HomeMy WebLinkAboutCONSTRUCTION DOCUMENTS PROJECT MANUAL FOR: 2009 Gates Park Pro Shop Reroofing City of Waterloo, Department of Leisure Services Waterloo, Iowa CONSTRUCTION DOCUMENTS INVISION DES MOINES WATERLOO 531 Commercial Street,#900 303 Watson Powell Jr.Way,#200 Waterloo, Iowa 50701 Des Moines, Iowa 50309 319.233.8419 515.633.2941 319.233.9772-fax 515.633.2942-fax invisionarch.com ARCHITECT'S COMMISSION NUMBER: 09025 SET NUMBER: mom ... • Nom Nom Imm Imo Moo w ar - Gates Park Pro Shop Reroofing City of Waterloo, Department of Leisure Services Waterloo, Iowa OWNER CITY OF WATERLOO, DEPARTMENT OF LEISURE SERVICES ARCHITECT INVISION ARCHITECTURE 531 Commercial Street, Suite 900 Waterloo, Iowa 50701 (319)233-8419 Fax: (319)233-9772 Contact: Roland Ganter, Project Manager STRUCTURAL ENGINEER BISHOP CONSULTING ENGINEERS, P. C. 8 East Southridge Road Marshalltown, Iowa 50158 (641)752-8290 Fax: (641)752-8954 Contact: Randy Bishop PRE-BID MEETING: 9:00 a.m. June 24,2009 BID DUE DATE: 4:00 p.m. July 6,2009 SPECIFICATIONS DATED: May 27, 2009 ARCHITECTS COMMISSION NUMBER: 09025 I hereby certify that this plan, specification or report was prepared by me or under my direct supervision and that I am a duly registered Professional Architect under the laws of the State of Iowa. Signature Date am. =me re. mm. awn •••• Mom Irmo Immt Moe sm. Sm.• TABLE OF CONTENTS DIVISION 00 -PROCUREMENT AND CONTRACTING REQUIREMENTS 00 21 13 Instructions to Bidders 00 41 00 Bid Form MBE/WBE Certified Contractor Guide for the City of Waterloo, Iowa MBE/WBE Business Enterprise Pre-Bid Contact Information City of Waterloo Certification of MBE/WBE Accomplishment 00 50 00 Contracting Forms and Supplements 00 73 00 Supplementary Conditions DIVISION 01 -GENERAL REQUIREMENTS 01 10 00 Summary 01 20 00 Price and Payment Procedures 01 22 00 Unit Prices 01 23 00 Alternates 01 30 00 Administrative Requirements 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 60 00 Product Requirements 01 70 00 Execution and Closeout Requirements 01 78 00 Closeout Submittals DIVISION 02 -EXISTING CONDITIONS 02 41 00 Demolition DIVISION 04-MASONY 04 01 00 Maintenance of Masonry DIVISION 06 -WOOD, PLASTICS, AND COMPOSITES 06 10 00 Rough Carpentry 06 11 13 Engineered Wood Products 06 17 53 Shop-Fabricated Wood Trusses DIVISION 07 -THERMAL AND MOISTURE PROTECTION 07 21 26 Blown Insulation 07 27 00 Air Barrier/Weather Resistant Barrier 07 46 23 Wood Siding Gates Park Pro Shop Reroofing Project#09025 00 01 10 City of Waterloo, Department of Leisure Services TABLE OF CONTENTS Waterloo, Iowa Page 1 of 2 07 51 00 Built-Up Bituminous Roofing 07 62 00 Sheet Metal Flashing and Trim 07 90 05 Joint Sealers DIVISION 09 - FINISHES 09 90 00 Painting and Coating Gates Park Pro Shop Reroofing Project#09025 00 01 10 City of Waterloo, Department of Leisure Services TABLE OF CONTENTS Waterloo, Iowa Page 2 of 2 SECTION 00 21 13 INSTRUCTIONS TO BIDDERS SUMMARY 1.01 DOCUMENT INCLUDES A. Invitation to Bid, with relevant information and requirements. INVITATION 2.01 BID SUBMISSION A. Bids for the Gates Park Pro Shop Reroofing, signed and under seal, executed, and dated will be received by the City of Waterloo at the City Clerk's Office, located at 715 Mulberry Street, Waterloo, Iowa; before 4:00 p.m. local standard time on the 6th day of July, 2009. B. Offers submitted after the above time shall be returned to the bidder unopened. C. Offers will be opened publicly immediately after the time for receipt of bids. 2.02 INTENT A. The intent of this Bid request is to obtain an offer to perform work to reroof the existing pro shop structure at Gates Park Municipal Golf Course located at 820 E. Donald St., Waterloo, Iowa 50703 for a Stipulated Sum contract, in accordance with the Contract Documents. 2.03 WORK IDENTIFIED IN THE CONTRACT DOCUMENTS A. Work of this proposed Contract comprises reroofing the existing structure, including general construction Work. B. Location: Existing Gates Park Municipal Golf Course located at 820 E. Donald S , Waterloo, Iowa 50703. 2.04 CONTRACT TIME A. Identify Contract Time in the Bid Form. The completion date in the Agreement shall be the Contract Time added to the commencement date. B. The bidder, in submitting an offer, accepts the Contract Time period stated for performing the Work. The completion date in the Agreement shall be the Contract Time added to the commencement date. The bidder may suggest a revision to the Contract Time with a specific adjustment to the Bid Amount. C. Commence Work on or after July 20th, 2009. No work will be permitted prior to this date. D. Owner requires that the work of this contract be completed as quickly as possible and consideration will be given to time of completion when reviewing the submitted bids. BID DOCUMENTS AND CONTRACT DOCUMENTS 3.01 DEFINITIONS A. Bid Documents: Contract Documents supplemented with Invitation To Bid, Instructions to Bidders, Information Available to Bidders, Bid Form Supplements To Bid Forms and Appendices identified. B. Contract Documents: Defined in AIA A201 Article 1 including issued Addenda. 3.02 CONTRACT DOCUMENTS IDENTIFICATION A. The Contract Documents are identified as Project Number 09025, as prepared by INVISION Gates Park Pro Shop Reroofing Project#09025 00 21 13 City of Waterloo, Department of Leisure Services INSTRUCTIONS TO BIDDERS Waterloo, Iowa Page 1 of 5 Architecture and with contents as identified in the Table of Contents. 3.03 BIDDER'S REPRESENTATIONS A. The Bidder by making a Bid represents that: 1. The Bidder has read and understands the Bidding Documents or Contract Documents, to the extent that such documentation relates to the Work for which the Bid is submitted, and for other portions of the Project, if any, being bid concurrently or presently under construction, 2. The Bid is made in compliance with Bidding Documents. 3. The Bidder has visited the site, become familiar with local conditions under which the Work is to be performed and has correlated the Bidder's personal observations with the requirements of the proposed Contract Documents. 4. The Bid is based upon the materials, equipment and systems required by the Bidding Documents without exception. 3.04 AVAILABILITY A. Bid Documents are made available only for the purpose of obtaining offers for this project. Their use does not grant a license for other purposes. B. Bid Documents may be obtained at the office of Architect which is located at 531 Commercial Street, Suite 900 Waterloo, Iowa. C. Bidder shall use complete sets of Bidding Documents in preparing Bids; neither the Owner nor Architect assumes responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents. D. Call INVISION Architecture, 531 Commercial Street, Suite 900, Waterloo, Iowa, 50701, 319-233-8419 for questions regarding availability of plans. 3.05 EXAMINATION A. Bid Documents may be viewed at the office of Architect which is located at 531 Commercial Street, Suite 900 Waterloo, Iowa. B. Bid Documents are on display at the offices of the following construction plan rooms: 1. Construction Update Plan Room, 645 32nd Avenue SW, Cedar Rapids, IA 52404, 319-369-4848. 2. Master Builders, 221 Park Street Des Moines, IA 50306, 515-288-8904. 3. McGraw-Hill Plan Room, 3875 Elmore Avenue Suite C, Davenport, Iowa 52807, 563-355-1250. 4. McGraw-Hill Plan Room, 2507 Ingersoll Avenue, Des Moines, IA 50312, 515-223-1046. 5. Construction Update Plan Room, 612 Mulberry, Waterloo, IA 50703, 319-233-8431. 6. Dubuque Builders Exchange, 801 Cedar Cross Road, Dubuque, IA 52003, 563-583-8459. 7. North Iowa Builders Exchange, 25 W. State Street, Mason City, IA 50401, 641-423-5334, C. Upon receipt of Bid Documents verify that documents are complete. Notify Architect should the documents be incomplete. D. Immediately notify Architect upon finding discrepancies or omissions in the Bid Documents. 3.06 INQUIRIES/ADDENDA A. Direct questions to Roland Ganter, rolandg@invisionarch.com, telephone 319-233-8419 Fax 319-233-9772. B. Addenda may be issued during the bidding period. All Addenda become part of the Contract Documents. Include resultant costs in the Bid Amount, C. Verbal answers are not binding on any party. Gates Park Pro Shop Reroofing Project#09025 00 21 13 City of Waterloo, Department of Leisure Services INSTRUCTIONS TO BIDDERS Waterloo, Iowa Page 2 of 5 D. The Bidder shall carefully study and compare the Bidding Documents with each other, and with other work being bid concurrently or presently under construction tot eh extent that it relates to the Work for which the Bid is submitted, shall examine the site and local conditions, and shall at once report to the Architect error, inconsistencies or ambiguities discovered. E. Clarifications requested by bidders must be in writing not less than 7 days before date set for receipt of bids. The reply will be in the form of an Addendum, a copy of which will be forwarded to known recipients and plan holders. F. Each bidder shall indicate receipt of addendum on bid form. 3.07 PRODUCT/ASSEMBLY/SYSTEM SUBSTITUTIONS A. Where the Bid Documents stipulate a particular product, substitutions will be considered up to 7 days before receipt of bids. B. When a request to substitute a product is made, Architect may approve the substitution and will issue an Addendum to known bidders. C. The submission shall provide sufficient information to determine acceptability of such products. D. Provide complete information on required revisions to other work to accommodate each proposed substitution. E. Provide products as specified unless substitutions are submitted in this manner and accepted. F. See Section 01 60 00- Product Requirements for additional requirements. SITE ASSESSMENT 4.01 SITE EXAMINATION A. Examine the project site before submitting a bid. Extra costs for Work not identified on the drawings, but clearly visible, will not be considered. 4.02 PREBID CONFERENCE A. A bidders conference will be scheduled for 9:00 a.m. local standard time on the 24th day of June, 2009; at the location of the existing Gates Park Municipal Golf Course pro shop. B. All general contract bidders and suppliers are invited. C. Representatives of Architect will be in attendance. D. Summarized minutes of this meeting will be circulated to attendees. These minutes will not form part of the Contract Documents. E. Information relevant to the Bid Documents will be recorded in an Addendum, issued to Bid Document recipients. QUALIFICATIONS 5.01 EVIDENCE OF QUALIFICATIONS A. To demonstrate qualification for performing the Work of this Contract, bidders may be requested to submit written evidence of financial position, license to perform work in the State. 5.02 SUBCONTRACTORS/SUPPLIERS/OTHERS A. Owner reserves the right to reject a proposed subcontractor for reasonable cause B. Refer to General Conditions. BID SUBMISSION Gates Park Pro Shop Reroofing Project#09025 00 21 13 City of Waterloo, Department of Leisure Services INSTRUCTIONS TO BIDDERS Waterloo, Iowa Page 3 of 5 6.01 SUBMISSION PROCEDURE A. Submit two copies of the executed offer on the Bid Forms provided, signed and sealed with the required security in a closed opaque envelope, clearly identified with bidder's name, project name and Owner's name on the outside. B. Improperly completed information, irregularities in security deposit, may be cause not to open the Bid Form envelope and declare the bid invalid or informal. C. Oral, telephonic, facsimile or other electronically transmitted bids will not be considered. D, The Bidder shall assume full responsibility for timely delivery at the location designated for receipt of Bids. E. An abstract summary of submitted bids will be made available to all bidders following bid opening. 6.02 BID INELIGIBILITY A. Bids that are unsigned, improperly signed or sealed, conditional, illegible, obscure, contain arithmetical errors, erasures, alterations, or irregularities of any kind, may at the discretion of the Owner, be declared unacceptable. B. Bid Forms, Appendices, and enclosures that are improperly prepared may, at the discretion of Owner, be declared unacceptable. C. Failure to provide security deposit, bonding or insurance requirements may, at the discretion of Owner, be waived. D. Bids are by invitation, only from selected bidders. Bids from unsolicited bidders may be returned. BID ENCLOSURES/REQUIREMENTS 7.01 SECURITY DEPOSIT A. Bids shall be accompanied by a security deposit as follows: 1. Bid Bond of a sum no less than 5 percent of the Bid Amount on AIA A310 Bid Bond Form or standard surety company form, or: certified bank check for 5 percent of bid amount made payable to the Owner. B. The security deposit will be returned after delivery to the Owner of the required Performance and Payment Bond(s) by the accepted bidder, C. Include the cost of bid security in the Bid Amount. D. If no contract is awarded, all security deposits will be returned. 7.02 PERFORMANCE ASSURANCE A. Accepted Bidder: Provide a Performance and Payment bond as described in Document 00 73 00 - Supplementary Conditions. 7.03 SALES AND USE TAXES A. This is a sales tax-free construction project. Bidders shall NOT include state sales taxes in their proposals. Owner will issue a state sales tax exemption certificate for all materials purchased for the project and will issue the appropriate tax exemption certificates and authorization letters to the Contractors and all subcontractors performing work on the project. Tax exemption certificates are applicable only for the specific project for which the certificates are issued. The Contractors shall provide a listing to the Owner of all appropriate subcontractors which are qualified to use the tax exemption certificate. The Contractors and Gates Park Pro Shop Reroofing Project#09025 00 21 13 City of Waterloo, Department of Leisure Services INSTRUCTIONS TO BIDDERS Waterloo, Iowa Page 4 of 5 subcontractors may make copies of the tax exemption certificate and may provide a copy to each supplier providing construction material. Materials for this contract may then be purchased free from sales tax. Suppliers shall retain this certificate for at least three years. 7.04 ADDITIONAL BID INFORMATION A. The selected bidder will be requested to complete the Supplements To Bid Forms within 24 hours after submission of bids. B. Equal Opportunity compliance is required for this project and is a part of these specifications. A minimum goal is five (5) percent of the subcontract bids to be awarded to minority or women-owned business enterprises. 1 MBE/WBE Contract Compliance Program: A copy of the Waterloo/Cedar Falls Minority and Women Business Enterprise Constriction and Maintenance Guide (Directory) is available from the City of Waterloo Contract Compliance Officer, 602 Mulberry, Waterloo, Iowa. C. Bidders shall submit the following Supplements with the Bid submission: 1. Each bidder submitting a bid shall enclose an executed Minority and/or Women Business enterprise Pre-Bid Contact Information Form (copy bound herein). OFFER ACCEPTANCE/REJECTION 8.01 DURATION OF OFFER A. Bids shall remain open to acceptance and shall be irrevocable for a period of thirty (30) days after the bid closing date. 8.02 ACCEPTANCE OF OFFER A. Owner reserves the right to accept or reject any or all offers. B. After acceptance by Owner, Architect on behalf of Owner, will issue to the successful bidder, a written Notice to Proceed. END OF INSTRUCTIONS TO BIDDERS Gates Park Pro Shop Reroofing Project#09025 00 21 13 City of Waterloo, Department of Leisure Services INSTRUCTIONS TO BIDDERS Waterloo, Iowa Page 5 of 5 SECTION 00 41 00 BID FORM THE PROJECT AND THE PARTIES 1.01 TO: A, Owner 1, City of Waterloo, Department of Leisure Services 1.02 FOR: A, Gates Park Pro Shop Reroofing 1.03 DATE: (Bidder to enter date) 1.04 SUBMITTED BY: (Bidder to enter name and address) A. Bidder's Full Name 1, Address Fax 2. City, State, Zip Phone 1.05 OFFER A. Having examined the Place of The Work and all matters referred to in the Instructions to Bidders and the Contract Documents prepared by INVISION Architecture for the above mentioned project, we, the undersigned, hereby offer to enter into a Contract to perform the Work for the Sum of: B. dollars C. ($ ), in lawful money of the United States of America, D. We have included the required security deposit as required by the Instruction to Bidders. 1.06 ACCEPTANCE A, This offer shall be open to acceptance and is irrevocable for thirty days from the bid closing date. B. If this bid is accepted by Owner within the time period stated above, we will: 1 Execute the Agreement within seven days of receipt of Notice of Award. 2. Furnish the required bonds within seven days of receipt of Notice of Award. 3, Commence work within seven days after written Notice to Proceed of this bid. 1.07 CONTRACT TIME A. If this Bid is accepted, we will: B. Complete the Work in calendar days from Notice to Proceed. (Bidder to enter number of days.) Project Name Project#09025 00 41 00 Location BID FORM Waterloo, Iowa Page 1 of 2 1.08 ALTERNATES A. Alternate No. 1 - Roofing Demolition 1. ADD/DEDUCT dollars, ($ ), in lawful money of the United States of America. 1.09 ADDENDA A. The following Addenda have been received. The modifications to the Bid Documents noted below have been considered and all costs are included in the Bid Sum. 1. Addendum # Dated 2, Addendum# Dated 3. Addendum# Dated 4. Addendum# Dated 1.09 UNIT PRICES A. The following are Unit Prices for specific portions of the Work as listed. The following is the list of Unit Prices: B. ITEM DESCRIPTION - UNIT QUANTITY - UNIT PRICE C. Unit Price No. 1: Over-demolition - per square foot per inch -$ 1.10 BID FORM SIGNATURE(S) A. (Bidder- print the full name of your firm) B. (Authorized signing officer, Title) END OF BID FORM Project Name Project#09025 00 41 00 Location BID FORM Waterloo, Iowa Page 2 of 2 CERTIFIED MBE / WBE CONTRACTORS CITY OF WATERLOO, IOWA L — j CONTRACT COMPLIANCE OFFICE Community Development Board ._ Carnegie Annex,Suite 202 620 Mulberry Street Waterloo,Iowa 50703 City WEB Site: www.ci.waterloo.ia.us Contract Compliance WEB Site for listing updates: http://www.wplwloo.lib.ia.us/contractcompliance/ Contact: Louis Starks, Contracts and Grants Coordinator — Email: louis.starks(awaterloo-ia.org Phone: (319) 291-4429 Fax: (319) 291-4431 MBE/WBE Certified Contractors List — Page 1 o f 7 CERTIFIED MBE CONTRACTORS CARTER ELECTRIC 725 Adams'Street Waterloo, IA 50703 Phone: (319) 232-9808 Pager: (319) 235-4021 Contact: Derrick Carter _ Specializing in: ELECTRICAL CONTRACTOR COCKHREN ROOFING 1708 Newell Street Waterloo, IA 50703 Phone: (319)232-7513 Contact: James Cockhren Specializing in: ROOFING CULPEPPER ELECTRIC 1731 Cottage Grove Avenue '— Waterloo, IA 50707 Phone: (319)235-0885 Fax: (319) 236-8177 Contact: Martin Culpepper Certified: City of Waterloo Certified MBE, Licensed Electrician Specializing in: -- ELECTRICAL CONTRACTOR DANIELS HOME IMPROVEMENT 339 Albany Street _ Waterloo, IA 50703 Phone: (319) 833-0118 Contact: Sammy Daniels Specializing in: ALL TYPES OF CONCRETE FLATWORK, POURED WALLS ALL TYPES, FOOTINGS, MBE/WBE Certified Contractors List Page 2 of 7 LIGHT DEMOLITION CERTIFIED MBE CONTRACTORS DENTER CORPORATION 426 Beech Street -- Waterloo, IA 50703 Phone: (319)236-9075 FAX: (319)236-0515 Contact: Terry Phillips Certified: City of Waterloo Certified MBE,Iowa DOT, TSB Certified Specializing in: COMMERCIAL AND RESIDENTIAL DEMOLITION, CONCRETE PAVING, DRIVEWAYS, TRUCKING(ALL TYPES), GENERAL CONSTRUCTION GREER'S WORKS 2003 Plainview Street Waterloo, IA 50703 Phone: (319) 233-4701 Contact: Willie Greer Specializing in: DRIVEWAYS, SIDEWALKS, CARPENTRY, ROOFING, GENERAL CONSTRUCTION ELIAS GROVER CEMENT CONTRACTORS 116 Carl Street Waterloo, IA 50703 Phone: (319)234-3839 Contact: Elias Grover, Owner Specializing in: ALL TYPES OF CONCRETE FLATWORK,ASPHALT, GENERAL CONSTRUCTION CLINTON JONES TRUCKING ►- 1202 Mulberry Street Waterloo,IA 50703 Phone: (319)235-4401 Contact: Clinton Jones Specializing in: MBE/WBE Certified Contractors List Page 3 of 7 L. 1 L 1 TRUCKING CERTIFIED MBE CONTRACTORS LOVE'S ENTERPRISE 835 West Fifth St. P.O. Box 246 Waterloo, IA 50704 Phone: (319) 233-3260 Contact: David Love Certified: Iowa DOT, City of Waterloo Certified MBE -.. Specializing in: CONCRETE PAVING,ASPHALT, DRIVEWAYS, SIDEWALKS, TRUCKING OLD GREER'S WORKS 2309 Springview Street Waterloo, IA 50707 Phone: (319)233-2150 Contact: David L. Greer, Sr. Specializing in: GENERAL CONSTRUCTION PAULINE COMPANY, INC. 139 Clark Street P. O. Box 1623 Waterloo, IA 50703 Phone: (319)236-2345 FAX: (319)236-1568 email: DJToay@aol.com Certified: Targeted Small Business, Iowa DOT, City of Waterloo Certified MBE Contact: W.C. Stokes, Owner Specializing in: EROSION CONTROL, TRUCKING, GUARDRAIL, CLEARING AND GRUBBING CONCRETE PAVING,ASPHALT, CURB AND GUTTER, DRIVEWAYS, SIDEWALKS, MASONRY WORK, ROOFING, CD BASKETS, ROADWAY PIPE, TILE LOCATING, REVETMENT, SHOULDERS, FIELD FENCE, GENERAL CONSTRUCTION WORK MBE/WBE Certified Contractors List Page 4 of 7 CERTIFIED MBE CONTRACTORS QUICK CONSTRUCTION 217 Bates Street -- Waterloo, IA 50703 Phone: (319) 232-5564 Contact: Leroy Harrington Specializing in: ALL TYPES OF CONCRETE FLATWORK AND GENERAL CONSTRUCTION CHARLIE SCHAUF TRUCKING 627 Adams Street Waterloo, IA 50703 Phone: (319) 232-4717 Contact: Charles Schauf Specializing in: TRUCKING ARTHUR TAYLOR 701 Albany Street Waterloo, IA 50703 Phone: (319) 235-0041 Contact: Arthur Taylor Certified: City of Waterloo Certified MBE GENERAL REHABILITATION MBE/WBE Certified Contractors List Page 5 of 7 CERTIFIED WBE CONTRACTORS ATLAS PAINTING, INC.* 911 Sycamore Street P.O. BOX 65 Waterloo, IA 50704 Phone: (319) 232-9164 Specializing in: COMMERCIAL AND INDUSTRIAL PAINTING GLADYS HEASLEY TRUCKING* (Currently Inactive as of 4/26/04) 807 W. Mullan Avenue Waterloo, IA 50701-5926 Phone: (319)234-8555 Cell: (319) 493-0208 Contact: Gladys Heasley Certified: City of Waterloo Certified WBE Specializing in: TRUCKING PETERMAN & HAES CARPET ONE* — 4003 University Avenue Waterloo, IA 50701 Phone : (319)233-6131 FAX: (319)233-6133 email: JR11486@cfu.net Certified: City of Waterloo WBE Contact : Carol Reese Specializing in: FLOOR COVERING MBE/WBE Certified Contractors List Page 6 of 7 CERTIFIED WBE CONTRACTORS WATCO CONSTRUCTION, INC.* 2920 Texas Street Waterloo, IA 50702 Phone : (319)233-7481 Certified: City of Waterloo WBE Contact : Patricia J. Kimball Specializing in: STORM SEWER, INLETS, DRAIN TILE, WATER MAIN, SANITARY SEWER, INTAKE STRUCTURES * DENOTES WOMEN BUSINESS ENTERPRISE MBE/WBE Certified Contractors List Page 7 of 7 3 o C Cl) O L E O O O O o O LE y O a) RS " co U O cr m a) CD L O C m Q O c a) y 0.0 Q O N Q a) w 7 O �' — 3 Ec w C U N o- ct N 0 O O 2 m 2 a) 7 a = ❑ C a) a)- `E E U p C U O) O- w N O O @ co 7 .: — C ( O O > >' V C O co 0 O N U O N 7 O °) N O O) 3 E os ❑ L � 3 0 E a) L � L a) O_.0 O t4 -C COo rn c a) o Y3 aim E `m f, E CO a) to o O N @ y0 W N C o C O 3 c DC l w -O m t a U CL nL °n mli a) Q W w L ) O oo 2LO cv) ° a) ~Z z° yu, o � o c c .Q � - W w Ce L o C f6 a) L N a) dZ o3 -ate c ; m _c � pW } O o W H 22m C • o > g a7 ° mN F- Q = � ° .g cow E . C9 � W _ m ID .N 2 t r o m Z_ d m NO u�i >, ° � a) '_Ea' 2aE`) > W a cn 0 W Z i,' mco LEuf) 5cn 0a = Z Z - .a c. n'� 3 0 � NWT o yOa W >, 3 0 .oa) 0) 0 ZN CC m a) L COf- "o > 6E4 W .. >, a L >_ o o) n$) a Z 3 a W O � � it) Ccc � � Na z c s c m co rn o W 0 a) W TA Q = ,3 a E N a) j Q y CO > CO CO C N ' a E a) C LL W CC Z C c') "a (7) c 3 a W a. 2 O `) OU U C d W m CO O W m ocl �- U � � � -J 2 a + > co o coL U v E O CO G C O c c o .n w m e Q O N LII .n a 3 m 2 `o H V re E W � E o a) a`) L _c L V 2 aw0 o ° W m a) > m L Q co Jm m a .° 20) ce U d '2 n� Na N 2 Z = aWC La) ''i c o Co m .0 ix L O o f N N p co C •a w O a) ' Z O 6 C 3 F- >o,N U O7 a Co O W C O Q U E@ .� '� L a) a a) C E o fx m C fn J L- 7 O Es = L V — .�gi��eyo -.a. O .8 p Z Q O N a) C O W p _ a) i � €} V m O C �� V) N U > O Z �f o C L N • a) N C 0 �iS iI��, m 2 _a) O L U -3 (6 a y a) a) �.lair? E QC C m 0 0 O .0 O 'V) -0 W E \ii a Z a n 0 ai n >- W o C E CO MOW U 0 w _ U)U 0a) (6 O ` 'O a) C w c1 C Cl) (I) 0 O 03 a 0 Z _0 -0 _ .� U) a) C O U U a) c° 2 D O O E (o ` 0 c N ° ' m ` co Q °U o a U 'tn CU6 c22 LL m C 0 ' _U Q O LL 0 -0 3 o > v o_la -0 � o o Z � -0 E U E o__c .- � vi3 Ccc°i) -6_ mcw U 0 w .)) c°i E me m a, F= m w U m C o 0 -O — -Ocna)') @ o E Q 2 • -0 UmoW • a) C L . c ° •U O ° m r, Lu fx a) O co -0 W 7.Y p O N L 2 O m a) 0 Q " 0 c m m O W Q'v, w c ° co— z Oa c c @ o 22 3La O m O U �. co 0 0 a) E � � U m � � ° aim actin c n o _c - c cu w >, a) C E a) -o U C ° E co o co C Ct N a CO m .(2 E o Y Q 0 CO o f o >, - 0 a) -0 -- o c E F- U c Z `) 2a_ 0-� income o Z � � cou°)i v°i o � Nm O cm o 0 c N � o 0 0 3 ° m � a) E -o O. Ce w '5 L •3 3 = � wr U CO c o o m U) co ° a) no W I O O U .E in T "O Q' a3 00 as 0 N Cl) U O N o_ Cl) N O U C a) J ,«. • C L L C N 3 > O a) U "O a) W Co E N C O_ a) O n. cn -0 Z m a) co _ '� m e w CO o) a) — CdOC o0- c`a@ c 0 a) > 3 a mW 0 co rn (4N a Ill 0 3 c a) C �j u°i c r` � m 3 w `= tn.. = o a ti ° ° m . EtE • a) ., a) w w � Ewo m E mo) Na) 2 Z ? 0 � O R o EW o 0 aci I— m asm :p 0 .E 0 n. W Z o ° Z W 3 � co •_ c . Cr) c cow Z t C U � �� a>i W � CO co U a) a) a) ) N 0 a) oEa) Ow, .,a) •oWca) u) U • � ow U oa°icn Cl) CO WQ 0ma a) -0 .5c o w co a) c aa) � � � ca �- ¢ c > � w E - - oa) � m � .u) 2 � o ° E Z o ca) o ° c Z oa a a a) o n o * ° ° c .- ._,a.) o w aai � O � � � Oo Oa) a) Cta)ct aoic � >,� > N > n.`o- oho mLL ,- E = z ° aaa) E ion a) E co > of i 3 c o rn c a ° Q o Z a) •/c U w a) ° o ca m c°i c o c C 0 c ° ° cn ° v) W LL a) t6 H (� cn to O N .o O L cn ,- L U T U >, c — CO H ` ° 0 c Q a) c = y � co W p mom° °) � � ° ` � � �.g U o =6 V ° ° o � a E n3 E o m LLi c •c3 � � > o o cL° L c cm o mH c o aa)) OCVa 0 a) L m m u) mu_ E ca N ac6) o > oY m o cr a) 3 c o • m -- 20 m � o o Do 0) co w o � Z � 3 � m a) 0 3 Q o °c' V o � mhC ° c 2 • o EF- 0om fa) a) � o po _� wo ° cn o `er m as o a a) >, coa c -O a) ` � c o cU -0 m ° COc o o > � a) � -O a) C0 E ° ° ° way ° O E 0- > ° a' o c a) cn ° N d a) Ct c c `) U cn o o ° O- 3 U -- a) ° U W V a) cn w -7 = °U .5Lcn c CD °i o >' U -�`O •C >' E a`Ni -E 'fl N Lai coo) � � ° o = aa)) »- ° ca ° � � _ = c.) U ' .6 o o E •c dp � W a) co U v) °° .� m 0 n3 > �' � '313a ° •3 •• o >'� 7 11. y 0in o wU o � � .0 o - Eo 'a> _ coi _aQ4- � a) na m o .a) o (- ° O N W ° a5 ° w c a) U a) a) = o L •� U • C U a) ° Q C a) E ° z t m ° C co m O oc N .> cn O z , , 2 'c- o a o N C oc � WL°Lv°) . aioE ° wU -003 m800c ° o00 U) oQ d) 0 o co O a) c cn N c O c cn a) C a) O SEc6 � cnoy � coco -° w@ a) a ° N � •N0U � o@coc@ o � Eo):oc o m -O a) 0 c ° r` ayi re la too z a�i (I)„, _c 2 � = •- coo � m -6w ° C co In = U � cn o 00E UC Cc w CO 000 -0v0i wW � m 0- w � � o - > ° O_ Q L rn .- - ° -O - >,•- a) m w 3 E a E m $ 0 0 •� ° m v) o co a) W aa) ._ 0.)w Q JD L W o S a) o o L m c c� O ct ° o - c ° , O a) .- co U ccp o o O � w .. w U E >,U o) 0 c -- as a c6 o W C .52 U ° > U c C W O m o 'C c ° - U ° < +L.' Lt2 C a O m co N N < y «�O. 0 > Q .. m � Z 2 a C < ° Q o m -0 D)m 0 0 - $ Lo 0 va .E v°) 0m o m ai _o w 0_ ca -0 C) -0 •0 E' C c .'vo) c) pU V o t U a) a) ° •� o 0 m Qco E .C: o -, s _, ccow 0 > o U a) a`) ac) w 0 E Ec 'E U - Eo < a`) ° U � H cam) 4_ I- a) ° -0 w c o2 E 'L .0 ca co . O c l a) .— a) ca Z c O rl 0. a 15 ,- U@ N O _o U M .2. 4 a) c.f) W H O Cl) - w �lP100\O CITY OF WATERLOO CERTIFICATION OF MBE/WBE ACCOMPLISHMENT (To be completed by the Prime Contractor and submitted with the final documents) Contract: Prime Contractor: Letting Date: Completion Date: MBE/WBE Commitment Listed on Pre-Bid Form: $ MBE/WBE Company Dollars Committed Dollar Amount Paid % of Goal $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ $ TOTAL (Name) the (Corporate Officer) of certify that the MBE/WBE _ (Prime Contractor) accomplishment to be true and accurate. (Date) (Signature) Form CCO-6 (11-28-2001) SECTION 00 50 00 CONTRACTING FORMS AND SUPPLEMENTS PART 1 GENERAL 1.01 AGREEMENT AND CONDITIONS OF THE CONTRACT A. The Agreement is based on AIA A101. B. The General Conditions are based on AIA A201, 1.02 FORMS A. Use the following forms for the specified purposes unless otherwise indicated elsewhere in the Contract Documents. B. Post-Award Certificates and Other Forms: 1, Schedule of Values Form: AIA G703. 2, Application for Payment Form: AIA G702 and G703. 1.03 REFERENCES A. AIA A101 -Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum; 2007. B. AIA A201 -General Conditions of the Contract for Construction; 2007, C. AIA G702 -Application and Certificate for Payment; 1992. D. AIA G703-Continuation Sheet; 1992. PART 2 PRODUCTS -NOT USED PART 3 EXECUTION -NOT USED END OF SECTION Gates Park Pro Shop Reroofing Project#09025 00 50 00 City of Waterloo, Department of Leisure Services CONTRACTING FORMS AND SUPPLEMENTS Waterloo, Iowa Page 1 of 1 SECTION 00 73 00 SUPPLEMENTARY CONDITIONS PART 1 GENERAL 1.01 SUMMARY 1.02 These Supplementary Conditions amend and supplement the General Conditions defined in Document 00 72 00 and other provisions of the Contract Documents as indicated below. All provisions that are not so amended or supplemented remain in full force and effect. 1.03 RELATED SECTIONS A. Section 00 50 00 - Contracting Forms and Supplements. PART 2 PRODUCTS -NOT USED PART 3 EXECUTION MODIFICATIONS TO AIA A201 4.01 ARTICLE 3.6 -TAXES A. Add the following subparagraph: 1. This is a sales tax-free construction project. Bidders shall NOT include state sales taxes in their proposals. Owner will issue a state sales tax exemption certificate for all materials purchased for the project and will issue the appropriate tax exemption certificates and authorization letters to the Contractors and all subcontractors performing work on the project. Tax exemption certificates are applicable only for the specific project for which the certificates are issued. The Contractors shall provide a listing to the Owner of all appropriate subcontractors which are qualified to use the tax exemption certificate. The Contractors and subcontractors may make copies of the tax exemption certificate and may provide a copy to each supplier providing construction material. Materials for this contract may then be purchased free from sales tax. Suppliers shall retain this certificate for at least three years. 4.02 3.7 PERMITS, FEES, NOTICES AND COMPLIANCE WITH LAWS A. 3.7.5: Modify§3.7.5 by adding the underlined words, so that the section now reads as follows: B. 3.7.5 If, in the course of the Work, the Contractor knowingly encounters and recognizes human remains, burial markers, archeological sites or previously undelineated wetlands not indicated in the Contract Documents, the Contractor shall immediately suspend any operations that would affect them and shall notify the Owner and Architect. Upon receipt of such notice, the Owner shall promptly take any action necessary to obtain governmental authorization required to resume the operations. The Contractor shall continue to suspend such operations until otherwise instructed by the Owner but shall continue with all other operations that do not affect those remains or features. Requests for adjustments in the Contract Sum and Ccntract Time arising from the existence or good faith belief of such existence of such remains c r features may be made as provided in Article 15. C. 3.7.1: Owner shall obtain Building Permit. 4.03 3.10 CONTRACTOR'S CONSTRUCTION SCHEDULES A. 3.10.2: Delete the last sentence of§3.10.2 so that the section now reads as follows: B. 3.10.2 The Contractor shall prepare a submittal schedule promptly after being awarded the Contract and thereafter as necessary to maintain a current submittal schedule, and shall submit the schedule(s)for the Architect's approval. The Architect's approval shall not unreasonably be Gates Park Pro Shop Reroofing Project#09025 00 73 00 City of Waterloo, Department of Leisure Services SUPPLEMENTARY CONDITIONS Waterloo, Iowa Page 1 of 3 delayed or withheld. The submittal schedule shall (1) be coordinated with the Contractor's construction schedule, and (2) allow the Architect reasonable time to review submittals. 4.04 ARTICLE 9 -PARA. 9.3-APPLICATIONS FOR PAYMENT A. Add the following subparagraph: 1. 9,3.2.1: Payments will be made to the extent of the substantiated value of the work performed in the previous month less a retainage amount of five (5) percent of the value of the work performed. At Substantial Completion, 95 percent of the contract amount shall be due and payable. 4.05 9.5 DECISIONS TO WITHHOLD CERTIFICATION A. 9.5,3: Delete in its entirety. 4.06 9.6 PROGRESS PAYMENTS A. 9.6.4: Delete the first two sentences of§9.6,4 so that it now reads as follows: B. 9.6.4 The Owner has the right to request written evidence from the Contractor that the Contractor has properly paid Subcontractors and material and equipment suppliers amounts paid by the Owner to the Contractor for subcontracted Work. If the Contractor fails to furnish such evidence within seven days, the Owner shall have the right to contact Subcontractors to ascertain whether they have been properly paid. Neither the Owner nor Architect shall have an obligation to pay or to see to the payment of money to a Subcontractor, except as may otherwise be required by law. 4.07 ARTICLE 11.5 -PERFORMANCE BOND AND PAYMENT BOND A. Add the following subparagraph: 1 11.5.3: The bond value requirements are as follows; a. Provide a 100 percent Performance Bond on AIA A312, or standard surety form b. Provide a 100 percent Payment Bond on AIA A311, or standard surety form. 4.08 13.1 GOVERNING LAW A, 13.1: Delete the words following "where the Project is located" in §13.1 so that it now reads as follows: B. 13.1 The Contract shall be governed by the law of the place where the Project is located. 4.09 13.7 TIME LIMITS ON CLAIMS A. 13.7: Strike§13.7 in its entirety. 4.10 13.7 COMMENCEMENT OF STATUTORY LIMITATIONS PERIOD A. 13,7.1 As between Owner and Contractor: 1, Before Substantial Completion, As to acts or failures to act occurring prior to the relevant date of Substantial Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion; 2, Between Substantial Completion and Final Certificate for Payment. As to acts or failures to act occurring subsequent to the relevant date of Substantial Completion and prior to issuance of the final Certificate for Payment; any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than the date of issuance of the final Certificates of Payment; and 3 After Final Certificate for Payment. As to acts of failures to act occurring after the relevant date of issuance of the final Certificate of Payment, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than the date of any act or failure to act by the Contractor Gates Park Pro Shop Reroofing Project#09025 00 73 00 City of Waterloo, Department of Leisure Services SUPPLEMENTARY CONDITIONS Waterloo, Iowa Page 2 of 3 pursuant to any Warranty provided under Section 3.5, the date of any correction of the Work or failure to correct the Work by the Contractor under Section 12.2, or the date of actual commission of any other act of failure to perform any duty or obligation by the Contractor or Owner, whichever occurs last. 4.11 INSURANCE A. Add the following subparagraph: 1 11.1.4 -Minimum limits for liability insurance required to be carried by the coitractor are as follows: a. General Liability: $1,000,000 Combined Single Limit per occurrence; $1 000,000 Aggregate. b. Automobile Liability: $1,000,000 Combined Single Limit. c. Worker's Compensation: Statutory Benefits; $100,000 Coverage B. d. Umbrella Liability: $1,000,000 Combined Single Limit; $2,000,000 Aggregate. 2. Provide Certificate of Insurance acceptable to the Owner specifying all insurance limits prior to beginning any site mobilization or work on site. The insurance shall be provided through a company rated A or better as determined by the A. M. Best Company. The Owner and INVISION Architecture shall be named as additional Insured. B. The Owner shall provide property insurance (Builder's Risk Insurance)for this project. ADDITIONAL ARTICLE - DEFINITIONS 5.01 Add the following: A. Products: Means new material, machinery, components, equipment, fixtures, and systems forming the Work, but does not include machinery and equipment used for preparation, fabrication, conveying and erection of the Work. Products may also include existing materials or components required for reuse. B. Furnish or Supply: To supply and deliver, unload, inspect for damage. C. Install: To unpack, assemble, erect, apply, place, finish, cure, protect, clean, anc ready for use. D. Provide: To furnish or supply, plus install. E. Project Manual: The Project Manual is the volume usually assembled for the Wcrk which includes the Bid Documents, Contract Documents, and Specifications. END OF DOCUMENT Gates Park Pro Shop Reroofing Project#09025 00 73 00 City of Waterloo, Department of Leisure Services SUPPLEMENTARY CONDITIONS Waterloo, Iowa Page 3 of 3 SECTION 01 10 00 SUMMARY PART1 GENERAL 1.01 PROJECT A. Project Name: Gates Park Pro Shop Reroofing. B. Owner's Name: City of Waterloo, Department of Leisure Services. C. Architects Name: INVISION Architecture. — D. Structural Engineers: Bishop Consulting Engineers, P.C. E. The Project consists of the construction to reroof the existing pro shop structure including general construction. — 1.02 CONTRACT DESCRIPTION A. Contract Type: A single prime contract based on a Stipulated Price as described in Section 00 50 00-Contracting Forms and Supplements. 1.03 DESCRIPTION OF ALTERATIONS WORK A. Scope of demolition and removal work is shown on drawings and specified in Section 02 41 00. 1.04 OWNER OCCUPANCY A. Owner intends to continue to occupy adjacent portions of the existing building during the entire construction period. — B. Owner intends to occupy the Project upon Substantial Completion. C. Cooperate with Owner to minimize conflict and to facilitate Owner's operations. D. Schedule the Work to accommodate Owner occupancy. 1.05 CONTRACTOR USE OF SITE AND PREMISES A. Construction Operations: Limited to areas noted on Drawings. B. Arrange use of site and premises to allow: 1. Owner occupancy. 2. Work by Others. 3. Use of site and premises by the public. C. Provide access to and from site as required by law and by Owner: 1. Emergency Building Exits During Construction: Keep all exits required by code open during construction period; provide temporary exit signs if exit routes are temporarily altered. D. Existing building spaces may not be used for storage. E. Time Restrictions:1. Coordinate hours of especially noisy exterior work with Owner. F. This is a tobacco free project site as required by State of Iowa Law. Use of tobacco is strictly prohibited on site. General Contractor shall coordinate enforcement efforts. PART 2 PRODUCTS-NOT USED PART 3 EXECUTION -NOT USED END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 10 00 City of Waterloo, Department of Leisure Services SUMMARY Waterloo, Iowa Page 1 of 1 _ SECTION 01 20 00 PRICE AND PAYMENT PROCEDURES PART 1 GENERAL 1.01 SECTION INCLUDES A. Procedures for preparation and submittal of applications for progress payments. B. Documentation of changes in Contract Sum and Contract Time. C. Change procedures. D. Procedures for preparation and submittal of application for final payment, 1.02 SCHEDULE OF VALUES A. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Architect for approval. B. Forms filled out by hand will not be accepted. C, Submit a printed schedule on AIA Form G703-Application and Certificate for Payment Continuation Sheet. Contractor's standard form or electronic media printout will be considered. D. Submit Schedule of Values in duplicate within 15 days after date of Owner-Contractor Agreement. E. Format: Utilize the Table of Contents of this Project Manual. Identify each line item with number and title of the specification Section. Identify General Conditions with a separate line item. F. Revise schedule to list approved Change Orders, with each Application For Payment. 1.03 APPLICATIONS FOR PROGRESS PAYMENTS A. Payment Period: Submit at intervals stipulated in the Agreement. B. Electronic media printout including equivalent information will be considered in lieu of standard form specified; submit sample to Architect for approval. C. Forms filled out by hand will not be accepted. D. Present required information in typewritten form. E. Form: AIA G702 Application and Certificate for Payment and AIA G703-Continuation Sheet including continuation sheets when required, F. Execute certification by signature of authorized officer. G. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored Products. H. List each authorized Change Order as a separate line item, listing Change Order number and dollar amount as for an original item of Work. I. Submit three copies of each Application for Payment. J. Include the following with the application: 1, Partial release of liens from major Subcontractors and vendors. 2. Certificates attesting to insurance of off-site stored products included in payment application. Gates Park Pro Shop Reroofing Project#09025 01 20 00 City of Waterloo, Department of Leisure Services PRICE AND PAYMENT FROCEDURES Waterloo, Iowa Page 1 of 3 K. When Architect requires substantiating information, submit data justifying dollar amounts in question. Provide one copy of data with cover letter for each copy of submittal, Show application number and date, and line item by number and description. 1.04 MODIFICATION PROCEDURES A. For minor changes not involving an adjustment to the Contract Price or Contract Time, Architect will issue instructions directly to Contractor. B. Architect will advise of minor changes in the Work not involving an adjustment to Contract Sum or Contract Time as authorized by the Conditions of the Contract by issuing supplemental instructions on AIA Form G710. C. For other required changes, Architect will issue a document signed by Owner instructing Contractor to proceed with the change, for subsequent inclusion in a Change Order. 1, The document will describe the required changes and will designate method of determining _ any change in Contract Sum or Contract Time. 2. Promptly execute the change. D. For changes for which advance pricing is desired,Architect will issue a document that includes a detailed description of a proposed change with supplementary or revised drawings and specifications, a change in Contract Time for executing the change with a stipulation of any overtime work required and the period of time during which the requested price will be considered valid, Contractor shall prepare and submit a fixed price quotation within 15 days. E. Contractor may propose a change by submitting a request for change to Architect, describing the proposed change and its full effect on the Work, with a statement describing the reason for the change, and the effect on the Contract Sum and Contract Time with full documentation and a statement describing the effect on Work by separate or other contractors. Document any requested substitutions in accordance with Section 01 60 00. F Computation of Change in Contract Amount: As specified in the Agreement and Conditions of the Contract. 1. For change requested by Architect for work falling under a fixed price contract, the amount will be based on Contractor's price quotation. 2. For change ordered by Architect without a quotation from Contractor, the amount will be determined by Architect based on the Contractor's substantiation of costs as specified for Time and Material work. G. Substantiation of Costs: Provide full information required for evaluation. 1. On request, provide following data: a. Quantities of products, labor, and equipment, b. Taxes, insurance, and bonds. c. Overhead and profit. d. Justification for any change in Contract Time. e. Credit for deletions from Contract, similarly documented. 2. Support each claim for additional costs with additional information: a. Origin and date of claim. b. Dates and times work was performed, and by whom. c. Time records and wage rates paid, d. Invoices and receipts for products, equipment, and subcontracts, similarly documented. H. Execution of Change Orders: Architect will issue Change Orders for signatures of parties as provided in the Conditions of the Contract. I. After execution of Change Order, promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Gates Park Pro Shop Reroofing Project#09025 01 20 00 City of Waterloo, Department of Leisure Services PRICE AND PAYMENT PROCEDURES Waterloo, Iowa Page 2 of 3 Contract Sum, J. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust times for other items of work affected by the change, and resubmit. K. Promptly enter changes in Project Record Documents, 1.05 APPLICATION FOR FINAL PAYMENT A. Prepare Application for Final Payment as specified for progress payments, identifying total adjusted Contract Sum, previous payments, and sum remaining due. B. Application for Final Payment will not be considered until the following have been accomplished: 1. All closeout procedures specified in Section 01 70 00, PART 2 PRODUCTS -NOT USED PART 3 EXECUTION -NOT USED END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 20 00 City of Waterloo, Department of Leisure Services PRICE AND PAYMENT PROCEDURES Waterloo, Iowa Page 3 of 3 SECTION 01 22 00 UNIT PRICES PART 1 GENERAL 1.01 SECTION INCLUDES A. List of unit prices, for use in preparing Bids. B. Measurement and payment criteria applicable to Work performed under a unit price payment method, 1.02 COSTS INCLUDED A. Unit Prices included on the Bid Form shall include full compensation for all required labor, products, tools, equipment, plant, transportation, services and incidentals; erection, application or installation of an item of the Work; overhead and profit. 1.03 MEASUREMENT OF QUANTITIES A. Measurement methods delineated in the individual specification sections complement the criteria of this section. In the event of conflict, the requirements of the individual specification section govern. B. Take all measurements and compute quantities Measurements and quantities will be verified by Architect. C. Assist by providing necessary equipment, workers, and survey personnel as required, 1.04 PAYMENT A. Payment for Work governed by unit prices will be made on the basis of the actual measurements and quantities of Work that is incorporated in or made necessary by the Work and accepted by the Architect, multiplied by the unit price. 1.05 SCHEDULE OF UNIT PRICES A. Unit Price Number One: Over-demolition of unsuitable polyisocycanurate insulation and replacement with suitable polyisocycanurate insulation properly installed, beyond amount identified in the documents. Price to be stated as cost per sq ft per inch.removed and replaced. PART 2 PRODUCTS -NOT USED PART 3 EXECUTION -NOT USED END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 22 00 City of Waterloo, Department of Leisure Services UNIT PRICES Waterloo, Iowa Page 1 of 1 SECTION 01 23 00 ALTERNATES PART 1 GENERAL 1.01 SECTION INCLUDES A, Procedures for pricing alternates 1.02 RELATED REQUIREMENTS A. Procedures for pricing alternates 1.03 ACCEPTANCE OF ALTERNATES A. Alternates quoted on Bid Forms will be reviewed and accepted or rejected at Owrer's option. Accepted alternates will be identified in the Owner-Contractor Agreement. B. Coordinate related work and modify surrounding work to integrate the Work of each alternate. 1.03 SCHEDULE OF ALTERNATES A. Alternate No. 1 - Roofing Demolition 1. Deduct the bid amount cost to delete the roofing tear-off down to the roof deck. Instead, spud off all gravel and place the new insulation on top of the existing roofing. Include in the bid amount replacing 200 square feet of existing wet insulation. Use one layer of 2 inch new polyisocycanurate insulation on top of existing roof in lieu of two layers of 1 1/2 inch polyisocycanurate insulation as specified. 2. Base Bid: As indicated. 3. Refer to Section 01 22 00 - Unit Prices for additional requirements. PART 2 PRODUCTS-NOT USED PART 3 EXECUTION -NOT USED END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 23 00 City of Waterloo, Department of Leisure Services ALTERNATES Waterloo, Iowa Page 1 of 1 SECTION 01 30 00 ADMINISTRATIVE REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Preconstruction meeting. B. Progress meetings. C. Construction progress schedule. D. Submittals for review, information, and project closeout. E. Number of copies of submittals. F. Submittal procedures. 1.02 PROJECT COORDINATION A. Project Coordinator: General Contractor, B. Cooperate with the Project Coordinator in allocation of mobilization areas of site; for field offices and sheds, for construction access, traffic, and parking facilities. C. During construction, coordinate use of site and facilities through the Project Coordinator. D. Comply with Project Coordinator's procedures for intra-project communications; submittals, reports and records, schedules, coordination drawings, and recommendations; and resolution of ambiguities and conflicts. E. Comply with instructions of the Project Coordinator for use of temporary utilities and construction facilities. F. Coordinate field engineering and layout work under instructions of the Project Coordinator. G. Make the following types of submittals to Architect through the Project Coordinator: 1, Requests for interpretation. 2. Requests for substitution. 3. Shop drawings, product data, and samples. 4. Test and inspection reports. 5. Manufacturer's instructions and field reports. 6. Applications for payment and change order requests. 7. Progress schedules. 8. Coordination drawings. 9 Closeout submittals. PART 2 PRODUCTS -NOT USED PART 3 EXECUTION 3.01 PRECONSTRUCTION MEETING A. Architect will schedule a meeting after Notice of Award. B. Attendance Required: 1. Owner. 2. Architect. 3, Contractor. C. Agenda: Gates Park Pro Shop Reroofing Project#09025 01 30 00 City of Waterloo, Department of Leisure Services ADMINISTRATIVE REQUIREMENTS Waterloo, Iowa Page 1 of 4 1. Execution of Owner-Contractor Agreement. 2. Submission of executed bonds and insurance certificates. 3. Distribution of Contract Documents. 4. Submission of list of Subcontractors, schedule of values, and progress schedule. 5. Designation of personnel representing the parties to Contract, and Architect. 6. Procedures and processing of field decisions, submittals, substitutions, applications for payments, proposal request, Change Orders, and Contract closeout procedures. 7. Scheduling. D Architect will record minutes and distribute copies within four days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made. 3.02 PROGRESS MEETINGS A. Contractor to schedule and administer meetings throughout progress of the Work at minimum monthly intervals. B. Make arrangements for meetings, prepare agenda with copies for participants, preside at meetings. C. Attendance Required: Job superintendent, major Subcontractors and suppliers, :)wner, Architect, as appropriate to agenda topics for each meeting. D. Agenda: 1 Review minutes of previous meetings. 2. Review of Work progress. 3. Field observations, problems, and decisions. 4. Identification of problems that impede, or will impede, planned progress. 5. Review of submittals schedule and status of submittals. 6. Maintenance of progress schedule. 7. Corrective measures to regain projected schedules. 8. Planned progress during succeeding work period. 9. Maintenance of quality and work standards, 10. Effect of proposed changes on progress schedule and coordination. 11. Other business relating to Work. E. Architect to record minutes and distribute copies within four days after meeting to participants, with two copies to Architect, Owner, participants, and those affected by decisions made. 3.03 CONSTRUCTION PROGRESS SCHEDULE A. If preliminary schedule requires revision after review, submit revised schedule within 10 days. B. Within 20 days after review of preliminary schedule, submit draft of proposed complete schedule for review. 1. Include written certification that major contractors have reviewed and accepted proposed schedule. C. Within 10 days after joint review, submit complete schedule. D. Submit updated schedule with each Application for Payment. E. Submit updated schedule with each Application for Payment. 3.04 SUBMITTALS FOR REVIEW A. When the following are specified in individual sections, submit them for review: 1. Product data. 2. Shop drawings. 3 Samples for selection. Gates Park Pro Shop Reroofing Project#09025 01 30 00 City of Waterloo, Department of Leisure Services ADMINISTRATIVE REQUIREMENTS Waterloo, Iowa Page 2 of 4 4, Samples for verification. B. Submit to Architect for review for the limited purpose of checking for conformance with information given and the design concept expressed in the contract documents. C. Samples will be reviewed only for aesthetic, color, or finish selection. D. After review, provide copies and distribute in accordance with SUBMITTAL PROCEDURES article below and for record documents purposes described in Section 01 78 00-CLOSEOUT SUBMITTALS. 3.05 SUBMITTALS FOR INFORMATION A. When the following are specified in individual sections, submit them for information: 1. Design data. 2. Certificates. 3. Test reports. 4. Inspection reports. 5. Manufacturer's instructions. 6. Manufacturer's field reports. 7. Other types indicated. B. Submit for Architect's knowledge as contract administrator or for Owner. No action will be taken. 3.06 SUBMITTALS FOR PROJECT CLOSEOUT A. When the following are specified in individual sections, submit them at project closeout: 1. Project record documents. 2. Operation and maintenance data. 3. Warranties. 4 Bonds. 5. Other types as indicated. B. Submit for Owner's benefit during and after project completion. 3.07 NUMBER OF COPIES OF SUBMITTALS A. Documents for Review: 1, Small Size Sheets, Not Larger Than 8-1/2 x 11 inches: Submit the number of copies that Contractor requires, plus two copies that will be retained by Architect. B. Documents for Information: Submit two copies. C. Documents for Project Closeout: Make one reproduction of submittal originally reviewed. Submit one extra of submittals for information. D. Samples: Submit the number specified in individual specification sections; one of which will be retained by Architect. 1. After review, produce duplicates. 2. Retained samples will not be returned to Contractor unless specifically so stated. 3.08 SUBMITTAL PROCEDURES A. Transmit each submittal with AIA Form G810.. B. Sequentially number the transmittal form. Revise submittals with original number and a sequential alphabetic suffix. C. Identify Project, Contractor, Subcontractor or supplier; pertinent drawing and detail number, and specification section number, as appropriate on each copy. Gates Park Pro Shop Reroofing Project#09025 01 30 00 City of Waterloo, Department of Leisure Services ADMINISTRATIVE REQUIREMENTS Waterloo, Iowa Page 3 of 4 D. Apply Contractor's stamp, signed or initialed certifying that review, approval, verification of Products required, field dimensions, adjacent construction Work, and coordination of information is in accordance with the requirements of the Work and Contract Documents. E Schedule submittals to expedite the Project, and coordinate submission of related items. F For each submittal for review, allow 15 days excluding delivery time to and from the Contractor. G. Identify variations from Contract Documents and Product or system limitations that may be detrimental to successful performance of the completed Work. H. Provide space for Contractor and Architect review stamps I. When revised for resubmission, identify all changes made since previous submission. J. Distribute copies of reviewed submittals as appropriate. Instruct parties to promptly report any inability to comply with requirements. K. Submittals not requested will not be recognized or processed. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 30 00 City of Waterloo, Department of Leisure Services ADMINISTRATIVE REDUIREMENTS Waterloo, Iowa Page 4 of 4 SECTION 01 40 00 QUALITY REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. References and standards B. Control of installation, C. Tolerances. D. Manufacturers'field services, 1.02 SUBMITTALS A. Certificates: When specified in individual specification sections, submit certification by the manufacturer and Contractor or installation/application subcontractor to Architect, in quantities specified for Product Data. 1. Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference data, affidavits, and certifications as appropriate. B. Manufacturer's Instructions: When specified in individual specification sections, submit printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, for the Owner's information, Indicate special procedures, perimeter conditions requiring special attention, and special environmental criteria required for application or installation. C. Manufacturer's Field Reports: Submit reports for Architect's benefit as contract administrator or for Owner 1. Submit for information for the limited purpose of assessing conformance with information given and the design concept expressed in the contract documents, 1.03 REFERENCES AND STANDARDS A. For products and workmanship specified by reference to a document or documents not included in the Project Manual, also referred to as reference standards, comply with requirements of the standard, except when more rigid requirements are specified or are required by applicable codes. B. Conform to reference standard of date of issue current on date of Contract Documents, except where a specific date is established by applicable code. C. Obtain copies of standards where required by product specification sections. D. Maintain copy at project site during submittals, planning, and progress of the specific work, until Substantial Completion. E. Should specified reference standards conflict with Contract Documents, request clarification from Architect before proceeding, F. Neither the contractual relationships, duties, or responsibilities of the parties in Contract nor those of Architect shall be altered from the Contract Documents by mention or inference otherwise in any reference document. PART 2 PRODUCTS -NOT USED PART 3 EXECUTION 3.01 CONTROL OF INSTALLATION A, Monitor quality control over suppliers, manufacturers, products, services, site conditions, and Gates Park Pro Shop Reroofing Project#09025 01 40 00 City of Waterloo, Department of Leisure Services QUALITY REQUIREMENTS Waterloo, Iowa Page 1 of 2 workmanship, to produce Work of specified quality. B. Comply with manufacturers' instructions, including each step in sequence. C. Should manufacturers' instructions conflict with Contract Documents, request clarfication from Architect before proceeding. D. Comply with specified standards as minimum quality for the Work except where more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship. E. Have Work performed by persons qualified to produce required and specified quality. F. Verify that field measurements are as indicated on shop drawings or as instructed by the manufacturer, G. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, and disfigurement. 3.02 TOLERANCES A. Monitor fabrication and installation tolerance control of products to produce acceptable Work. Do not permit tolerances to accumulate. B. Comply with manufacturers'tolerances. Should manufacturers'tolerances conflict with Contract Documents, request clarification from Architect before proceeding. C. Adjust products to appropriate dimensions; position before securing products in p ace. 3.03 MANUFACTURERS' FIELD SERVICES A. When specified in individual specification sections, require material or product suppliers or manufacturers to provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust and balance of equipment as applicable, and to initiate instructions when necessary. B. Report observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers'written instructions. 3.04 DEFECT ASSESSMENT A. Replace Work or portions of the Work not conforming to specified requirements. B. If, in the opinion of Architect, it is not practical to remove and replace the Work, Architect will direct an appropriate remedy or adjust payment. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 40 00 City of Waterloo, Department of Leisure Services QUALITY REQUIREMENTS Waterloo, Iowa Page 2 of 2 SECTION 01 50 00 TEMPORARY FACILITIES AND CONTROLS PART 1 GENERAL 1.01 SECTION INCLUDES A Temporary utilities. B Temporary telephone service. C, Temporary sanitary facilities. D. Security requirements. E. Vehicular access and parking. F. Waste removal facilities and services. 1.02 TEMPORARY UTILITIES A. The existing electrical power, lighting and water sources may be used by the contractors free of charge. 1.03 TELECOMMUNICATIONS SERVICES A. Provide, maintain, and pay for telephone service to field office at time of project mobilization. Cellular service is acceptable. 1.04 TEMPORARY SANITARY FACILITIES A. Provide and maintain required facilities and enclosures. Provide at time of project mobilization. B. Use of existing facilities within the construction area as coordinated with the Owner's representative is not permitted. C, Maintain daily in clean and sanitary condition. D. At end of construction, return facilities to same or better condition as originally found. 1.05 EXTERIOR ENCLOSURES A. Provide temporary insulated weather tight closure of exterior openings to accommodate acceptable working conditions and protection for Products. 1.06 SECURITY A. Provide security and facilities to protect Work, existing facilities, and Owner's operations from unauthorized entry, vandalism, or theft. B, Coordinate with Owner's security program. 1.07 VEHICULAR ACCESS AND PARKING A. Provide temporary parking areas to accommodate construction personnel. When site space is not adequate, provide additional off-site parking. B. Existing parking areas may be used for construction parking. Coordinate with Owner. 1.08 WASTE REMOVAL A. Provide waste removal facilities and services as required to maintain the site in clean and orderly condition. B. Provide containers with lids, Remove trash from site weekly. Gates Park Pro Shop Reroofing Project#09025 01 50 00 City of Waterloo, Department of Leisure Services TEMPORARY FACILITIES AND CONTROLS Waterloo, Iowa Page 1 of 2 C. If materials to be recycled or re-used on the project must be stored on-site, provide suitable non-combustible containers; locate containers holding flammable material outside the structure unless otherwise approved by the authorities having jurisdiction. D. Open free-fall chutes are not permitted. Terminate closed chutes into appropriate containers with lids. 1.09 REMOVAL OF UTILITIES, FACILITIES,AND CONTROLS A. Restore existing facilities used during construction to original condition. PART 2 PRODUCTS -NOT USED PART 3 EXECUTION -NOT USED END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 50 00 City of Waterloo, Department of Leisure Services TEMPORARY FACILITIES AND CONTROLS Waterloo, Iowa Page 2 of 2 SECTION 01 60 00 PRODUCT REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. General product requirements. B. Transportation, handling, storage and protection C, Product option requirements. D. Substitution limitations and procedures. 1.02 SUBMITTALS A Product Data Submittals: Submit manufacturer's standard published data, Mark each copy to identify applicable products, models, options, and other data Supplement manufacturers' standard data to provide information specific to this Project. B. Shop Drawing Submittals: Prepared specifically for this Project; indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances. C. Sample Submittals: Illustrate functional and aesthetic characteristics of the product, with integral parts and attachment devices. Coordinate sample submittals for interfacing work. 1. For selection from standard finishes, submit samples of the full range of the manufacturer's standard colors, textures, and patterns. D. Indicate utility and electrical characteristics, utility connection requirements, and location of utility outlets for service for functional equipment and appliances. PART 2 PRODUCTS 2.01 NEW PRODUCTS A. Provide new products unless specifically required or permitted by the Contract Documents. B. Do not use products having any of the following characteristics: 2.02 PRODUCT OPTIONS A. Products Specified by Reference Standards or by Description Only: Use any product meeting those standards or description. B. Products Specified by Naming One or More Manufacturers: Use a product of one of the manufacturers named and meeting specifications, no options or substitutions allowed. C. Products Specified by Naming One or More Manufacturers with a Provision for Substitutions: Submit a request for substitution for any manufacturer not named. PART 3 EXECUTION 3.01 SUBSTITUTION PROCEDURES A. Instructions to Bidders specify time restrictions for submitting requests for substitutions during the bidding period. Comply with requirements specified in this section. B. Document each request with complete data substantiating compliance of proposed substitution with Contract Documents. C. A request for substitution constitutes a representation that the submitter: Gates Park Pro Shop Reroofing Project#09025 01 60 00 City of Waterloo, Department of Leisure Services PRODUCT REQUIREMENTS Waterloo, Iowa Page 1 of 2 1. Has investigated proposed product and determined that it meets or exceeds the quality level of the specified product. 2. Will provide the same warranty for the substitution as for the specified product. 3. Will coordinate installation and make changes to other Work that may be required for the Work to be complete with no additional cost to Owner 4. Waives claims for additional costs or time extension that may subsequently become apparent. 5. The burden of proof of the merit of the proposed substituition is upon the proposer. D. Substitution Submittal Procedure: 1. Submit three copies of request for substitution for consideration. Limit each request to one proposed substitution. 2. Submit shop drawings, product data, and certified test results attesting to the proposed product equivalence. Burden of proof is on proposer. 3, The Architect will notify Contractor in writing of decision to accept or reject request.. 3.02 TRANSPORTATION AND HANDLING A. Coordinate schedule of product delivery to designated prepared areas in order to minimize site storage time and potential damage to stored materials. B. Transport and handle products in accordance with manufacturer's instructions. C. Transport materials in covered trucks to prevent contamination of product and littering of surrounding areas. D. Promptly inspect shipments to ensure that products comply with requirements, quantities are correct, and products are undamaged. E. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage. F. Arrange for the return of packing materials, such as wood pallets, where economically feasible. 3.03 STORAGE AND PROTECTION A. Designate receiving/storage areas for incoming products so that they are delivered according to installation schedule and placed convenient to work area in order to minimize waste due to excessive materials handling and misapplication. B. Store and protect products in accordance with manufacturers' instructions. C. Store with seals and labels intact and legible. D. Store sensitive products in weather tight, climate controlled, enclosures in an enwonment favorable to product. E. For exterior storage of fabricated products, place on sloped supports above grour d. F. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products. G. Prevent contact with material that may cause corrosion, discoloration, or staining. H. Provide equipment and personnel to store products by methods to prevent soiling disfigurement, or damage. I, Arrange storage of products to permit access for inspection Periodically inspect to verify products are undamaged and are maintained in acceptable condition. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 60 00 City of Waterloo, Department of Leisure Services PRODUCT REQUIREMENTS Waterloo, Iowa Page 2 of 2 SECTION 01 70 00 EXECUTION AND CLOSEOUT REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Examination, preparation, and general installation procedures. B. Requirements for alterations work, including selective demolition, except removal, disposal, and/or remediation of hazardous materials and toxic substances,. C. Pre-installation meetings. D. Cutting and patching. E. Cleaning and protection. F. Closeout procedures, except payment procedures. 1.02 SUBMITTALS A. See Section 01 30 00-Administrative Requirements, for submittal procedures. B. Cutting and Patching: Submit written request in advance of cutting or alteration that affects: 1. Structural integrity of any element of Project. 2, Integrity of weather exposed or moisture resistant element. 3, Efficiency, maintenance, or safety of any operational element. 4, Visual qualities of sight exposed elements. 1.03 QUALIFICATIONS A. For survey work, employ a land surveyor registered in the State in which the Project is located and acceptable to Architect. Submit evidence of Surveyor's Errors and Omissions insurance coverage in the form of an Insurance Certificate. B. For field engineering, employ a professional engineer of the discipline required for specific service on Project, licensed in the State in which the Project is located. 1.04 PROJECT CONDITIONS A. Dust Control: Execute work by methods to minimize raising dust from construction operations. Provide positive means to prevent air-borne dust from dispersing into atmosphere. B. Noise Control: Provide methods, means, and facilities to minimize noise produced by construction operations. C. Pollution Control: Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations. 1.05 COORDINATION A. Coordinate scheduling, submittals, and work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later. B. Coordinate completion and clean-up of work of separate sections, C. After Owner occupancy of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Owner's activities. Gates Park Pro Shop Reroofing Project#09025 01 70 00 City of Waterloo, Department of Leisure Services EXECUTION AND CLOSEOUT REQUIREMENTS Waterloo, Iowa Page 1 of 5 PART 2 PRODUCTS 2.01 PATCHING MATERIALS A. New Materials: As specified in product sections; match existing products and work for patching and extending work. B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard. C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01 60 00, PART 3 EXECUTION 3.01 EXAMINATION A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work. Start of work means acceptance of existing conditions. B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached. C. Examine and verify specific conditions described in individual specification sections. D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication. E. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work, Beginning of cutting or patching means acceptance of existing conditions. 3.02 PREPARATION A. Clean substrate surfaces prior to applying next material or substance. B. Seal cracks or openings of substrate prior to applying next material or substance. C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond. 3.03 PREINSTALLATION MEETINGS A. When required in individual specification sections, convene a preinstallation meeting at the site prior to commencing work of the section. B. Require attendance of parties directly affecting, or affected by, work of the specific section. C. Notify Architect four days in advance of meeting date. D. Prepare agenda and preside at meeting: 1, Review conditions of examination, preparation and installation procedures. 2. Review coordination with related work. E. Record minutes and distribute copies within two days after meeting to participants with two copies to Architect, Owner, participants, and those affected by decisions made. 3.04 GENERAL INSTALLATION REQUIREMENTS A. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement. B. Make vertical elements plumb and horizontal elements level, unless otherwise indicated. Gates Park Pro Shop Reroofing Project#09025 01 70 00 City of Waterloo, Department of Leisure Services EXECUTION AND CLOSEOUT REQUIREMENTS Waterloo, Iowa Page 2 of 5 C. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated. D. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated. E. Make neat transitions between different surfaces, maintaining texture and appearance. 3.05 ALTERATIONS A. Drawings showing existing construction and utilities are based on casual field observation and existing record documents only. 1 Verify that construction and utility arrangements are as shown. 2. Report discrepancies to Architect before disturbing existing installation. 3. Beginning of alterations work constitutes acceptance of existing conditions. B. Maintain weatherproof exterior building enclosure except for interruptions required for replacement or modifications; take care to prevent water and humidity damage. 1. Where openings in exterior enclosure exist, provide construction to make exterior enclosure weatherproof. 2. Insulate existing ducts or pipes that are exposed to outdoor ambient temperatures by alterations work. C. Remove existing work as indicated and as required to accomplish new work.. 1. Remove items indicated on drawings. 2. Relocate items indicated on drawings. 3. Where new surface finishes are to be applied to existing work, perform removals, patch, and prepare existing surfaces as required to receive new finish; remove existing finish if necessary for successful application of new finish. 4. Where new surface finishes are not specified or indicated, patch holes and damaged surfaces to match adjacent finished surfaces as closely as possible. D. Protect existing work to remain. 1, Prevent movement of structure; provide shoring and bracing if necessary. 2. Perform cutting to accomplish removals neatly and as specified for cutting new work. 3. Repair adjacent construction and finishes damaged during removal work. E. Adapt existing work to fit new work: Make as neat and smooth transition as possible. F. Patching: Where the existing surface is not indicated to be refinished, patch to match the surface finish that existed prior to cutting. Where the surface is indicated to be refinished, patch so that the substrate is ready for the new finish. G. Refinish existing surfaces as indicated: 1. Where rooms or spaces are indicated to be refinished, refinish all visible existing surfaces to remain to the specified condition for each material, with a neat transition to adjacent finishes. 2. If mechanical or electrical work is exposed accidentally during the work, re-cover and refinish to match. H. Clean existing systems and equipment. I. Remove demolition debris and abandoned items from alterations areas and dispose of off-site; do not burn or bury. J. Do not begin new construction in alterations areas before demolition is complete. K. Comply with all other applicable requirements of this section. 3.06 CUTTING AND PATCHING A. Whenever possible, execute the work by methods that avoid cutting or patching. Gates Park Pro Shop Reroofing Project#09025 01 70 00 City of Waterloo, Department of Leisure Services EXECUTION AND CLOSEOUT REQUIREMENTS Waterloo, Iowa Page 3 of 5 B. See Alterations article above for additional requirements. C. Perform whatever cutting and patching is necessary to: 1, Complete the work. 2. Fit products together to integrate with other work. 3. Provide openings for penetration of mechanical, electrical, and other services. 4. Match work that has been cut to adjacent work. 5. Repair areas adjacent to cuts to required condition. 6. Repair new work damaged by subsequent work. 7. Remove samples of installed work for testing when requested. 8, Remove and replace defective and non-conforming work. D. Execute cutting and patching including excavation and fill to complete the work, tc uncover work in order to install improperly sequenced work, to remove and replace defective or non-conforming work, to remove samples of installed work for testing when requested, to provide openings in the work for penetration of mechanical and electrical work, to execute patching to complement adjacent work, and to fit products together to integrate with other work. E. Execute work by methods that avoid damage to other work and that will provide appropriate surfaces to receive patching and finishing. In existing work, minimize damage and restore to original condition F. Employ skilled and experienced installer to perform cutting for weather exposed and moisture resistant elements, and sight exposed surfaces. G. Fit work air tight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces. H. At penetrations of fire rated walls, partitions, ceiling, or floor construction, completely seal voids with fire rated material, to full thickness of the penetrated element. I Patching: 1 Finish patched surfaces to match finish that existed prior to patching. On continuous surfaces, refinish to nearest intersection or natural break For an assembly, refinish entire unit 2, Match color, texture, and appearance. 3. Repair patched surfaces that are damaged, lifted, discolored, or showing other imperfections due to patching work, If defects are due to condition of substrate, repair substrate prior to repairing finish. J. Refinish surfaces to match adjacent finish. For continuous surfaces, refinish to nearest intersection or natural break. For an assembly, refinish entire unit. K Make neat transitions. Patch work to match adjacent work in texture and appearance. Where new work abuts or aligns with existing, perform a smooth and even transition. 3.07 PROGRESS CLEANING A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition. B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space. C. Broom and vacuum clean interior areas prior to start of surface finishing, and continue cleaning to eliminate dust. D. Collect and remove waste materials, debris, and trash/rubbish from site weekly and dispose off-site; do not burn or bury. 3.08 PROTECTION OF INSTALLED WORK Gates Park Pro Shop Reroofing Project#09025 01 70 00 City of Waterloo, Department of Leisure Services EXECUTION AND CLOSEOUT REQUIREMENTS Waterloo, Iowa Page 4 of 5 A. Protect installed work from damage by construction operations. B. Provide special protection where specified in individual specification sections. C. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage. D, Protect finished surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials. E. Prohibit traffic or storage upon waterproofed or roofed surfaces. If traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer F Remove protective coverings when no longer needed; reuse or recycle plastic coverings if possible, 3.09 FINAL CLEANING A. Use cleaning materials that are nonhazardous. B. Clean debris from roofs, gutters, downspouts, and drainage systems. C. Clean site; sweep paved areas, rake clean landscaped surfaces. D. Remove waste, surplus materials, trash/rubbish, and construction facilities from the site; dispose of in legal manner; do not burn or bury. 3.10 CLOSEOUT PROCEDURES A. Make submittals that are required by governing or other authorities. B. Notify Architect when work is considered ready for Substantial Completion. C. Submit written certification that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Architect's review. D. Correct items of work listed in executed Certificates of Substantial Completion and comply with requirements for access to Owner-occupied areas. E. Notify Architect when work is considered finally complete. F. Complete items of work determined by Architect's final inspection. 3.11 MAINTENANCE SERVICE A. Maintenance Period: As indicated in specification sections or, if not indicated, not less than one year from the Date of Substantial Completion or the length of the specified warranty, whichever is longer. B. Examine system components at a frequency consistent with reliable operation. Clean, adjust, and lubricate as required. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 70 00 City of Waterloo, Department of Leisure Services EXECUTION AND CLOSEOUT REQUIREMENTS Waterloo, Iowa Page 5 of 5 SECTION 01 78 00 CLOSEOUT SUBMITTALS PART 1 GENERAL 1.01 SECTION INCLUDES A. Project Record Documents. B. Operation and Maintenance Data. C. Warranties and bonds. 1.02 RELATED SECTIONS A. Section 01 3000 -Administrative Requirements: Submittals procedures, shop drawings, product data, and samples B. Section 01 7000- Execution and Closeout Requirements: Contract closeout procedures. C. Individual Product Sections: Specific requirements for operation and maintenance data. D. Individual Product Sections: Warranties required for specific products or Work. 1.03 SUBMITTALS A. Project Record Documents: Submit documents to Architect after substantial completion. B. Two Binders: Commercial quality, 8-1/2 x 11 inch three D side ring binders with durable plastic covers; 2 inch maximum ring size which include the data described below. When multiple binders are used, correlate data into related consistent groupings. C. Warranties and Bonds: 1. Warranties and Bonds to be included in the binders described above and correlate with respective specification section. 2. For equipment or component parts of equipment put into service during construction with Owner's permission, submit documents within ten days after acceptance. 3. Make other submittals within ten days after Date of Substantial Completion, prior to final Application for Payment. 4. For items of Work for which acceptance is delayed beyond Date of Substantial Completion, submit within ten days after acceptance, listing the date of acceptance as the beginning of the warranty period. PART 2 PRODUCTS - NOT USED PART 3 EXECUTION 3.01 PROJECT RECORD DOCUMENTS A. Maintain on site one set of the following record documents; record actual revisions to the Work: 1, Drawings. 2. Specifications rebound with addendum included. 3. Change Orders and other modifications to the Contract. 4. Reviewed shop drawings, product data, and samples. 5. Manufacturer's instruction for assembly, installation, and adjusting. B. Ensure entries are complete and accurate, enabling future reference by Owner. C. Store record documents separate from documents used for construction. D. Record information concurrent with construction progress. Gates Park Pro Shop Reroofing Project#09025 01 78 00 City of Waterloo, Department of Leisure Services CLOSEOUT SUBMITTALS Waterloo, Iowa Page 1 of 3 E. Specifications: Legibly mark and record at each product section description of actual products installed, including the following: 1. Product substitutions or alternates utilized. 2. Changes made by Addenda and modifications. F. Record Drawings and Shop Drawings: Legibly mark each item to record actual construction including: 1 Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work. 2. Field changes of dimension and detail. 3. Details not on original Contract drawings, 3.02 BINDERS A. Organize binders with tabs labeled with the respective division. All manuals, operation information and supplemental data described below is to be included as required and sorted by division accordingly_ B. Cover: Identify each binder with typed or printed title to identify title of Project; identify subject matter of contents. C. Include the following information organized by division: 1. OPERATION AND MAINTENANCE DATA a. For Each Product or System: List names, addresses and telephone numbers of Subcontractors and suppliers, including local source of supplies and replacement parts. b, Product Data: Mark each sheet to clearly identify specific products and component parts, and data applicable to installation. Delete inapplicable information. 2. OPERATION AND MAINTENANCE DATA FOR MATERIALS AND FINISHES a. For Each Product, Applied Material, and Finish: 1) Product data, with catalog number, size, composition, and color and texture designations. b. Instructions for Care and Maintenance: Manufacturer's recommendations for cleaning agents and methods, precautions against detrimental cleaning agents and methods, and recommended schedule for cleaning and maintenance. c. Additional information as specified in individual product specification sections. 3. OPERATION AND MAINTENANCE DATA FOR EQUIPMENT AND SYSTEMS a. For Each Item of Equipment and Each System: 1) Description of unit or system, and component parts. 2) Identify function, normal operating characteristics, and limiting conditions, 3) Include performance curves, with engineering data and tests. 4) Complete nomenclature and model number of replaceable parts. b. Operating Procedures: Include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and any special operating instructions. c. Maintenance Requirements: Include routine procedures and guide for preventative maintenance and trouble shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions. d. Provide servicing and lubrication schedule, and list of lubricants required. e. Include manufacturer's printed operation and maintenance instructions. f. Include sequence of operation by controls manufacturer. g. Provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance. h, Provide list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage. Gates Park Pro Shop Reroofing Project#09025 01 78 00 City of Waterloo, Department of Leisure Services CLOSEOUT SUBMITTALS Waterloo, Iowa Page 2 of 3 i. Additional Requirements: As specified in individual product specification sections. 4. OPERATION AND MAINTENANCE MANUALS a. Prepare instructions and data by personnel experienced in maintenance and operation of described products b. Prepare data in the form of an instructional manual. c. Provide tabbed dividers for each separate product and system, with typed description of product and major component parts of equipment. 5. WARRANTIES AND BONDS a Obtain warranties and bonds, executed in duplicate by responsible Subcontractors, suppliers, and manufacturers, within ten days after completion of the applicable item of work. Except for items put into use with Owner's permission, leave date of beginning of time of warranty until the Date of Substantial completion is determined. b. Verify that documents are in proper form, contain full information, and a-e notarized. c. Co-execute submittals when required. d. Retain warranties and bonds until time specified for submittal. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 01 78 00 City of Waterloo, Department of Leisure Services CLOSEOUT SUBMITTALS Waterloo, Iowa Page 3 of 3 SECTION 02 41 00 DEMOLITION PART 1 GENERAL 1.01 SECTION INCLUDES A. Selective demolition of building elements for alterations purposes. 1.02 RELATED REQUIREMENTS A, Section 01 10 00-Summary: Limitations on Contractor's use of site and premises. B. Section 01 10 00 -Summary: Description of items to be salvaged or removed for re-use by Contractor. C. Section 01 50 00 -Temporary Facilities and Controls; Site fences, security, protective barriers, and waste removal. D. Section 01 60 00- Product Requirements: Handling and storage of items removed for salvage and relocation. E. Section 01 70 00 - Execution and Closeout Requirements: Project conditions; protection of bench marks, survey control points, and existing construction to remain; reinstallation of removed products. 1.03 REFERENCE STANDARDS A. 29 CFR 1926- U.S. Occupational Safety and Health Standards; current edition. B. NFPA 241 -Standard for Safeguarding Construction, Alteration, and Demolition Operations; 2004 PART 2 PRODUCTS -- NOT USED PART 3 EXECUTION 3.01 SCOPE A. Remove the existing roofing system to existing structural roof deck to complete installation of new roofing system. A. Remove the existing roofing system as needed to complete installation of new roofing system. B. Remove other items indicated, for salvage, relocation, and recycling. 3.02 GENERAL PROCEDURES AND PROJECT CONDITIONS A. Comply with applicable codes and regulations for demolition operations and safety of adjacent structures and the public, 1. Obtain required permits. 2. Provide, erect, and maintain temporary barriers and security devices. 3. Use physical barriers to prevent falling accidents that could be hazardous to workers or the public 4, Conduct operations to minimize effects on and interference with adjacent structures and occupants. 5. Conduct operations to minimize obstruction of public and private entrances and exits; do not obstruct required exits at any time; protect persons using entrances and exits from removal operations. B, Do not begin removal until receipt of notification to proceed from Owner, Gates Park Pro Shop Reroofing Project#09025 02 41 00 City of Waterloo, Department of Leisure Services DEMOLITION Waterloo, Iowa Page 1 of 2 C. Protect existing structures and other elements that are not to be removed. D If hazardous materials are discovered during removal operations, stop work and r otify Architect and Owner; hazardous materials include regulated asbestos containing materials. lead, PCB's, and mercury E. Do not remove more existing roofing material than can be made water tight by new roofing material by the end of each day's work. F. Perform demolition in a manner that maximizes salvage and recycling of materials. 1. Dismantle existing construction and separate materials. 2. Set aside reusable, recyclable, and salvageable materials; store and deliver o collection point or point of reuse. 3.03 SELECTIVE DEMOLITION FOR ALTERATIONS A. Drawings showing existing construction and utilities are based on casual field observation and existing record documents only. 1. Verify that construction arrangements are as shown. 2 Report discrepancies to Architect before disturbing existing installation. 3. Beginning of demolition work constitutes acceptance of existing conditions. B. Remove existing work as indicated and as required to accomplish new work. 1. Remove items indicated on drawings. C. Protect existing work to remain. 1. Perform cutting to accomplish removals neatly and as specified for cutting new work. 2 Repair adjacent construction and finishes damaged during removal work. 3. Patch as specified for patching new work 3.04 DEBRIS AND WASTE REMOVAL A. Remove debris,junk, and trash from site. B. Leave site in clean condition, ready for subsequent work. C. Clean up spillage and wind-blown debris from public and private lands. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 02 41 00 City of Waterloo, Department of Leisure Services DEMOLITION Waterloo, Iowa Page 2 of 2 SECTION 04 01 00 MAINTENANCE OF MASONRY PART 1 GENERAL 1.01 SECTION INCLUDES A. Repointing of existing mortar joints. B. Mortar. C. Stone sealer. 1.02 REFERENCE STANDARDS A. ACI 530/ASCE 5/TMS 402 - Building Code Requirements for Masonry Structures; American Concrete Institute International; 2005. B. ACI 530.1/ASCE 6/TMS 602 -Specification for Masonry Structures; American Concrete Institute International; 2005. C. ASTM C 91 -Standard Specification for Masonry Cement; 2005. D. ASTM C 150 -Standard Specification for Portland Cement; 2005. E. ASTM C 207- Standard Specification for Hydrated Lime for Masonry Purposes; 2006. F. ASTM C 270-Standard Specification for Mortar for Unit Masonry; 2007. 1.03 SUBMITTALS A. Product Data: Provide data for mortar. 1.04 QUALITY ASSURANCE A. Comply with provisions of ACI 530/ASCE 5/TMS 402 and ACI 530.1/ASCE 6/TMS 602, except where exceeded by requirements of the contract documents. 1.05 FIELD CONDITIONS A. Cold and Hot Weather Requirements: Comply with requirements of ACI 530.1/ASCE 6/TMS 602 or applicable building code, whichever is more stringent. PART 2 PRODUCTS 2.01 MORTAR MATERIALS A. Masonry Cement: ASTM C 91, Type N. B. Portland Cement: ASTM C 150, Type I; color as required to produce approved color sample. 1. Not more than 0.60 percent alkali. 2. Hydrated Lime: ASTM C 207, Type S. C. Water: Clean and not detrimental. 2.02 MORTAR MIXES A. Mortar for Existing Masonry Veneer: ASTM C 270, using the Proportion Specification. 1. Exterior, Non-Loadbearing Masonry: Type N. B. Mixing: Use mechanical batch mixer and comply with referenced standards. 2.03 STONE SEALER A. Sealer for Existing Limestone Veneer: Impregnating, invisible and breathable sealer, protects Gates Park Pro Shop Reroofing Project#09025 04 01 00 City of Waterloo, Department of Leisure Services MAINTENANCE OF MASONRY Waterloo, Iowa Page 1 of 2 exposed natural stone from damage caused by water, salts and oil-based stains. 1. Product: "Stain-Proof' manufactured by Dry Treat; or approved equivalent. PART 3 EXECUTION 3.01 EXAMINATION A. Verify that surfaces to be cleaned are ready for work of this section. 3.02 PREPARATION A. Protect surrounding elements from damage due to restoration procedures. B. Carefully remove and store removable items located in areas to be restored. C. Separate areas to be protected from restoration areas using means adequate to t::revent damage. 3.03 REPOINTING A. Perform repointing prior to cleaning masonry surfaces. B. Cut out loose or disintegrated mortar in joints to minimum 1/2 inch depth or until s: and mortar is reached. C. Use power tools only after test cuts determine no damage to masonry units will result. D. Do not damage masonry units. E, When cutting is complete, remove dust and loose material by brushing, F. Premoisten joint and apply mortar. Pack tightly in maximum 1/4 inch layers. Fo-m a smooth, compact concave joint to match existing. G. Moist cure for 72 hours. 3.04 STONE SEALING A. Apply in accordance with manufacturer's instructions. B. Ensure surfaces to be treated are dry, clean and free of residues C. Product is to be applied without thinning. D, Generously saturate the surface with product using a low-pressure hand spray, a clean brush, or similar. Avoid contact with surrounding areas. Repeat when the surface becomes touch dry, or a minimum of 10 minutes. E. Allow the product to penetrate into the surface, polish surface with a clean white dry cloth to remove excess product. 3.05 CLEANING A. Immediately remove stains, efflorescence, or other excess resulting from the wort of this section. B. Remove excess mortar, smears, and droppings as work proceeds and upon completion. C. Clean surrounding surfaces. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 04 01 00 City of Waterloo, Department of Leisure Services MAINTENANCE OF MASONRY Waterloo, Iowa Page 2 of 2 SECTION 06 10 00 ROUGH CARPENTRY PART 1 GENERAL 1.01 SECTION INCLUDES A. Roof deck sheathing. B. Roofing nailers. C, Preservative treated wood materials. D. Concealed wood blocking, nailers, and supports. E. All wood in contact with roofing, waterproofing, or flashing to be preservative treated. 1.02 REFERENCE STANDARDS A. ASTM A 153/A 153M -Standard Specification for Zinc Coating (Hot-Dip) on Iron and Steel Hardware; 2005. B. AWPA C2- Lumber, Timber, Bridge Ties and Mine Ties--Preservative Treatment by Pressure Processes;American Wood-Preservers'Association; 2003. C. AWPA U1 - Use Category System: User Specification for Treated Wood; American Wood-Preservers'Association; 2007. D. PS 1 -Structural Plywood; 2007. E. , PS 20-American Softwood Lumber Standard; National Institute of Standards and Technology (Department of Commerce); 2005, F. WWPA G-5 -Western Lumber Grading Rules; Western Wood Products Association; 2005. 1.03 SUBMITTALS A. Submit Material Safety Data Sheets(MSDS)to roof system manufacturer for acceptance of wood treatment. 1.04 QUALITY ASSURANCE A. Lumber: Comply with PS 20 and approved grading rules and inspection agencies. 1.05 DELIVERY, STORAGE,AND HANDLING A. General: Cover wood products to protect against moisture. Support stacked products to prevent deformation and to allow air circulation. PART 2 PRODUCTS 2.01 DIMENSION LUMBER A. Sizes: Nominal sizes as indicated on drawings, S4S. B. Moisture Content: S-dry or MC19. C. Joists or Rafters (2 x 6 through 2 x 12): 1. Species: Douglas Fir-Larch, unless indicated otherwise. 2. Grade: No. 1 and better. D. Miscellaneous Framing, Blocking, Nailers, Grounds, and Furring: 1. Lumber: S4S, No. 1 or Construction Grade. 2. Boards: Standard or No. 3. Gates Park Pro Shop Reroofing Project#09025 06 10 00 City of Waterloo, Department of Leisure Services ROUGH CARPENTRY Waterloo, Iowa Page 1 of 3 2.02 CONSTRUCTION PANELS A. Roof Sheathing: APA PRP-108/APA PRPR-108, Form B455, CDX plywood, Exposure Class, and as follows: 1 Thickness: 5/8 inch, nominal. 2.03 ACCESSORIES A. Fasteners and Anchors: 1. Metal and Finish: Hot-dipped galvanized steel per ASTM A 153/A 153M for nigh humidity and preservative-treated wood locations, unfinished steel elsewhere. 2.04 FACTORY WOOD TREATMENT A. Treated Lumber and Plywood: Comply with requirements of AWPA U1 - Use Category System for wood treatments determined by use categories, expected service conditions, and specific applications. 1, Preservative-Treated Wood: Provide lumber and plywood marked or stamped by an ALSC-accredited testing agency, certifying level and type of treatment in accordance with AWPA standards. B. Preservative Pressure Treatment of Lumber Above Grade: AWPA Use Category UC3B, Commodity Specification A(Treatment C2) using waterborne preservative to 0.25 lb/cu ft retention. 1, Kiln dry lumber after treatment to maximum moisture content of 19 percent. 2. Treat lumber in contact with roofing, flashing, or waterproofing. 3. Treat lumber in contact with masonry or concrete. PART 3 EXECUTION 3.01 PREPARATION A. Coordinate installation of rough carpentry members specified in other sections. 3.02 INSTALLATION -GENERAL A. Select material sizes to minimize waste, B. Reuse scrap to the greatest extent possible; clearly separate scrap for use on site as accessory components, including: shims, bracing, and blocking. 3.03 BLOCKING, NAILERS, AND SUPPORTS A. Provide framing and blocking members as indicated or as required to support finishes, fixtures, specialty items, and trim. 3.04 ROOF-RELATED CARPENTRY A. Coordinate installation of roofing carpentry with deck construction, framing of roof openings, and roofing assembly installation. 3.05 INSTALLATION OF CONSTRUCTION PANELS A. Roof Sheathing: Secure panels with long dimension perpendicular to existing framing members, with ends staggered and over firm bearing. 3.06 REPAIR OF EXISTING ROOF SHEATHING A, Remove and replace any wood decking that has rotted or has been damaged in existing deck removal. Provide structural surface ready for reroofing materials. 3.07 SITE APPLIED WOOD TREATMENT A. Apply preservative treatment compatible with factory applied treatment at site-sawn cuts, Gates Park Pro Shop Reroofing Project#09025 06 10 00 City of Waterloo, Department of Leisure Services ROUGH CARPENTRY Waterloo, Iowa Page 2 of 3 complying with manufacturer's instructions. B. Allow preservative to dry prior to erecting members. 3.08 CLEANING A. Waste Disposal: 1. Comply with applicable regulations. 2. Do not burn scrap on project site. 3. Do not send materials treated with pentachlorophenol, CCA, or ACA to co-generation facilities or"waste-to-energy"facilities. B. Do not leave any wood, shavings, sawdust, etc. on the ground or buried in fill. C. Prevent sawdust and wood shavings from entering the storm drainage system. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 06 10 00 City of Waterloo, Department of Leisure Services ROUGH CARPENTRY Waterloo, Iowa Page 3 of 3 SECTION 06 11 13 ENGINEERED WOOD PRODUCTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Laminated veneer lumber. 1.02 RELATED REQUIREMENTS A. Section 06 10 00- Rough Carpentry B. Section 06 17 53-Shop-Fabricated Wood Trusses. 1.03 SUBMITTALS A. Product Data: Provide technical data on wood preservative materials, applicatior technique and resultant performance information. B. Shop Drawings: Indicate framing system, sizes and spacing of members, loads and cambers, bearing and anchor details, bridging and bracing, framed openings. 1. Submit design calculations. 1.04 REGULATORY REQUIREMENTS A. Conform to applicable code for loads, seismic zoning, and other load criteria. PART 2 PRODUCTS 2.01 MATERIALS A. Laminated Veneer Lumber: See structural drawings. PART 3 EXECUTION 3.01 EXAMINATION A. Verify that supports are ready to receive units. B. Verify sufficient end bearing area. 3.02 PREPARATION A. Coordinate placement of bearing items. 3.03 ERECTION A. Set structural members level and plumb, in correct positions where indicated. B, Provide temporary bracing and anchorage to hold members in place until permanently secured. C. Fit members together accurately without trimming, cutting, or other unauthorized modification. 3.04 TOLERANCES A. Framing Members: 1/2 inch maximum from true position. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 06 11 13 City of Waterloo, Department of Leisure Services ENGINEERED WOOD PRODUCTS Waterloo, Iowa Page 1 of 1 SECTION 06 17 53 SHOP-FABRICATED WOOD TRUSSES PART 1 GENERAL 1.01 SECTION INCLUDES A. Shop fabricated wood trusses for roof framing. B. Bridging, bracing, and anchorage. C. Accessories, including joist hangers. 1.02 RELATED REQUIREMENTS A. Section 06 10 00- Rough Carpentry: Installation requirements for miscellaneous framing, B. Section 06 18 00-Glue-Laminated Construction. 1.03 REFERENCE STANDARDS A. ASTM A 653/A 653M -Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process; 2007. B. RIS (GR)-Standard Specifications for Grades of California Redwood Lumber; Redwood Inspection Service; 2000. C. TPI 1 -National Design Standard for Metal Plate Connected Wood Truss Construction; Truss Plate Institute; 2002 and errata (ANSI/TPI 1). D. TPI DSB-89 -Recommended Design Specification for Temporary Bracing of Metal Plate Connected Wood Trusses; Truss Plate Institute; 1989 E. BCSI 1 - Building Component Safety Information Booklet: The Guide to Good Practice for Handling, Installing & Bracing of Metal Plate Connected Wood Trusses;joint publication of the Truss Plate Institute and the Wood Trust Council of America; 2006, 1.04 DESIGN REQUIREMENTS A. Comply with applicable code for structural loading criteria and fire retardant requirements 1.05 SUBMITTALS A. Product Data: Manufacturer's data sheets on plate connectors, bearing plates, and metal bracing components. B. Shop Drawings: Show truss configurations, sizes, spacing, size and type of plate connectors, cambers, framed openings, bearing and anchor details, and bridging and bracing. 1. Include identification of engineering software used for design. 2, Provide shop drawings stamped or sealed by design engineer. 1.06 QUALITY ASSURANCE A. Truss Design, Fabrication, and Installation: In accordance with TPI 1, TPI DSB-89, and BCSI. B. Fabricator Qualifications: Company specializing in manufacturing the products specified in this section with minimum three years of documented experience. 1.07 DELIVERY, STORAGE,AND HANDLING A. Handle and erect trusses in accordance with BCSI 1. B. Store trusses in vertical position resting on bearing ends. Gates Park Pro Shop Reroofing Project#09025 06 17 53 City of Waterloo, Department of Leisure Services SHOP-FABRICATED WOOD TRUSSES Waterloo, Iowa Page 1 of 2 PART 2 PRODUCTS 2.01 MATERIALS A, Lumber: 1. Grade: RIS (GR), Grade to achieve structural requirements. 2. Moisture Content: Between 7 and 9 percent. 3. Lumber fabricated from old growth timber is not permitted. B. Steel Connectors: Hot-dipped galvanized steel sheet, ASTM A 653/A 653M Stru:;tural Steel (SS) Grade 33/230, with G90/Z275 coating; die stamped with integral teeth; thickness as indicated. C Truss Bridging: Type, size and spacing recommended by truss manufacturer 2.02 ACCESSORIES A. Joist Hangers: Electrogalvanized steel, heavy duty-duty connectors. 1. Product: "HU24 TF" manufactured by Simpson Strong Tie; or approved eqL valent. B. Wood Blocking, Bridging, Plates, and Miscellaneous Framing: As specified in SEstion 06 10 00. C Fasteners: Electrogalvanized steel, type to suit application. D. Bearing Plates: Electrogalvanized steel. 2.03 FABRICATION A. Fabricate trusses to achieve structural requirements specified. B. Brace wood trusses in accordance with TPI DSB-89 and BCSI 1. PART 3 EXECUTION 3.01 EXAMINATION A. Verify that field measurements are as indicated. B. Verify that supports and openings are ready to receive trusses. 3.02 PREPARATION A. Coordinate placement of bearing items. 3.03 ERECTION A. Install trusses in accordance with manufacturer's instructions and TPI DSB-89 and BCSI 1; maintain a copy of each TPI document on site until installation is complete. B. Set members level and plumb, in correct position. C Do not field cut or alter structural members without approval of Architect. D. Install permanent bridging and bracing. E. Coordinate placement of decking with work of this section, 3.04 TOLERANCES A. Framing Members: 1/2 inch maximum, from true position. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 06 17 53 City of Waterloo, Department of Leisure Services SHOP-FABRICATED WOOD TRUSSES Waterloo, Iowa Page 2 of 2 SECTION 07 21 26 BLOWN INSULATION PART 1 GENERAL 1.01 SECTION INCLUDES A. Ceiling: Loose insulation pneumatically placed, and poured into joist spaces through access holes. 1.02 REFERENCE STANDARDS A. ASTM C 764-Standard Specification for Mineral Fiber Loose-Fill Thermal Insulation; 2007, B. ASTM C 1015-Standard Practice for Installation of Cellulosic and Mineral Fiber Loose-Fill Thermal Insulation; 2006. 1.03 SUBMITTALS A. Product Data: Provide data on product characteristics, performance criteria, limitations. 1.04 ADMINISTRATIVE REQUIREMENTS A. Cooridinate placement of blown insulation with construction specified in other sections. PART 2 PRODUCTS 2.01 MANUFACTURERS A. Blown Insulation: 1. CertainTeed Corporation: www.certainteed.com. 2. GreenFiber: www.cocooninsulation.com. 3. Johns Manville Corporation: www.jm.com. 4. Substitutions: See Section 01 60 00-Product Requirements. 2.02 MATERIALS A. Loose Fill Insulation: ASTM C 764, mineral wool fiber type, nodulated for pour and bulk for pneumatic placement. 1 Thermal Conductivity: 0.27 BTU in/(hr sq ft deg F). 2, Installed Thickness: As indicated on drawings. PART 3 EXECUTION 3.01 EXAMINATION A. Verify that substrate, adjacent materials, and insulation are dry and ready to receive insulation. B. Verify spaces are unobstructed to allow placement of insulation. 3.02 INSTALLATION A. Install insulation in accordance with ASTM C 1015 and manufacturer's instructions. B. Pour insulation to completely fill joist spaces. C. Completely fill intended spaces. Leave no gaps or voids. 3.03 CLEANING A. Remove loose insulation residue. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 07 21 26 City of Waterloo, Department of Leisure Services BLOWN INSULATION Waterloo, Iowa Page 1 of 1 SECTION 07 27 00 AIR BARRIER/WEATHER RESISTANT BARRIER PART 1 GENERAL 1.01 SECTION INCLUDES A. Air paper. 1.02 RELATED REQUIREMENTS A. Section 06 10 00-Rough Carpentry: Wall Sheathing. B. Section 07 46 23-Wood Siding. C. Section 07 90 05-Joint Sealers, 1.03 SUBMITTALS A. Product Data: Submit product specifications, technical data and installation instructions of manufacturer equaling or exceeding those specifications. PART 2 PRODUCTS 2.01 MANUFACTURERS A. Air Barrier: 1, DuPont Weatherization Systems: www.dupont.com. 2. Substitutions: See Section 01 60 00 - Product Requirements. 2.02 MATERIALS A. Air Barrier: Flash spunbonded olefin, non-woven, non-perforated secondary weather resistant barrier. 1 Product: "Tyvek Commercial" manufactured by DuPont; or approved equivalent. B. Performance Characteristics 1, AATCC-127, Water Penetration Resistance, exceeded at 280. 2. TAPPI T-460, Gurley Hill (sec/100cc)Air infiltration at>1500 seconds. 3. ASTM E 96 Method B(g/m2-24hr.)Water vapor transmission of 200 4. TAPPI T-41 D, Basis weight of 2.7oz/yd. 5. ASTM E96 Method B, Water Vapor Transmission: 28 perms. 6, ASTM E1677, Air Retarder Material Standard Specification, Type I air barrie- C. Sealing Tape/Fasteners 1. Steel Frame Construction: 1 5/8 inch rust resistant screws with 2 inch diameter plastic cap. 2. Wood Frame Construction: Nails with 2 inch diameter plastic cap. 3. Caulks or Sealants: Polyurethane or elastomeric sealants. See Section 07 90 05. PART 3 EXECUTION 3.01 INSTALLATION A. Install air barrier over exterior side of exterior wall sheathing. B. Overlap air barrier at corners of building by a minimum of 12 inches, all other veil cal seams minimum of 6 inches. C. Attach air barrier to wood with plastic cap nails every 12 to 18 inches on vertical stud line with wood stud framing, and screws with washers to metal stud framing. Gates Park Pro Shop Reroofing Project#09025 07 27 00 City of Waterloo, Department of Leisure Services AIR BARRIER/WEATHER RESISTANT BARRIER Waterloo, Iowa Page 1 of 2 D. Tape all horizontal and vertical seams, E. Seal all tears and cuts in air barrier with tape. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 07 27 00 City of Waterloo, Department of Leisure Services AIR BARRIER/WEATHER RESISTANT BARRIER Waterloo, Iowa Page 2 of 2 SECTION 07 46 23 WOOD SIDING PART 1 GENERAL 1.01 SECTION INCLUDES A. Board siding for walls. 1.02 RELATED REQUIREMENTS A. Section 06 10 00- Rough Carpentry; Siding substrate. B. Section 07 27 00-Air Barrier/Weather Resistant Barrier; Air paper. C. Section 07 62 00 -Sheet Metal Flashing and Trim: Product requirements for mete fleshings and trim associated with wood siding for placement by this section. D. Section 07 90 05-Joint Sealers: Sealant at perimeter. E. Section 09 90 00-Painting and Coating: Prime and finish painting. 1.03 REFERENCE STANDARDS A. APA B840 -303 Siding Manufacturing Specifications; APA-The Engineered Woc;d Association; 1997, revised 1999. 1.04 SUBMITTALS A. Product Data: Provide data indicating materials. PART 2 PRODUCTS 2.01 SIDING A. Siding Panels: APA Rated Siding 303-6-S/W, Exterior exposure class, panel sty e. 1, Panel Size, Texture, and Finish: Match existing. 2.02 ACCESSORIES A. Nails: Corrosion resistant type; non-staining, of size and strength to securely and rigidly retain the work; prefinished to match siding finish. B. Flashing: Galvanized steel as specified in Section 07 62 00. PART 3 EXECUTION 3.01 EXAMINATION A. Verify that substrates are ready to receive work. B. Do not begin until unacceptable conditions have been corrected. C. If substrate preparation is the responsibility of another installer, notify Architect of unsatisfactory preparation before proceeding. 3.02 PREPARATION 3.03 INSTALLATION A. Install siding in accordance with manufacturer's instructions. B. Fasten siding in place, level and plumb, 1. Arrange for orderly nailing pattern. Blind nail except on over trim. 2. Install siding for natural shed of water. Gates Park Pro Shop Reroofing Project#09025 07 46 23 City of Waterloo, Department of Leisure Services WOOD SIDING Waterloo, Iowa Page 1 of 2 3. Position cut ends over bearing surfaces. Sand cut edges smooth and clean. C. Sand work smooth and set exposed nails and screws. D. Prepare for site finishing specified in Section 09 90 00. 3.04 TOLERANCES A. Maximum Variation From Plumb and Level: 1/4 inch per 10 feet. B. Maximum Offset From Joint Alignment: 1/16 inch, END OF SECTION Gates Park Pro Shop Reroofing Project#09025 07 46 23 City of Waterloo, Department of Leisure Services WOOD SIDING Waterloo, Iowa Page 2 of 2 SECTION 07 51 00 BUILT-UP BITUMINOUS ROOFING PART 1 GENERAL 1.01 SECTION INCLUDES A. Built-up roofing membrane, conventional application. B. Insulation, flat. C. Vapor retarders, D. Cover board. E. Base flashings. F. Roofing accessories. 1.02 RELATED REQUIREMENTS A. Section 06 10 00- Rough Carpentry: Wood roof deck sheathing, nailers and curos. B. Section 07 62 00 -Sheet Metal Flashing and Trim: Counterflashings and gutters 1.03 REFERENCE STANDARDS A. ASTM C 1289-Standard Specification for Faced Rigid Cellular Polyisocyanurate Thermal Insulation Board; 2007 B. ASTM D 41 -Standard Specification for Asphalt Primer Used in Roofing, Dampprpofing, and Waterproofing; 2005. C. ASTM D 226- Standard Specification for Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing; 2006. D, ASTM D 312 -Standard Specification for Asphalt Used in Roofing; 2000 (Reapproved 2006). E. ASTM D 1863-Standard Specification for Mineral Aggregate Used on Built-Up Roofs; 2005. F. ASTM D 2178 - Standard Specification for Asphalt Glass Felt Used in Roofing and Waterproofing; 2004, G. ASTM D 4586 -Standard Specification for Asphalt Roof Cement, Asbestos-Free; 2007. H. NRCA ML104 -The NRCA Roofing and Waterproofing Manual; National Roofing Contractors Association; Fifth Edition, with interim updates. 1.04 ADMINISTRATIVE REQUIREMENTS A, Coordinate with installation of associated counterflashings installed by other sectians as the work of this section proceeds B. Preinstallation Meeting: Convene one week before starting work of this section. 1. Review preparation and installation procedures and coordinating and schedi.Iing required with related work. 1.05 SUBMITTALS A. Product Data: Provide data indicating membrane and bitumen materials, base flashing materials, insulation, vapor retarder, and surfacing. B. Shop Drawings: Indicate joint or termination detail conditions, conditions of interface with other materials, and mechanical fastener layout. Gates Park Pro Shop Reroofing Project#09025 07 51 00 City of Waterloo, Department of Leisure Services BUILT-UP BITUMINOUS ROOFING Waterloo, Iowa Page 1 of 5 C. Manufacturer's Installation Instructions: Indicate special procedures. D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements. E. Warranty: Submit manufacturer warranty and ensure forms have been completed in Owners name and registered with manufacturer. 1.06 QUALITY ASSURANCE A. Perform work in accordance with NRCA Roofing and Waterproofing Manual. B. Manufacturer Qualifications: Company specializing in manufacturing the products specified in this section with minimum three years of documented experience. C. Applicator Qualifications; Company specializing in performing the work of this section approved by manufacturer. 1.07 DELIVERY, STORAGE,AND HANDLING A. Deliver products in manufacturer's original containers, dry, undamaged, with seals and labels intact. B. Store products in weather protected environment, clear of ground and moisture. C. Protect foam insulation from direct exposure to sunlight. 1.08 FIELD CONDITIONS A. Do not apply roofing membrane during unsuitable weather. B Do not apply roofing membrane when ambient temperature is below 40 degrees F. C. Do not expose materials vulnerable to water or sun damage in quantities greater than can be weatherproofed the same day. 1.09 WARRANTY A. Provide manufacturer's standard, no dollar limit, 20 year material and labor warranty to cover failure to prevent penetration of water. PART 2 PRODUCTS 2.01 MANUFACTURERS A. Built-Up Bituminous Roofing Systems: 1. Firestone Building Products: www.firestonebpco.com 2. Johns Manville Corporation: www.jm.com. 3. CertainTeed Corporation: www.certainteed.com. 4. GAF Materials Corporation: www.gaf.com. 5. Substitutions; See Section 01 60 00 -Product Requirements. 2.02 ROOFING -CONVENTIONAL APPLICATION A. Built-up Bituminous Roofing; Asphalt felt membrane, four ply plus base sheet, with vapor retarder and insulation. B. Overview of Roofing System: 1. Wood deck, see Section 06 10 00- Rough Carpentry. 2. Mechanically fastened base sheet to wood deck. 3. Two-ply, Type IV felt vapor retarder; hot asphalt attached to base sheet. 4. Two layers, 1-1/2 inch flat polyisocyanurate (3 inches total); hot asphalt attached. 5. One layer, 1/2 inch wood fiber cover board; hot asphalt attached. 6. Four-ply, Type IV felt built-up roof system with gravel surfacing; hot asphalt attached. Gates Park Pro Shop Reroofing Project#09025 07 51 00 City of Waterloo, Department of Leisure Services BUILT-UP BITUMINOUS ROOFING Waterloo, Iowa Page 2 of 5 C. Surfacing: Asphalt and gravel flood coat. D. Product: "BUR Systems" manufactured by Firestone Building Products; or apprc✓ed equivalent. 2.03 SHEET MATERIALS A. Vapor Retarder: ASTM D 2178-97a, Type IV, asphalt impregnated, glass fiber rrat reinforced roofing ply. 1. Roll Width: 39.4 inches. 2. Roll Length: 164.5 feet. 3. Thickness: 30 mil. 4. Product: "Ply IV(4) M" manufactured by Firestone Building Products; or approved equivalent. B. Base Sheet: ASTM D 4601-98 Type II; high-performance asphalt impregnated and coated glass fiber mat reinforced sheet. 1 Roll Width: 39.4 inches. 2. Roll Length: 98.7 feet. 3. Product: "MB Base M" manufactured by Firestone Building Products; or apl roved equivalent. 2.04 BITUMINOUS MATERIALS A. Bitumen: ASTM D 312 Type III, asphalt. B. Primer: ASTM D 41, asphalt type. C, Roof Cement: ASTM D 4586, Type II. 2.05 INSULATION A. Polyisocyanurate Board Insulation: Rigid cellular foam, complying with ASTM C 1289, Type I, aluminum foil both faces; Class 1, non-reinforced foam core, and with the following characteristics: 1. Compressive Strength: 20 psi. 2. Board Size: 48 x 48 inches. 3. R-Value: 6.0 per inch. 4. Board Thickness: 1-1/2 inch, per layer; 2 layers total. 5. Board Edges: Square. 6. Product: "ISO 95+ GL" manufactured by Firestone Building Products; or approved equivalent. 2.06 COVER BOARD A. Cover Board: Cellulosic wood fiber insulation with an emulsion coating on one s.irface, 1/2 inch thick. 1. Product: "FiberTop" manufactured by Firestone Building Products; orapprcved equivalent. 2.07 SURFACING MATERIALS A. Aggregate: ASTM D 1863; sound, hard washed river gravel, 1/4 inch minimum tp 1/2 inch maximum size. 2.08 ACCESSORIES A. Prefabricated Roofing Expansion Joint Flashing: As recommended by manufacturer. B. Cant Strips: Perlite board insulation; expanded perlite mineral aggregate, ASTM C 728 Gates Park Pro Shop Reroofing Project#09025 07 51 00 City of Waterloo, Department of Leisure Services BUILT-UP BITUMINOUS ROOFING Waterloo, Iowa Page 3 of 5 C. Sheathing Joint Tape: Paper type, 2 inch wide, self adhering. D. Insulation Joint Tape: Glass fiber reinforced type as recommended by insulation manufacturer, compatible with roofing materials; 6 inches wide; self adhering. E. Vapor Retarder and Base Sheet Fasteners: As recommended by manufacturer for attachment of Base Sheet into wood deck substrate. PART 3 EXECUTION 3.01 EXAMINATION A. Verify that surfaces and site conditions are ready to receive work. B. Verify deck is supported and secure. C. Verify deck is clean and smooth, flat, free of depressions, waves, or projections, properly sloped and suitable for installation of roof system. D. Verify that roof openings, curbs, and penetrations through roof are solidly set, and cant strips are in place. 3.02 WOOD DECK PREPARATION A. Verify flatness and tightness of joints of wood decking. Fill knot holes with latex filler. B. Seal joints of plywood with tape C. Conventional Application: Apply vapor retarder. 3.03 VAPOR RETARDER INSTALLATION A. Mopped Vapor Retarder: 1. Attach ASTM D 4601-98 base sheet to deck with nail type fastener or manufacturer approved fastener type. Provide spacing and pattern of attachment as required by manufacturer. 2. Apply bitumen at rate recommended by manufacturer. 3. Embed one ply vapor retarder felt over attached base sheet; lap plies 4 inches; seal joints with bitumen. 4. Mop bitumen glaze coat over base sheet at a rate of 10 lb/square and embed one ply (second ply) of vapor retarder felt; lap edges 4 inches; seal joints with bitumen. B. Extend vapor retarder under cant strips and blocking. 3.04 INSULATION INSTALLATION A. Attachment of Insulation: Embed insulation into flood coat mopping of hot bitumen in accordance with roofing and insulation manufacturers' instructions. B. Attachment of Insulation: Embed insulation in flood coat mopping of hot bitumen in accordance with roofing and insulation manufacturers' instructions. C. Lay subsequent layers of insulation with joints staggered minimum 6 inch from joints of preceding layer. D. Lay boards with edges in moderate contact without forcing. Cut insulation to fit neatly to perimeter blocking and around penetrations through roof. E. Tape joints of insulation in accordance with roofing and insulation manufacturers' instructions. F. Do not apply more insulation than can be covered with membrane in same day. 3.05 MEMBRANE APPLICATION Gates Park Pro Shop Reroofing Project#09025 07 51 00 City of Waterloo, Department of Leisure Services BUILT-UP BITUMINOUS ROOFING Waterloo, Iowa Page 4 of 5 A. Equiviscous Temperature(EVT) at Point of Application: In accordance with NRCA and manufacturer recommendations. B. Install ASTM D 2178-97a, Type IV, asphalt impregnated, glass fiber mat reinforced roofing ply membrane in accordance with manufacturer's instructions. Four-ply membrane application. C. Install roofing expansion joints where indicated. Make joints watertight. D. Coordinate installation of roof drains and related flashings. 3.06 AGGREGATE SURFACING A. Apply uniform flood coat of bitumen at rate recommended by manufacturer. B. While flood coat is hot, embed aggregate at rate recommended by manufacturer. C. Sweep away loose aggregate and apply second flood coat of bitumen at a rate recommended by manufacturer. D. While second flood coat is hot, embed aggregate at rate recommended by manufacturer. E. Evenly distribute aggregate and ensure bond with flood coat. Extend aggregate to bottom edge of cant strips. 3.07 ROOF COATING INSTALLATION A. Apply roof coatings in accordance with roofing and coating manufacturers' instructions. 3.08 FIELD QUALITY CONTROL A. Require site attendance of roofing system manufacturer daily during installation o'the Work. 3.09 CLEANING A. Remove bituminous markings from finished surfaces. B. In areas where finished surfaces are soiled by bitumen or other source of soiling caused by work of this section, consult manufacturer of surfaces for cleaning advice and cor form to their documented instructions. C. Repair or replace defaced or damaged finishes caused by work of this section. 3.10 PROTECTION A. Protect installed roofing and flashings from construction operations. B. Where traffic must continue over finished roof membrane, protect surfaces using durable materials. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 07 51 00 City of Waterloo, Department of Leisure Services BUILT-UP BITUMINOUS ROOFING Waterloo, Iowa Page 5 of 5 SECTION 07 62 00 SHEET METAL FLASHING AND TRIM PART 1 GENERAL 1.01 SECTION INCLUDES A Fabricated sheet metal items, including flashings, counterflashings, gutters, and downspouts, 1.02 RELATED REQUIREMENTS A. Section 06 10 00- Rough Carpentry: Wood nailers. B. Section 07 51 00-Built-Up Bituminous Roofing: Roofing system, C. Section 07 90 05-Joint Sealers, 1.03 REFERENCE STANDARDS A. AAMA 2605-Voluntary Specification, Performance Requirements and Test Procedures for Superior Performing Organic Coatings on Aluminum Extrusions and Panels; 2005. B. ASTM A 653/A 653M -Standard Specification for Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron Alloy-Coated (Galvannealed) by the Hot-Dip Process; 2006a. C. ASTM A 666-Standard Specification for Annealed or Cold-Worked Austenitic Stainless Steel Sheet, Strip, Plate, and Flat Bar; 2003, D. ASTM D 226- Standard Specification for Asphalt-Saturated Organic Felt Used in Roofing and Waterproofing; 2006. E. ASTM D 4586 -Standard Specification for Asphalt Roof Cement, Asbestos-Free; 2000 (Reapproved 2006). F. SMACNA(ASMM) -Architectural Sheet Metal Manual; Sheet Metal and Air Conditioning Contractors' National Association; 2003. 1.04 SUBMITTALS A. Shop Drawings: Indicate material profile,jointing pattern,jointing details, fastening methods, flashings, terminations, and installation details B. Samples: Submit two samples 4 x 4 inches in size illustrating metal finish color. 1.05 QUALITY ASSURANCE A. Perform work in accordance with SMACNA Architectural Sheet Metal Manual requirements and standard details, except as otherwise indicated. 1.06 DELIVERY, STORAGE,AND HANDLING A. Stack material to prevent twisting, bending, and abrasion, and to provide ventilation. Slope metal sheets to ensure drainage. B. Prevent contact with materials that could cause discoloration or staining. PART 2 PRODUCTS 2.01 SHEET MATERIALS A. Galvanized Steel: ASTM A 653/A 653M, with G90/Z275 zinc coating; minimum 0.02 inch thick base metal. B. Pre-Finished Galvanized Steel: ASTM A 653/A 653M, with G90/Z275 zinc coating; minimum Gates Park Pro Shop Reroofing Project#09025 07 62 00 City of Waterloo, Department of Leisure Services SHEET METAL FLASHING AND TRIM Waterloo, Iowa Page 1 of 3 0,02 inch thick base metal, shop pre-coated with modified silicone coating. 1, PVDF (Polyvinylidene Fluoride) Coating: Superior Performance Organic Fir sh, AAMA 2605; multiple coat, thermally cured fluoropolymer finish system; Dark Bronze'color to match existing. C Stainless Steel Sheet: ASTM A 666, Type 304. 2.02 ACCESSORIES A. Fasteners: Galvanized steel, with soft neoprene washers. B, Underlayment: ASTM D 226, organic roofing felt, Type I ("No. 15"). C. Primer: Zinc chromate type. D. Protective Backing Paint: Zinc molybdate alkyd. E. Sealant: As specified in Section 07 90 05. F. Plastic Cement: ASTM D 4586, Type I. 2.03 FABRICATION A. Form sections true to shape, accurate in size, square, and free from distortion or Defects. B. Form pieces in longest possible lengths. C. Hem exposed edges on underside 1/2 inch; miter and seam corners. D. Form material with flat lock seams, except where otherwise indicated, At movinc joints, use sealed lapped, bayonet-type or interlocking hooked seams. E. Fabricate corners from one piece with minimum 18 inch long legs; seam for rigidity, seal with sealant. F. Fabricate vertical faces with bottom edge formed outward 1/4 inch (6 mm) and hemmed to form drip. G. Fabricate flashings to allow toe to extend 2 inches over roofing gravel. Return and brake edges. 2.04 GUTTER AND DOWNSPOUT FABRICATION A, Gutters: SMACNA Architectural Sheet Metal Manual, profile to match existing. B. Downspouts: Profile to match existing. C. Gutters and Downspouts: Size indicated. D. Accessories: Profiled to suit gutters and downspouts. 1. Anchorage Devices: In accordance with SMACNA requirements. 2. Gutter Supports: Brackets. 3. Downspout Supports: Brackets E. Seal metal joints. PART 3 EXECUTION 3.01 EXAMINATION A. Verify roofing termination and base flashings are in place, sealed, and secure. 3.02 PREPARATION A. Install starter and edge strips, and cleats before starting installation. Gates Park Pro Shop Reroofing Project#09025 07 62 00 City of Waterloo, Department of Leisure Services SHEET METAL FLASHING AND TRIM Waterloo, Iowa Page 2 of 3 B. Back paint concealed metal surfaces with protective backing paint to a minimum dry film thickness of 15 mil. 3.03 INSTALLATION A. Secure fleshings in place using concealed fasteners. Use exposed fasteners only where permitted. B. Apply plastic cement compound between metal fleshings and felt fleshings. C. Fit fleshings tight in place. Make corners square, surfaces true and straight in planes, and lines accurate to profiles. D. Seal metal joints watertight. E. Secure gutters and downspouts in place using concealed fasteners. F. Slope gutters 1/4 inch per foot minimum, END OF SECTION Gates Park Pro Shop Reroofing Project#09025 07 62 00 City of Waterloo, Department of Leisure Services SHEET METAL FLASHING AND TRIM Waterloo, Iowa Page 3 of 3 SECTION 07 90 05 JOINT SEALERS PART 1 GENERAL 1.01 SECTION INCLUDES A. Sealants and joint backing. 1.02 REFERENCE STANDARDS A. ASTM C 834 -Standard Specification for Latex Sealants; 2005. B. ASTM C 920 -Standard Specification for Elastomeric Joint Sealants; 2005, C. ASTM C 1193-Standard Guide for Use of Joint Sealants; 2005a. 1.03 ADMINISTRATIVE REQUIREMENTS A. Coordinate the work with other sections referencing this section. 1.04 SUBMITTALS A Product Data: Provide data indicating sealant chemical characteristics. 1.05 FIELD CONDITIONS A. Maintain temperature and humidity recommended by the sealant manufacturer di.ring and after installation, PART 2 PRODUCTS 2.01 GENERAL REQUIREMENTS A. All adhesives used on this project (including, but not limited to, adhesives for carpet tile, plastic laminate, wall coverings, adhesive for wood or sealants) shall be those with the lowest possible VOC content below 20 grams per liter and which meet the requirements of the manufacturer of the products adhered or involved. Adhesives and sealants with formaldehyde or heavy metals are prohibited. 2.02 SEALANTS A. Type El -General Purpose Exterior Sealant: Polyurethane; ASTM C 920, Grade: NS, Class 25, Uses M, G, and A; single component, gun grade. 1. Color: Standard colors matching finished surfaces. 2. Product: NP-1 manufactured by Sonneborn; Dynatrol 1 manufactured by P ?cora; PSI 901/RC1 manufactured by Polymeric Systems, Inc.; or approved equivalent. 3. Applications: Use for: a Expansion joints in floor slab b. Joints between masonry, and other materials. c. Other exterior joints for which no other sealant is indicated. B. Type E2 - Exterior Metal Joint Sealant: Butyl or polyisobutylene, nondrying, non skinning, noncuring. 1, Product: Multi-Purpose Sealant manufactured by Sonneborn; BC-158 manufactured by Pecora; PSI 301 manufactured by Polymeric Systems, Inc.; or approved 'valent. 2, Applications: Use for: a. Concealed sealant bead in sheet metal work. Gates Park Pro Shop Reroofing Project#09025 07 90 05 City of Waterloo, Department of Leisure Services JCINT SEALERS Waterloo, Iowa Page 1 of 3 C. Type E3-Exterior Metal Joint Sealant; Single compound silicone elastomeric compound and compatible silicone sealant; conforming to the following; 1. Color: Standard colors matching finished surfaces, or paintable, 2. Class: Class 25 sealant, per ASTM 920. 3. Durability and Longevity: Permanent. 4. Product: "3M Fire Barrier 2000+" manufactured by 3M Fire Protection Products; or approved equivalent. 5. Applications: Use for: a. Heat resistant joints in chimney cap flashing. 2.03 ACCESSORIES A. Primer; Non-staining type, recommended by sealant manufacturer to suit application. B. Joint Cleaner: Non-corrosive and non-staining type, recommended by sealant manufacturer; compatible with joint forming materials. C. Joint Backing: Round foam rod compatible with sealant; ASTM D 1667, closed cell PVC; oversized 30 to 50 percent larger than joint width. D. Bond Breaker: Pressure sensitive tape recommended by sealant manufacturer to suit application, PART 3 EXECUTION 3.01 EXAMINATION A. Verify that substrate surfaces are ready to receive work. B. Verify that joint backing and release tapes are compatible with sealant. 3.02 PREPARATION A. Remove loose materials and foreign matter that could impair adhesion of sealant. B. Clean and prime joints in accordance with manufacturer's instructions. C. Perform preparation in accordance with manufacturer's instructions and ASTM C 1193. D. Protect elements surrounding the work of this section from damage or disfigurement. 3.03 INSTALLATION A. Perform work in accordance with sealant manufacturer's requirements for preparation of surfaces and material installation instructions. B. Perform installation in accordance with ASTM C 1193. C. Measure joint dimensions and size joint backers to achieve width-to-depth ratio, neck dimension, and surface bond area as recommended by manufacturer, except where specific dimensions are indicated. D. Install bond breaker where joint backing is not used. E. Install sealant free of air pockets, foreign embedded matter, ridges, and sags. G. Apply sealant within recommended application temperature ranges. Consult manufacturer when sealant cannot be applied within these temperature ranges. F. Tool joints concave, G Joints in concrete paving and slabs to be level with top surface of concrete. Gates Park Pro Shop Reroofing Project#09025 07 90 05 City of Waterloo, Department of Leisure Services JOINT SEALERS Waterloo, Iowa Page 2 of 3 3.04 CLEANING A. Clean adjacent soiled surfaces. 3.05 PROTECTION A. Protect sealants until cured. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 07 90 05 City of Waterloo, Department of Leisure Services JOINT SEALERS Waterloo, Iowa Page 3 of 3 SECTION 09 90 00 PAINTS AND COATINGS PART 1 GENERAL 1.01 SECTION INCLUDES A. Surface preparation. B. Field application of paints 1.02 REFERENCE STANDARDS A. 40 CFR 59, Subpart D- National Volatile Organic Compound Emission Standards for Architectural Coatings; U.S. Environmental Protection Agency; current edition. B. MPI (APL) -Master Painters Institute Approved Products List; Master Painters and Decorators Association; current edition, www.paintinfo.com. C. MPI (APSM) - Master Painters Institute Architectural Painting Specification Manual; Master Painters and Decorators Association; 2004. 1.03 SUBMITTALS A. Product Data: Provide data on all finishing products. B. Samples: Submit two painted samples, illustrating selected colors and textures for each color and system selected with specified coats cascaded. Submit on cardboard, 4 x 4 inch in size. C Maintenance Data: Submit data on cleaning, touch-up, and repair of painted and coated surfaces. 1.04 DELIVERY, STORAGE,AND PROTECTION A. Deliver products to site in sealed and labeled containers; inspect to verify acceptability. B. Container Label: Include manufacturer's name, type of paint, brand name, lot number, brand code, coverage, surface preparation, drying time, cleanup requirements, color designation, and instructions for mixing and reducing. C. Paint Materials: Store at minimum ambient temperature of 45 degrees F and a maximum of 90 degrees F, in ventilated area, and as required by manufacturer's instructions. 1.05 ENVIRONMENTAL REQUIREMENTS A. Do not apply materials when surface and ambient temperatures are outside the temperature ranges required by the paint product manufacturer. B. Follow manufacturer's recommended procedures for producing best results, including testing of substrates, moisture in substrates, and humidity and temperature limitations. C. Provide approximate lighting level of 80 ft candles measured mid-height at substrate surface during all coating applications. 1.05 EXTRA MATERIALS A. Supply 1 gallon of each color; store where directed. B. Label each container with color in addition to the manufacturer's label. PART 2 PRODUCTS 2.01 MANUFACTURERS Gates Park Pro Shop Reroofing Project#09025 09 90 00 City of Waterloo, Department of Leisure Services PAINTS AND COATINGS Waterloo, Iowa Page 1 of 4 A. Paints: 1. Benjamin Moore Paints: www.benjaminmoore.com. 2. Sherwin-Williams: www,sherwin-williams.com. 3. Diamond-Vogel Paints: www.diamondvogel.com. 4. Pittsburgh Paints; www.pittsburghpaints.com. 5. Substitutions: See Section 01 60 00- Product Requirements. 2.02 PAINTS AND COATINGS -GENERAL A. Paints and Coatings: Ready mixed, except field-catalyzed coatings. Prepare pigments: 1. To a soft paste consistency, capable of being readily and uniformly disperses: to a homogeneous coating. 2. For good flow and brushing properties. 3 Capable of drying or curing free of streaks or sags. 2.03 PAINT SYSTEMS -EXTERIOR A. Dimension Lumber, Primed, Alkyd, 2 Coat: Includes vertical wood paneling: 1. Touch-up with oil/alkyd primer. 2. Satin: Two coats of alkyd enamel to match existing, 2.04 ACCESSORY MATERIALS A. Accessory Materials: Linseed oil, shellac, turpentine, paint thinners and other materials not specifically indicated but required to achieve the finishes specified; commercial quality. B. Patching Material: Latex filler. PART 3 EXECUTION 3.01 EXAMINATION A Verify that surfaces are ready to receive Work as instructed by the product manufacturer, B. Examine surfaces scheduled to be finished prior to commencement of work. Report any condition that may potentially affect proper application. 3.02 PREPARATION A Prepare surfaces as specified in MPI Architectural Painting Specification Manual and as follows for the applicable surface and coating; if multiple preparation treatments are specified, use as many as necessary for best results; where the Manual references external standards for preparation (e.g. SSPC standards), prepare as specified in those standards; comply with coating manufacturer's specific preparation methods or treatments, if any. B. Coordinate painting work with cleaning and preparation work so that dust and other contaminants do not fall on newly painted, wet surfaces. C. Surface Appurtenances: Prior to preparing surfaces or finishing, remove electrical plates, hardware, light fixtures, light fixture trim, escutcheons, machined surfaces, fittings and similar items already installed that are not to be painted. 1. If removal is impractical or impossible because of the size or weight of the item, provide surface-applied protection before preparation and finishing. 2. After completing painting in each space or area, reinstall items removed using workers skilled in the trades involved. D. Surfaces: Correct defects and clean surfaces which affect work of this section. Remove or repair existing coatings that exhibit surface defects. E. Marks: Seal with shellac those which may bleed through surface finishes. F. Exterior Wood to Receive Opaque Finish: Remove dust, grit, and foreign matter. Seal knots, Gates Park Pro Shop Reroofing Project#09025 09 90 00 City of Waterloo, Department of Leisure Services PAINTS AND COATINGS Waterloo, Iowa Page 2 of 4 pitch streaks, and sappy sections, Fill nail holes with tinted exterior calking compound after prime coat has been applied. Back prime concealed surfaces before installation. 3.03 APPLICATION A. Apply products in accordance with manufacturer's instructions and as specified or recommended by MPI Manual, using the preparation, products, sheens, textures, and colors as indicated. 1 Remove, refinish, or repaint work not complying with requirements. B. Do not apply finishes over dirt, rust, scale, grease, moisture, scuffed surfaces, or other conditions detrimental to formation of a durable coating film; do not apply finishes to surfaces that are not dry, C. Use applicators and methods best suited for substrate and type of material being applied and according to manufacturer's instructions. 1 Brush Application: Use brushes best suited for the type of material applied; use brush of appropriate size for the surface or item being painted; produce results free of visible brush marks. 2. Roller Application: Use rollers of carpet, velvet back, or high-pile sheep's wool as recommended by manufacturer for material and texture required. 3. Spray Application: Use airless spray equipment with orifice size as recommended by manufacturer for material and texture required. 4. Where application method is listed in the MPI Manual for the paint system that application method is required; otherwise any application method recommended by manufacturer for material used and objects to be painted is acceptable. D. Minimum Coating Thickness: Apply paint materials no thinner than manufacturer's recommended spreading rate; provide total dry film thickness of entire system as recommended by manufacturer. 1. Number of coats and film thickness required are the same regardless of application method. 2. If undercoats, stains, or other conditions show through final coat of paint, apply additional coats until paint film is of uniform finish, color, and appearance. 3. Give special attention to ensure edges, corners, crevices, welds, and exposed fasteners receive dry film thickness equivalent to that of flat surfaces. E. Apply finish to completely cover surfaces with uniform appearance without brush marks, runs, sags, laps, ropiness, holidays, spotting, cloudiness, or other surface imperfections. 1. Before applying finish coats, apply a prime coat of material recommended by manufacturer, unless the surface has been prime coated by others; where evidence of suction spots or unsealed areas in first coat appear, recoat primed and sealed surfaces to ensure finish coat with no burn through or other defects due to insufficient sealing, 2. Apply first coat to surface that has been cleaned, pretreated, or otherwise prepared as soon as practical after preparation and before subsequent surface deterioration. 3. Do not apply succeeding coats until the previous coat has cured as recommended by manufacturer. 4. Do not recoat until paint has dried to where it feels firm, does not deform or feel sticky under moderate thumb pressure, and application of another coat will not cause the undercoat to lift or lose adhesion. 5. If manufacturer's instructions recommend sanding to produce a smooth, even surface, sand between coats. 6, Before applying next coat vacuum clean surfaces of loose particles Use tack cloth to remove dust and particles just prior to applying next coat. 3.04 CLEANING A. Collect waste material which may constitute a fire hazard, place in closed metal containers, and Gates Park Pro Shop Reroofing Project#09025 09 90 00 City of Waterloo, Department of Leisure Services PAINTS AND COATINGS Waterloo, Iowa Page 3 of 4 remove daily from site. B At the end of each workday, remove empty cans, rags, rubbish, and other discarded paint materials from site. C, Protect other work, whether being painted or not, against damage by painting. Correct damage by cleaning, repairing or replacing, and repainting as approved by Architect. D. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces, Comply with procedures specified in MPI Manual. END OF SECTION Gates Park Pro Shop Reroofing Project#09025 09 90 00 City of Waterloo, Department of Leisure Services PAINTS AND COATINGS Waterloo, Iowa Page 4 of 4