HomeMy WebLinkAboutPeterson_Contractors_-_Cont._No._1133_FQS_CO__4_-_12.15.25Docusign Envelope ID: 7B4C7A31-81A5-4F30-97C0-BDBF9C8B9370
CHANGE ORDER NO. 4
Owner City of Waterloo Date: 11/3/2025
Project FY 2026 Airport Fence Relocation
Owner's Contract No.
1133 Contractor: Peterson Contractors Inc.
Date of Contact Start 6/26/2025
Contract Amount: $ 317,080.00
You are directed to make the following changes in the Contract Documents. Description:
6 CHAIN -LINK FENCE (10' FABRIC WITH BARBED WIRE) REMOVAL $ 1.25 /LF x -1675 LF $ (2,093.75)
9 TOPSOILING, 4 INCHES (FURNISHED FROM OFF THE SITE) $ 10.00 /CY x 1110 CY $ 11,100.00
10 EMBANKMENT -IN -PLACE (FURNISHED FROM ON THE SITE) $ 10.00 /CY x 740 CY $ 7,400.00
11 PAVEMENT REMOVAL, ASPHALT $ 4.25 /SY x 10025 SY $ 42,606.25
12 ORANGE MESH SAFETY FENCE, 48-INCH $ 6.25 /LF x -3980 LF $ (24,875.00)
13 HYDRAULIC SEEDING, SEEDING, FERTILIZING AND MULCHING, TYPE ] $ 3,000.00 /AC x 3.35 AC $ 10,050.00
14 WATTLES, 9-INCH $ 2.00 /LF x -1745 LF $ (3,490.00)
15 WATTLES, REMOVAL $ 0.50 /LF x -1745 LF $ (872.50)
TOTAL ADDITIONS $ 39,825.00
Reason for Change Order
6, 9, 10-15 Final quantity adjustments based on field measurements.
CONTRACT PRICE
Original: $ 317,080.00 Original Working Days
Previous C.O.s (ADD/DEDUCT) $ 39,630.03
This C.O. (ADD/DEDUCT) $ 39,825.00 Revised Working Days:
Contract Price with all approved
Change Orders:
$ 396,535.03
CONTRACT TIME
To Substantial To Final
Completion Completion
9/30/20251
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein,
including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further
time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
API
BY:
pffuSigned by:
aittl&filA, Ralf
8gc49Signatu re)
ACCEPTED:
BY:
Digitally signed by Chris D. Fleshner
DN: C=US, E=cleshner@pcius.com, 0="Peterson Contractors,
Chris D. Fleshnerinc.",CN=Chrsapproving tDovng tner
Reason: I am his document
Date: 2025.11.03 16:44:27-06'00'
Contractor (Authorized Signature)
ACCEPTED:
BY:
AECOM
12/15/2025
Date
11-03-2025
Date
11-04-2025
Date
AECOM
60764963 I 4
Project No. C.O. No.