.00) 52 EXISTING 6-IN FORCE MAIN TIE-IN WRH CAR 17 $ 21,378.68 53 BOLLARDS WRH CAR 18 $ 6,247.07 54 MAG METER WRH CAR 19 $ 11,454.26 TOTAL $ 10,527.01 ADDITION Reason for Change Order Change Order Request (CAR) 15 is to extend the final completion date to 05/30/2025 due to unforseen delays. The delay is time for MidAmerican Energy to move an existing gas main that was in the way to connect to the existing sanitary sewer. The location of the gas main was not correct in the plans and was unknown till August. It took 4 months for MidAmerican Energy to disconnect that gas main. Work is on schedule to have the lift station operational by 01/31/2025. The remaining work is cosmetic. 4 CAR 16 is a deduction for reduced demolition of the existing lift station. WRH will complete the task as previously described except the existing wet will be abandoned in place below 10 feet instead of full removal. A full description is provided on the attached CAR 16 from WRH, Inc. 52 CAR 17 is an addition to extend the existing 6-IN force main to provide additional overflow relief. 53 CAR 18 is an addition to provide additional bollards to protect the building and generator pad. 54 Car 19 is an addition to increase the size of the magnetic meter from 10-IN to 12-IN. CONTRACT PRICE SRF NON- SRF Original: $ 6,184,087.00 $ 6,184,087.00 $ - Previous C.O.s This C.O. $ 99,682.29 $ 10,527.01 $ 99,682.29 $ 10,527.01 $ $ - Contract Price with all approved $ 6,294,296.30 $ 6,294,296.30 $ - Total Change Orders: $ 110,209.30 1.78% Total CO % TOTAL $ 6,294,296.30 Original Completion Date: Revised Completion Date: CONTRACT TIME To Substantial To Final Completion Completion 11/30/2024 1/31/20251 5/30/2025 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. APPROVELN.�r[tn �Ll i r,[ BY: Q� l lA ` / [LG� 1 Owner (Authorized Signature) ACCEPTED: BY: 1 /21 /2025 Date January 8, 2025 Contractor (Authorized Signature) Date ACCEPTED: BY: January 8, 2025 AECOM Date AECOM 60726355 I 6 Project No. C.O. No. Project: CAR No. 15 Reference: RFQ # Change Authorization Request (CAR) DATE 01/06/25 Job No. 2401-00-1428 Location Waterloo, IA Contract No. A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this authorization is requested so that the material may be purchased and to prevent any delay in field operations. Reason for Change: ( ) Design Request ( ) Owner Request ( ) Other ---- Explain ( ) Field Condition ( X ) Suggested by Contractor 1) Description of Change: (Refer to drawings, specification, addenda, bulletin if applicable) Due to delays caused by entities outside of the project scope (MidAmerican Energy - Gas) resulting in work being pushed outside the normal construction season, WRH is requesting an exension to the project completion date. WRH requests that the project completion date be set at May 30, 2025. 2) It is requested that the completion date be; by calendar days. 3) Basis of Payment: a) ( X ) Firm price for performing this change is (X) increased / ( ) decreased by is ( ) increased / ( ) decreased by is ( ) increased / ( ) decreased by b) c) d) ( ( ( ) Unit Price ( X ) extended ( ) decreased $0.00 $0.00 $0.00 $0.00 Change to be performed per unit prices in Contract $0.00 ) The time required to prepare and agree upon a detailed estimate prior to proceeding with the change would unduly delay job progress. The following is an approximate estimate to assist Owner in determining whether or not change should be made. If notified to proceed, a detailed estimate in the form agreed upon, with supporting details, will be submitted after receipt of said notice. Approximate Estimate is $0.00 CHANGE WILL NOT BE MADE PROCEED ON THE FOLLOWING BASIS: Firm Price Estimate of Price Unit Price in Contract Comments: ( ) Time and Material ( ) Change in Completion Date ( ) No Change Submitted by: $u01 a Approved by Brad Oja, Project Manager Owner WRH, Inc. Date: 1/6/2025 Date: Project: CAR No. 16 Reference: RFQ # Change Authorization Request (CAR) DATE 01/06/25 Job No. 2401-00-1428 Location Waterloo, IA Contract No. A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this authorization is requested so that the material may be purchased and to prevent any delay in field operations. Reason for Change: ( ) Design Request ( ) Owner Request ( ) Other ---- Explain ( X ) Field Condition ( ) Suggested by Contractor 1) Description of Change: (Refer to drawings, specification, addenda, bulletin if applicable) Deduction for not demolishing complete underground wet well and valve vault. WRH will remove all existing process pumps, piping, valves, etc. and salvage/dispose. Existing pipe connections will be plugged and flowable grout will be placed in the bottom of each underground structure. Sand will be placed in inside each void up to the top 5 to 10 feet of each structure (final amount to be determined based on field conditions) of which will be removed and legally disposed. The remaining excavation will he aradPd accnrdina to nrnipct design 2) It is requested that the completion date be; by calendar days. 3) Basis of Payment: a) ( X ) Firm price for performing this change is ( ) increased / (X ) decreased by b) c) d) ( ( ( ) Unit Price ( ) extended ( ) decreased ($28,553.00) $0.00 Change to be performed per unit prices in Contract $0.00 The time required to prepare and agree upon a detailed estimate prior to proceeding with the change would unduly delay job progress. The following is an approximate estimate to assist Owner in determining whether or not change should be made. If notified to proceed, a detailed estimate in the form agreed upon, with supporting details, will be submitted after receipt of said notice. Approximate Estimate is ($28,553.00) CHANGE WILL NOT BE MADE PROCEED ON THE FOLLOWING BASIS: Firm Price Estimate of Price Unit Price in Contract Comments: ( ) Time and Material ( ) Change in Completion Date ( ) No Change Submitted by: $u01 D Approved by Brad Oja, Project Manager Owner WRH, Inc. Date: 1/6/2025 Date: Project: CAR No. 17 Reference: RFQ # Change Authorization Request (CAR) DATE 01/06/25 Job No. 2401-00-1428 Location Waterloo, IA Contract No. A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this authorization is requested so that the material may be purchased and to prevent any delay in field operations. Reason for Change: ( ) Design Request ( ) Owner Request ( ) Other ---- Explain ( X ) Field Condition ( ) Suggested by Contractor 1) Description of Change: (Refer to drawings, specification, addenda, bulletin if applicable) No longer abondoning 6" sanitary sewer force main. Excavate to tie-in with bends and ductile iron piping and connect at manhole 1. Coordinate work with 8" gravity main excavation to utilize north - south excavation to manhole 1. 2) It is requested that the completion date be; by 8 calendar days. 3) Basis of Payment: a) ( X ) Firm price for performing this change is (X) increased / ( ) decreased by is ( ) increased / ( ) decreased by is ( ) increased / ( ) decreased by b) c) d) ( ( ( ) Unit Price ( X ) extended ( ) decreased $21,378.68 $0.00 $0.00 $0.00 Change to be performed per unit prices in Contract $0.00 ) The time required to prepare and agree upon a detailed estimate prior to proceeding with the change would unduly delay job progress. The following is an approximate estimate to assist Owner in determining whether or not change should be made. If notified to proceed, a detailed estimate in the form agreed upon, with supporting details, will be submitted after receipt of said notice. Approximate Estimate is $21,378.68 CHANGE WILL NOT BE MADE PROCEED ON THE FOLLOWING BASIS: Firm Price Estimate of Price Unit Price in Contract Comments: ( ) Time and Material ( ) Change in Completion Date ( ) No Change Submitted by: $u01 a Approved by Brad Oja, Project Manager Owner WRH, Inc. Date: 1/6/2025 Date: Project: CAR No. 18 Reference: RFQ # Change Authorization Request (CAR) DATE 01/06/25 Job No. 2401-00-1428 Location Waterloo, IA Contract No. A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this authorization is requested so that the material may be purchased and to prevent any delay in field operations. Reason for Change: ( X ) Design Request ( ) Owner Request ( ) Other ---- Explain ( X ) Field Condition ( ) Suggested by Contractor 1) Description of Change: (Refer to drawings, specification, addenda, bulletin if applicable) Add nine (9) bollards. Four (4) additional bollards to the project around the transformer, two (2) additional bollards by the electrical building, and three (3) additioanl bollards by the generator. 2) It is requested that the completion date be; by 1 calendar days. 3) Basis of Payment: a) ( X ) Firm price for performing this change is (X) increased / ( ) decreased by is ( ) increased / ( ) decreased by is ( ) increased / ( ) decreased by b) c) d) ( ( ( ) Unit Price ( X ) extended ( ) decreased $6,247.07 $0.00 $0.00 $0.00 Change to be performed per unit prices in Contract $0.00 ) The time required to prepare and agree upon a detailed estimate prior to proceeding with the change would unduly delay job progress. The following is an approximate estimate to assist Owner in determining whether or not change should be made. If notified to proceed, a detailed estimate in the form agreed upon, with supporting details, will be submitted after receipt of said notice. Approximate Estimate is $6,247.07 CHANGE WILL NOT BE MADE PROCEED ON THE FOLLOWING BASIS: Firm Price Estimate of Price Unit Price in Contract Comments: ( ) Time and Material ( ) Change in Completion Date ( ) No Change Submitted by: $u01 a Approved by Brad Oja, Project Manager Owner WRH, Inc. Date: 1/6/2025 Date: Project: CAR No. 19 Reference: RFQ # Change Authorization Request (CAR) DATE 01/06/25 Job No. 2401-00-1428 Location Waterloo, IA Contract No. A Change in the scope of work is indicated below and Owner's prompt approval or rejection of this authorization is requested so that the material may be purchased and to prevent any delay in field operations. Reason for Change: ( ) Design Request ( ) Owner Request ( ) Other ---- Explain ( ) Field Condition ( X ) Suggested by Contractor 1) Description of Change: (Refer to drawings, specification, addenda, bulletin if applicable) Project specifications listed a 10" magentic flow meter, project requires a 12" magnetic flow meter. 2) It is requested that the completion date be; by 3 calendar days. 3) Basis of Payment: a) ( X ) Firm price for performing this change is (X) increased / ( ) decreased by is ( ) increased / ( ) decreased by is ( ) increased / ( ) decreased by b) c) d) ( ( ( ) Unit Price ( X ) extended ( ) decreased $11,454.26 $0.00 $0.00 $0.00 Change to be performed per unit prices in Contract $0.00 ) The time required to prepare and agree upon a detailed estimate prior to proceeding with the change would unduly delay job progress. The following is an approximate estimate to assist Owner in determining whether or not change should be made. If notified to proceed, a detailed estimate in the form agreed upon, with supporting details, will be submitted after receipt of said notice. Approximate Estimate is $11,454.26 CHANGE WILL NOT BE MADE PROCEED ON THE FOLLOWING BASIS: Firm Price Estimate of Price Unit Price in Contract Comments: ( ) Time and Material ( ) Change in Completion Date ( ) No Change Submitted by: $u01 a Approved by Brad Oja, Project Manager Owner WRH, Inc. Date: 1/6/2025 Date: