HomeMy WebLinkAboutAECOM_-_Twy_A_CRS_Amendment__1_-_8.4.2025 Docusign Envelope ID:55842E20-D4D1-4961-8912-6E73E09D88F6
PECOM
CONSTRUCTION-RELATED SERVICES (CRS)
PAVEMENT REHABILITATION
RECONSTRUCTION TAXIWAY A WEST
FAA AIP NO. 3-19-0094-053
FAA AIP NO. 3-19-0094-056 (BIL)
WATERLOO REGIONAL AIRPORT
WATERLOO, IOWA
AMENDMENT NO. 1
WHEREAS, an Individual Project Agreement was entered into by the City of Waterloo (Client) and
AECOM Technical Services, Inc. (ATS) dated May 1, 2023, for the Pavement Rehabilitation project;
and
WHEREAS, the Client and ATS now desire to enter into Amendment No. 1 to move funds for
additional geotechnical subconsultant costs for Braun Intertec.
NOW THEREFORE, it is mutually agreed to amend the original Individual Project Agreement as
follows:
I. Project Description —The project is described in the agreement for the above referenced
project dated May 1, 2023.
II. Scope of Services—There is no change in the Scope of Services from the agreement dated
May 1,2023. This modification reallocates Six Thousand Three Hundred Eighty-Eight Dollars
($6,388.00) from ATS's budget to the subcontract expense for Braun Intertec to provide
additional geotechnical services during the construction phase of the project.
III. Compensation
Compensation for services for this project will not change the cost-plus fixed fee of Four
Hundred Twenty-Three Thousand ($423,000.00). See attached Revised Exhibit B,
Consultant Cost Summary showing the funds being moved from ATS to Braun Intertec.
IV. General Conditions
Except as specifically amended by this Individual Project Agreement, services shall be
provided in accordance with the Professional Services Agreement for the Waterloo Regional
Airport, entered between AECOM Technical Services, Inc. ("ATS") and the City of Waterloo
("Client") dated February 4, 2020.
APPROVED: APPROVED:
CITY OF WATERLOO, IOWA AECOM TECHNICAL SERVICES, INC.
DocuSigned by:
By 6kvdiv, AAvf By
Quentin M. Hart, Mayor Michelle M. Sweeney, PE, PTOE
Associate Vice President
Date 8/4/2025 Date July 1, 2025
L:\Secure_DCS\Administration\AGREE\SUPPLE\ALO CRS Pavement Rehab Taxiway A West Amendment No.1.docx
Docusign Envelope ID:55842E20-D4D1-4961-8912-6E73E09D88F6
Revised Exhibit B
Amendment 1
Pavement Rehabilitation / Reconstruct Taxiway A West
Waterloo Regional Airport
Waterloo, Iowa
FAA AIP Project No. 3-19-0094-053/ FAA AIP Project No. 3-19-0094-056 (BIL)
Construction Related Services
Consultant Cost Summary
I. Direct Labor Cost
Category Hours Rate/Hour Amount
Senior Professional 174 $99.80 $17,365.20
Project Professional 372 $76.65 $28,513.80
Staff Professional 198 $55.50 $10,989.00
Professional 104 $33.60 $3,494.40
CADD Operator II 52 $39.05 $2,030.60
CADD Operator 1 24 $26.30 $631.20
Senior Technician 1559 $44.70 $69,687.30
Technician 444 $31.60 $14,030.40
Project Support 166 $37.85 $6,283.10 $153,025.00
3093
11. Payroll Burden and Overhead Costs 123.50% $188,985.88
111. Direct Project Expenses
Category Units Rate/Unit Amount
Mileage 3900 0.655 2,554.50
Per Diem 0 50.00 0.00
Lodging 0 90.00 0.00
B/W Copies 3,000 0.06 180.00
Color Copies 500 0.22 110.00
Plan Copier 100 0.50 50.00
EDM Equipment 72 12.50 900.00
GPS Equipment 20 25.00 500.00
Miscellaneous, Other 1,000.00 $5,294.50
IV. AECOM Estimated Actual Costs $347,305.38
Rounded $347,300.00
V. Subcontract Expense
Braun - Geotechnical Investigation $24,388.00
VI. Estimated Actual Costs $371,700.00
Vi 1. Fixed Fee (15% of Items I & 11) Rounded $51,300.00