Engineering Group
April 18, 2026
Revision 1 April 30, 2026
Mr. Chris Dolan
Arena Manager
Young Arena
Waterloo, IA 50703
Via Email: CHRIS.DOLAN@waterloo-ia.org
RE: Professional Engineering Services Proposal: Young Arena — Chiller and Cooling Tower
Replacement
Ice System Design and Construction Observation Phase Services
Dear Mr. Dolan:
We are pleased to submit this proposal to provide professional engineering services for the
above -mentioned project. The following proposal outlines our understanding of the project by
defining the scope of our services and key assumptions made in preparing this proposal and fees
associated with the Scope of Work.
ABOUT B32 ENGINEERING GROUP, INC.
Our team has extensive and specialty experience in programming, evaluations, concept design,
and design and construction phase services for all types of ice rink projects. Successfully
completing over 450 ice rink related projects, including some of the most recent and state-of-the-
art NCAA Division 1 college hockey facilities; our team, led by Scott Ward, is a leader in the ice
rink industry providing some of the most innovative, cost-effective, and energy -efficient design
solutions. We know these unique facilities very well, have a thorough understanding of their
needs and performance requirements and have the in-depth, specialty experience required to
successfully complete this project for you, the City of Waterloo Leisure Services, and other project
partners.
We have submitted to you our complete Ice Rink Statement of Qualifications for your review. We
would be happy to provide additional information regarding projects, references, etc. at your
request.
We recently completed an Ice System Evaluation, dated June 20, 2025, of the ice system
(including refrigeration system, ice rink floor system and dasherboard system) at the Young
Arena.
A few "local" ice rink projects that have completed or are currently working on includes The
Landing Ice Rink - Bettendorf, Marion Central Plaza Ice Skating Trail - Marion, MidAmerican
Energy Company RecPlex third sheet addition - West Des Moines, Ames/ISU Ice Arena (ice system
study), Xtreme Arena - Coralville, Main Street Landing - Davenport.
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
1
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
Engineering Group
Some of the more notable projects that B32 is currently working on, or have recently completed,
include the following (NCAA and large venues highlighted in red font)
Professional NHL (New and Renovation)
Baptist Health Ice Plex Florida Panthers Ft. Lauderdale FL (2 sheets)
Xcel Energy Center, St. Paul MN (MN Wild)
American Airlines Center, Dallas TX (Dallas Stars, study)
Ice Den, Coral Springs FL (Owned by Florida Panthers)
Minor Professional ECHL, SPHL, AHL (New and renovation)
Port Wentworth Ice Cove, Port Wentworth GA (2 sheets)
Owens Ice Arena, Peoria IL (2 sheets)
Pelham Civic Complex, Pelham AL (2 sheets)
Blue Cross Arena, Rochester NY (10,000 seats)
Mohegan Sun Arena, Wilkes Barre PA (10,000 seats)
NCAA College Division 1 (New)
Northeastern University, Boston MA
Sacred Heart University, Fairfield CT
Augustana University, Sioux Falls SD
Kalamazoo Event Center, MI (Western Mich and Kalamazoo Wings)
University of St Thomas, St. Paul MN (2 sheets)
NCAA Division 1 and Division 3 College (Renovation)
3MAM at Mariucci University of Minnesota, Minneapolis MN
Berry Event Center University of Northern Michigan, Marquette MI
Ingalls Rink -Yale University, New Haven CT
Baker Rink -Princeton University, Princeton Ni
Conte Forum -Boston College, Boston MA
Carlson Center -University of Alaska Fairbanks, AK
Tuttle North Ice Arena SUNY Brockport NY
Sage Rink, Hamilton College, Hamilton NY
Bird Arena, Ohio University, Athens OH
National Hockey Center, St. Cloud University, MN (2 sheets)
College Prep (Renovation)
Nobles Greenough School, Dedham MA
Community Facilities (Renovation)
Braemar Ice Arena, Edina MN (4 sheets)
Oakton Ice Arena, Oakton IL (2 sheets)
EPIC, Fort Collins CO (2 sheets)
National Sports Center, Super Rink Blaine MN (8 sheets)
Joliet Ice Arena, Joliet IL
Bloomington Ice Gardens, Bloomington MN (3 sheets)
Maple Grove Community Center, Maple Grove MN (3 sheets)
Hoyt Lakes Ice Rink, Hoyt Lakes MN
Hermantown Ice Rink, Hermantown MN (2 sheets)
Northwoods Credit Union Arena, Cloquet MN (2 sheets)
Marathon County Ice Rinks, Wausau WI (2 sheets)
Litchfield Civic Center, Litchfield MN
Webster Groves Ice Rink, Webster Groves MO
Kirkwood Ice Rink, Kirkwood MO
Playland Casino, Rye NY (3 sheets)
Pat Odonnell Civic Center, Ironwood MI
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
Graham Arena, Rochester MN (2 sheets)
Oak Lawn Ice Arena, Oak Lawn IL
Community Facilities (New)
Hockey Hall of Fame Rink, Inver Grove Heights MN
Mosaic Quarters, Tucson AZ (3 sheets)
Richmond VA (2 sheets)
Bowie Ice Arena, Bowie MD
Fargo Parks Sports Center, Fargo ND (2 sheets)
Mobile Arena, Mobile AL (10,000 seats)
Palm Beach Gardens Iceplex, Palm Beach Gardens FL (2 sheets)
East Brunswick NJ (2 sheets)
Car Shield Ice Rink, Chesterfield MO (2 sheets)
Northfield, MN
Belmont, MA
Woodman's Community Center, Janesville WI (2 sheets)
Prairie Lakes Ice Arena, Watertown SD (2 sheets)
Outdoor Facilities (New)
Middle Park Landing, Bettendorf IA (ice rink)
Jacobson Plaza, Sioux Falls SD (skating trail)
Landmark Ice Rink, Washington DC (skating trail)
Heartland of America, Omaha NE (skating trail)
Warwick Ice Rink, Warwick RI (ice rink)
Windows on the Waterfront, Holland MI (skating trail)
Laskar Pool and Ice Rink, Central Park NY (ice rink)
The Rivers Edge Ice Rink, Davenport IA (ice rink)
Central Plaza Ice Skating Loop, Marion IA (skating trail)
Schenley Ice Rink, Pittsburgh PA (ice rink)
Steinberg Pavilion Ice Rink, St. Louis MO (ice rink)
Elm Street Plaza Ice Rink, Cincinnati OH (ice rink)
City Park Ice Skating Ribbon, Bondurant IA (ice rink)
Red Arrow Park, Milwaukee WI (ice rink)
Ewart Park, Joplin MO (skating trail)
Studies
Panthers Ice Den, Coral Springs FL
Pasadena Ice Skating Rink, Pasadena CA
Young Area, Waterloo IA
American Airlines Arena, Dallas TX
Soldotna Regional Sports Complex, AK
Kenai Multi -purpose Facility, Kenai AK
Ames Ice Arena, Ames IA
Mennen Sports Center, Morristown Ni
Glacier Ice Rink, Missoula MT
Winter Lodge, Palo Alto CA
University of Illinois Urbana -Champaign
M Health Fairview Sports Center, Woodbury MN
BOK Center, Tulsa OK
West Seneca NY
2
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
Engineering Group
Lou & Gib Reese Ice Arena, Newark OH Richmond Ice Zone, Richmond VA
Woodbridge Community Center, Woodbridge NJ Resch Center, Green Bay WI
We can provide you with references for any one of our many successfully completed ice rink
projects at your request. Here are a few references to start with:
1. San Jose Ice at San Jose (San Jose Sharks Practice Facility, 2 new sheets and renovated 3 existing
sheets) and SAP Center (Shark's game facility).
Reference: Jon Gustafson, Vice President, Sharks Ice LLC, 408.999.6751.
jgustafson@sharksice.com
2. Great Park Ice and Sports Complex, Irvine CA (Anaheim Ducks practice facility, 4 sheets),
Reference: Art Trottier, Vice President —The Rinks. 714.518.3201
attrottier@the-rinks.com
3. Grand Casino Arena and TRIA Rink, St. Paul, MN (MN Wild Practice and Game Facilities)
Reference: Jim Ibister, Minnesota Wild Sr. VP of Administration. 0.651.265.4801
Jlbister@wild.com
Reference: Travis Larson, Ice Operations and Event Manager, Grand Casino Arena, 651-726-8160,
tlarson@wild.com
4. Baptist Ice Plex at Memorial War Memorial, Fort Lauderdale, FL (Panthers Practice Facility)
Reference: Melissa Fitzgerald, General Manager, Florida Panthers. 954.835.8515
fitzgeraldm@floridapanthersc.com
5. 3M Arena at Mariucci, University of Minnesota, Minneapolis
Reference: Craig Flor, Athletic Facility Manager, 612-625-8365, florx003@umn.edu
6. Martire Family Arena, Sacred Heart University, Fairfield CT
Reference: MS/L/A/Mo Izzo, Executive Director of University Construction,
izzom2@sacredheart.edu 0.203.396.8467
7. Ralph Engelstad Arena, Grand Forks ND
Reference: Jody Hodgson, General Manager 0.701.777.6633 iodyh@theralph.com
9. Super Rink, National Sports Center, Blaine MN
Reference: Neil Ladd, Senior Director, National Sports Center, 0.763.458.6618
nladd@nscsports.org
10. Herb Brooks National Hockey Center, St. Cloud State University MN
Reference: Cory Portner, Director 0.320.308.5118 cmportner@stcloudstate.edu
11. ImOm Arena, Dubuque IA
Reference: Robert Schiesl, Assistant City Engineer, City of Dubuque IA 0.563.5889.4270
bschiesl@cityofdubuque.org
12. Ed Robson Arena, Colorado College, CO
Reference: Michael Brubaker, Mechanical Services Engineer, 719-389-7115,
Michael.brubaker@coloradocollege.edu
13. Hobey Baker Rink, Princeton University, Princeton NJ
Reference: Danielle Matuch, Project Manager -Facilities Operations, Princeton University
0.609.258.3063 dmatuch@princeton.edu.
14. Belmont New Arena, Belmont MA
Reference: Mark Haley, board member, 0.617.886.7400 MHaley@haleyaldrich.com
Reference: Ted Galante, The Galante Architecture Studio, Inc. 0.617.576.2500
tg@galantearchicture.com
15. Bloomington Ice Gardens, Bloomington MN
Reference: Lenny Schmitz, Ice Garden Manager, 0.952.563.8787 Ischmitz@BloomingtonMN.gov
16. Civic Center and All Seasons Arena, Mankato MN
Reference: Mr. Jim Tatge, Facilities Project Coordinator, City of Mankato MN 0.507.387.8504
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
3
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
Engineering Group
jtatge@mankatomn.gov
TEAM MEMBERS
Principal and President of B32 Engineering Group, Inc., Scott Ward and our team will work closely
with you and the design team on this project. Scott has over 30 years of experience in civil and
mechanical engineering fields. He has extensive knowledge of public facilities (e.g., ice arenas,
water and wastewater treatment, community centers, aquatic centers, etc.) and associated
feasibility and evaluation studies, project development, funding applications, and the design and
construction process. His education and engineering experience uniquely qualifies him for the
specialized design requirements of ice systems. He has been involved in over 450 ice rink projects
since 1997, including professional practice facilities, NCAA Division 1 college venues, single and
multi -sheet community arenas, and outdoor ice rinks. Scott is integrally involved in each ice rink
project and has owned the business since 2007.
In addition to Scott's professional expertise, he grew up playing hockey and spent the majority of
his time in an ice rink facility in southern Minnesota. He continued to play recreational hockey
through college, coached youth hockey and was coaching coordinator for 16 years. He is an avid
hockey player and supporter of youth hockey and ice skating activities. The application of this
practical insight helps ensure each facility, and its systems are designed to meet your needs,
operate successfully and be a gathering place for the community.
Education
Master of Science in Mechanical Engineering, University of Minnesota, 2000
Bachelor of Civil Engineering, University of Minnesota, 1995
Registration
Registered Professional Engineer in: AL, AK, AZ, CO, CT, FL, IA, IL, MA, MD, ME, MI, MN, MO, NC,
ND, NE, NH, NJ, NM, NY, OH, OR, PA, RI, SD, TN, TX, VA, VT, WA, WI, WV, WY.
Professional Affiliations
American Society of Heating, Refrigeration and Air Conditioning Engineers (ASHRAE)
Minnesota Ice Arena Managers Association (MIAMA)
Wisconsin Ice Arena Managers Association (WIAMA)
North East Ice Skating Mangers Association (NEISMA)
Ice Skating Institute (ISI)
United States Ice Rink Association (formerly STAR)
Minnesota Recreation and Park Association (MRPA)
Examples of Ice Arena Projects:
See B32 Engineering Group, Inc. Ice Rink Statement of Qualifications for more information.
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
4
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
f
Engineering Group
PROJECT UNDERSTANDING
Young Arena is a 3,000-seat multipurpose arena with one ice rink floor system. The facility was
constructed in 1994. The facility is heavily used from 6am to 10pm daily and serves the
community offering skating programs at every level including public skating, Waterloo Blackhawks
(USHL Tier I Junior Team), Waterloo Warriors (Midwest High School Hockey League), Waterloo
Youth Hockey, Cedar Valley Figure Skating Club, Waterloo Adult Hockey Association, etc.
B32 completed an evaluation of the ice system in June 2025. Since that time the facility has
replaced one pump on the system. The majority of the refrigeration equipment, including the
chiller (evaporator) system, was installed with the original construction of the building and is over
30 years old reaching or exceeding its expected life of 25-30 years. The existing evaporative
condenser was installed in 2000 and is 26 years old, exceeding its expected life of 20-25 years.
The City of Waterloo Leisure Services has requested a proposal from B32 Engineering Group, Inc.
for design and construction administration services to replace the existing Vilter VSC 205
evaporative condenser system and shell and tube chiller (evaporator) system for the same type
and size of equipment. We will work closely with you, Young Arena staff and Leisure Services on
this project. B32 will provide all front end and Division 0 and 1 documents and assemble bidding
documents, etc.
Project Schedule
No specific project schedule was provided other than construction taking place in 2027.
Design: 2026
Construction: 2027 (Ice is typically removed around June 1 and installed again in September)
Cost Estimate
There was no project budget or cost estimate provided for this scope.
SCOPE OF WORK
B32 Engineering Group, Inc. will provide a step-by-step design approach as described below:
Step 1 —Design Phase
During this step B32 Engineering Group, Inc. will:
1.1 Kickoff Meeting (In -person): In -person meeting with you and Leisure Services to discuss the
following.
1. Project goals, schedule and budget.
2. Evaporator condenser and chiller options. The proposed fee in this proposal
assumes these systems are being replaced with the same or similar systems.
3. Concerns with the current equipment that is to remain in place (e.g. pumps, water
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
5
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
Engineering Group
tank, piping, controls, electrical, tower structure/foundation, compressors, controls,
etc.), project schedule, other project goals, etc.
4. Related work not covered in this proposal.
5. We will also verify and document existing conditions during this site visit.
1.2 Design Meetings (virtual): Follow up virtual meeting(s) with you and Leisure Services to
discuss project progress.
1.3 Prepare preliminary drawings and technical specifications in CSI format for our review.
1.4 Prepare front end documents, bidding documents, construction contracts, general conditions,
and Division 0 and 1 documents for City review.
1.5 Prepare an Opinion of Probably Construction Costs.
1.6 Provide project schedule.
1.8 Review preliminary drawing and specifications with you and make final changes before
issuing a final set of documents.
Step 2 — Bid Phase
During this Step B32 Engineering Group, Inc. will:
2.1 Provide recommendation on bidding and award schedule.
2.2 Prepare Advertisement for Bid.
2.3 Distribute copies of bid documents. Make the bid documents available through Quested and
linked through B32's website.
2.4 Answer questions from contractors, suppliers, Leisure Services, the City, etc. during the
bidding period.
2.5 Organize a pre -bid meeting with the contractors. B32 will be on -site for this meeting. B32 did
not include attending this meeting in person. We can provide this as an extra service.
2.6 Bid opening. Review the bid results, prepare bid tabulation, and provide input on award of
construction contract. B32 did not include attending the bid opening in person. We can
provide this as an extra service.
2.7 Prepare construction contracts for review and approval by the City.
Step 3 — Construction Administration
We will provide the following construction administration service.
3.1 Contract Administration: Review pay request, RFIs, change orders, etc. and provide
recommendations to you and Leisure Services. Participate in virtual progress meetings no
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
6
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
Engineering Group
more than two (2) per month. Review shopdrawings for equipment and materials used on
the project, answer questions regarding the drawings and specifications during
construction, and review photos of construction progress.
3.2 Progress visit (in person). Perform a progress visit when all of the main equipment is set
and piping installation has begun.
3.3 Final site visit after startup (In -person). Perform a final walkthrough of the systems
generating a list of items (punch list) to be completed.
3.4 Any additional site visits, currently not included in our proposal, would be included under
additional services and may include:
■ Preconstruction meeting (1 visit).
■ Progress verification (1-2 visits).
• Post -occupancy system performance verification (1 visit). Visit the site after the ice
system has been up and running, has been tested and balanced, to verify the operation
of the ice system is as designed. If the Owner will be providing commissioning, we will
assist the Owner's commissioning agent by providing information on the ice system as
requested. We did not include commissioning services in this proposal.
■ Warranty walkthrough (1 visit). Walk through the facility 10-11 months after substantial
completion to identify potential warranty information.
ASSUMPTIONS
This proposal is based on the following assumptions.
■ GETTING STARTED - Prior to starting the work, B32 Engineering Group, Inc. will be provided
with full information regarding the City's requirements including any special or extraordinary
considerations for the Project or special services needed and will be provided with all
pertinent existing data.
INFORMATION - B32 Engineering Group, Inc. will be relying on CAD files and topographic
surveys completed and prepared by others and provided to B32 by the City. B32 Engineering
Group, Inc. assumes no liability for the accuracy of such drawings or surveys. B32 did not
included creating a CAD file for this project in this proposal.
■ EXCLUSIONS - In preparing this proposal, certain items have been excluded from the scope of
services that may or may not be required. Should these services become necessary, B32
Engineering Group Inc. can provide them as Additional Services. The following services have
been excluded from this proposal:
Developing electronic files (AutoCAD, etc.) for use as background drawings for the design
for this project. We assume the City has these files available.
• Structural engineering for the cooling tower supports. Assume existing concrete supports
are sufficient and will be reused.
■ Design for other systems or parts of the refrigeration system other than the evaporative
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
7
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
f
Engineering Group
condenser and chiller (evaporator) system.
Ice rink floor and dasher board systems.
Evaluation of site and soil conditions in or near the building.
Rebates, grants, or other funding applications.
Energy modeling and calculations.
• Life cycle cost analysis.
■ Permit applications.
• Concept drawings of improvements to the facility.
• Commissioning of systems.
• Local and State code review meetings.
■ Environmental reviews, reports or permits.
■ Building energy simulation.
Sampling, laboratory and on -site material testing or performance and intrusive testing
• Hazardous material testing
■ Surveying
• Record plans or as-builts.
Project advocacy beyond the normal standard of care.
COST OF SERVICES
We propose the following lump fee for the services outlined in this proposal.
PHASE
DESIGN PHASE (STEP 1), 1 SITE VISIT
FEE
$15,700
BIDDING PHASE INCLUDING CONTRACTS (STEP 2), 1 SITE VISIT
$4,782
CONSTRUCTION ADMINISTRATION (STEP 3) 2 SITE VISITS
$8,482
TOTAL FIXED FEE SERVICES
$28,964
Conditions of Proposed Fee:
EXPENSES - Reimbursable expenses are in addition to the fees stated above and will be
invoiced in accordance with our standard fee schedule.
Taxes not included in fee.
▪ PAYMENTS — All payments due B32 Engineering Group, Inc. shall be made within 30 days
after receipt of invoice. Services will be invoiced once per month. Finance charges will be
applied to all payments not received within 30 days of invoicing. B32 Engineering Group,
Inc., shall have the right to suspend work on the project upon invoice past due more than
sixty (90) days from presentation, unless or until B32 Engineering Group, Inc. is satisfied
that payment is forthcoming.
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
8
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
f
Engineering Group
ADDITIONAL SERVICES — Additional Services, if authorized in advance, will be billed in
accordance with our standard fee schedule.
■ FEE SCHEDULE - The attached fee schedule is valid through December 31, 2026. Any
services furnished after December 31, 2026, will be charged in accordance with our 2027
fee schedule. We will not increase any item on the fee schedule by more than 5% per year
for work performed in 2027. The lump sum fee will remain unchanged for 2027.
QUALIFICATIONS — The proposed construction administration fee is based on the Owner
hiring an experienced ice rink contractor meeting the qualifications of B32 Engineering
Group, Inc. standard Section 131811 — Ice Rink General Requirements that in general states
the contractor must have successfully completed five (5) ice rink projects of similar scope in
the past five (5) years.
■ INSURANCE. This proposal is based on the following insurance coverage carried by B32
Engineering Group, Inc.
Category
Insurance Limits
Comp General Liability and Bodily Injury
$2M each occurrence
$4M general aggregate
Professional Liability
$5M each claim
$5M aggregate
Umbrella Liability
$2M each occurrence
$2M aggregate
• This proposal is based upon completion of our services by September 1, 2027.
• This document serves as record of the basic terms of our agreement. Upon receipt of a
countersigned copy of this letter, we assume you will provide B32 Engineering Group, Inc.,
with an agreement for review and comment.
B32 ENGINEERING GROUP, INC. IS BEST VALUE FOR YOUNG ARENA,
LEISURE SEVICES AND THE CITY OF WATERLOO.
In addition to having an extensive resume of over 450 very successful ice rink projects of all types
and sizes nationwide, B32 Engineering Group, Inc., brings to your project:
Experience with the newest and most technological advanced NCAA ice arena facilities in the
United States.
- Extensive ice rink design and construction experience providing a clear understanding of what
works and what doesn't work.
■ Extensive single -sheet and multi -sheet ice rink design experience providing the knowledge of
proper pumping and flow design to allow individual flow and temperature control to each
sheet of ice and central refrigeration system design maximizing system performance and
efficiency. As one example, we were involved in the ice system design for two 4-sheet
complexes for the same Owner with very tight budgets and two different building types. I
have designed many multi -sheet facilities.
• Extensive experience with natural refrigerants such as CO2-based ice systems and ammonia -
based ice systems.
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
9
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
Engineering Group
• Experience with codes, regulations, statues and ordinances applicable to indoor ice arena
facilities.
■ Personal attention. The Owner of B32 Engineering Group, Inc., Scott Ward, will be assigned to
manage this project for you. This project will be a priority for the B32 Engineering Group, Inc.
■ Performance. B32 congratulates the following 2026 Champions and is proud to have designed
the ice they skate on:
United States Olympic Team (Women's)—NSC Super Rink Blaine MN & Olympic Center in Lake
Placid NY
NCAA (Women's) — University of Wisconsin Badgers
ACHA DI — Ohio University Bobcats
Minnesota High School Class AA (Girls) — Hill -Murray Pioneers
Minnesota High School Class AA (Boys) — Moorhead Spuds
2026 IIHF World Junior Championship — Grand Casino Arena St Paul MN and 3M Arena at Mariucci,
University of Minnesota
Experience and passion foster innovation. B32 Engineering Group, Inc. was the first in the ice rink
industry to:
Design an ice system that regenerates a desiccant system using waste heat recovered from
the refrigeration system in place of natural gas. (Northfield Ice Arena- MN)
■ Design a conversion (direct to indirect) of an existing Holmsten Ice Rink's direct refrigeration
system that uses the existing equipment to minimize costs with little or no loss in operating
efficiency. This provided the City with the widest range of options for replacing or renovating
the existing ice system in the North Arena. (Lund Arena - Gustavus Adolphus College -MN)
Design a geothermal -based ice system without a well field and using a city water source,
maximizing waste heat recovery and providing superior efficiency and reliability without
losing performance. (Brooklyn Park Activity Center -MN)
■ Design a geothermal -based ice system that uses industrial grade refrigeration technology for
a long -life span and ammonia refrigerant to maximize efficiency and reduce greenhouse gas
emissions. (Burnsville Ice Center -MN)
• Design of first CO2-based ice systems in the United States. B32 Engineering Group, Inc. has
designed 11 total CO2-based ice systems with the first in 2014. (Anchorage AK Eagle River AK,
Palmer AK, St. Michael MN, Princeton University, Yale University, Northeastern University,
Belmont MA, St. Louis MO).
Design ice systems for LEED certified ice arena facilities including Bentley University MA
(Platinum), Amsoil Arena -Duluth MN (Gold), Great Park Ice & Sport Anaheim CA (Silver),
Deerfield Academy (Gold), and others. B32 Engineering Group, Inc. is always striving to apply
sustainable practices including waste heat recovery, water reuse, using recycled water to
make the ice sheet, geothermal, natural light, etc.
Thank you for the opportunity to be involved in this project. We are confident you will find our
qualifications, experience, and reputation at the top of the industry. We encourage you to call
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
10
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
f
Engineering Group
any references for any project that we have worked on.
If this proposal meets with your approval and is consistent with your understanding, please sign
and return an original copy of this letter by mail. In the event we do not receive a signed copy of
this letter, and we are authorized to begin work verbally, we will assume the terms and
conditions of this proposal have been accepted by you.
We are very excited about this opportunity, and we look forward to personally sharing our
experience and knowledge of ice arena facilities and ice systems with you, Leisure Services, the
City of Waterloo, and other project Stakeholders. If you have any questions, please feel free to
contact me on my mobile at 651.492.1376.
Sincerely,
B32 ENGINEERING GROUP, INC.
3--4.
Scott A. Ward, P.E.
President
Enclosure: 2026 Professional Services Fee Schedule
We can provide you with our Ice Rink Statement of
Qualifications at your request.
B32 ENGINEERING GROUP, INC.,
2211 O'Neil Road, Hudson, WI 54016
t 651.256.3090 f 715.808.0842 www.B32eng.com
Agreed to and accepted,
Signed by:
Poo 15eq-suA,
393E8397B3D3421._.
By
Mayor
Title
6/15/2026
Date
11
Docusign Envelope ID: 0C676AAC-5407-8CF8-808C-E4E04747B93D
APPENDIX A
•
Engineering Group
B32 2026 PROFESSIONAL SERVICES FEE SCHEDULE R1
Effective: January 1, 2026, December 31, 2026
HOURLY RATES
LABOR CATEGORY HOURLY RATES
Principal $275-$290
Senior Project Engineer/Project Manager $200-$275
Senior Project Manager/Designer/Senior Project
Coordinator
$165-$185
Project Engineer/Project Manager $145-$165
Designer $100-$120
Intern $85-$95
Marketing $110-$130
Administrative $90-$110
REIMBURSABLE EXPENSES
Reimbursable expenses include, but are not limited to the following:
• Mileage (current IRS rate).
Parking/Tolls
• Travel Expenses: airfare, lodging, rental cars, and electronic communication in connection with the project.
• Meals will be billed at $75 per diem.
• Reproductions, plots, report materials and standard form documents as outlined in the table below.
Item Size Black & White Color
Photocopies/Printing 8.5 x 11 $0.37 $1.37
11x17 $0.53 $2.63
Plots and Scans over 11x17 in size At cost of outside service
• Outside services (printing, testing, etc.).
• Delivery Services (UPS, FedEx, etc.).
• Subconsultant Services.
• Other similar direct project -related expenditures.
Reimbursable expenses are billable at 12% over cost and per diem.
All payments due to B32 Engineering Group, Inc. shall be made within 45 days after receipt of invoice. B32 invoices monthly.
These rates are subject to adjustment each year on January 1.