HomeMy WebLinkAboutCHANGE ORDER NO. 2 CHANGE ORDER NO. 2
Owner: City of Waterloo,Iowa
Date: July 10,2009
Project: Storage Building-Water Pollution Control Facility
Contractor: Prairie Construction Company,Inc.
Owner's Contract No.: ---
$ 314,823.00
Date of Contract Start:
You are directed to make the following changes in the Contract Documents. Description:
Overexcavate Material at Footings and Replace Unsuitable Material With Clean Crushed Stone: Cost Breakdown Attached
Reason for Change Order:
Encountered unsuitable material during excavation for building footings.
CONTRACT TIMES(Calendar Days)
CONTRACT PRICE
To Completion
Original:
$ 314,823.00 Original: June 30,2009
Previous C.O.s(ADD/DEDUCT): $
1,668.00 Previous C.O.s(ADD/DEDUCT): 65 Days
This C.O.(ADD/D£41JC4): $ 7,460.60 This C.O.(ADD/DEDUCT):
Contract Price With All Approved September 3,2009
Change Orders: $ 323,951.60 REVISED:
Original Completion Date: June 30,2009
Revised Completion Date: September 3,2009
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s)ordered herein,including all impact,delays,and
acceleration costs. Other than the dollar amount and time allowance listed above,there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
APPROVED:
By: OL..ZL Date:
Omer(Authoriz:. Signature)
ACCEPTED: /
�1/ , �0 July 14, 2009
By: .cGw
Contrac or(Authorized Signa re Date:
Michael L. Christiason, President
AECOM
106083 2
Project No. Change Order No.
106083/Adm/00-CO No. I.doc