HomeMy WebLinkAboutMANUAL OF PROCEDURE FOR BIDDING 05/26/2010 WED 10: 41 FAX 319 291 4523 Waste Management -,-.-• City Hall 0002/011
GENERAL CONDI'I'l(.)NS
The Manual of the Recommended Procedure for Competitive Bidding and Award of Building Contracts
Construction Council of Iowa, Shall govern this project.
The bid deadline set for the submission of'bids will be strictly adhered to and bids received atler the deadline will be
returned to the bidder unopened.
Lowest Responsible Bidder
The contract will be awarded to the lowest responsible bidder. The term"lowest responsible bidder" implies the
bidder is responsible,not only financially but also in terms of having a reputation fir credible perfirrmance and being
able to perform the contract. The Board has the right to determine if the bidder is responsible,whether the bidder
has bid according to the specifications and whether the other interests of the Board are satisfied by letting the
contract to the bidder(i.e.,best interest to the City of Waterloo).
The City of Waterloo has discretion in awarding the bid to the"lowest responsible bidder". The lowest dollar figure
is only one of the factors the Board may consider. The Board may consider the business,judgement of the bidder,the
bidder's record of liability or performance, financial resources,construction experience,ability to secure required
bonds and insurance coverage. lithe lowest bidder is determined to not be responsible, the Board will furnish
documentation to the bidder with their reasons.
Acceptance of a bid by itself does not constitute a contract. The improvement ordinance, the signed successful bid,
and resolution of the City of Waterloo accepting the bid,where all legal requirements are met,will constitute a
written agreement. -)
7
05/26/2010 WED 10: 41 FAX 319 291 4523 Waste Management City Hall
003/011
SUPPLEMENTARY GENERAL, CONDITIONS
The following supplementary general conditions are intended to modify and expand the referenced General
Conditions and shall be in addition to any and all other requirements_
FRIABLE ASBESTOS
If during the construction of the project work involving friable asbestos or hazardous or toxic substances is
uncovered the owner or the owners representative shall be notified immediately and the owner with his own forces or
by subcontract shall be solely responsible for the selection and complete investigation,removal and disposition of
the friable or hazardous substances not identified in these specifications.
The Contractor shall be indemnified and held harmless from all claims and costs incurred in defending claims based
on friable or hazardous substances discovered at the project.
Contractor shall make any claims for delay or additional costs incurred immediately upon discovery of friable or
hazardous substance. These claims specifically exclude any mishandling of non-friable asbestos by the Contractor
or his subcontractors.
MANUFACTURERS INSTRUCTIONS
All manufactured materials shall be installed as directed by the manufactures published literature. The
manufacturer's literature shall govern unless these specifications are in conflict, in which case the more stringent
shall apply.
RESPONSIBILITY
The Contractor shall assume full responsibility for any and all damage to the building; its contents or grounds caused
by work associated with this project,either by their own forces or a subcontractor employed by the Contractor.
TAXES
The Contractor shall be responsible for their subcontractors and suppliers to pay all Federal,State and local taxes
including Iowa Sales and Use Taxes for all supplies and materials used and made part.of these projects. The
Contractor is required to include in his bid the Iowa Sales tax and shall pay the tax to the State. The Contractor shall
submit to the owner upon completion and acceptance of the work information necessary to enable the Owner to
request refund of Taxes for materials and supplies refundable per Iowa Code 422.45(7). The Owner will provide
the proper forms for this information.
PERMIT FEES
The contractors shall pay for any required permits including all work associated with the project.
BUILDING CODE
All work under this specification shall be in strict accordance with requirements of the local Code Authority.
8
05/26,/2010 WED 10: 41 FAX 319 291 4523 Waste Management --- City Hall l 004/011
EQUAL EMPLOYMENT OPPORTUNTY
During performance of this the Contractor agrees to the following;
The Contractor will not discriminate against any employee or applicant for employment because of race,creed,
color,religion, national origin, sex,age or physical or mental disability. The Contractor will take affirmative action
to ensure that applicants are employed and that employees are treated during employment without regard to their
race, creed,color,religion,national origin,sex,age or physical or mental disability except where it relates to a bona
fide occupational qualification. Such action shall include but not be limited to the following: employment,
upgrading,demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other
forms of compensation; and selection for training, including apprenticeship.
AWARD OF SUBCONTRACTS
No payments shall be made until a subcontractor and supplier list is submitted to the Owner.
CHANGE ORDERS
No changes shall be made to the contract price until authorized by the Owner in writing.
OCCUPATIONAL SAFETY & HEALTH ACT
The Contractor shall be responsible for compliance with all applicable State and Federal Safety and Health
requirements.
PROJECT START DATES AND COMPLETION DATES, PENAL SUM
Time is of the essence on this project. Work may commence after the notice of award and will be substantially
complete on or before the 30th of July 2010 or be subject to$ 100.00 per day penal sum.
INSURANCE REQUIREMENTS
Liability Insurance
The Contractor shall purchase and maintain Comprehensive General Liability Insurance and Comprehensive
Automobile Liability Insurance to cover operations of the Contractor and their subcontractors,product and
completed operations, personal injury, and contractual liability to include coverage for the Hold Harmless and
Indemnification required as part of this project.
Minimum limits of Liability shall be,
Comprehensive General Liability including Premises-Operation; Independent Contractor's Protection; Products and
Completed Operations
Bodily Injury $ 500,000.00 each occurrence
$ 1,000,000,00 annual aggregate
Property Damage $ 500,000.00 each occurrence
$ 1,000,000.00 annual aggregate
Products and completed operations to be maintained for one year after final payment,
9
05/26./2010 WED 10: 42 FAX 319 291 4523 Waste Management --b-• City Hall lJ005/011
Property Damage Liability Insurance will provide X",C"and U" coverage for Explosion,Collapse, and
Underground Hazard Exposures.
Contractual Liability:
Bodily Injury $ 500,000.00 each occurrence
Property Damage $ 500,000.00 each occurrence
$ 1,000,000.00 annual aggregate
Personal Injury, with Employment Exclusion deleted;
$ 1,000,000.00 annual aggregate
Comprehensive Automobile Liability
Bodily Injury $ 500,000.00 each person
$ 1,000,000.00 each occurrence
Property Damage $ 500,000.00 each occurrence
The limits of liability may be covered by a combination or the above-described policy and any Umbrella Excess
Liability attachment in the amount of$ 1,000,000.00.
The Contractor shall either require each of their subcontractors to procure and maintain during the life of their
subcontract,public liability and property damage coverage of the type and amounts specified above or insure the
subcontractor's activities with his own policy.
Insurance on equipment,tools, sheds,plant,etc. shall be covered by the Contractor
Workman Compensation Insurance
The Contractor shall purchase and maintain Worker's Compensation including$ 100,000.00 Employers Liability
Coverage Statutory for State and Statutory for applicable Federal.
The Contractor shall purchase and maintain in a company or companies lawfully authorized to do business in the
jurisdiction in which the project is located coverage as stated above. The City of Grundy Center is to be named as
additional insured on all policies. And to the fullest extent permitted by law the Contractor shall indemnify and hold
harmless the Owner.
10
05/26/2010 WED 10: 42 FAX 319 291 4523 Waste Management --- City Hall 2006/011
DIVISION I — GENERAL_, REQUIREMENTS
SUMMARY OF WORK
This section provides an outline of the work required for rooting the Administration Building at the Waterloo Waste
Water Treatment Facility.
The contractor shall provide all materials,equipment, methods and means necessary to complete the required work
including all demolition and repair as called out in the specifications.
RELATED SUBCONTRACTORS
The Contractor will be responsible for the work of any subcontractors including sheet metal work,asbestos
abatement,plumbing, electrical etc. which is required to complete the project. Scheduling is the responsibility of the
Contractor and must be completed in an orderly and timely manner within the projects time frame.
USE OF SITE AND PREMISES
Access to the roof areas will be arranged with the Owners representative. The Owner will maintain uninterrupted use
of each building.
The Owner shall furnish electricity if needed. All wiring for the transmission of electrical service, temporary or
otherwise is the Contractors responsibility.
Contractor will be responsible for protection of the building and grounds. Any damage caused by the contractor shall
be repaired at no additional cost to the owner.
The Contractor is expected to coordinate the storage of material with the Owners representative in order to place
material in an area that will be convenient to the Administration Building. This also applies to equipment access to
the buildings.
The Contractor is responsible for furnishing sanitation facilities and drinking water.
The Contractor shall protect the Owners property as needed to ensure ii is left in the same condition as when the
project began.
The Contractor is responsible for maintaining the project in a clean and watertight condition at the end of each day's
work.
All demolition shall be removed from site and disposed of legally.
PRE-ROOFING CONFERENCE
After award of project, the Contractor,their supervisory personal, and the Owner representative shall meet at an
agreed upon location to coordinate the execution of the work. The Contractor shall furnish the owner a list of their
off-hour emergency contacts and phone numbers.
The Contractor shall furnish to the Owner before this meeting all required bonds, permits,schedule of values,
required notification of State regulatory authorities, proof of insurance, and a list of subcontractors and suppliers as
needed.
ll
05/26/2010 WED 10: 42 FAX 319 291 4523 Waste Management -.-.-. City Hall 0007/011
ALLOWANCES
There are no allowances included in this contract.
APPLICATION FOR PAYMENT
No payments will be made until the following have been submitted;
Pre-Construction Meeting
All necessary Bonds& Insurance Coverages are on file
Permit is purchased and copy is on file
List of subcontractors and suppliers is on file
Documentation of any required manufacturer's warranties
BI-MONTHLY PAYMENT APPLICATIONS
Payment request will be submitted on MA Document G702&(1703. It shall be signed by an authorized agent of the
Contractor and notarized.
Contractor shall show retainage of 5%of completed work amount to be held from each application for payment.
Upon substantial completion of the entire work and acceptance by the Owner the Owner may authorize payment of
up to 95%of the contract amount. Upon completion of the project to the satisfaction of the City of Waterloo and
after all required warranties, lien waivers,tax refund forms,etc. are on file the Owner will release the remaining 5%
for payment.
ALTERNATES
There are no alternate prices required for this project.
VOLUNTARY ALTERNATES
No voluntary alternates will be accepted or considered for the projects included in these specifications.
ADDENDA
Changes to the specifications will be done by written addenda and must be acknowledged on the space provided on
the BID FORM.
Changes in Contract price will require written acceptance by the Owners representative and will require
photographic documentation by the Contractor. The Owner will furnish the Contractor written acceptance of the
change based on unit prices and shall issue a change in the purchase order to reflect the change in price.
12
05/26/2010 WED 10: 42 FAX 319 291 4523 Waste Management City Hall ll008/011
DESCRIPTION OF EXISTINC CONDITIONS
The existing roof assembly consists of a 60-mil 1'.Pl)M ballasted roof system over 1/8"tapered expanded polystyrene
over two-plies of type 1115 rag felt installed with hot asphalt over a mechanically attached layer of'A" gypsum board.
SCOPE OF WORK
The existing ballast rock, edge metal, EPDM membrane,and tapered extruded polystyrene are to be removed and
disposed of.
The roofing contractor is expected to raise all roof penetrations to maintain a minimum of 8"of flashing height.
Install a 1/8"tapered isocyanurate system(min.2.5")and aV,"primed dens deck over the vapor barrier.
Mechanically attach the isocyanurate and dens deck assembly through the vapor seal to the steel roof deck in a
manner that meets or exceeds a 1-60 wind uplift rating.
Install a fully adhered 60-mil EPDM rubber membrane over the mechanically attached insulation assembly.
Furnish and install new perimeter edge metal, roof jacks for heat stacks, pipe boots, pitch pockets,and all other
roofing related sheet metal to complete the project.
Provide a manufacturers 20-year No Dollar Limit warranty and a Midwest Roofing Contractors two-year
Workmanship warranty upon completion of the project.
Note: Roofing Contractor to include all costs associated with removal and reinstallation of the mechanical
equipment in order to properly install the new roof system.
13
05/26/2010 WED 10: 42 FAX 319 291 4523 Waste Management - -- City Hall Z009/011
DIVISION VII — MOISTURE PROTECTION
SINGLE PLY ROOF SYSTEMS,ONE PLY, EULLY-ADflERE,D
The following specification is for the replacement of the Administrative Building roof located at the Waterloo Waste
Treatment Facility located at 3505 (Easton Avenue, Waterloo, Iowa.
SUMMARY OF WORK
This project will consist of removing the existing ballasted roof system and hauling it oft-site. 'l'he contractor will
then install a new fully adhered roof system as detailed in this document. The project also includes installation of
new shop fabricated roof edge metal and installation of new shop fabricated countertlashing for roof to wall flashing
details at the clear story window. Contractor will furnish owner with manufacturer's twenty-year(20 yr)NDI,type
warranty upon project completion.
Contractor shall be responsible for his own measurements and drawings.
Contractor shall adhere as closely as possible to standards set forth in the most recent issue of NRCA Roofing and
Waterproofing Manual for proper detailing and installation of FPDM roofing.
Contractor shall employ skilled applicators and maintain full-lime on site supervision during this project.
Contractor shall be a firm specializing in low slope roofing that has been in business a minimum of five years.
To indicate compliance with the specification, upon completion of the reroofing project submit to the owner a
complete list of all materials used including manufacturer's name and product information.
ROOFING SPECIFICATION
Remove and dispose of the existing ballast rock, EPDM membrane,and tapered expanded polystyrene roof
insulation.
Contractor is responsible for disconnect and reconnect of rooftop FHVAC and electrical as necessary. All
disconnects are to be reconnected after the roof is completed.
Contractor shall notify owner's representative of any necessary structural repairs. Any work the contractor is
directed to perform will be an extra above the contract price.
Raise all curbs, edges,control joints and expansion joints to accommodate the new insulation height.
Install a 1/8"tapered isocyanurate system(min. 2.5")and a '/" primed dens deck over the vapor barrier. The board
is to be installed with no gap or joints larger that '/". Insulation is to be neatly fitted around penetrations and firmly
butted against curbs skylights and walls. No more insulation shall be installed than can be covered with the required
membrane specification on the same day. Stagger/offset layers of insulation a minimum of 6".
Mechanically attach the isocyanurate and dens deck assembly through the vapor seal to the steel roof deck in a
manner that meets or exceeds a 1-60 wind uplift rating.
14
05/26/2010 WED 10: 42 FAX 319 291 4523 Waste Management ��-. City Hall 1f010/011
Place 60-mil EPDM rubber without stretching over the insulation. Allow the 60-mil membrane to relax for
approximately 1/2 hour. Sheet will be free of buckles and wrinkles. Install fully-adhered 60-mil roof membrane by
folding the sheet back in half to expose the underside of the membrane. Using the membrane manufstcturcr's
bonding adhesive and a short nap roller apply the bonding adhesive to the membrane and the insulation at
manufacturer recommended rates. Allow adhesive to dry until it is tacky. Roll the membrane into the substrate
while the adhesive is still tacky. Brush the bonded area immediately with a soft broom to insure a solid bond. Repeat
the process until the membrane is fully adhered. Do not apply bonding adhesive to the splice area.
Membrane splice will be formed using the manufacturer's seam tape. Clean the splice area of the both sheets using
the membrane manufactures' splice cleaning material until dirt, dust, and foreign material that will interfere with
splicing is removed. The splice area should be black in color when this procedure is finished. Splice area shall be
dry and clean. Prepare the seam with manufacturers' approved primer. Splices are to be installed in strict
accordance with the membrane manufacturer's procedures to insure splices are assembled correctly.
After the splice has been assembled, install T scam patches, and if required, install lap sealant in strict accordance
with the membrane manufacturer's procedures.
Additional membrane securement is required at the perimeter of each roof section, level, curb flashing, skylight,
penthouse, expansion joint, etc. and where any angle change exceeds 2" per one foot of horizontal rise. This
additional securement will be accomplished using the manufacturer's reinforced perimeter fastening strip. This strip
will be mechanically attached using threaded screw type fasteners and 2" seam plates that attach it to the structural
substrate. Fasteners in the strip shall be placed a minimum of one per lineal foot.
Properly flash in strict accordance with the manufacturer's procedures and methods all sheet metal, drains, sewer
vent stacks, and other roof projections and penetrations so the final roof assembly will be warrantable by the
membrane manufacturer for a period of fifteen years,and is watertight and free from defects due to workmanship.
Install new perimeter edge metal and counter flashing using shop fabricated 29 Ga. prefinished galvanized sheet
metal,Color Klad Brand or equal. This work is to be installed in a watertight manner, free from waves,warps,
buckles, or distortion,allowing for expansion and contraction.
As a requirement of the project the contractor will survey this roof application each year for a period of two years
and repair any defects in the roof assembly. The results of the inspection and any necessary repairs will be submitted
in writing to the City of Waterloo. This survey,report,and necessary repairs will be done at no cost to the owner.
Furnish a signed copy of Iowa Roofing Contractors Association guarantee to the owner for this project. Guarantee
period will be two(2)years.
Supply the owner with a signed written copy of the membrane manufactures twenty (20)-year warranty covering,
insulation, fasteners, membrane and related flashing, and workmanship, and a copy of the membrane manufacturer
20-year material warranty. Acceptable manufacturers for this project will be Carlisle, Firestone,Genflex or Versico,
the warranties will include the roof insulation, fasteners,membrane and related accessories, all materials installed in
this roof system with the exception of the sheet metal shall be furnished by a single source, that source being the
membrane manufacturer.
15
05/26,/2010 WED 10: 42 FAX 319 291 4523 Waste Management --- City Hall 2011/011
DIVISION VII — MOIS'i'URE, PROTECTION
FLASHING AND SHEET METAL
SUMMARY OF WORK
This section includes furnishing all necessary labor,material and equipment needed to install sheet metal work as
called out in the specifications. it shall include all necessary sheet metal required to complete the project.
Contractor shall be responsible for his own measurements and drawings.
Contractor shall adhere as closely as possible to standards set forth in the most recent addition of the NRCA Roofing
and Waterproofing Manual and comply with the details called out in the latest addition of the SMACNA Manual for
workmanship, design,joining and attachment of the sheet metal components.
Contractor shall employ skilled applicators and maintain full time on site supervision during this project.
Contractor shall be a firm specializing in architectural sheet metal that has been in business a minimum of five years.
Terms and condition set forth in the General and Supplementary Conditions are applicable to this section.
Prefininshed metal shall carry a written 20-year non-prorated warranty covering fade,chalking, and film integrity.
Upon delivery of sheet metal components to the project sites place in area protected from the weather. Components
are to be carefully handled to protect from scratching and denting, prior to installation. Dented, scratched or
damaged components will be removed form the projects and replaced at no additional cost to the Owner.
Prefinished metal,Color Klad by Vincent Metals, and UNA-Klad by Copper Sales are acceptable for use,
Galvanized iron to be galvanized iron sheet or copper as called out in the specifications. Prefinished metal shall be
24 gauge extra smooth, primed both sides and factory painted on one side with Kynar 500/Flylar based
fluoropolymer coating system. Standard colors to be selected,
Fasten the sheet metal to blocking and grounds per SMACNA recommendations,
All seams to be caulked and sealed watertight.