HomeMy WebLinkAboutBlack_Hawk_County_-_Agreement_-_(Donald_St_Resurfacing)_-_4.7.2025Docusign Envelope ID: 722763F4-1 F54-4496-BA4C-953837DF90A0
Black Hawk County Engineer's Office
Cooperative Agreement
For Construction Projects
Location Donald Street
Work Type HMA Pavement Widening with
HMA Resurfacing
Project No. STP-S-0007(177)--5E-07
This Agreement is entered into by and between Black Hawk County, Iowa hereafter designated the
"County', and the City of Waterloo, Iowa hereinafter designated the "City".
The County proposes to establish or make improvements to County Road D16 (Donald Street) from Sage
Road easterly to County Road V49 (Raymond Road) within Black Hawk County, Iowa. Refer to Exhibit A.
The County and the City are willing to jointly participate in said project, in the manner hereinafter provided;
and
This Agreement reflects the current concept of this project which is subject to modification by mutual
agreement between the County and the City; and
Therefore, it is agreed as follows:
1. Project Information
a. The County shall be the lead local governmental agency for carrying out the provisions of this
Agreement.
b. All notices required under this Agreement shall be made in writing to the City's and/or the County's
contact person. The City's contact person shall be the City Engineer, Jamie Knutson, P.E.
The County's contact person shall be the County Engineer, Catherine Nicholas, P.E.
2. Project Design
a. The County shall be responsible for the design of all proposed improvements.
b. The City shall review and approve the plans before Letting and review and approve the contract cost
before the contract is approved.
c. The project plans, specifications and engineer's cost estimate shall be prepared and certified by the
County.
3. Project Costs
a. The City shall contribute 25% toward the estimated project cost as shown on Exhibit B.
b. Once the project has been completed, the City will reimburse the County the full 25% of actual
construction costs incurred on the project.
Docusign Envelope ID: 722763F4-1 F54-4496-BA4C-953837DF90A0
4. Bid Letting
a. The County shall submit the plans, specifications, estimate, and all other contract documents for
review by the Iowa Department of Transportation.
b. The project will be let by the Iowa Department of Transportation in accordance with its normal letting
procedures.
c. The County shall be the contracting authority for the project.
5. Construction & Maintenance
a. The County shall be responsible for the daily inspection of the project, including the compilation of a
daily log of materials, equipment, and labor used on the project.
b. The County shall comply with the procedures and responsibilities for materials testing and
construction inspection according to the Iowa Department of Transportation's Materials Instructional
Memorandums (I.M.'s) and the Construction Manual. If requested, the Iowa Department of
Transportation may be able to perform some testing services. If performed, the Iowa Department of
Transportation will bill the County for testing services according to its normal policy.
6. Payments and Reimbursements
a. The County shall be responsible for making payments to the contractor(s) for all project costs
incurred in the development and construction of the project.
b. Upon completion of the project, the County will submit to the City an itemized claim for
reimbursement for eligible project activities. Reimbursement claims shall include certification by a
Professional Engineer licensed to practice in the State of Iowa that all eligible project activities for
which reimbursement is requested have been paid in full and completed in substantial compliance
with the terms of this Agreement.
c. The total payment shall be made payable in two increments as set forth below. The payments and
their increments pursuant to the Cooperative Agreement shall be made by the City, to the County, as
follows as full and complete satisfaction regarding this agreement and this project:
a. 1/2 of the actual City's division of work cost total by or before June 30, 2027; and
b. the remaining cost total by or before June 30, 2028.
d. Payments shall be made payable to Black Hawk County and submitted to the Black Hawk County
Engineer, 316 E. 5th Street, Courthouse 2nd Floor, Waterloo, Iowa 50703.
7. General Provisions
a. The County shall maintain records, documents, and other evidence in support of the work performed
under the terms of this Agreement. All accounting practices applied, and all records maintained will
be in accordance with generally accepted accounting principles and procedures.
b. If any part of this Agreement is found to be void and unenforceable then the remaining provisions of
this Agreement shall remain in effect.
Docusign Envelope ID: 722763F4-1 F54-4496-BA4C-953837DF90A0
c. This Agreement is not assignable without the prior written consent of the City.
d. It is the intent of both (all) parties that no third -party beneficiaries be created by this Agreement.
e. In case of dispute concerning the terms of this Agreement, the parties shall submit the matter to
arbitration pursuant to Iowa Code Chapter 679A. Either party has the right to submit the matter to
arbitration after ten (10) days' notice to the other party of their intent to seek arbitration. The written
notice must include a precise statement of the disputed question. The City and the County agree to
be bound by the decision of the appointed arbitrator. Neither party may seek any remedy with the
State or Federal courts absent exhaustion of the provisions of this paragraph for arbitration.
f. This Agreement may be executed in two (2) counterparts, each of which so executed will be deemed
to be an original.
g.
This Agreement, as well as the unaffected provisions of any previous agreement(s), addendum(s),
and/or amendment(s); represents the entire Agreement between the County and City regarding this
project. All previously executed agreements will remain in effect except as amended herein. Any
subsequent change or modification to the terms of this Agreement will be in the form of a duly
executed amendment to this document.
IN WITNESS WHEREOF, each of the parties hereto has executed this Agreement as of the date shown
opposite its signature below.
BOARD OF SUPERVISORS OF BLACK HAWK COUNTY, IOWA:
By: Date
Chairperson
ATTEST:
By:
County Auditor
CITY OF WATERLOO, IOWA:
DocuSigned by:
B �tt,lnl iln,
y D052M78nnc8440.
City of Waterloo Mayor
ATTESDocusigned by:
By:
Fdzae
ril(09AB44F...
Date 4/7/2025
Docusign Envelope ID: 722763F4-1 F54-4496-BA4C-953837DF90A0
Exhibit A
Donald Street
Beginning of Project Sta. = 99+00
End of Project Sta. = 310+95
c
MOLINE RD
K
26
27
:
i5
OUNKERTON
32
33
BIG ROCK RDE
.
34
3:
RD E
36
o w
PILOT GROVE
0
— 36
31
�
d.
6 Q
AIRLINE HWY E
SCHENK RD
ELK RUN RD N
x
3
c.
Y
W
w 2
Z
c.
0
RAYMOND RD N-
ORDWAY RC N
C
_
Ia
ce
l0
7
8
9
10
11
V49I2
7
DEWAF
13
1,0
••
co
PILOT GROVE
o
WATERLOO
DONALDSTE
- 15
=
RAYMOND RD N
I
26
25
L
V4
R-12W
N
R-11W
Docusign Envelope ID: 722763F4-1F54-4496-BA4C-953837DF90A0
Black Hawk
County
Road Department
Black Hawk County
Donald Street HMA Widening with HMA Resurfacing
ST P-S-0007(177)--5 E-07
PROJECT COST ESTIMATE
Date:
Est. By:
Check By:
Exhibit B
11113/2024
C.A W
ITEM #
ITEM CODE
BID ITEM DESCRIPTION
QUANTITY
UNIT
RATE
TOTAL
1
2102-2713090
EXCAVATION, CLASS 13, WASTE
2620
CY
$ 26.00
$ 681.20
2
2121-7425020
GRANULAR SHOULDERS, TYPE B
2,150.00
TON
$ 23.00
$ 55.900.00
3
2213-2713300
EXCAVATION, CLASS 13, FOR WIDENING
1,260.93
CY
$ 32.00
$ 40.349.78
4
2213-8201050
BASE WIDENING, 5 IN. HOT MIX ASPHALT MIXTURE
9,078.67
SY
$ 2400
$ 217.883.03
5
2214-5145150
PAVEMENT SCARIFICATION
56,588.00
SY
$ 4.00
$ 234,352.00
6
2303-1032500
HOT MIX ASPHALT STANDARD TRAFFIC, INTERMEDIATE COURSE. 1/2 IN_ MIX
8,200.00
TON
$ 46.00
$ 377200.00
7
2303-1033500
HOT MIX ASPHALT STANDARD TRAFFIC, SURFACE COURSE, 1/2 IN. MIX, NO SPECIAL
FRICTION REQUIREMENT
8,500.00
TON
$ 43.00
$ 403 000.00
8
2303-1258283
ASPHALT BINDER, PG 58-28S, STANDARD TRAFFIC
1002.00
TON
$ 600.00
$ 601.200.00
9
2303-6911000
HOT MIX ASPHALT PAVEMENT SAMPLES
1.00
LS
$ 1,600.00
$ 1..600.00
10
2303-7000610
PAYMENT ADJUSTMENT INCENTIVE/DISINCENTIVE FOR HMA MIXTURE LABORATORY
VOIDS (FORMULA- BY PAY FACTOR)
40 OOQ00
EACH
$ 1.00
$ 40.000.00
11
2303-7000620
PAYMENT ADJUSTMENT INCENTIVE/DISINCENTIVE FOR HMA MIXTURE FIELD VOIDS
(FORMULA - 8Y PAY FACTOR)
40000.00
EACH
$ 1.00
$ 40.000.00
12
2303-9091010
RUMBLE STRIP PANEL (HMA SURFACE)
3.00
EACH
$ 500,00
$ 1,500.00
13
2315-8275025
SURFACING, DRIVEWAY, CLASS A CRUSHED STONE
900.00
TON
$ 26.00
$ 23.400.00
14
2317-7000120
PAYMENT ADJUSTMENT INCENTIVE/DISINCENTIVE FOR HMA PAVEMENT SMOOTHNESS
(BY SCHEDULE)
22 800.00
EACH
$ 1.00
$ 22.800.00
15
2505-4008120
REMOVAL OF STEEL BEAM GUARDRAIL
282.50
LF
$ 8.50
$ 2,401.25
16
2505-4008300
STEEL BEAM GUARDRAIL
150.00
LF
$ 28.00
$ 4.200.00
17
2505-4021720
STEEL BEAM GUARDRAIL TANGENT END TERMINAL, BA-205
4.00
EACH
$ 3,200.00
$ 12,800.00
18
2505-4502100
STEEL BEAM GUARDRAIL, POST ADAPTER UNIT, BA-210
2400
EACH
$ 400.00
$ 9,600.00
19
2515-6745600
REMOVAL OF PAVED DRIVEWAY
14.70
5Y
$ 30.00
$ 441.00
20
2527-9263109
PAINTED PAVEMENT MARKING, WATERBORNE OR SOLVENT -BASED
1,677.52
STA
$ 24.00
$ 40.260.48
21
2528-8445110
TRAFFIC CONTROL
1_00
LS
$ 12,000.00
$ 12000.00
22
2528-8445113
FLAGGERS
130.00
EACH
$ 575.00
$ 74.750.00
23
2528-8445115
PILOT CARS
25.00
EACH
$ 865.00
$ 21.625.00
24
2533-4980005
MOBILIZATION
1.00
LS
$ 200,000,00
$ 200.000.00
25
2548-0000100
M ILLED SHOULDER RUMBLE STRIPS, HMA SURFACE
408.53
STA
$ 22.00
$ B.887.66
To
al Project Cost
$ 2,451, 936.43
11H&2024
G WCSK CrvillCivil3C ProleclsiPAV-Crnaltl St (Waterloo CL -to Raymond Rd) 50141Cost-Estimates-Desgn Tabs15014-11.1aster Project Tabs 8 Estimate Template (1 Div)