HomeMy WebLinkAboutNotice to Bidders - FY26 CIP Pipelining Phase VA - Contract 1141NOTICE TO BIDDERS CONTRACT NO. 1141 NB-1 of 4
AECOM #60743622 FY 2026 CIPP
NOTICE TO BIDDERS
For the Taking of Construction Bids for the
FY 2026 CIP Pipelining Phase VA
In the City of Waterloo, Iowa
CONTRACT NO. 1141
RECEIVING OF BIDS
Sealed proposals will be received by the City Clerk of the City of Waterloo, Iowa, at her office in the City
Hall of the said City on the 26th day of February 2026, until 1:00 p.m. for the construction of the FY
2026 CIP PIPELINING PHASE VA, CONTRACT NO. 1141, as described in detail in the plans and
specifications now on file in the Office of the City Clerk.
OPENING OF BIDS
All bids received will be opened in the Council Chambers at City Hall in the City of Waterloo, Iowa, on
the 26th day of February 2026, at 1:00 p.m. and the proposals will be acted upon at such later time and
place as may then be fixed by the City Council. It is anticipated that the City Council will act upon the
proposals at their regular meeting on April 6, 2026.
PUBLIC HEARING
The Council of said City will conduct a public hearing on the proposed plans, specifications, form of
contract, and estimate of cost for the construction of the described improvement project at 5:30 p.m.
on March 16th, 2026, said hearing to be held in the Harold E. Getty Council Chambers in City Hall in
said City.
Office at 319-291-4323 by 4:45 p.m. to obtain conference call information. Alternatively, you may
email your comments to comments@waterloo-ia.org and they will be read during the public
hearing. Please state the public hearing item on which you wish to speak.
SCOPE OF WORK
Work of this Contract entails construction of Cured-In-Place Pipelining (CIPP) sanitary sewer lining
located in the City of Waterloo, identified as Sewer Service Area 16 (SA16), as shown on the Drawings.
The project includes cleaning, root removal, televising, CIP pipelining and lateral grouting of the following
quantities:
8-Inch Diameter CIPP 16,074 LF
10-Inch Diameter CIPP 2,375 LF
12-Inch Diameter CIPP - 999 LF
18-Inch Diameter CIPP 173 LF
21-Inch Diameter CIPP 336 LF
Laterals - 360 EA
BEGINNING AND COMPLETION DATES
The work under the proposed contract shall commence after
date submitted by the Contractor at the preconstruction conference and approved by the Engineer. Once
work commences, periods of inactivity shall be minimized. All items shall be completed on or before
December 4, 2026.