HomeMy WebLinkAboutPROJECT WORKSHEETS AND PROJECT APPLICATION SUMMARY - 7/23/2007 .0001/7Mil
Fields of Opportunities STATE OF IOWA
CHESTER J.CULVER DEPARTMENT OF PUBLIC DEFENSE
GOVERNOR IOWA HOMELAND SECURITY AND
EMERGENCY MANAGEMENT DIVISION
PATTY JUDGE DAVID L.MILLER,ADMINISTRATOR
LT.GOVERNOR
July 23, 2007
Ms. Nancy Eckert, City Clerk Disaster#: DR-1688-IA
City of Waterloo PA ID #: 013-82425-00
715 Mulberry Street Package#(s): 66
Waterloo, IA 50703
Dear Ms. Eckert:
Enclosed are copies of your Project Worksheets (PW's) and Project Application Summary (P.2), for your Public
Assistance application.
It is very important that you review each Project Worksheet for:
• accuracy/completeness;
• the scope of work to determine differences, if any, between the Project Worksheet and what
was agreed upon when the site was inspected;
• calculation errors and corresponding dollar amounts.
If there are specific issues or discrepancies on a Project Worksheet you need to notify the Public Assistance
Officer immediately. Remember, you have 30 days from the receipt of this letter to request to have any issue
reconsidered for eligibility.
When all of your small projects are 100% complete, or when any one of your large projects is 100%
complete, please notify the Public Assistance Office of Iowa Homeland Security and Emergency Management
Division so that we may begin the closeout process. Remember, in the event that your actual project costs
exceed the approved amount shown on the project worksheet, you have 60 days from the date on which the
project work was completed to officially request a project cost adjustment, which must include documentation of
all project costs.
Payments received from Iowa Homeland Security and Emergency Management Division should be redeemed
upon receipt, regardless of the status of the respective project(s) they pertain to. The Catalog of Federal
Domestic Assistance (CFDA) number may be found on the"Payment Voucher"form enclosed with each warrant.
All records of work associated with the claimed costs on every project are to be maintained for a minimum of
three (3) years from the closing date of the grant or sub-grant and are subject to State and Federal review under
the "Single Audit Act, as amended" and the "Single Audit Act Amendments of 1996, as amended".
The Office of Management and Budget Circular A-133, the "Single Audit Act, as amended", and the "Single Audit
Act Amendments of 1996, as amended", require that Non-Federal entities that expend $500,000.00 or more in a
year in Federal awards shall have a single audit conducted. A program specific audit may be conducted in place
of a single audit if the auditee meets the terms specified in Office of Management and Budget Circular A-133
§ .200, paragraph C.
If there is a "finding" relating to a Federal program administered by Iowa Homeland Security and
Emergency Management Division:
A copy of the official audit must be submitted within nine (9) months of the end of the auditee's fiscal year
to:
State Fiscal Office
Department of Public Defense
7105 NW 70th Avenue, Bldg B-61
Johnston, IA 50131
If there are no "findings"
A copy of the audit report is not required, but the auditee shall provide written notification that:
♦ an audit was conducted, including -
entity (auditee) name
Catalog of Federal Domestic Assistance (CFDA) number(s)
the period covered by the audit
dollar amount expended
♦ the schedule of findings and questioned costs disclosed no audit findings relating to Federal
award(s) administered by Iowa Homeland Security and Emergency Management Division
♦ the summary of schedule of prior audit findings did not report on the status of any audit findings
related to Federal award(s) administered by Iowa Homeland Security and Emergency Management
Division
If you have any questions or concerns, please call the Public Assistance Office of Iowa Homeland
Security and Emergency Management Division at (515) 725-3231.
Sincerely,
Pevc 45 rf a.rper
Dennis Harper
State Public Assistance Officer
Enclosures
7105 NW 70th AVENUE/CAMP DODGE/ BLDG. W-4/JOHNSTON, IOWA 50131-1824 /515-725-3231
W W W.IOWAHOMELANDSECURITY.ORG
DATE:07/23/2007 FEDERAL EMERGENCY MANAGEMENT AGENCY
PROJECT APPLICATION SUMMARY (P.2)
DISASTER#: 1688
PACKAGE NO: 66
P.A. ID: 013-82425-00 APPLICANT: WATERLOO,CITY OF
PW# VSN CAT INF COST SHR PROJECTED COMPL DATE APPROVED PW AMOUNT
943 0 E N N 09/14/2008 $2,750.00
Site Number: 1
DAMAGED HAZARD MATERIAL TRNG CENTER
FACILITY:
1925 NEWELL STREET,WATERLOO, IOWA 50707
FACILITY
LOCATION: THE APPLICANT HAS RECEIVED QUOTES FROM TWO COMPANIES TO DO REPAIRS;SERVICE ROOFING
COMPANY AND KOCH CONSTRUCTION.THEY HAVE OPTED TO USE SERVICE ROOFING COMPANY FOR$2,750.00.
SCOPE OF WORK: THEY DID THE ORIGINAL ROOFING(10 YEARS AGO)AND DID RE-ROOFING 8 YEARS AGO.COPIES OF EACH
ATTACHED TO PW.
ALL COSTS SEEM REASONABLE.
PROPERTY INSURANCE DECLARATION PAGE ATTACHED.APPLICANT HAS$50,000.00 DEDUCTIBLE.
1 PW $AMOUNT ELIGIBLE $FEDERAL SHARE
PWs: $2,750.00 $2,062.50
SUBGRANTEE ADMIN EXP: $55.00 $55.00
TOTAL: $2,805.00 $2,117.50
Page 1 of 2
DATE:07/23/2007 FEDERAL EMERGENCY MANAGEMENT AGENCY
PROJECT APPLICATION SUMMARY(P.2)
DISASTER#: 1688
PACKAGE NO: 66
GRAND TOTAL: 1 PW
$AMOUNT ELIGIBLE $FEDERAL SHARE
PWs: $2,750.00 $2,062.50
SUBGRANTEE ADMIN EXP: $55.00 $55.00 GRANTEE
TOTAL: $2,805.00 $2,117.50 ADMIN EXP: $10.59
APPROVED BY: RICHARD CRUSE DATE: 07/13/2007
DISASTER RECOVERY MANAGER
Page 2 of 2
PROJECT WORKSHEET REPORT
DECLARATION NO. FEMA-IA-DR1688 PREPARED DATE 06/27/2007
FIPS NO. 013-82425-00
REPORT DATE 07/20/2007 15:19
APPLICANT NAME WATERLOO,CITY OF
SUBDIVISION INF TYPE O INF
• NON-INF
FEMA PW# 943 VSN 0 REF# WLOO-E1 0 REC
CATEGORY E. Public Buildings COUNTY BLACK HAWK FUNDING OPTION COST SHARE 0.75
STD PROJECT NO. 599 PROJECT TITLE PUBLIC BUILDINGS AND FACILITIES
PROJECTED CMPLTN DT 09/14/2008 ACTUAL CMPLTN DT WORK COMPLETE AS OF 06/27/2007 0 %
ELIGIBILITY Yes AMOUNT ELIG$2,750.00 FEDERAL SHARE $2,062.50 PRIORITY Normal
BEGIN DESIGN DT BEGIN CONSTR DT —PW REVIEWER DATA
END DESIGN DT END CONSTR DT REVIEWER NAME DATE
INITIAL REVIEW WELTON,GEORGIA 06/29/2007
PREPARER DIAZ,C FINAL REVIEW CRUSE,RICHARD 07/05/2007
ROLE PO DATA SOURCE Paper
STATE
MT PROP 0 Yes• No VALIDATED • Yes 0 No
DATE OBLGTD 07/13/2007 PACKAGE DATE 07/13/2007 PNP QUESTIONS 0 Yes• No STATE RVWD 0 Yes• No
PACKAGE ID 66 ATTACH • Yes 0 No
Does the Scope of Work change the pre-disaster conditions at the site? 0 Yes • No 0 Unsure
Special Considerations issues included? Yes 0 No 0 Unsure
Is there insurance coverage on this facility? • Yes 0 No 0 Unsure
Hazard Mitigation proposal included? 0 Yes • No 0 Unsure
Page 1 of 6
PROJECT WORKSHEET REPORT
DECLARATION NO.FEMA-IA-DR1688 PREPARED DATE 06/27/2007
FIPS NO, 013-82425-00
APPLICANT NAME WATERLOO,CITY OF REPORT DATE 07/20/2007 15:19
SUBDIVISION INF TYPE 0 INF
NON-INF
FEMA PW# 943 VSN 0 REF# WLOO-E1 0 REC
SITE NUMBER 1 of 1
FACILITY NAME HAZARD MATERIAL TRNG CENTER Latitude
ADDRESS Longitude
CITY STATE IA ZIP
Was this site previously damaged?0 Yes 0 No Unsure
SITE NUMBER 1 -LOCATION
1925 NEWELL STREET,WATERLOO, IOWA 50707
SITE NUMBER 1 -DAMAGE DIMENSIONS AND DESCRIPTION
COMMENCING ON FEBRUARY 23RD THRU MARCH 2ND,2007.A SEVERE WINTER STORM OCCURRED THAT DEPOSITED EXCESSIVE
ICING UP TO 1 INCH THICK THROUGHOUT THE CITY OF WATERLOO, IOWA.
THE CITY'S HAZARDOUS MATERIALS REGIONAL TRAINING CENTER BUILDING WAS COVERED IN ICE.THE APPROXIMATELY TOTAL
SF OF ROOF=6900 SF.THE PERCENT DAMAGED=30-50 PERCENT OF THE ROOF, PER BUILDING COORDINATOR PAT BROCKWAY.
THE DAMAGE WAS CREATED FROM SHARP ICE FORMATIONS FALLING FROM THEIR COMMUNICATION TOWER ON TO THE FLAT
ROOF MADE OF'RUBBERIZED BLADDER'MATERIAL,CREATING HOLES AND DAMAGING THE ROOF TOP ABOVE A SMALL PORTION OF
THE ADMINISTRATIVE OFFICES AND THE ADJOINING CLASSROOMS. SEE ATTACHED DRAWING AND PICTURES.
SITE NUMBER 1 -SCOPE OF WORK
THE APPLICANT HAS RECEIVED QUOTES FROM TWO COMPANIES TO DO REPAIRS;SERVICE ROOFING COMPANY AND KOCH
CONSTRUCTION.THEY HAVE OPTED TO USE SERVICE ROOFING COMPANY FOR$2,750.00.
THEY DID THE ORIGINAL ROOFING(10 YEARS AGO)AND DID RE-ROOFING 8 YEARS AGO.COPIES OF EACH ATTACHED TO PW.
ALL COSTS SEEM REASONABLE.
PROPERTY INSURANCE DECLARATION PAGE ATTACHED.APPLICANT HAS$50,000.00 DEDUCTIBLE.
Page 2 of 6
PROJECT WORKSHEET REPORT
DECLARATION NO. FEMA-IA-DR1688 PREPARED DATE 06/27/2007
FIPS NO. 013-82425-00
APPLICANT NAME WATERLOO,CITY OF REPORT DATE 07/20/2007 15:19
SUBDIVISION INF TYPE 0 INF
FEMA PW# 943 VSN 0 REF# WLOO-E1 NON-INF
� REC
COST ESTIMATE
ITEJ VSN OD L MATERIAL AND/OR DESCRIPTION J UOMJ I QTY UNIT PRICE COST
1 0 0000 WORK TO BE COMPLETED 0 0 $.00 $0.00
2 0 9003 CONTRACT COSTS LS 1 $2,750.00 $2,750.00
Eligible Amounts: Total(this version) $2,750.00
Total Oblig To Date $2,750.00
Unobligated+Obligated $2,750.00
Federal Share for Obligated and Unobligated $2,062.50
SPECIAL CONSIDERATIONS
1 Does the damaged facility or item of work have insurance coverage and/or is it an insurable risk
(e.g., buildings,equipment,vehicles,etc.)? • Yes 0 No 0 Unsure
COMMENTS: 06/28/2007 15:36:55 CITY HAS$50,000.00 DEDUCTIBLE FOR EACH INCIDENT.
2 Is the damaged facility located within a floodplain or coastal high hazard area and/or does it have
an impact on a floodplain or wetland? Yes • No Unsure
3 Is the damaged facility or item of work located within or adjacent to a Coastal Barrier Resource
System Unit or an Otherwise Protected Area? Yes • No Unsure
4 Will the proposed facility repairs/reconstruction change the pre-disaster conditions(e.g.,footprint,
material, location,capacity,use or function)? Yes No 0 Unsure
5 Does the applicant have a hazard mitigation proposal or would the applicant like technical
assistance for a hazard mitigation proposal? Yes • No Unsure
6 Is the damaged facility on the National Register of Historic Places or the state historic listing?Is it
older than 50 years?Are there more,similar buildings near the site? Yes • No Unsure
7 Are there any pristine or undisturbed areas on,or near,the project site?Are there large tracts of
forestland? 0 Yes • No 0 Unsure
8 Are there any hazardous materials at or adjacent to the damaged facility and/or item of work?
Yes • No 0 Unsure
g Are there any other environmental or controversial issues associated with the damaged facility
and/or item of work? Yes • No Unsure
Page 3 of 6
PROJECT WORKSHEET REPORT
DECLARATION NO.FEMA-IA-DR1688
PREPARED DATE 06/27/2007
FIPS NO. 013-82425-00
APPLICANT NAME WATERLOO,CITY OF REPORT DATE 07/20/2007 15:19
SUBDIVISION INF TYPE O INF
FEMA PW# 943 VSN 0 REF# WLOO-E1 • NON-INF
0 REC
ENVIRONMENTAL -All Environmental Review is complete.
Laws and Executive Orders Review-All Other Laws/EOs complete.-GWELTON1
Laws/EOs Status
Coastal Barriers Resources Act(CBRA) Gen Revw/NA
Clean Water Act(CWA) Gen Revw/NA
Coastal Zone Management Act(CZMA) Gen Revw/NA
Endangered Species Act(ESA) Gen Revw/NA
Fish and Wildlife Coordination Act(FWCA) Gen Revw/NA
National Historic Preservation Act(NHPA) Gen Revw/NA
Clean Air Act(CAA) Gen Revw/NA
E.O. 11988: Floodplains Gen Revw/NA
E.O. 11990:Wetlands Gen Revw/NA
E.O. 12898: Environmental Justice for Low Income and Minority Populations Gen Revw/NA
NEPA Level of Review-07/20/2007 15:19:00-This project is statutorily excluded from the requirements of the National Environmental Policy Act
and no other environmental review or documentation is required.-GWELTON1
Page 4 of 6
•
PROJECT WORKSHEET REPORT
DECLARATION NO.FEMA-IA-DR1688
PREPARED DATE 06/27/2007
FIPS NO. 013-82425-00
APPLICANT NAME WATERLOO,CITY OF REPORT DATE 07/20/2007 15:19
SUBDIVISION INF TYPE 0 INF
FEMA PW# 943 VSN 0 •
NON-INF
REF# WLOO-E1 0 REC
Standard Conditions
1. Any change to the approved scope of work will require re-evaluation for compliance with NEPA and other Laws and Executive Orders.
2. This review does not address all federal, state and local requirements.Acceptance of federal funding requires recipient to comply with all federal,state
and local laws. Failure to obtain all appropriate federal,state and local environmental permits and clearances may jeopardize federal funding.
3. If ground disturbing activities occur during construction, applicant will monitor ground disturbance and if any potential archeological resources are
discovered,will immediately cease construction in that area and notify the State and FEMA.
GENERAL COMMENTS
STRUCTURE REPAIR
THIS PROJECT IS FOR REPAIR/RESTORATION OF STRUCTURES TO PREDISASTER CONDITION. REPAIR/REPLACEMENT TO
PREDISASTER CONDITION IS STATUTORILY EXCLUDED FROM FURTHER REVIEW UNDER THE NATIONAL ENVIRONMENTAL POLICY
ACT. PROJECTS THAT ONLY AFFECT STRUCTURES LESS THAN 50 YEARS OLD DO NOT REQUIRE HISTORIC PRESERVATION REVIEW.
THE APPLICANT HAS IDENTIFIED NO ENVIRONMENTAL ISSUES WITH THIS PROJECT.PAUL CHINN 6/28/2007
RECORD MAINTENANCE
COMPLETE RECORDS AND COST DOCUMENTS FOR ALL APPROVED WORK MUST BE MAINTAINED FOR AT LEAST 3 YEARS FROM THE
DATE THE LAST PROJECT WAS COMPLETED OR FROM RECEIPT OF FINAL PAYMENT,WHICHEVER IS LATER. ALL APPROVED PWS
WITHIN A PROJECT APPLICATION ARE SUBJECT TO RANDOM AUDITS. QUARTERLY REVIEWS ARE CONDUCTED ON ALL APPROVED
PW'S WHICH EQUAL OR EXCEED$59,700 AND HAVE NOT RECEIVED FINAL PAYMENT. ANY JURISDICTION RECEIVING$500,000 OR
MORE IN TOTAL FEDERAL FINANCIAL ASSISTANCE IN A FISCAL YEAR MUST SUBMIT A COPY OF ITS SINGLE AUDIT(AS REQUIRED BY
THE SINGLE AUDIT ACT OF 1984)TO THE STATE.-PAUL CHINN 6/28/2007
Page 5 of 6
PROJECT WORKSHEET REPORT
DECLARATION NO.FEMA-IA-DR1688
FIPS NO. 013-82425-00
PREPARED DATE 06/27/2007
APPLICANT NAME WATERLOO,CITY OF REPORT DATE 07/20/2007 15:19
SUBDIVISION INF TYPE Q INF
FEMA PW# 943 VSN 0 •
NON-INF
REF# WLOO-E1 O REC
PW REQUIRED REVIEWS
REVIEW ASSIGNED DATE DATE
REVIEW STATUS RECOMMENDATION REVIEWER REVIEWER SUBMITTED REVIEWED
Initial Complete Eligible
gweltonl 06/28/2007 06/29/2007
Insurance Complete Eligible
rcruse2 06/29/2007 07/05/2007
STATE Complete Eligible
phall 06/29/2007 06/30/2007
Final Complete Eligible
rcruse2 07/05/2007 07/05/2007
Page 6 of 6