HomeMy WebLinkAboutCANGE ORDER 1 Community Development Block Grant Program
Change Order# 1
Change Order Date: February 23,2009
Owner City of Waterloo Contractor D.W.Zinser Co., Inc.
Address 715 Mulberry Address P.O. Box 398 Walford, IA 53251
Proceed
Case Number 156-D-GO-03--03-08 Date March 9, 2009
The Following change(s) is(are)authorized in the above identified contract: Add Delete
ADD
1. Well Capping by Sawyer Wells F of Fence $7,591.00
2. Soil Compaction Testing by Terracon $1,250.00
THIS BID WAS REVIEWED AND FOUND TO BE COST REASONABLE BY THE UNDERSIGNED
CONTRACTS AND GRANTS COORDINATOR.THE PROPOSED METHOD OF CONSTRUCTION TO CORRECT THE
DEFICIENCIES AND THE MATERIALS TO BE USED ARE SATISFACTORY AND IN COMPLIANCE
WITH THE CITY'S PROGRAM GUIDELINES.
Original Contract Amount: $120,000.00
Increase: $8,841.00 Increase: $ 8,841.00
Decrease: $ - Decrease: $ -
New Total: $ 128,841.00 Net Change: $ 8,841.00