Project Title: Huntington Road and Katoski Drive Reconstruction
AGREEMENT FOR SERVICES
ADDENDUM No. 25-03
FOTH Project Number:
CLIENT Project Number:
(If applicable)
0025W013.00
Contract #1123
This Addendum (in addition to and subject to the conditions contained in the Agreement for Services dated March 17, 2025),
(hereinafter "Addendum"), is made and entered into 2nd day of March, 2026 by and between FOTH INFRASTRUCTURE &
ENVIRONMENT, LLC, (hereinafter "Consultant") and City of Waterloo, (hereinafter "Client"), for the services described under
the Scope of Services (the "Services").
CLIENT: City of Waterloo
Address: 715 Mulberry Street, Waterloo, Iowa 50023
Phone No: 319-291-4312
Scope of Services:
See Exhibit A
Schedule:
Email Address: Jamie.Knutson@waterloo-ia.org
Client hereby agrees to retain Consultant to perform the following Services:
Not Applicable
Services shall be performed according to the following schedule:
Compensation:
In consideration of these Services, the Client agrees to pay Consultant compensation as follows:
❑ Lump -Sum in the amount of $ .00
Unit Cost/Time Charges (Standard Rates) with a total amount not -to -exceed $75,000.00
❑ Unit Cost/Time Charges (Standard Rates) for an estimated cost of $ .00
❑ Other as stated here:
Special Conditions (if any):
Entire Agreement: This Addendum, along with other approved Addendums, together with and subject to the Agreement for
Services referenced above, constitutes the entire understanding between the parties with respect to the subject matter
hereof. This Addendum may be modified by subsequent written addenda mutually agreeable by both parties.
IN WITNESS WHEREOF, this Agreement is accepted on the date last written below, subject to the terms and conditions
above stated and the provisions set forth herein.
CLIENT
a —Signed by:
Signed: Pm- Got -sun,
"-393E8397B3D3421...
Name (printed): Dave Boesen
Title: Mayor
Date: 03/02/2026
FOTH INFRASTRUCTURE & ENVIRONMENT, LLC
Signed:
Name (printed): `don Resler, PE
Title: Lead Civil Engineer
Date: March 2, 2026
Signed:
Name (printed): Dave Kapler, PE
Title: Senior Vice President
Date: March 2, 2026
Page 1 of 2 Rev. 03/31 /2021
Docusign Envelope ID: 2BA02A85-E195-4590-93B8-E23065DB8755
Exhibit A
Scope of Services
Project Background
Refer to previous Huntington Road and Katoski Drive Reconstruction Agreement for Services Addendum No. 25-01
for a synopsis of the project background.
BASIC SERVICES OF THE CONSULTANT
The Scope of Services and basis for Compensation derivation are as follows:
1. Supplemental survey was completed for the temporary school entrance and temporary
sidewalk to incorporate into the design.
2. Multiple alignments and profiles were analyzed to minimize impacts to properties on the
north side of Huntington Road.
3. Additional design work was required to relocate the trail along Katoski Drive to the east
side of the roadway.
4. Additional design work was required to utilize elements of the existing storm sewer
system, including design modifications to standard storm sewer structures, to reduce the
construction cost of the project.
5. Additional coordination was required with MidAmerican Energy to address roadway and
roundabout lighting design.
6. Additional traffic modeling was required for the Greenhill Road roundabout due to the
complexity of the geometry of the existing roadway.
7. Two additional Rectangular Rapid Flashing Beacons (RRFBs) were designed due to the
relocation of the trail along Katoski Drive to the east side of the roadway.
8. Additional landscape design was required to develop a concept that reduced construction
and maintenance costs.
9. A plat of survey was completed for the exchange of property between the school district
and Conrad property at 2620 Huntington Road to facilitate the design of the trail along the
north side of Huntington Road.
10. Additional coordination was required with the school district and their site contractor to
avoid conflicts during construction and ensure the design of both projects interconnected
with each other.