HomeMy WebLinkAboutPROJECT MANUAL - SEPTEMPER 2017 A COM Flow Equalization Facility Overflow Connection to Satellite WPCF City of Waterloo, Iowa City Contract No. 880 AECOM #60336756 Prepared For. City of Waterloo 715 Mulberry Street Waterloo, Iowa 50703 Prepared By: AECOM 501 Sycamore Street, Suite 222 P.O. Box 1497 Waterloo, Iowa 50704-1497 September 2017 FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF CITY OF WATERLOO, IOWA City Contract No. 880 Prepared For: City of Waterloo, Iowa Prepared By: AECOM September 2017 I hereby certify that this engineering document was prepared by me or under my direct personal supervision and that I am a duly licensed 44, q � Professional Engineer under the laws of the state of Iowa. HARMANJlT :G= 3. MALLHI '� 0 20808 • rrr HARMANJIT MX_LHI, PE' Date /0 w ik 1L`3tS License No. 20806 r'ttJttitJi flftttltti1414\1``t My license renewal date is December 31, 2018. Pages or sheets covered by this seal: FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF CITY OF WATERLOO, IOWA City Contract No. 880 CONTRACT DOCUMENTS TABLE OF CONTENTS 1. NOTICE TO BIDDERS 2. NOTICE OF PUBLIC HEARING NB-1-4 3. INSTRUCTIONS TO BIDDERS NPH 1-2 4. SRF REQUIRED FRONT-END SPECIFICATIONS WITH DAVIS-BACON IB 1-9 REQUIREMENTS (Exhibit 12A, Including Attachments 1 Through 9) SRF-1 to SRF-33 5. FORM OF BID OR PROPOSAL 6. SALES TAX EXEMPTION INFORMATION FORM FB 1-2 7. FORM OF BID BOND STE 1 8. NON-COLLUSION AFFIDAVITS BB 1 9. EQUAL OPPORTUNITY CLAUSE NCA 1-2 10. TITLE VI CIVIL RIGHTS EO 1-2 TV11. RESIDENT BIDDER AND NON-RESIDENT BIDDER CERTIFICATION1 1 RB 12. AFFIRMATIVE ACTION PROGRAM 1-3 11. POTENTIAL ITEMS OF WORK FOR MBE/WBE PARTICIPATION 1 8 SUBCONTRACTOR'S BID REQUEST FORM, M 1 LETTER FORM FOR SUBCONTRACTOR QUOTES, M 2 MBE/WBE SCOPE LETTER, M 3 MBE AND/OR WBE PREBID CONTACT INFORMATION FORM MM 4 5-6 12. WATERLOO/CEDAR FALLS MINORITY AND WOMEN BUSINESSES ENTERPRISE CONSTRUCTION AND MAINTENANCE CONTRACTOR'S GUIDE 13. STATEMENT OF BIDDER'S QUALIFICATIONS 1-4 14. GENERAL SPECIAL PROVISIONS SBQ 1-2 15. SPECIAL PROVISIONS GSP 1-4 SP 1 The City of Waterloo has adopted the 2017 edition of the "URBAN STANDARD SPECIFICATIONS FOR PUBLIC IMPROVEMENTS MANUAL" (SUDAS) as the City's Standard Specifications. The Standard Specifications are amended by the City of Waterloo's Supplemental Specifications to the 2017 edition of SUDAS. Section 01 11 00 Summary of Work Section 01 29 73 Schedule of Values 01 11 00-1 to 01 11 00-2 Section 01 33 10 Submittals 01 29 73-1 to 01 29 73-2 Section 01 43 00 Testing Laboratory Services 01 33 10-1 to 01 33 10-9 Section 01 43 00A Testing 01 43 00 1 to 01 43 00-2 Section 01 50 10 Temporary Construction Facilities and Utilities 01 43 00A-1 to 01 43 00A-2 Section 01 57 00 Temporary Controls 01 50 10-1 to 01 50 10-3 Section 01 60 10 Material and Equipment 01 57 00-1 to 01 57 00-3 Section 01 78 23 Operation and Maintenance (O&M) Data 01 60 23-110 to 010 60 310-8 -14 78 to 78 23-14 TABLE OF CONTENTS TABLE 603367TENT 7 Flow Equalization Faclity City Contract No.880 Overflow Connection to Satellite WPCF Section 01 78 39 Project Record Documents 01 78 39-1 to 01 78 39-2 Section 02 66 20 High Density Polyethylene (HOPE) Geomembrane 0-009 96 0-1 to 09 66 to 02 66 00-14 4 Section 09 96 10 Coatings05 0 33 55 02-1 to 26 2-12 26 05 Section 26 05 02 Basic Materials and Methods to 33 05 2-12 Section 33 05 13 Manholes and Inlets 40 05 13-1 to 40 05 13-5 3-5 Section 40 05 05 Process Mechanical Piping System 13 _ 16. GENERAL SPECIFICATIONS FOR CONSTRUCTION GS SGS 1- 1 17. SUPPLEMENTAL GENERAL SPECIFICATIONS FOR CONSTRUCTION 18. FORM OF CONTRACT PFB 1-6 1-4 4 -- 19. FORM OF PERFORMANCE BOND B 1-2 20. FORM OF PAYMENT BOND APPENDIX CO-1 1. CHANGE ORDER FORM 2. Davis-Bacon Wage Rates and Forms: 10 Pages A. Davis-Bacon Wage Rates 0 Pages B. Form WH-347 Payroll and Certification C. Form SF-1444 Request for Authorization of Additional 5 Pages Classification and Rate 1 Page D. Form WH-321 Notice Poster Flow Equalization Faclity TABLE CONTENTS City Contract No.880 Overflow Connection to Satellite WPCF AECOM 60336756-2017 NOTICE TO BIDDERS For the Taking of Construction Bids for the FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF In the City of Waterloo, Iowa RECEIVING OF BIDS CONTRACT NO. 880 Sealed proposals will be received by the City Clerk of the City of Waterloo, Iowa, at her office in the City Hall of the said City on the 26th day of October, 2017, until 1:00 p.m. for the construction of the FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF, City Contract No. 880, as described in detail in the plans and specifications now on file in the Office of the City Clerk. OPENING OF BIDS All proposals received will be opened in the First Floor Conference Room at City Hall, in the City of Waterloo, Iowa, on the 26th day of October, 2017, at 1:00 p.m., and the proposals will be acted upon at such later time and place as may then be fixed by the City Council. PUBLIC HEARING The Council of said City will conduct a public hearing on the proposed plans, specifications, form of contract, and estimate of cost for the construction of the above-described improvement project at 5:30 p.m. on October 30, 2017, said hearing to be held in the Harold E. Getty Council Chambers in City Hall in said City. SCOPE OF WORK — This project consists of the installation of a new 24-inch gravity main that would connect Flow Equalization Basin No 2 with the Satellite Aeration Basin. A control valve and flow meter will be installed on this line. The project also includes a 12-inch force main that would connect the Satellite Aeration Basin with the Easton Aeration Basins and the upstream anoxic basin. BEGINNING AND COMPLETION DATES The work under the proposed contract shall be commenced within ten (10) working days after receipt of "Notice to Proceed" and all items shall be substantially complete by April 30, 2018, and finally complete on or before May 31, 2018. METHOD OF PAYMENT TO CONTRACTOR The Contractor will be paid against bi-monthly estimates in cash on the basis of ninety-five percent (95%) of the work as it is completed and materials delivered and work approved. Final payment will be made thirty-one (31) days after completion of the work and acceptance by the Council. Before final payment is made, vouchers showing that all subcontractors and workmen and all persons furnishing materials have been fully paid for such materials and labor will be required unless the City is satisfied that material, men and laborers have been paid. The Contractor is hereby notified that if the City does not have cash on hand to pay monthly pay estimates, according to Chapter 384.57 of the Code of Iowa, payment may be made by anticipatory warrants issued bearing a rate of interest not exceeding that permitted by Chapter 74A, Code of Iowa. PLANS AND SPECIFICATIONS Plans and Specifications governing the construction of the proposed improvements have been prepared by AECOM, which plans and specifications and also the prior proceedings of the City Council referring to and defining said proposed improvements are hereby made a part of this notice, and the proposed contract by reference shall be executed in compliance therewith. NOTICE TO BIDDERS NB-1 of 4 AECOM 60336756-2017 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF Complete digital Plans and Specifications are available at www.questcdn.com. You may download the digital documents free of charge from Questcdn by inputting Questcdn Project#5375964 on the website's Project Search page. Please contact Questcdn.com at 952-233-1632 or info@questcdn.com for assistance in free membership registration, downloading and working with this digital project information. Optional paper copies of the Plans and Specifications are available from AECOM, 501 Sycamore Street, Suite 222, Waterloo, Iowa, upon receipt of a $150.00 deposit (CHECK ONLY). Deposits are fully refundable if the plans and specifications are returned in usable condition (i.e., generally free of highlights, ink markings, tears, stickers, water stains and soiling) to the Waterloo AECOM office listed above by the end of the 14th consecutive day after the project has been awarded. No deposits will be refunded for any requests or plans received after the 14th consecutive day, which includes plans returned via mail service. Plan holders are responsible for ascertaining when the project has been awarded. If the plan holder is the prime contractor, or a subcontractor or supplier of the prime contractor that has been awardedo returned to rimecontractor the p j mu t submit Plans da list Specifications subcontractors not need tandesuppl suppliers forretheceive City andposit. The consul consulting prime engineer to verify eligibility for the refundable deposit. Please DO NOT obtain Bid Documents from any source other than Questcdn.com or through the AECOM Waterloo office as listed above. Obtaining documents through any other source could prevent Bidder from being included on the official AECOM Planholders List which, in turn, may cause the Bidder to not receive addenda or other time-sensitive / bid-critical documents. The City has the right to reject any bids that do not have current bidding documents included in the Bid Submission. Upon award of the project, the prime contractor, his subcontractors and suppliers shall be supplied with the needed number of plans and specifications at no additional cost. CONTRACT AWARD A contract will be awarded to the qualified bidder submitting the lowest bid. The City reserves the right to reject any or all bids, re-advertise for new bids, and to waive informalities in the bids submitted that might be in the best interest of the City. Bids may be held by the City of Waterloo, Iowa, for a period not to exceed thirty (30) days from the day of the opening of bids for the purpose of reviewing the bids and investigating the qualifications of bidders, prior to awarding the contract. By virtue of statutory authority, a preference will be given to products and provisions grown and coal produced with the State of Iowa and preference will be given to local domestic labor in the construction of the improvement. PROPOSALS SUBMITTED The bidder shall submit bids on the items listed in the proposal. The bidder shall clearly write or type the unit bid price and the bid item extension (Unit Price x Estimated Qty) in numerals on the blanks provided. Should there be any discrepancy between the unit bid price and extension, the City of Waterloo shall consider the unit bid price as being the valid unit bid price. The bidder has the option to submit a computer-generated spreadsheet in lieu of the portion of the Form of Bid or Proposal, which includes the Bid Item Number, Description, Unit, Estimated Quantity, Unit Bid Price, Total Bid Price and Total Bid. The computer-generated spreadsheet shall include all of the information listed in that portion of the Form of Bid or Proposal as well as bear the signature of the Prime Contractorspreadsheet, the (with wi hlalternates,l If applicable) shall also be indicated TOTAL BID in the space(s) prove bidders who submit a computer-generated d on the Form of Bid or Proposal. —" BIDDERS NB-2 of 4 Flow Equalization Facility NOTICE City Contract No.880 Overflow Connection to Satellite WPCF AECOM60336756-2017 BID SECURITY REQUIRED -- All bids must be accompanied in a separate envelope by a certified or cashier's check drawn on an Iowa bank, or a bank chartered under the laws of the United States, a certified share draft drawn on a credit union in Iowa or chartered under the laws of the United States, or bid bond, (on the form furnished by the City) payable to the City of Waterloo, Iowa, in the sum of not less than five percent (5%) of the bid submitted, which certified check, certified share draft or bid bond will be held as security that the Bidder will enter into a Contract for the construction of the work and will furnish the required bonds, and in case the successful Bidder shall fail or refuse to enter into the Contract and furnish the required bonds, his bid security may be retained by said City as agreed upon liquidated damages. If bid bond is used, it must be signed by both the Bidder and the surety or surety's agent. Signature of surety's agent must be supported by accompanying Power of Attorney. -- PERFORMANCE& PAYMENT BONDS The successful bidder will be required to furnish a "Performance Bond" and a "Payment Bond" within ten (10) days after forms are presented to him in an amount equal to one hundred percent (100%) of the contract price, said bond to be issued by a responsible surety approved by the City Council and shall guarantee the faithful performance of the contract and the terms and conditions therein contained, and shall guarantee the prompt payment of all materials and labor and protect and save harmless the City from claims of any kind caused by the operations of the contractor. MAINTENANCE BOND --- Before the Contractor shall be entitled to receive final payment for work done under this contract, it shall execute and file a bond in the penal sum of not less than 100% of the total amount of the contract, same to be known as "Maintenance Bond," and which bond must be approved by the City Council, and which bond is in addition to the bond given by the Contractor to guarantee the completion of the work. CONTRACT COMPLIANCE PROGRAM/SUBCONTRACTING The program proposes numerical projections regarding utilization of Minority Business Enterprise (MBE) and Women Business Enterprise (WBE) as Subcontractors, vendors and suppliers in the performance of Contracts awarded by the City of Waterloo, Iowa. A goal of at least ten percent (10%) for MBE participation on all City funded construction projects that are estimated at $50,000.00 or more. A goal of at least two percent (2%) for WBE participation on all City funded construction projects that are estimated at $50,000.00 or more. Any project funded in part or in total with federal funds shall follow the respective agencies'contract compliance programs and goals. The Prime Contractor shall make "good-faith efforts" to meet the Contract Compliance MBE/WBE goals. The MBE/WBE subcontractors, suppliers or vendors must provide the Prime Contractor a reasonably competitive price for the service being rendered or the Contractor is not required to accept their bid. LIQUIDATED DAMAGES Time is an essential element of this contract. It is important that the work be diligently pursued to completion. If the work is not completed within the specified contract period, plus authorized extensions, the contractor shall pay to the City Liquidated Damages in the amount of Five Hundred Dollars ($500.00) per day, for each day, as further described herein, in excess of the authorized time. Days beyond the specified completion date for which Liquidated Damages will be charged will be working days that the contractor does, or could have worked, from Monday through Saturday. Sundays will be counted only if work is performed. Partial working days will be considered as a full working day. Days not chargeable for Liquidated Damages will include rain days, Sunday if no work is done, and legal holidays. Working days will cease to be charged when only punch list items remain to be completed. Punch list items do not include contract bid items or approved change/extra work orders. NOTICE TO BIDDERS NOTICE 6033675 NB-3 of 4 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF When the Contractor believes the project to be substantially completed, a written notice stating the same shall be submitted to the Engineer and a request made for a Punch List. If the work under the Contract extends beyond the normal construction season for such work the Contractor shall submit to the Engineer in writing a request that working days counted toward the project be suspended until work is resumed the following construction season. This amount is not construed as a penalty. These damages are for the cost to the City of providing the required additional inspection, engineering and contract administration. PRE-CONSTRUCTION CONFERENCE eld for the Before the work is conference shall bes sattended by the prime contractor,contract, a conference shall be purpose discussing subcontractors orsand City Officials. the contract. The RESIDENT BIDDER/NON-RESIDENT BIDDER Attention of bidders is called to compliance with the provisions of the Resident Bidder/Non-Resident Bidder requirements. Each bidder submitting a bid shall execute and include with the bid, a Resident Bidder Certification or a Non-Resident Bidder Certification in the form(s) herein provided. SALES TAX EXEMPTION CERTIFICATES Contractors and approved subcontractors will be provided a Sales Tax Exemption Certification to purchase building materials or supplies in the performance of construction contracts let by the City of Waterloo. Posted pursuant to the provisions of Chapter 26 of the City Code of Iowa. CITY OF WATERLOO, IOWA BY: Kelley Felchle City Clerk 60336756-2017 W NB-4 of 4 Flow Equalization Facility NOTICE BIDDERS City Contract No.880 Overflow Connection to Satellite PCF AECOM NOTICE OF PUBLIC HEARING On Proposed Plans, Specifications, Form of Contract, And Estimate of Cost For the FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF In the City of Waterloo, Iowa CONTRACT NO. 880) RECEIVING OF BIDS Sealed proposals will be received by the City Clerk of the City of Waterloo, Iowa, at her office in the City Hall of the said City on the 26th day of October, 2017, until 1:00 p.m. for the of FLO EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITEonstruc WPCF, City t C nt aact No. 880, as described in detail in the plans and specifications now on file in the Office of the City Clerk. OPENING OF BIDS All proposals received will be opened in the First Floor Conference Room at City Hall, in the City of Waterloo, Iowa, on the 26th day of October, 2017, at 1:00 p.m., and the proposals will be acted upon at such later time and place as may then be fixed by the City Council. PUBLIC HEARING Notice is hereby given that the Council of said City will conduct a public hearing on the proposed plans, specifications, form of contract, and estimate of cost for the construction of the above-described improvement project at 5:30 p.m. on the 30th day of October, 2017, said hearing to be held in the Harold E. Getty Council Chambers in City Hall in said City. The proposed plans, specifications, form of contract, and estimate of cost for said improvements heretofore prepared by AECOM for the City of Waterloo are now on file in the office of the City Clerk for public examination, and any person interested therein may file written objection thereto with the City Clerk before the date set for said hearing, or appear and make objection thereto with the City Clerk before the date set for said hearing, or appear and make objection thereto at the meeting above set forth. The NOTICE TO BIDDERS can be viewed at the following locations: 1) City of Waterloo web site at http://ci.waterloo.ia.us/ 2) Plan rooms: Master Builders of Iowa 221 Park Street, PO Box 695 Des Moines, IA 50303 '- McGraw Hill Construction Dodge 3315 Central Ave. Hot Springs,AR 71913 Reed Construction Data 30 Technology Parkway South, Ste. 500 Norcross, GA 30092 3) Plan Room Web sites: Master Builders of Iowa web site at www. www.mbionline.corn Dodge Lead web site: http://dodgeprojects.construction.com/ Reed Const. Data Lead web site: http://www.cmdgroup.com/project-leads/ NOTICE OF PUBLIC HEARING NPH-1 of 2 AECOM 60336756-2017 City Contract No.880 OverflowFlow Equalization Faclity Connection to Satellite WPCF SCOPE OF WORK This project consists of the installation of a new 24-inch gravity main that would connect Flow Equalization Basin No 2 with the Satellite Aeration Basin. A control valve and flow meter will be installed on this line. The project also includes a 12-inch force main that would connect the Satellite Aeration Basin with the Easton Aeration Basins and the upstream anoxic basin. Published pursuant to the provisions of Chapter 26 of the City Code of Iowa andupon order to the City Council of said Waterloo, Iowa, on the day of CITY OF WATERLOO, IOWA BY: Kelley Felchle City Clerk 60 PUBLIC HEARING NPH-2 of 2 Flow Equalization Faclity NOTICECity Contract No.880 Overflow Connection to Satellite WPCF AECOM 336756-2017 INSTRUCTIONS TO BIDDERS 1. EXPLANATIONS TO BIDDERS Any explanation desired by a bidder regarding the meaning or interpretation of the Notice to Bidders, Plans, Specifications, etc., must be requested in writing and with sufficient time allowed for a reply to reach bidders before submission of their bids. Any interpretation made will be in the form of an amendment of the Notice to Bidders, Plans, Specifications, etc., and will be furnished to all prospective bidders. Its receipt by the bidder must be acknowledged in the space provided on the Proposal Form or by letter or telegram received before the time set for opening of bids. Oral explanations or instructions given before the award of the contract will not be binding. 2. EXAMINATION OF PROPOSED WORK Bidders should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work, and the general and local conditions which can affect the work or the cost thereof. Failure to do so will not relieve bidders from responsibility for estimating properly the difficulty or cost of successfully performing the work. The owner will assume no responsibility for any understanding or representation concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the Notice to Bidders, the Specifications or related documents. 3. PREPARATION OF BIDS a. Bids shall be submitted on the forms furnished, or copies thereof, and must be manually signed. If erasures or other changes appear on the forms, each erasure or change must be initialed by the person signing the bid. The bidder has the option to submit a computer-generated spreadsheet in lieu of the portion of the Form of Bid or Proposal, which includes the Bid Item Number, Description, Unit, Estimated Quantity, Unit Bid Price, Total Bid Price, and Total Bid. The computer- generated spreadsheet shall include all of the information listed in that portion of the Form of Bid or Proposal as well as bear the signature of the Prime Contractor submitting the bid. For the bidders who submit a computer-generated spread- sheet, the TOTAL BID (with alternates, if applicable) shall also be indicated in the space(s) provided on the Form of Bid or Proposal. b. The Bid Form may provide for submission of a price or prices for one or more items, which may be lump sum bids, alternate prices, schedule items resulting in a bid on a unit of construction or a combination thereof, etc. When the Bid Form explicitly requires that the bidder bid on all items, failure to do so will disqualify the bid. When submission of a price on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted. c. Unless called for, alternate bids will not be considered. d. Modifications of bids already submitted will be considered if received at the office designated in the Notice to Bidders by the time set for closing of bids. Telegraphic modifications will be considered, but should not reveal the amount of the original or revised bid. e. In preparing his bid, the bidder shall specify the price, written legibly in ink or with the typewriter, at which he proposes to do each item of work. The unit price shall be stated in figures in the blank space provided (i.e., $7.14). In items where unit price is required, the total amount of each item shall be computed at the unit prices bid for the quantities given on the Bid Form and stated in figures in the blank space provided. INSTRUCTIONS TO BIDDERS AECOM 6033675TO IB-1 to IB-9 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF If the bidder chooses to submit the unit prices, total bid price, and total bid on a computer-generated spreadsheet, all numbers shall be easily legible. f. Any changes or alterations made in the Bid Form, or any addition thereto, may cause the rejection of the bid. No bid will be considered which contains a clause in which the contractor reserves the right to accept or reject a contract awarded him by the city Council of Waterloo. Bids in which the unit prices are obviously unbalanced may be rejected. g. If the bidder does not qualify as a resident bidder, the nonresident bidder shall specify on the project proposal whether any preference to resident bidders, including but not limited to any preference to bidders, the imposition of any type of labor force preference, or any other form of preferential treatment to bidders or laborers from that state or foreign country is in effect in the nonresident bidder's state or country of domicile at the time of a bid submittal. 4. SUBMISSION OF BIDS a. A bid must be sealed in a separate envelope and marked to indicate its contents and be accompanied by the bid security in a separate envelope. If forwarded by mail, the two envelopes shall be placed in a third and mailed to the City Clerk/Auditor. All bids must be filed with the City Clerk/Auditor of the City of Waterloo at his office in the City Hall before the time specified for closing bids. b. Bids received prior to the advertised hour of opening will be securely kept sealed. The officer whose duty it is to open them will decide when the specified time has arrived, and no bid received thereafter will be considered; except that when a bid arrives by mail after the time fixed for opening, but before the reading of all other bids is completed, and it is shown to the satisfaction of the City of Waterloo, Iowa, that the non-arrival on time was due solely to delay in the mails for which the bidder was not responsible, such bid will be received and considered. c. Bidders are cautioned that, while telegraphic modifications of bids may be received as provided above, such modifications, if not explicit and if in any sense subject to misinterpretation, shall made the bid so modified or amended, subject to rejection. 5. LATE BIDS AND MODIFICATIONS OR WITHDRAWALS Bids and modifications or withdrawals thereof received at the office designated in the Notice to Bidders after the exact time set for closing of bids will not be considered. However, a modification which is received from an otherwise successful bidder, and which makes the terms of the bid more favorable to the City of Waterloo, will be considered at any time it is received and may therefore be accepted. Bids may be withdrawn by written or telegraphic request received from bidders prior to the time set for closing of bids. 6. PUBLIC OPENING OF BIDS Bids will be publicly opened at that time and place set for opening in the Notice to Bidders. Their content will be made public for the information of bidders and others interested who may be present either in person or by representative. 7. BID SECURITY REQUIRED All bids must be accompanied in a separate envelope by a certified or cashier's check drawn on an Iowa bank, or a bank chartered under the laws of the United States, a certified share draft drawn on a credit union in Iowa or chartered under the laws of the United States, or bid bond (on the form furnished by the City) payable to the City of Waterloo, Iowa, in the sum of not less than five percent (5%) of the bid submitted, which certified check, certified share draft or bid bond will be held as security that the Bidder will enter into a Contract for the construction of the work and IB-1 to IB-9 Flow Equalization Facility INSTRUCTIONS BIDDERS City Contract No.880 Overflow Connection to Satellite WPCF AECOM 60336756-2017 will furnish the required bonds, and in case the successful Bidder shall fail or refuse to enter into the Contract and furnish the required bond, his bid security may be retained by said City as agreed upon liquidated damages. If bid bond is used, it must be signed by both the bidder and the surety or surety's agent. Signature of surety's agent must be supported by accompanying Power of Attorney. 8. COLLUSIVE AGREEMENTS a. Each bidder submitting a bid shall execute and include with the bid, a Non-Collusion Affidavit in the form herein provided, to the effect that he as not colluded with any other person, firm, or corporation in regard to any bid submitted. b. Each bidder submitting a bid shall have each proposed subcontractor, if any, execute and submit to the City Contract Compliance Officer by 5:00 P.M. the business day following the day bids on this project are due, a Non-Collusion Affidavit in the form herein provided, to the effect that he has not colluded with any other person, firm, or corporation in regard to any bid submitted. Before executing any subcontract, the successful bidder shall submit the name of any proposed subcontractor for approval by the City. 9. MINORITY AND/OR WOMEN BUSINESS ENTERPRISE SUBCONTRACTORS a. CITY OF WATERLOO AND/OR WOMEN BUSINESS ENTERPRISE PRE-BID CONTACT INFORMATION FORM The City of Waterloo Minority and/or Women Business Enterprise Pre-Bid Contact Information Form shall be submitted with the Form of Bid or Proposal. Failure to do so shall be grounds for the bid being rejected if subcontracting is proposed by the prime contractor. 10. MBE/WBE CONTRACT COMPLIANCE PROGRAM PURPOSE The purpose of the Contract Compliance Program (hereinafter called Program) is to act as an impetus for increasing the participation of minority and women disadvantaged business enterprise (MBE/WBE) in City awarded construction contracts. The Program does not propose to eliminate any bonafide contractor or subcontractor from bidding on City contracts, but it will hopefully serve as a needed stimulus to help local MBE/WBE's grow and eventually become mainstream contractors and subcontractors. _ This Contract Compliance Program does not propose to include any set-aside or quotas, but only flexible goals where "good-faith efforts" are required by the contractor to use MBE/WBE subcontractors. This Program shall not eliminate the need for contractors to continue their "good-faith efforts" in using MBE/WBE subcontractors on City contracts estimated at less than $50,000. The City of Waterloo will make every effort to reduce in-house construction and maintenance work that would be more cost effectively performed by the private sector and, thus, would allow additional bidding opportunities for MBE/WBE firms. The City Contract Compliance Officer shall be advised of all City of Waterloo awarded construction contracts. INSTRUCTIONS TO BIDDERS AECOM 60336756-2017 IB-1 to IB-9 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF DEFINITIONS Goals: A flexible numerically expressed objective which contractors are required to make"good- faith efforts." The key to the requirement is to make documented efforts. Goals are neither set-a-sides nor a device to achieve proportional representation or equal results. Numerical goals do not create set-a-sides for specific groups, nor are they designed to achieve proportional representation or equal results. Rather, the goal-setting process in affirmative action planning is used to target and measure the effectiveness of affirmative action efforts to eradicate and prevent discrimination. Quota: A flat numerical requirement that the contractor is required to meet in order to obtain the benefit or be in compliance. The numerical goal component of affirmative action programs is not designed to be, nor may it properly or lawfully be interpreted as, permitting unlawful preferential treatment and quotas with respect to persons of any race, color, religion, sex, or national origin. The regulations at 41 CFR 60-2.12(a), 60-2.15 and 60-2.30, specifically prohibit discrimination and the use of goals as quotas. (U.S. Department of Labor)Set-Aside: An arrangement in which a particular contract is reserved for competition solely among minority and women business enterprises. Contractor. As used in this document means contractor, subcontractor, supplier, vendor, an professional service provider. Minority Business Enterprise(MBE) Any business, which is at least 51%, owned by one or more minorities and whose management and daily business operations are controlled by one or more such individuals and is on the current State Unified Certification List, or were listed on the City of Waterloo Certified MBE/WBE Contractors list as of July 1, 2002 Women Business Enterprise (WBE): Any business which is at least 51% owned by one or more women and whose management and daily business operations are controlled by one or more such individuals and is on the current State Unified Certification List, or were listed on the City of Waterloo Certified MBE/WBE Contractors list as of July 1, 2002 Minority: Any person or persons who are considered as socially and economically disadvantaged because of their identity as a group member without regard to their individual qualities. The groups include: Black American, Hispanic American, Native Americans, Eskimos, Aleuts, and Asian-Pacific Americans. 13 C.F.R. 124-1.1(c)(3)(ii)( ). Lowest Responsible Bidder: Bidder who has offered the lowest bid and who has exhibited skill relative to the type of work b idve judgment, financial t Program pand they, and evidence of working with the Contract Compliance Program. Afflrma Broker: One buying or selling for others on commission or other fee basis without maintaining a warehouse or other similar inventory storage facility. Mayor's Advisory Committee: Mayor's Advisory Committee for Minority, Female, and Disadvantaged Business Enterprise. IB-1 to IB-9 Flow Equalization Facility AECOM 03 INSTRUCTIONS 6- BIDDERS City Contract No.880 Overflow Connection to Satellite WPCF AECOM 60336756-2017 Good Faith Efforts: The successful bidder shall be selected on the basis of having submitted the lowest responsible bid. The obligation of the bidder is to make good faith efforts. The bidder can demonstrate that it has done so by the following: 1. The Prime Contractor met the project goal- No Action necessary 2. If the Prime Contractor failed to meet the goal, they must submit documentation of good faith efforts. CONTRACT COMPLIANCE PROGRAM SUBCONTRACTING The program proposes numerical projections or goals regarding utilization of Minority Business Enterprise (MBE) and Women Business Enterprise (WBE) as subcontractors in the performance of contracts awarded by the City of Waterloo, Iowa. A goal of at least 10% for MBE participation on all City funded construction projects that are estimated at $50,000 or more and projects under $50,000 where applicable at the Contract Compliance Officer's discretion. There is at least 2% WBE goal on City funded projects. Any project which is funded solely or in part with Federal funds shall follow the respective agencies contract compliance program and goals. Any project which is funded solely or in part with State funds shall follow the respective agencies contract compliance program and goals. The City of Waterloo Contract Compliance Program is for City awarded construction contracts only. The prime contractor shall make "good-faith efforts" to meet the Contract Compliance MBE/WBE goals. The MBE/WBE subcontracts must provide the prime contractor a reasonably competitive price for the service being rendered or the contractor is not required to accept the bid. Administrative Reconsideration: As part of this reconsideration, the bidder will have the opportunity to provide written documentation or arguments concerning the issue of whether they made adequate good faith efforts to meet the goals. The bidder will have the opportunity to meet in person with the City of Waterloo's Administrative Reconsideration Committee to discuss the issue of whether they made adequate good faith efforts. The Administrative Reconsideration Committee will forward a written decision on reconsideration to the Mayor and City Council, explaining the basis for finding that the bidder did or did not meet the goal or make adequate good faith efforts to do so. Documentation required will include but is not limited to the following: * Making portions of the work available for MBE/WBE subcontracting * Evidence of negotiating with MBE/WBE firms * MBE/WBE quotes obtained and non-MBE/WBE quotes used * Reasons agreements were not reached * Follow-up after initial solicitations * Efforts to assist in obtaining equipment, supplies and materials (at competitive prices), bonding, lines of credit, insurance, etc. * Evidence of past compliance or non-compliance by same contractor The Contract Compliance Officer will determine the weight to be given to each item listed above(supported by appropriate documentation) based on overall program goals. RESPONSIBILITIES City of Waterloo A. The City Contract Compliance Officer has the responsibility to assure the City's compliance with Federal, State and Municipal regulations. INSTRUCTIONS TO BIDDERS AECOM 60336756-2017TOIB-1 to IB-9 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF B. The City Contract Compliance Officer is responsible for maintaining a current directory of certified firms. Certification of MBE/WBE/DBE contractors is through the Iowa Department of Transportation and its Unified Certification Program. Only firms certified based on guidelines prescribed in 49 CFR Part 26 and provisions of this agreement, shall be recognized as certified by the City of Waterloo. C. The City Contract Compliance Officer is responsible for making available a list of future project information notices to MBE/WBE firms. appropriate — D. The City Contract Compliance Officer shall send notices to appro p MBE/WBE firms in the directory of each bid solicitation with opening date. E. The City Contract Compliance Officer will receive MBE/WBE Letter(s) of Intent to Bid and within two (2) business days forward the complete list of MBE/WBE bidders who submitted a Letter of Intent to Bid to prime contractors. �/. Prime Contractors In order to be in compliance with the guidelines of this program, the prime contractor must show good-faith efforts in following the MBE/WBE Contract Compliance Program. Good-faith efforts include, but are not limited to, the following: A. Prime contractors shall send solicitation letters (Form CCO-3) to appropriate MBE/WBE (those certified in directory prepared by City Contract Compliance Officer) at least seven (7) working days prior to bid date. Letters should identify specific items to be subcontracted. A minimum of three (3) disadvantaged business contacts must be made and documented, if there are at least three disadvantaged businesses offering services in the area to be subcontracted (See City of Waterloo MBE/WBE Certification List). If less than three (3) are offering the services to be subcontracted, then a contact is required for any that are listed as providing that service. If the Prime Contractor submitsf a the EIWBE E/DBE contact not on the City's MBE/WBE list, attach a copy Certifications from another government agency. e to fy firms perform B. p of the work,the City Contract t Compliance MOffi e B should be contacted portions prime contract bidder is contctd for assistance immediately. C. Prime contract bidders may solicit MBE/WBE proposals by telephone or personal interviews, but all such contacts shall be confirmed by Certified Mail, or — subcontract bid request forms (Form CCO-2). D. If any MBE/WBE business submitting bids is not selected for subcontract award, documentation must accompany the "MBE/WBE Business Enterprise Pre-Bid Contact Information Form" (Form CCO-4 and CCO-4A) on why the MBE/WBE was not selected. These reasons could include: a. Not low bid. Copies of the competing bids may be required for verification. b. MBE/WBE did not bid,withdrew bid or non-responsive. c. Documentation of other business-related reason for not selecting the — MBE/WBE business for a subcontract. d. Prime contractor self performs work. e. Any other reason relied on by prime. The Contract Compliance Officer will determine the weight to be given to each item listed — above (supported by appropriate documentation) based on overall program goals. IB-1 to IB-9 Flow Equalization Facility AECOM 03 INSTRUCTIONS 6- BIDDERS City Contract No.880 Overflow Connection to Satellite WPCF AECOM 60336756-2017 MBE/WBE Firms F. MBE/WBE firms shall be certified by the Iowa Department of Transportation as owners and controllers of their respective businesses, or were listed on the City of Waterloo Certified MBE/WBE Contractors list as of July 1, 2002. G. MBE/WBE firms must perform the work on the project; they cannot act as a broker by subcontracting the work out to others. C. Each MBE/WBE firm planning to submit quotes on construction projects with goals, shall submit a Letter of Intent to Bid (Form CCO-5) to the City Contract Compliance Officer seven (7) working days prior to bid opening, listing specific items which the MBE/WBE firm is interested in bidding. If sufficient Letters of Intent to Bid are not received by the City Contract Compliance Officer seven (7) working days prior to bid opening, goals on subject project will be reduced accordingly. Agreements between the bidder/proposer and a MBE/WBE in which the MBE/WBE promises not to provide subcontracting quotations to other bidders/proposers are prohibited. NON-COMPLIANCE OF CONTRACTORS A. Noncompliance exists when the contractor's actions are not consistent with the requirements of the Contract Compliance Program in the areas of employment and subcontracting. B. A bidder's failure to show good-faith efforts to meet project goals or a failure to use certified MBE/WBE firms may be grounds for finding its bid not responsible. C. The Contract Compliance Officer shall submit to City Council his/her recommendation on any non-compliant contract in writing. NOTICE TO PROCEED Notice to proceed on any project with goals will not be issued until City Contract Compliance Officer determines the lowest responsible bidder has used good-faith efforts to comply with this Compliance Program and the bid was responsive. CONCLUSION This program repeals or revises all sections of previous Waterloo Contract Compliance Programs. 11. EMPLOYMENT AND BUSINESS OPPORTUNITY To the greatest extent feasible, suppliers, subcontractors, and low income workers owning businesses or living in the Waterloo area must be given priority in supplying materials, bidding for subcontract work, or applying for employment by the contractor on this project. Opportunities for training and for employment arising in connection with this project, shall to the greatest extent feasible be made available to lower income persons residing in the project area. The contract area is the City of Waterloo. The City of Waterloo will require the contractor to document his efforts in securing lower income workers living in the project area and in purchasing supplies from, and awarding subcontracts to, businesses owned by persons residing in the project area. 12. STATEMENT OF BIDDER'S QUALIFICATIONS Each bidder shall, upon request of the City of Waterloo, Iowa, submit on the form furnished for that purpose (a copy of which is included in the contract documents), a statement of bidder's qualifications, his experience record in constructing the type of improvements embraced, and his organization and equipment available for the work contemplated; and, when specifically INSTRUCTIONS TO BIDDERS IB-1 to IB-9 AECOM 60336756-2017 City Contract No.880 Overflow Connection Flow n o Satelliteto WPCF requested, a detailed financial statement. The City of Waterloo, Iowa, shall have the right to take such steps as it deems necessary to determine the ability of the bidder to perform his obligations under the contract, and the bidder shall furnish the City of Waterloo, Iowa, all such information and data for this purpose as it may request. The right is reserved to reject any bid where an investigation of the available evidence or information does not satisfy the City of Waterloo, Iowa, that the bidder is qualified to carry out properly the terms of the contract. 13. AWARD OF CONTRACT a. Award of contract will be made to that responsive and responsible bidder whose bid, conforming to the Specifications, is most advantageous to the City of Waterloo; price and other factors considered. The intention is to award the contract at any time of opening bids, but the right is reserved to postpone such action for a reasonable time, not exceeding thirty(30) days. b. The City Council may, when in its interest, reject any or all bids or waive any informality in — bids received. c. The bidder shall submit bids on all the items listed in the proposal and shall state the unit bid price in words in the blank spaces provided beneath the item description. Should there be any discrepancy between the unit bid price in words and listed numeral unit bid price, the City of Waterloo shall consider the unit bid price in words as being the valid unit bid price. A computer-generated spreadsheet as herein provided shall also be acceptable. Proposals requiring mathematical computations to determine unit prices or totals will be rejected. A contract will be awarded to the qualified bidder submitting the lowest total bid as indicated in the NOTICE TO BIDDERS. _.. d. When a contract for a public improvement is to be awarded to the lowest responsive and responsible bidder, a resident bidder shall be allowed a preference as against a nonresident bidder from a state or foreign country if that state or foreign country gives or requires any preference to bidders from that state or foreign country, including but not limited to any preference to bidders, the imposition of any type of labor force preference, or any other form of preferential treatment to bidders or laborers from that state or foreign country. The preference allowed shall be equal to the preference given or required by the state or foreign country in which the nonresident bidder is a resident. In the instance of a resident labor force preference, a nonresident bidder shall apply the same resident labor force preference to a public improvement in this state as would be required in the construction of a public improvement by the state or foreign country in which the nonresident bidder is a resident. 14. EXECUTION OF AGREEMENT, BONDS, AND CERTIFICATE OF INSURANCE a. Subsequent to the award and within ten (10) days after the prescribed forms are presented for signature, the successful bidder shall execute and deliver to the City of Waterloo, Iowa, an agreement in the form included in the contract documents in such number of copies as the City of Waterloo, Iowa, may require. b. Having satisfied all conditions of award as set forth elsewhere in these documents, the successful bidder shall, within the period specified in paragraph "a" above, furnish a surety bond and a payment bond in a penal sum not less than the amount of the contract as awarded, as security for the faithful performance of the contract and terms and conditions therein contained and shall guarantee the prompt payment of all persons, firms, or corporations to whom the contractor may become legally indebted for labor, materials, tools, equipment, or services of any nature including utility and transportation services, employed or used by him in performing the work. The bonds shall protect and save harmless the City from claims and damages of any kind caused by the operations of the contractor and shall also guarantee the maintenance of the contract improvements for the eriod stated in the Notice of andthei acceptance Hearing after by the City. Such bonds shall beinothe completion form as that included IB-1 to IB-9 Flow Equalization Facility AECOM 03 INSTRUCTIONS 6- BIDDERS City Contract No.880 Overflow Connection to Satellite WPCF AECOM 60336756-2017 in the contract documents and shall bear the same date as, or a date subsequent to that of the agreement. The current Power of Attorney for the person who signs for any surety company shall be attached to such bonds. c. The successful bidder shall, within the period specified in paragraph "a" above, furnish a certificate of insurance for approval in amounts of not less than the amounts specified in the General Specifications for Construction, Section F. No. 4 "Liability Insurance," Pages 14 to 15 of 19 Pages. The certificate of insurance shall be furnished in such number of copies as the City of Waterloo may require. The City of Waterloo shall be named as an "Additional Insured." The contractor shall similarly submit his subcontractor's certificates of insurance in the amounts for approval before each commences work. The contractor shall carry or require that there be Workmen's Compensation Insurance for all his employees and those of his subcontractors engaged in work at the site, in accordance with State Workmen's Compensation Laws. d. The failure of the successful bidder to execute such agreement and to supply the required bond or bonds within ten (10) days after the prescribed forms are presented for signature, or within such extended period as the City of Waterloo, Iowa, may grant, based upon reasons determined sufficient by the City of Waterloo, Iowa, may either award the contract to the next lowest bidder or re-advertise for bids, and may charge against the bidder the difference between the amount of the bid an the amount for which a contract for the work is subsequently executed, irrespective of whether the amount thus due exceeds the amount of the bid guaranty. If a more favorable bid is received by re- advertising, the defaulting bidder shall have no claim against the City of Waterloo, Iowa, for a refund. 15. RECIPROCAL RESIDENT BIDDER PREFERENCE Attention of bidders is called to the requirement of complying with the provisions of the Resident Bidder/Non-Resident Bidder requirement. Each bidder submitting a bid shall execute and include with the bid, a Resident Bidder Certification or a Non-Resident Bidder Certification in the form(s) herein provided. INSTRUCTIONS TO BIDDERS FlFacility AECOM 6TIONS 6-2017 IB-1 to IB-9 City Contract No.880 Overflow Connectionyto Satellite WPCF SRF Required Front-End Specifications , Attachment 1: Certification of Non-Segregated Facilities Form SRF (to be completed and signed by Prime Contractor and submitted with the bid) STATE Attachment 2: Statement in Advertisement for Bids on Debarment and REVOLVING FUND Suspension/Certification Regarding Debarment and Suspension Form (to be completed and signed by Prime Contractor and submitted with the bid) Attachment 3: Disadvantaged Business Enterprise Certification Form (to be completed and signed by Prime Contractor and submitted with the bid) Attachment 4: DBE Program Subcontractor Performance Form (to be completed and signed by Prime and DBE Subcontractor for each subcontract and submitted with the bid) Attachment 5: DBE Program Subcontractor Utilization Form (to be completed and signed by Prime Contractor and submitted with the bid) Attachment 6: DBE Program Subcontractor Participation Form (for voluntary use of DBEs) Attachment 7: Other Federal Requirements Language A. Standard Equal Employment Opportunity Specifications B. Federal Labor Standards Provisions (including Davis-Bacon prevailing wage rates) C. Preservation of Open Competition and Government Neutrality D. Historical and Archeological Finds E. Prohibitions on Procurement from Violating Facilities Attachment 8: Right of Entry and Records Retention Attachment 9: Use of American Iron and Steel Please note: The Davis Bacon wage determination received from the Iowa Finance Authority is included in Appendix 2 of this specification. May 2015 INVESTING IN IOWA'S WATER SRF-1 Attachment 1 SRF Required Front-End Specifications (This form must be completed and signed by Prime Contractor and submitted with the bid) U.S. Environmental Protection Agency Certification of Non-Segregated Facilities (Applicable to contracts, subcontracts, and agreements with applicants who are themselves performing Federally assisted construction contracts, exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause.) By the submission of this bid, the bidder, offeror, applicant, or subcontractor certifies that he does not maintain or provide for his employees any segregated facilities at any of his establishments, and that he does not permit his employees to perform their services at any location, under his control, where segregated facilities are maintained. He certifies further that he will not maintain or provide for his employees any segregated facilities at any of his establishments, and that he will not permit his employees to perform their services at any location, under his control, where segregated facilities are maintained. The bidder, offeror, applicant, or subcontractor agrees that a breach of this certification is a violation of the Equal Opportunity clause in this contract. As used in this certification, the term "segregated facilities" means any waiting rooms, work areas, restrooms and washrooms, restaurants and other eating areas, time clocks, locker rooms and other storage or dressing areas, parking lots, drinking fountains, recreation or entertainment areas, transportation, and housing facilities provided for employees which are segregated by explicit directive or are in fact segregated on the basis of race, creed, color, or national original, because of habit, local custom, or otherwise. He further agrees that (except where he has obtained identical certifications from proposed subcontractors for specific time periods) he will obtain identical certifications from proposed subcontractors prior to the award of subcontracts exceeding $10,000 which are not exempt from the provisions of the Equal Opportunity clause; that he will retain such certifications in his files; and that he will forward the following notice to such proposed subcontractors (except where the proposed subcontractors have submitted identical certifications for specific time periods): NOTICE TO CERTIFICATIONS OF NON-SEGREGATED SUBCONTRACTORSPECTIVE FACILITIESENT FOR A Certification of Non-segregated Facilities, as required by the May 9, 1967, order (33 F.R. 7808, May 28, 1968) on Elimination of Segregated Facilities, by the Secretary of Labor, must be submitted prior to the award of a subcontract exceeding $10,000 which is not exempt from the provisions of i�h o Equal subcontracts during a periodortunity clause. The (i.e., quarterly, semiannually,ation may be deoher for each subcontract o r annually). Date Signature Name and Title of Signer (Please Type) NOTE: The penalty for making false statements in offers is prescribed in 18 U.S.C. 1001. EPA-7 5720-4.2 SRF-2 May 2015 Attachment 2 SRF Required Front-End Specifications (This form must be completed and signed by the Prime Contractor and submitted with the bid.) Debarments and Suspensions Any bidder or equipment supplier whose firm or affiliate is listed in on the U.S. General Services Administration Excluded Parties List System web site at http://www.epls.gov/will be prohibited from the bidding process. Anyone submitting a bid who is listed on this web site will be determined to be a non-responsive bidder in accordance with 40 CFR Part 31. United States Environmental Protection Agency Washington, DC 20460 Certification Regarding Debarment, Suspension, and Other Responsibility Matters The prospective participant certifies to the best of its knowledge and belief that it and the principals: (a) Are not presently debarred, suspended, proposed for debarment, declared ineligible, — or voluntarily excluded from covered transactions by any Federal department or agency; (b) Have not within a three year period preceding this proposal been convicted of or had a civil judgment rendered against them for commission o f fraud or a criminal offense in connection with obtaining, attempting to obtain, or performing a public (Federal, State, or local) transaction or contract under a public transaction: violation of Federal or — State antitrust statutes or commission of embezzlement, theft, forgery, bribery, falsification or destruction of records, making false statements, or receiving stolen property; (c) Are not presently indicted for otherwise criminally or civilly charged by a government entity (Federal, State, or local) with commission of any of the offenses enumerated in paragraph (1) (b) of this certification; and (d) Have not within a three-year period preceding this application/proposal had one or more public transaction s (Federal, State, or local) terminated or cause or default. I understand that a false statement on this certification may be ground for rejection of this proposal or termination of the award. In addition, under 18 U SC Sec. 10 01, a false statement ma y result in a fine of up to $10,000 or imprisonment for up to 5 years, or both. Typed Name & Title of Authorized Representative Signature of Authorized Representative Date ❑ I am unable to certify to the above statements. My explanation is attached. EPA Form 5700-49 (11-88) SRF-3 May 2015 Attachment 3 — SRF Required Front-End Specifications (This form must be completed and signed by Prime Contractor and submitted with the bid.) Disadvantaged Business Enterprise (DBE) Solicitation It is EPA's policy that recipients of EPA financial assistance through the State Revolving Fund — programs award a "fair share" of subagreements to small, minority and women-owned businesses, collectively know as Disadvantaged Business Enterprises (DBEs). Iowa's Fair Share goals are: Minority-Owned Business Women-Owned Business Enterprise (MBE) Goal Enterprise (WBE) Goal 1.7% 2.2% Construction ° 5.6% Supplies 0.6/° 11.3% Services 2.5% 2.5% 10.4% Goods/Equipment 1 $% 7.4% Average Only work performed by certified DBEs can be counted toward the goals. In Iowa, DBEs must — be certified through the Iowa Department of Transportation (IDOT). Information on certification requirements and a list of certified DBEs is on the IDOT website at http://www.iowadot.gov/contracts/contracts eeoaa.htm. Prime contractors' DBE requirements for SRF projects include: • Taking affirmative steps for DBE participation • Documenting the efforts and the proposed utilization of certified DBEs PROJECT INFORMATION SRF Applicant: Bidder: Address: Contact Person: Signature: Phone Number: E-Mail Address: Check if Prime Contractor is: ❑ Minority-Owned ❑ Women-Owned SRF-4 May 2015 GOOD FAITH EFFORTS CHECKLIST Please complete the checklist to determine if you have complied with the requirement to make good faith efforts to ensure that certified DBEs have the opportunity to compete for procurements funded by EPA financial assistance funds. Bidders/offerers must make good faith efforts prior to submission of bids/proposals. 1. Did you ensure that DBEs are made aware of contracting opportunities to the fullest extent practicable through outreach and recruitment activities? ❑ Yes ❑ No 2. Did you make information on forthcoming opportunities available to DBEs and arrange time frames for contracts and establish delivery schedules, where the requirements permit, in a way that encourages and facilitates participation by DBEs in the competitive process? This includes, whenever possible, posting solicitation for bids or proposals for a minimum of 30 calendar days before the bid or proposal closing date. ❑ Yes ❑ No 3. Did you consider in the contracting process whether firms competing for large contracts could subcontract with DBEs? This will include dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by DBEs in the competitive process. ❑ Yes ❑ No 4. Did you encourage contracting with a consortium of DBEs when a contract is too large for one of these firms to handle individually? ❑ Yes ❑ No 5. Did you use the services of the Small Business Administration and the Minority Business Development Agency of the Department of Commerce to identify potential subcontractors? ❑ Yes ❑ No 6. List the potential DBE subcontractors that were contacted. Only list those that are certified through the Iowa Department of Transportation. Name How Contacted Response (e.g. did not respond, (e.g. letter, phone not interested, not competitive) call, fax, e-mail) PROPOSED UTILIZATION OF DBE SUBCONTRACTORS Please include Attachments 4 and 5 to document the proposed utilization of certified DBE subcontractors. SRF-5 May 2015 CONTRACT ADMINISTRATION PROVISIONS Several contract provisions are required to prevent unfair practices that adversely affect DBEs. These include: 1. Prime Contractor must pay its Subcontractor for satisfactory performance no more than 30 days from the Prime Contractor's receipt of payment from the SRF loan recipient. 2. Prime Contractor must notify the SRF loan recipient in writing prior to termination of a DBE subcontractor for convenience. 3. Prime t ContractorEfforts a DBE subcontractor toctor failscomplete work under a subcontract for any subcontractor reason. SRF-6 May 2015 Attachment 4 SRF Required Front-End Specifications (This form must be completed and signed by Prime and DBE Subcontractor for each subcontract and submitted with the bid.) OMB Control No: 2090-0030 Approved 8/13/2013 Approval Expires 8/31/2015 United States Environmental Protection Agency Disadvantaged Business Enterprise Program DBE Subcontractor Performance Form This form is intended to capture the DBE1 subcontractor's2 description of work to be performed and the price of the work submitted to the prime contractor. An EPA Financial Assistance Agreement recipient must require its prime contractor to have its DBE subcontractors complete this form and include all completed forms in the prime contractor's bid or proposal package. Subcontractor Name Project Name Bid/Proposal No. Assistance Agreement ID No. Point of Contact (if known) Address Telephone No. Email Address Prime Contractor Name Issuing/Funding Entity Contract Item Description of Work Submitted to the Prime Contractor Involving Price of Work Submitted to Number Construction, Services, Equipment or Supplies the Prime Contractor DBE Certified by DOT SBA Meets/exceeds EPA certification standards? Other: YES NO Unknown 'A DBE is a Disadvantaged, Minority, or Woman Business Enterprise that has been certified by an entity from which EPA accepts certification as described in 40 CFR 33.204-33.205 or certified by EPA. EPA accepts certifications from entities that meet or exceed EPA certification standards as described in 40 CFR 33.202. 2Subcontractor is defined as a company, firm,joint venture, or individual who enters into an agreement with a contractor to provide services pursuant to an EPA award of financial assistance. EPA Form 6100-3 (DBE Subcontractor Performance Form)—Page 1 SRF-7 May 2015 OMB Control No: 2090-0030 Approved 8/13/2013 Approval Expires 8/31/2015 United States Environmental Protection Agency Disad DBnterprise Program E Subcontractor taged Business EPerformance Form gning is form es not signify I certifymm underent penalty o subcontractors uj ry that the contracto sforgoing above. I aatements are true and correct.m aware of that in the event of aI replacement of aosubcontractor,I will — commitment to utilize the subco adhere to the replacement requirements set forth in 40 CFR Part 33 Section 33.302 (c). Prime Contractor Signature Print Name Date _ Title Subcontractor Signature Print Name Date Title three (3) hours The publicreporting and reco burden c Agency's for this collection of inormation is esmated to need for this information,the accuracy of the providedeburden estimates, per response. Send comments on the A 9e and any suggested methods for minimizing respondent burden, including through the use of automated collection1200 techniquesn lva to Ave.,Director, Collection Washington,tton, D.C. 20460.Ivision, U.S.Include the OMB controlnumberl in anyrotection gency (2822T),cor correspondence. Do not send ..- Pennsylvania A N 9 the completed form to this address. EPA Form 6100-3 (DBE Subcontractor Performance Form)—Page 2 SRF-8 May 2015 Attachment 5 SRF Required Front-End Specifications (This form must be completed and signed by Prime Contractor and submitted with the bid if utilizing DBE subcontractors.) OMB Control No: 2090-0030 Approved 8/13/2013 Approval Expires 8/31/2015 United States Environmental Protection Agency Disadvantaged Business Enterprise Program DBE Subcontractor Utilization Form This form is intended to capture the prime contractor's actual and/or intended use of identified certified DBE1 subcontractors2 and the estimated dollar amount of each subcontract. An EPA Financial Assistance Agreement Recipient must require its prime contractors to complete this form and include it in the bid or proposal package. Prime contractors should also maintain a copy of this form on file. Prime Contractor Name Project Name Bid/Proposal No. Assistance Agreement ID No. Point of Contact (if known) Address Telephone No. Email Address Issuing/Funding Entity I have identified potential DBE certified subcontractors YES NO If es, please complete the table below. If no, 'lease ex.lain: Subcontractor Company Address/Phone/Email Estimated Dollar Currently DBE Name/Company Name Amount Certified? 11111111 1111111 Continue on back if needed 1A DBE is a Disadvantaged, Minority, or Woman Business Enterprise that has been certified by an entity from which EPA accepts certification as described in 40 CFR 33.204-33.205 or certified by EPA. EPA accepts certifications from entities that meet or exceed EPA certification standards as described in 40 CFR 33.202. p 2Subcontractor is defined as a company, firm,joint venture, or individual who enters into an agreement with a contractor to provide services pursuant to an EPA award of financial assistance. EPA Form 6100-4(DBE Subcontractor Utilization Form)—Page 1 SRF-9 May 2015 OMB Control No: 2090-0030 -- Approved 8/13/2013 Approval Expires 8/31/2015 United States Environmental Protection Agency DisadvanDaBE Business Enterprise Program — Subcontractor Utilization Form ct ot Icert ify under penalty of perjury that the forgoing statements are truei and the orret . Signing this form of a does no signify, I will a commitment to utilize the subcontractors above. I am aware oft a tadhere to the replacement requirements set forth in 40 CFR Part 33 Section 33.302 (c). Primemliiiiii Contractor Signature miiiiiiiiiil MIIIIIIIIIIIIIIIIUIIIIIIIIIIIIIIIIIII Date three (3) hours The expo reportingd d re on g burdenor this for thistion of information is estimated to infomation,the accuracy of the prrovidedeburden estimates, — per response. Send comments on the Agency's and any suggested methods for minimizing respondent burden, including through the use of automated 8 collection00 techniques to Ave.,Director, CollectWashington, D.C.on trategies 20460.Ivision, U.S.Include the OMB controlnumberl non anygency corre correspondence. Do not send Pennsylvania A NW,Washingt , the completed form to this address. — EPA Form 6100-4(DBE Subcontractor Utilization Form)—Page 2 SRF-10 May 2015 Attachment 6 SRF Required Front-End Specifications (This form is not required for bidding. It is fort the voluntary use of DBE Subco ntractors.) OMB Control No: 2090-0030 Approved 8/13/2013 Approval Expires 8/31/2015 United States Environmental Protection Agency Disadvantaged Business Enterprise Program DBE Subcontractor Participation Form An EPA Financial Assistance Agreement Recipient must require its prime contractors to provide this form to its DBE subcontractors. This form gives a DBE' subcontractor2 the opportunity to describe work received and/or report any concerns regarding the EPA-funded project(e.g. in areas such as termination by prime contractor, late payments, etc.). The DBE subcontractor can, as an option, complete and submit this form to the EPA DBE Coordinator at any time during the project period of performance. Subcontractor Name Project Name Bid/Proposal No. Assistance Agreement ID No. Point of Contact (if known) Address Telephone No. Email Address Prime Contractor Name Issuing/Funding Entity Contract Item Description of Work Received from the Prime Contractor Involving Amount Received by Number Construction, Services, Equipment or Supplies Prime Contractor 'A DBE is a Disadvantaged, Minority,or Woman Business Enterprise that has been certified by an entity from which certification as described in 40 CFR 33.204-33.205 or certified by EPA. EPA accepts certifications from entities that meet orcexpceed EPA certification standards as described in 40 CFR 33.202. 2Subcontractor is defined as a company, firm,joint venture, or individual who enters into an agreement with a contractor to provide services pursuant to an EPA award of financial assistance. EPA Form 6100-2(DBE Subcontractor Participation Form)—Page 1 SRF-11 May 2015 OMB Control No: 2090-0030 Approved 8/13/2013 Approval Expires 8/31/2015 United States Environmental Protection Agency Disadvantaged Subcontractor ParticipationDBErise Program ipat on Form Please use the space below to report any concerns regarding the above EPA-funded project: Subcontractor Signature Print Name Title Date EPA FORM 6100-2 (DBE Subcontractor Participation Form) Return to: Regional Coordinator, Small Business Utilization, U.S. Environmental Protection Agency, Region 7, 11201 Renner Blvd., Lenexa, KS 66219 e The public reporting and recordkeeping burden for this collection of information accuracytiated d to paveragebhreen(3) hours timates, per response. Send comments on the Agency's need for this information, and any suggested methods for minimizing respondent burden, including through the use of automated collection techniquesen lva to Ave.,Director, Collection D.C. 20460.Ivision, U.S.Include the OMB controlnumberl non anygency (2822T), 1200 cor correspondence. Do not send Pennsylvania A NW,Washington, the completed form to this address. EPA Form 6100-2(DBE Subcontractor Participation Form)—Page 2 SRF-12 May 2015 Attachment 7 SRF Required Front-End Specifications Other Federal Requirements Language A. Standard Federal Equal Employment Opportunity Construction Contract Specifications (Executive Order 11246) 1. As used in these specifications: a. "Covered area" means the geographical area described in the solicitation from which this contract resulted; b. "Director" means Director, Office of Federal Contract Compliance Programs, United States Department of Labor, or any person to whom the Director delegates authority; c. "Employer identification number" means the Federal Social Security number used on the Employer's Quarterly Federal Tax Return, U.S. Treasury Department Form 941. d. "Minority" includes: (i) Black (all persons having origin in any of the Black African racial groups not of Hispanic origin); (ii) Hispanic (all persons of Mexican, Puerto Rican, Cuban, Central or South American or other Spanish Culture or origin, regardless of race); (iii) Asian and Pacific Islander (all persons having origins in any of the original peoples of the Far East, Southeast Asia, the Indian Sub-continent, or the Pacific Islands); and (iv) American Indian or Alaskan Native (all persons having origins in any of the original peoples of North America and maintaining identifiable tribal affiliations through membership and participation or community identification). 2. Whenever the Contractor, or any Subcontractor at any tier subcontracts a portion of the work involving any construction trade, it shall physically include in each subcontract in excess of $10,000 the provisions of these specifications and the Notice which contains the applicable goals for minority and female participation and which is set forth in the solicitations from which this contract resulted. 3. If the Contractor is participating (pursuant to 41 CFR 6-4.5) in a Hometown Plan approved by the U.S. Department of Labor in the covered area either individually or through an association, its affirmative action obligations on all work in the Plan area (including goals and timetables) shall be in accordance with that Plan for those trades which have unions participating in the Plan. Contractors must be able to demonstrate their participation in and compliance with the provisions of any such Hometown Plan. Each Contractor or Subcontractor participating in an approved Plan is individually required to comply with its obligations under the EEO clause, and to make a good faith effort to achieve each goal under the Plan in each trade in which it has employees. The overall good faith performance by other Contractors or Subcontractors toward a goal in an approved Plan does not excuse any covered Contractor's or Subcontractor's failure to take good faith efforts to achieve the Plan goals and timetables. 4. The Contractor shall implement the specific affirmative action standards provided in paragraphs 7a through p of these specifications. The goals set forth in the solicitation from which this contract resulted are expressed as percentages of the total hours of employment and training of minority and female utilization the Contractor should reasonably be able to achieve in each construction trade in which it has employee in the covered area. Covered construction contractors performing construction work in geographical areas where they do not have a SRF-13 May 2015 Federal or federally assisted construction contract shall apply the minority and female goals established for the geographical area where the work in being performed. Goals are published periodically in the Federal Register in notice form, and such notices may be obtained from any Office of Federal Contract Compliance Programs office or from Federal procurement contracting officers. The Contractor is expected to make substantially uniform progress in meeting its goals in each craft during the period specified. 5. Neither the provisions of any collective bargaining agreement, nor the failure by a union with whom the Contractor has a collective bargaining agreement, to refer either minorities or women shall excuse the Contractor's obligations under these specifications, Executive Order 11246, or the regulations promulgated pursuant thereto. 6. In order for the nonworking training hours of apprentices and trainees to be counted in meeting the goals, such apprentices and trainees must be employed by the Contractor during the training period, and the Contractor must have made a commitment to employ the apprentices and trainees at the completion of their training, subject to the availability of employment opportunities. Trainees must be trained pursuant to training programs approved by the U.S. Department of Labor. 7. The Contractor shall take specific affirmative actions to ensure equal employment opportunity. The evaluation of the Contractor's compliance with these specifications shall be basedcueunt n its effort to efforts fully, ve and shall implement affirmativeum results from its tions. The act on steps atleastras extensivell document these Y as the following: a. Ensure and maintain a working environment free of harassment, intimidation, and coercion at all sites, and in all facilities at which the Contractor employees are assigned to work. The Contractor, where possible will assign two or more women to each construction project. The Contractor shall specifically ensure that all foremen, superintendents, and other on-site supervisory personnel are aware of and carry out the Contractor's obligation to maintain such a working environment, with specific attention to minority or female individuals working at such sites or in such facilities. b. Establish and maintain a current list of minority and female recruitment sources, provide written notification to minority and female recruitment sources and to community organizations when the Contractor or its unions have employment opportunities available and maintain a record of the organizations' responses. c. Maintain a current file of the names, addresses and telephone numbers of each minority and female off-the-street applicant and minority or female referral from a union, a recruitment source or community organization and of what action was taken with respect to each such individual. If such individual was sent to the union hiring hall for referral and was not referred back to the Contractor by the union or, if referred, not employed by the Contractor, this shall be documented in the file with the reason therefore, along with whatever additional actions the Contractor may have taken. d. Provide immediate written notification to the Director when the union or unions with which the Contractor has a collective bargaining agreement has not referred to the Contractor a minority person or woman sent by the Contractor, or when the Contractor has other information that the union referral process has impeded the Contractor's effort, to meet its obligations. e. Develop on-the-job training opportunities and/or participate in training programs for the area which expressly include minorities and women, including upgrading programs and apprenticeship and trainee programs relevant to the Contractor's employment needs, especially those programs funded or approved by the Department of Labor. The SRF-14 May 2015 Contractor shall provide notice of these programs to the source complied under 7b above. f. Disseminate the Contractor's EEO policy by providing notice of the policy to unions and training programs and requesting their cooperation in assisting the Contractor in meeting its EEO obligations; by including it in any policy manual and collective bargaining agreement; by publicizing it in the company newspaper, annual report, etc.; by specific review of the policy with all management personnel and with all minority and female employees at least once a year; and by posting the company EEO policy on bulletin boards accessible to all employees at each location where construction work is performed. g. Review, at least annually, the company's EEO policy and affirmative action obligations under these specifications with all employees having any responsibility for hiring, assignment, layoff, termination or other employment decisions including specific review of these items with onsite supervisory personnel such as Superintendents, General Foremen, etc., prior to the initiation of construction work at any job site. A written record shall be made and maintained identifying the time and place of these meetings, persons attending, subject matter discussed, and disposition of the subject matter. h. Disseminate the Contractor's EEO policy externally by including it in any advertising in the news media, specifically including minority and female news media, and providing written notification to and discussing the Contractor's EEO policy with other Contractors and Subcontractors with whom the Contractor does or anticipates doing business. i. Direct its recruitment efforts, both oral and written, to minority, female and community organizations, to schools with minority and female students and to minority and female recruitment and training organizations serving the Contractor's recruitment area and employment needs. Not later than one month prior to the date for the acceptance of applications for apprenticeship or other training by any recruitment source, the Contractor shall send written notification to organizations such as the above, describing the openings, screening procedures, and test to be used in the selection process. j. Encourage present minority and female employees to recruit other minority persons and women and, where reasonable, provide after school, summer and vacation employment to minority and female youth both on the site and in other areas of a Contractor's workforce. k. Validate all tests and other selection requirements where there is an obligation to do so under 41 CFR Part 60-3. 1. Conduct, at least annually, an inventory and evaluation at least of all minority and female personnel for promotional opportunities and encourage these employees to seek or to prepare for, through appropriate training, etc., such opportunities. m. Ensure that seniority practices, job classifications work assignments and other personnel practices, do not have a discriminatory effect by continually monitoring all personnel and employment related activities to ensure that the EEO policy and the Contractor's obligations under these specifications are being carried out. n. Ensure that all facilities and company activities are nonsegregated except that separate or single-user toilet and necessary changing facilities shall be provided to assure privacy between the sexes. o. Document and maintain a record of all solicitations of offers for subcontracts from minority and female construction contractors and suppliers, including circulation of solicitations to minority and female contractor associations and other business associations. p. Conduct a review, at least annually, of all supervisors' adherence to and performance under the Contractor's EEO policies and affirmative action obligations. SRF-15 May 2015 8. Contractors are encouraged to participate in voluntary associations which assist in fulfilling one or more of their affirmative action obligations (7a through p). The efforts of a contractor association, joint contractor-union, contractor-community, or other similar group of which the contractor is a member and participant, may be asserted as fulfilling any one or more of its obligations under 7a through p of these Specifications provided that the contractor actively participates in the group, makes every effort to assure that the group has a positive impact on the employment of minorities and women in the industry, ensures that the concrete benefits of the program are reflected in the Contractor's minority and female workforce participation, makes a good faith effort to meet its individual goals and timetables, and can provide access to documentation which demonstrates the effectiveness of actions taken on behalf of the Contractor. The obligation to comply, however, is the Contractor's and failure of such a group to fulfill an obligation shall not be a defense for the Contractor's noncompliance. 9. A single goal for minorities and a separate single goal for women have been established. The Contractor, however, is required to provide equal employment opportunity and to take affirmative action for all minority groups, both male and female, and all women, both minority and non-minority. Consequently, the Contractor may be in violation of the Executive Order if a particular group is employed in a substantially disparate manner(for example, even though the Contractor has achieved its goals for women generally, the Contractor may be in violation of the Executive Order if a specific minority group of women is underutilized). 10. The Contractor shall not use the goals and timetable or affirmative action standards to discriminate against any person because of race, color, religion, sex, or national origin. 11. The Contractor shall not enter into any Subcontract with any person or firm debarred from Government contracts pursuant to Executive Order 11246. 12. The Contractor shall carry out such sanctions and penalties for violation of these specifications and of the Equal Opportunity Clause, including suspension, termination and cancellation of existing subcontracts as may be imposed or ordered pursuant to Executive Order 11246, as amended, and its implementing regulations, by the Office of Federal Contract Compliance Programs. Any Contractor who fails to carry out such sanctions and penalties shall be in violation of these specifications and Executive Order 11246, as amended. 13. The Contractor, in fulfilling its obligations under these specifications, shall implement specific affirmative action steps at least as extensive as those standards prescribed in paragraph 7 of these specifications so as to achieve maximum results from its efforts to ensure equal employment opportunity. If the Contractor fails to comply with the requirements of the Executive Order, the implementing regulations, or these specifications, the Director shall proceed in accordance with 41 CFR 60-4.8. 14. The Contractor shall designate a responsible official to monitor all employment related activity to ensure that the company EEO policy is being carried out, to submit reports relating to the provisions hereof as may be required by the Government and to keep records. Records shall at least include for each employee the name, address, telephone numbers, construction trade, union affiliation if any, employee identification number when assigned, social security number, race, sex, status (e.g., mechanic, apprentice, trainee, helper, or laborer), dates of changes in status, hours worked per week in the indicated trade, rate of pay, and locations at which the work was performed. Records shall be maintained in an easily understandable and retrievable form; however, to the degree that existing records satisfy this requirement, contractors shall not be required to maintain separate records. SRF-16 May 2015 15. Nothing herein provided shall be construed as a limitation upon the application of other laws which establish different standards of compliance or upon the application of requirements for the hiring of local or other area residents (e.g., those under the Public Works Employment Act of 1977 and the Community Development Block Grant Program). Federal Register, Vol. 43, No. 68 - Friday, April 7, 1978 (Corrected May 5, 1978). Effective Date: May 8, 1978 Federal Register, Vol. 45, No. 194. Paragraph 4, revised October 3, 1980 Effective Date: September 30, 1980 APPENDICES A and B-80 Notice of Requirement for Affirmative Action To Ensure Equal Employment Opportunity (Executive Order 11246) 1. The Offeror's or Bidder's attention is called to the "Equal Opportunity Clause" and the — "Standard Federal Equal Employment Specifications" set forth herein. 2. The goals and timetables for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows: (See Appendix B-80 and Appendix A Below) These goals are applicable to all the Contractor's construction work (whether or not it is Federal — or federally assisted) performed in the covered area. If the contractor performs construction work in a geographical area located outside of the covered area, it shall apply the goals established for such geographical area where the work is actually performed. With regard to this second area, the contractor also is subject to the goals for both its federally involved and non- federally involved construction. The Contractor's compliance with the Executive Order and in the regulations in 41 CFR Part 60-4 shall be based on its implementation of the Equal Opportunity Clause, specific affirmative action obligations required by the specifications set forth in 41 CFR 60-4.3(a), and its efforts to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade, and the contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from Contractor to Contractor or from project to project for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, the Executive Order and the regulations in 41 CFR Part 60-4. Compliance with the goals will be measured against the total work hours performed. 3. The Contractor shall provide written notification to the Director of the Office of Federal Contract Compliance Programs within 10 working days of award of any construction subcontract in excess of$10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the name, address and telephone number of the subcontractor, employer Identification number of the subcontractor, estimated dollar amount of the subcontract, and the geographical area in which the subcontract is to be performed. SRF-17 May 2015 4. As used in this Notice, and in the contract resulting from this solicitation, the "covered area" is (State of Iowa). APPENDIX A The following goals and timetables for female utilization shall be included in all Federal and federally assisted construction contracts and subcontracts in excess of $10,000. The goals are applicable to the contractor's aggregate on-site construction workforce whether or not part of that workforce is performing work on a Federal or federally assisted construction contract or subcontract. Area covered: Goals for Women apply nationwide. Timetable Goals (percent) From Apr. 1, 1978 until March 31, 1979 3.1 From Apr. 1, 1979 until March 31, 1980 5.0 From Apr. 1, 1980 until March 31, 1981 6.9 Published, Federal Register May 5, 1978 APPENDIX B-80 Until further notice, the following goals for minority utilization in each construction craft and trade shall be included in all Federal or federally assisted construction contracts and subcontracts in excess of $10,000 to be performed in the respective geographical areas. The goals are applicable to each nonexempt contractor's total onsite construction workforce, regardless of whether or not part of that workforce is performing work in a Federal, federally assisted or nonfederally related project, contract or subcontract. Construction contractors which are participating in an approved Hometown Plan (see 41 CFR 60-4.5) are required to comply with the goals of the Hometown Plan with regard to construction work they perform in the area covered by the Hometown Plan. With regard to all their other covered construction work, such contractors are required to comply with the applicable SMSA of EA goal contained in this appendix B-80. SRF-18 May 2015 Economic Areas State: Iowa Goal % 096 Dubuque IA: SMSA Counties: 2200 Dubuque, IA .. 0.6 IA Dubuque Non-SMSA Counties 0.5 IA Allamakee, IA Clayton, IA Delaware, IA, Jackson IA, Winneshiek 099 Davenport Rock Island Moline, IA-IL: SMSA Counties: -' 1960 Davenport Rock Island Moline, IA-IL 4.6 IL Henry, IL Rock Island Moline, IA Scott Non-SMA Counties 3.4 IL Carroll, IL Hancock, IL Henderson, IL ,Mercer, IL Whiteside, IA Clinton, IA Des Moines, IA Henry, IA Lee, IA Louisa, IA, Muscatine, MO Clark 100 Cedar Rapids, IA: SMSA Counties: 1360 Cedar Rapids, IA 1.7 IA Linn Non-SMSA Counties 1.5 IA Benton, IA Cedar, IA Iowa, IA Johnson, IA, Jones, IA, Washington 101 Waterloo, IA: SMSA Counties: 8920 Waterloo-Cedar Falls, IA 4.7 IA Black Hawk Non-SMSA Counties 2.0 IA Bremer, IA Buchanan, IA Butler, IA Cerro Gordo, IA Chickasaw, IA Fayette, IA Floyd, IA Franklin, IA Grundy, IA Hancock, IA Hardin, IA Howard, IA Mitchell, IA Winnebago, IA Worth 102 Fort Dodge, IA: Non-SMSA Counties 0.4 IA Buena Vista, IA Calhoun, IA Carroll, IA Clay, IA Dickinson, IA Emmet, IA Greene, IA Hamilton, IA Humboldt, IA Kossuth, IA Palo Alto, IA Pocahontas, IA Sac, IA Webster, IA Wright 103 Sioux City, IA: SMSA Counties: 7720 Sioux City, IA-NE 1.9 IA Woodbury, NE Dakota SRF-19 May 2015 Non-SMSA Counties 1.2 IA Cherokee, IA Crawford, IA Ida, IA Monona, IA O'Brien, IA Plymouth, IA Sioux, NE Antelope, NE Cedar, NE Cuming, NE Dixon, NE Knox, NE Madison, NE Pierce, NE Stanton, NE Thurston, NE Wayne, SD Bon Homme, SD Clay, SD Union, SD Yankton 104 Des Moines, IA: SMSA Counties: 2120 Des Moines, IA 4.5 IA Polk, IA Warren Non SMSA Counties: 2.4 IA Adair, IA Appanoose, IA Boone, IA Clarke, IA Dallas, IA Davis, IA Decatur, IA Guthrie, IA Jasper, IA Jefferson, IA Keokuk, IA Lucas, IA Madison, IA Mahaska, IA Marion, IA Marshall, IA Monroe, IA Poweshiek, IA Ringgold, IA Story, IA Tama, IA Union, IA Van Buren, IA Wapello, IA Wayne 143 Omaha, NE: SMSA Counties: 7 6 5920 Omaha, NE-IA IA Pottawattamie, NE Douglas, NE Sarpy Non-SMSA Counties 5.3 IA Adams, IA Audubon, IA Cass, IA Fremont, IA Harrison, IA Mills, IA Montgomery, IA Page, IA Shelby, IA Taylor, NE Burt, NE Cass, NE Colfax, NE Dodge, NE Platte, NE Saunders, NE Washington Published, Federal Register October 3, 1980 B. Federal Labor Standards Provisions (including Davis-Bacon prevailing wage rates) Applicability The Project or Program to which the construction work covered by this contract pertains is being assisted by the United States of America and the following Federal Labor Standards Provisions are included in this Contract pursuant to the provisions applicable to such Federal assistance. (1) Minimum wages. (i) All laborers and mechanics employed or working upon the site of the work will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account (except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto and made a part hereof, regardless of any contractual relationship which may be alleged to exist between the contractor and such laborers and mechanics. Contributions made or costs reasonably anticipated for bona fide fringe benefits under section 1(b)(2) of the Davis-Bacon Act on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions of paragraph (a)(1)(iv) of this section; also, regular contributions made or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or programs which cover the particular weekly period, are deemed to be constructively made or incurred during such weekly period. Such laborers and mechanics shall be paid the appropriate wage rate and fringe benefits on the wage determination for the classification of work actually performed, without regard to skill, SRF-20 May 2015 except as provided in Sec. 5.5(a)(4). Laborers or mechanics performing work in more than one classification may be compensated at the rate specified for each classification for the time actually worked therein: Provided, That the employer's payroll records accurately set forth the time spent in each classification in which work is performed. The wage determination (including any additional classification and wage rates conformed under paragraph (a)(1)(ii) of this section) and the Davis-Bacon poster (WH-1321) shall be posted at all times by the contractor and its subcontractors at the site of the work in a prominent and accessible place where it can be easily seen by the workers. (ii)(A) The contracting officer shall require that any class of laborers or mechanics, including helpers, which is not listed in the wage determination and which is to be employed under the contract shall be classified in conformance with the wage determination. The contracting officer shall approve an additional classification and wage rate and fringe benefits therefore only when the following criteria have been met: (1) The work to be performed by the classification requested is not performed by a classification in the wage determination; and (2) The classification is utilized in the area by the construction industry; and (3) The proposed wage rate, including any bona fide fringe benefits, bears a reasonable relationship to the wage rates contained in the wage determination. (B) If the contractor and the laborers and mechanics to be employed in the classification (if known), or their representatives, and the contracting officer agree on the classification and wage rate (including the amount designated for fringe benefits where appropriate), a report of the action taken shall be sent by the contracting officer to the Administrator of the Wage and Hour Division, Employment Standards Administration, U.S. Department of Labor, Washington, DC 20210. The Administrator, or an authorized representative, will approve, every additional classification action within 30 days of receipt and so advisedify the contracting officer or will notify the contracting officer within the 30-day period that additional time is necessary. (C) In the event the contractor, the laborers or mechanics to be employed in the classification or their representatives, and the contracting officer do not agree on the proposed classification and wage rate (including the amount designated for fringe benefits, where appropria-e), the contracting officer shall refer the questions, including the views of all interested parties and the recommendation of the contracting officer, to the Administrator for determination. The Administrator, or an authorized representative, will issue a determination within 30 days of receipt and so advise the contracting officer or will notify the contracting officer within the 30-day period that additional time is necessary. (D) The wage rate (including fringe benefits where appropriate) determined pursuant to paragraphs (a)(1)(ii) (B) or (C) of this section, shall be paid to all workers performing work in the classification under this contract from the first day on which work is performed in the classification. (iii) Whenever the minimum wage rate prescribed in the contract for a class of labo-ers or _ mechanics includes a fringe benefit which is not expressed as an hourly rate, the con Tractor shall either pay the benefit as stated in the wage determination or shall pay another bDna fide fringe benefit or an hourly cash equivalent thereof. — (iv) If the contractor does not make payments to a trustee or other third person, the contractor may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in providing bona fide fringe benefits under a plan or program, Provided, That the Secretary of Labor has found, upon the written request of the contractor, that the applicable standards of the Davis-Bacon Act have been met. The Secretary of Labor may require the contractor to set aside in a separate account assets for the meeting of obligations under the plan or program. SRF-21 May 2015 on own action r upon written request of an authorized (2) Withholding. The EPA shall ups withhold or�ause to be withheld from the contractor representative of the Department ofLabor under this contractor any oth to Davis-Bacon prevailing wage eral contract with the same ne contractor, or any requirements, which ist held federally-assisted contract subject ay by the same prime contractor, so much of the accrued payments or advaest as may,be considered necessary to pay laborers and mechanics, including apprentices, and helpers, employed by the contractor or any subcontractor the full amount of wages requir d by the contract. In the event of failure to pay any laborer or mechanic, including any app trainee, or helper, employed or working on the site of the work, all or part of the wages orquired by the contract, the EPA may, after written notice to the contractor, sponsor, applicant, owner, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds until such violations have ceased. (3) Payrolls and basic records. (i) Payrolls and basic records relating thereto shall be maintained by the contractor during the course of the work and preserved for a period of three years thereafter for all laborers and mechanics working at the site of the work. Such records shall contain the name, address, and social security number of each such worker, his or her correct classification, hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in section 1(b)(2)(B) of the Davis-Bacon Act), daily and weekly number of hours worked, deductions made and actual wages id. Whenever the Secretary of Labor has f of and under y costs CFR 5.5(a)(1)(iv) that the wages of any laborer or mechanic include the amount reasonably anticipated in providing benefits under a plan or program described in section I(b)(2)(B) of the Davis-Bacon Act, the contractor shall maintain records which show that the commitment to provide such benefits beele, that the plan or n communicated in nw 9 ing to the laborers or ram is financially responsible, and that the plan program has e mechanics affected, and records which show the costs anticipated ipo trainees or the actde al cost incurred in providing such benefits. Contractors employing apprentices n programs shall maintain written evidence of the registration of tiapprenticeship and t a pees programs and the natios d certification of trainee programs, the registration of the app and wage rates prescribed in the applicable programs. (ii)(A) The contractor shall submit weekly for each week in which federal agency)work if the is performed a copy of all payrolls to the (write in name of appropriate agency is a party to the contract, but ifothr owgency er, asls not such a the case may beyfohtransme ass on willo submit the payrolls to the applicant, sponsor, (write in name of agency). The payrolls submitted shall set out accurately and completely all of the information required to be maintained under 29 CFR 5.5(a)(3)(i), except that full social security numbers and home addresses shall not bee included on weeklyr trans eansmimployeeInstead the payrolls shall only need to include an individually identifying the last four digits of the employee's form social desiredsecurity Opt Optional Fohm WH 134d7 isavaylablerfor this oll information may be submitted any purpose from the Wage and Hour Division Web site at httr` l/www dol govlesalwhdtforms/ h3 7str.htm or its successor site. The prime ayrolls by all subcontractors. Contractors contractorand is copies responsible for the submission of of p subcontractors shall maintain the full social security number and current address of eaach covered worker, and shall provide them pon a t ast ctt but if the(write agency is not s P h a party, the e federal agency) if the agency is a party to the co contractor will submit them to the applicant, sponsor, or owner, as the case may be, for transmission to the (write in name of a cy), the investigation o�r, or the Wage aud t of ompl andce with prevailing Hour Division of the Department of Labor for purposes of an wage requirements. It is not a violation of this section for a prime contractor to require a subcontractor to provide addresses and social security numbers to the prime contractor for its SRF-22 May 2015 own records, without weekly submission to the sponsoring government agency (or the applicant, sponsor, or owner). (B) Each payroll submitted shall be accompanied by a -Statement of Compliance," signed by the contractor or subcontractor or his or her agent who pays or supervises the payment of the persons employed under the contract and shall certify the following: (1) That the payroll for the payroll period contains the information required to be provided under Sec. 5.5 (a)(3)(ii) of Regulations, 29 CFR part 5, the appropriate maintained under Sec. 5.5 (a)(3)(i) of Regulations, 29 CFR part 5, and that such information is correct and complete; (2) That each laborer or mechanic (including each helper, apprentice, on the contract during the payroll period has been paid the full weekly wagestearn trainee)ee i hout rebate, either directly or indirectly, and that no deductions have been made either directly or indirectly from the full wages earned, other than permissible deductions as set forth in Regulations, 29 CFR part 3; (3) That each laborer or mechanic has been paid not less than the applicable wage rates and fringe benefits or cash equivalents for the classification of work performed, as specified in the applicable wage determination incorporated into the contract. (C) The weekly submission of a properly executed certification set forth on the reverse side of Optional Form WH-347 shall satisfy the requirement for submission of the -Statement of Compliance" required by paragraph (a)(3)(ii)(B) of this section. (D) The falsification of any of the above certifications may subject the contractor or subcontractor to civil or criminal prosecution under section 1001 of title 18 and section 231 of title 31 of the United States Code. (iii) The contractor or subcontractor shall make the records required under paragraph (a)(3)(i) of this section available for inspection, copying, or transcription by authorized representatives of the EPA or the Department of Labor, and shall permit such representatives to interview employees during working hours on the job. If the contractor or subcontractor fails to submit the required records or to make them available, the Federal agency may, after written notice to the contractor, sponsor, applicant, or owner, take such action as may be necessary to cause the suspension of any further payment, advance, or guarantee of funds. Furthermore, failure to submit the required records upon request or to make such records available may be grounds for debarment action pursuant to 29 CFR 5.12. (4) Apprentices and trainees--(i) Apprentices. Apprentices will be permitted to work at less than the predetermined rate for the work they performed when they are employed pursuant to and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer and Labor Services, or with a State Apprenticeship recognized by the Office, or if a person is employed in his or her first 90 days of probationary ency employment as an apprentice in such an apprenticeship program, who is not individually registered in the program, but who has been certified by the Office of Apprenticeship Training, Employer and Labor Services or a State ApprenticeshipA eligible for probationary employment as an a Agency Y (where appropriate) to be . The a of apprentices to journeymen on the job site in any craft classification shall not)beg elowable atertio than the ratio permitted to the contractor as to the entire work force under the registered program. Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated above, shall be paid not less than the applicable wage rate on the wage determination for the classification of work actually performed. In addition, any apprentice work on the job site in excess of the ratio permitted under the registered program shall be paid o of less than the applicable wage rate on the wage determination for the work actually performed. Where a contractor is performing construction on a project in a locality other than that in which its program is registered, the ratios and wage rates (expressed in percentages of the journeyman's SRF-23 May 2015 hourly rate) specified in the contractor's or subcontractor's registered program shall be observed. Every apprentice must be paid at not less than the rate specified in the registered program for the apprentice's level of progress, expressed as a percentage of the journeymen hourly rate specified in the applicable wage determination. Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. n cf the Ad cation,inistra or determines that a different practice prevails for the applicableapprentice frges shall be paid in accordance with that determination. In the event the Office of Apprenticeship Training, Employer and Labor Services, or a State Apprenticeship Agency recognized by the Office, withdraws approval of an apprenticeship program, the contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved. (ii) Trainees. Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, shall not Employment be gand Training eater than perm itted tration. The under the plan ratio of trainees to journeymen on the job site approved by the Employment and Training Administration. Every trainee must be paid at not less than the rate specified in the approved program for the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination. Trainees shall be aid fringe benefits in accordance with benefits,the trait rovisions ees shall be paid of the trainee program. If the trainee program does not mention fringe of the full amount of fringe benefits listed on the wage determination ceshess the e Administratorssoc with the Wage and Hour Division determines that there is an apprenticeship program the corresponding journeyman age rate on the wage determination which n ices. Any employee lisovides for less ted on the payroll atra t a nee rate who than full fringe benefitss for for app roved b the Employment and Training is not registered and participating in a training plana rateon the wage determination for Administration shall be paid not less than the applicable wage the classification of work actually performed. theln adition, any trainee performing registered program shall be paid o of less than the work on the job site in excess of the ratio permittedlly applicable wage rate on the wage determination for the work actof a p a nirt d. In thegram, the event the Employment and Training Administration withdraws approval contractor will no longer be permitted to utilize trainees at less than the applicableb predetermined rate for the work performed until an acceptable program is approved. (iii) Equal employment opportunity. The utilization of apprentices, trainees and journeymen under this part shall be in conformity with the equal employment opportunity requirements of Executive Order 11246, as amended, and 29 CFR part 30. (5) Compliance with Copeland Act requirements. The contractor shall comply with the rated by requirements or ct2 CFR part 3, which are contactor or subcontractor shall insert in any surence in ls contract. bcontracts the clauses (6) Subcontracts. The contained in 29 CFR 5.5(a)(1) through (10) and such other clauses as the (write in the name of the Federal agency) may by appropriate instructions require, and also a clause requiring the ctor subcontractors to include these -ncllaance any lower subcontractor or lower tieh s e pbcontractorime a w th all shall be responsible for the co p by the contract clauses in 29 CFR 5.5. (7) Contract termination: debarment. A breach of te and for debahme t as at contractor and a suclauses in 29 CFR bcon ac oe act grounds for termination of the contract, as provided in 29 CFR 5.12. SRF-24 May 2015 (8) Compliance with Davis-Bacon and Related Act requirements. All rulings and interpretations of the Davis-Bacon and Related Acts contained in 29 CFR parts 1, 3, and 5 are herein incorporated by reference in this contract. (9) Disputes concerning labor standards. Disputes arising out of the labor standards provisions of this contract shall not be subject to the general disputes clause of this contract. Such disputes shall be resolved in accordance with the procedures of the Department of Labor set forth in 29 CFR parts 5, 6, and 7. Disputes within the meaning of this clause include disputes between the contractor(or any of its subcontractors) and the contracting agency, the U.S. Department of Labor, or the employees or their representatives. (10) Certification of eligibility. (i) By entering into this contract, the contractor certifies that neither it (nor he or she) nor any person or firm who has an interest in the contractor's firm is a person or firm ineligible to be awarded Government contracts by virtue of section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1). (ii) No part of this contract shall be subcontracted to any person or firm ineligible for award of a Government contract by virtue of section 3(a) of the Davis-Bacon Act or 29 CFR 5.12(a)(1). (iii) The penalty for making false statements is prescribed in the U.S. Criminal Code, 18 U.S.C. 1001. (b) Contract Work Hours and Safety Standards Act. The Agency Head shall cause or require the contracting officer to insert the following clauses set forth in paragraphs (b)(1), (2), (3), and (4) of this section in full in any contract in an amount in excess of$100,000 and subject to the overtime provisions of the Contract Work Hours and Safety Standards Act. These clauses shall be inserted in addition to the clauses required by Sec. 5.5(a) or 4.6 of part 4 of this title. As used in this paragraph, the terms laborers and mechanics include watchmen and guards. (1) Overtime requirements. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek. (2) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (b)(1) of this section the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (b)(1) of this section, in the sum of$10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (b)(1) of this section. (3) Withholding for unpaid wages and liquidated damages. The loan recipient shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (b)(2) of this section. (4) Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses set forth in paragraph (b)(1) through (4) of this section and also a clause requiring the SRF-25 May 2015 subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (b)(1) through (4) of this section. (c) In addition to the clauses contained in paragraph (b), in any contract subject only to the Contract Work Hours and Safety Standards Act and not to any of the other statutes cited in Sec. 5.1, the Agency Head shall cause or require the contracting officer to insert a clause requiring that the contractor or subcontractor shall maintain payrolls and basic payroll records during the course of the work and shall preserve them for a period of three years from the completion of the contract for all laborers and mechanics, including guards and watchmen, working on the contract. Such records shall contain the name and address of each such employee, social security number, correct classifications, hourly rates of wages paid, daily and weekly number of hours worked, deductions made, and actual wages paid. Further, the Agency Head shall cause or require the contracting officer to insert in any such contract a clause providing that the records to be maintained under this paragraph shall be made available by the contractor or subcontractor for inspection, copying, or transcription by authorized representatives of the EPA and the Department of Labor, and the contractor or subcontractor will permit such representatives to interview employees during working hours on the job. C. Preservation of Open Competition and Government Neutrality Towards Government Contractors' Labor Relations on Federal and Federally Funded Construction Projects (Executive Order 13202, as amended by Executive Order 13208) Executive Order 13202, signed February 17, 2001 and amended April 4, 2001, requires all executive agencies that issue grants to ensure Government neutrality toward contractors' labor relations. This applies to recipients of SRF assistance. The Executive Order prohibits discrimination against contractors and their employees in construction contracts based upon labor affiliation or lack thereof. SRF assistance recipients and any construction managers acting on their behalf must ensure that bidding specifications, project agreements, and other controlling documents do not require, prohibit, or otherwise discriminate, with respect to labor affiliation or lack thereof. D. Historical and Archeological Finds If, during the course of construction, evidence of deposits of historical or archeological interest is found, the contractor shall cease operations affecting the find. The owner shall then notify the State Revolving Fund Environmental Review Specialist, who shall in turn notify the State Historic Preservation Office. The SRF shall consult with the SHPO and other interested parties to determine the proper course of action regarding the discovery. No further disturbance of the deposits shall ensue until the SRF Environmental Review Specialist determines that the project activities in that area may proceed. Compensation to the contractor, if any, for lost time or changes in construction to avoid the find, shall be determined in accordance with changed conditions or change order provisions of the specifications. andAuthorityfor this derives 00If human remainsn arediscovered then Historic Preservation stateAct law also applies IC 263B.seq.) and 36 CFR Part 800. SRF-26 May 2015 E. Prohibitions on Procurement from Violating Facilities (Section 306, Clean Air Act; Section 508, Clean Water Act; Executive Order 11738) Both the Clean Water Act and the Clean Air Act prohibit federal agencies from extending assistance by way of loans or contracts to persons who have been convicted of violations of either law. Executive Order 11738 was issued to coordinate enforcement by the U.S. Environmental Protection Agency, which shall designate facilities which have given rise to a conviction for an offense under the criminal provisions of the Clean Air Act and the Clean Water Act. The Executive Order also prohibits agencies from extending assistance to facilities that are not in compliance with either Act. SRF assistance recipients may not procure goods, services, or materials from suppliers listed by the EPA as violators. The Excluded Parties Listing System is located at nttpa/epls.arnet.gov. Attachment 8 SRF Required Front-End Specifications Right of Entry and Records Retention The recipient shall provide access at all times for the Department of Natural Resources, the Iowa Finance Authority, the state auditor, and the U.S. EPA Office of the Inspector General to all project records and documents for inspection and audit purposes for a period of three years after the date of last loan payment. The same access to the project site(s) shall be provided for inspection purposes. 92.8 (2).6.e. State inspections. Personnel of the department shall have the right to examine all construction aspects of the project, including materials and equipment delivered and stored on site for use on the project. SRF-27 May 2015 Attachment 9 SRF Required Front-End Specifications "American Iron and Steel" Requirements H.R. 3547, the "Consolidated Appropriations Act, 2014," enacted January 17, 2014 by the U.S. Congress, includes "American Iron and Steel" provisions that require Clean Water and Drinking Water State Revolving Fund assistance recipients of these funds to use iron and steel produced in the United States. H.R. 3547 includes the following language in Division G, Title IV, under the heading, "Use of American Iron and Steel": Sec. 436. (a)(1) None of the funds made available by a State water pollution control revolving fund as authorized by title VI of the Federal Water Pollution Control Act (33 U.S.C. 1381 et seq.) or made available by a drinking water treatment revolving loan fund as authorized by section 1452 of the Safe Drinking Water Act (42 U.S.C. 300j-12) shall be used for a project for the construction, alteration, maintenance, or repair of a public water system or treatment works unless all of the iron and steel products used in the project are produced in the United States. (2) In this section, the term "iron and steel products" means the following products made primarily of iron and steel: lined or unlined pipes and fittings, manhole covers and other municipal castings, hydrants, tanks, flanges, pipe clamps and restraints, valves, structural steel, reinforced precast concrete, and construction materials. (b) Subsection (a) shall not apply in any case or category of cases in which the Administrator of the Environmental Protection Agency (in this section referred to as the "Administrator") find that— (1) applying subsection (a) would be inconsistent with the public interest; (2) iron and steel products are not produced in the United States in sufficient and reasonably available quantities and of a satisfactory quantity; or (3) inclusion of iron and steel products produced in the United States will increase the cost of the overall project by more than 25 percent. (c) If the Administrator receives a request for a waiver under this section, the Administrator shall make available to the public on an informal basis a copy of the request and information available to the Administrator concerning the request, and shall allow for informal public input on the request for at least 15 days prior to making a finding based on the request. The Administrator shall make the request and accompanying information available by electronic means, including on the official public Internet Web site of the Environmental Protection Agency. The final guidance and any published waivers are found at: http:/Iwater.epa.govigrants funding/aisrequirement.cfm. In particular the contractor should pay attention to the guidance for documentation of compliance. There is also a waiver for incidental items; in order to qualify for this waiver the total materials and costs for the project must be tracked and incidental items identified. SRF-28 May 2015 Sample "American Iron and Steel"Contract Language In order to fulfill the requirements, the assistance recipient must in good faith design the project and solicit bids for construction with U.S.-made iron and steel. The following information will be included in any contracts resulting from this request for bids: The Contractor acknowledges to and for the benefit of the City of ("Purchaser") and the State of Iowa (the "State")that it understands the goods and services under this Agreement are being funded with monies made available by the Clean Water State Revolving Fund and/or Drinking Water State Revolving Fund and such law contains provisions commonly known as "American Iron and Steel;" that requires all of the iron and steel products used in the project to be produced in the United States ("American Iron and Steel Requirement") including iron and steel products provided by the Contactor pursuant to this Agreement. The Contractor hereby represents and warrants to and for the benefit of the Purchaser and the State that (a)the Contractor has reviewed and understands the American Iron and Steel Requirement, (b) all of the iron and steel products used in the project will be and/or have been produced in the United States in a manner that complies with the American Iron and Steel Requirement, unless a waiver of the requirement is approved, and (c) the Contractor will provide any further verified information, certification or assurance of compliance with this paragraph, or information necessary to support a waiver of the American Iron and Steel Requirement, as may be requested by the Purchaser or the State. Notwithstanding any other provision of this Agreement, any failure to comply with this paragraph by the Contractor shall permit the Purchaser or State to recover as damages against the Contractor any loss, expense, or cost(including without limitation attorney's fees) incurred by the Purchaser or State resulting from any such failure (including without limitation any impairment or loss of funding, whether in whole or in part, from the State or any damages owed .., to the State by the Purchaser). While the Contractor has no direct contractual privity with the State, as a lender to the Purchaser for the funding of its project, the Purchaser and the Contractor agree that the State is a third-party beneficiary and neither this paragraph (nor any other provision of this Agreement necessary to give this paragraph force or effect) shall be amended or waived without the prior written consent of the State. Sample Certifications As indicated in the contract language, it will be the responsibility of the Contractor to obtain certifications that the products and materials used in the project are U.S.-made. EPA recommends the use of a step certification process for documenting compliance with AIS requirements, similar to one used by the Federal Highway Administration. Step certification creates a paper trail which documents the location of the manufacturing process involved with the production of steel and iron materials. Each handler (supplier, fabricator, manufacturer, — processor, coater, etc.) of the iron and steel products certifies that their step in the process was domestically performed. The following information is provided as a sample letter of step certification for AIS compliance. Documentation must be provided on company letterhead. In this example, there may be multiple letters from different manufacturers if one manufacturer did not perform all of the steps. SRF-29 May 2015 Date Company Name Company Address City, State Zip Subject: American Iron and Steel Step Certification for Project(XXXXXXXXXX) I, (company representative), certify that the (melting, bending, coating, galvanizing, cutting, etc.) process for(manufacturing or fabricating)the following products and/or materials shipped or provided for the subject project is in full compliance with the American Iron and Steel requirement as mandated in EPA's State Revolving Fund Programs. Item,Products and/or Materials: 1. Xxxx w 2. Xxxx 3. Xxxx Such process took place at the following location:If any of the above compliance statements change while providing material to this project we will immediately notify the prime contractor and the engineer. Signed by company representative Alternatively, the final manufacturer that delivers the iron or steel product to the worksite, vendor, or contractor, may provide a certification asserting that all manufacturing processes occurred in the U.S. and providing detailed information on the steps involved. The following is a template for this type of final certification. SRF-30 May 2015 4 SRF Template American Iron and Steel Certification Letter STATE — On Manufacturer's Letterhead IRON& rRoN&STEEL,INC. — STEEL 1959 Steel Drive INC. Ironville,OH 12345 MATERIAL CERTIFICATION April 30; 2015 _ RE: Job Name. Waterprojectville: Iowa—2015 State Revolving Fund Water Infrastructure Project SRF Project Number: CS1920999 01 --------------- References the SRF Project — I certif.,- that the processes for manufacturing or fabricating the following products and or materials provided for the subject project took place at the following Lr S. locations: Quantity Description Manufacturing Processes Location Where Processes Occurred . .._ — 3 count i AB123456 1"Gate Valve Melting.,poured machined Ironville. OH 60 count XY654321 Reinforced Concrete Melted rolled. fabricated Steel City,IA Manhole 60 count XZ123456 Manhole Cover Melted,cast,finished Stainless,MS 1200 linear feet A13654321 4'Ductile Iron Water Melted,rolled_ finished Pipet.• Pipe I further certify that , products and or materials are in full compliance with the American Iron and teel requirements as mandated in the U.S. Environmental Specifies the Protection Agen- s State Revolving Fund programs It'any of the above Manufacturing compliance st ements change while providing material to this project we will Processes and immediately notify the supplier, prime contractor, consulting engineer, or project the U.S. — owner, Locations Specifies the On behalf of IRON& STEEL, EN(' Where They— Products and Were page Soda Quantities Performed Signature of Jane Smith — Manufacturer's Product Quality Manager Representative ..._ SRF-31 May 2015 Covered and Non-Covered Items The EPA issued a waiver for de minimus incidental components of eligible water and wastewater infrastructure projects. Funds used for such de minimus incidental components — cumulatively may comprise no more than a total of 5% of the total cost of the materials used in and incorporated into a project. The in and incorporated intolincidental a prntal item may not exceed 1% of the total cost of the materials used De minimus incidental items include miscellaneous, generally low-cost components that are essential for, but incidental to, the construction and are incorporated into the physical structure of the project. For many of these incidental components, the country of manufacture and the availability of alternatives are not readily or reasonably identifiable prior to procurement in the normal course of business. For others, the country of manufacture may be known but the miscellaneous character in conjunction with the low cost, individually and (in total) as typically — procured in bulk, mark them as properly incidental. Examples of incidental components could include small washers, screws, fasteners (i.e., nuts and bolts), miscellaneous wire, corner bead, ancillary tube, etc. Examples of items that are clearly not incidental include significant process fittings (i.e., tees, elbows, flanges, and brackets), distribution system fittings and valves, force main valves, pipes, treatment and storage tanks, large structural supports, etc. Assistance recipients should in consultation with their contractors determine the items to be covered by this waiver, must retain relevant documentation (i.e. invoices) as to those items, and must summarize in rep thehs to tl e costate of Iowa the types and/or categories of items to which of incidental components for each type or category, and the this waiver is applied, total c calculations by which they determined the total cost of materials used in and incorporated into the project. The successful bidder will fill out the materials spreadsheet (shown below) and submit it to the assistance recipient to indicate covered and non-covered items proposed to be procured for the project. American Iron and Steel Materials Spreadsheet—to be Submitted by Successful Bidder r^ Iowa Department of Natural Resources-May 2014 Based on EPA Memorandum(4/15/2014j: De Minimus Waiver of Section 436 of P.L 113-76,Consolidated Appropriation Acts(CAA),2014 Cnoose ar Item.. Project: itined/unlined pipes or fittings Date: i. Bidder: 'Manhole covers Municipal castings sand restraints;valves;structural steel;hydrants, 'Covered Pr Pipes clamps or restraints .ipesorfittings;manhole covers;municipal castings;pipe clamp tanks;hang Valves .nstrudionmaterials. Structural steel `�- "Incidenta Hydrants ' low-cost items,often procured in bulk,such as washers,screws,fastene rs,small amounts of wire,etc. Tanks Bid Amount Bid Amount Documentation item is Incidental and Reinforced Description OtherClaimed under . Reinforced precast concrete ...ucts if Not Included in Covered Products incidentals Will be Obtained will M imus Waiver" iConstruction materials Covered Products V ,�, 1 s" '4e 11111111111111111111111111111 ��1111.111911.1111 3 Choose an tem, 3 .".Dose an,tem. 4 :.-nose an rten:: �M�Min U 5 ose an Re`:. " ®, ...., 6 sea ate.•.., 7 8 4 ®®� ®lIMINII SRF-32 May 2015 At the end of construction, the contractor will submit a final list showing covered and non- covered items. .>, American Iron and Steel Materials Spreadsheet with de Minimus Items Iowa Department of Natural Resources-May 2014 Based on EPA Memorandum(4/15/2614): De Minimus Waiver of Section 436 of P.L.113-76,Consolidated Appropriation Acts(CAA),2014 Project: Contractor: 1 I Submitted By: Date: Total Materials - Final De Minimus List Total Amount Covered I Percent(mustbe5%or less of Cost: Under de Minimus Waiver mate vials cost) 'Covered Products include:Unedorunlined iU p ptr ct on materials. manhole covers;municipal castings;pipe clamps and restraints;valves;structural steel;hydrants, tanks;flanges;Products include: Lint orunlie;copesorfittngs; n, "Incidental Berns are miscellaneous,generally ow-cost items,often procured in bulk,such as washers,screws,fasteners,small amounts of wire,etc. Covered Products` Description if Not Included Date Dollar Amount Dollar Amount Documentation Incidental" in Covered Products Purchased Covered Incidentals Received 1 ^:one a^far... Products 2 3 Choose an tern. L] U 4 Choose an item.. L] U 5 Choose an item. L] U 6 Choose an item. U U U These documents are available on-line at htto://www.iowasrf.com/about srf/use-of-american- iron-and-steel/. SRF-33 May 2015 FORM OF BID OR PROPOSAL FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF CONTRACT NO.880 CITY OF WATERLOO, IOWA Honorable Mayor and City Council Waterloo, Iowa Gentlemen: 1. The undersigned, being a Corporation existing under the laws of the State of Partnership consisting of the followin a s having familiarized (himself) (themselves) (itself) with the existing conditions on the project area affecting the cost of the work, and with all the contract documents listed in the Table of Contents and Addenda (if any), as prepared by the City Engineer of the City of Waterloo now on file in the office of the City Clerk, City Hall, Waterloo, Iowa, hereby proposes to furnish all supervision, technical personnel, labor, materials, machinery, tools, appurtenances, equipment, and services, including utility and transportation services required to construct and complete this FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF, City Contract No. 880„ all in accordance with the above-listed documents and for the unit prices for work in place for the following items and quantities: FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF CONTRACT NO. 880 Item Estimated Unit Bid Total Bid Description escription Unit Quantity Price Priect 1 Flow Equalization Facility Overflow Connection to Satellite WPCF LS 1.0 $ $ TOTAL BID 2. It is understood that the quantities set forth are approximate only and subject to variation and that the unit bid price for the work done shall govern in the actual payment to Contractor. 3. In submitting this bid, the bidder understands that the right is reserved by the City of Waterloo, Iowa, to reject any or all bids. If written notice of the acceptance of this bid is mailed, telegraphed, or delivered to the undersigned within thirty(30)days after the opening thereof, or at any time thereafter before this bid is withdrawn, the undersigned agrees to execute and deliver an agreement in the prescribed form and furnish the required bond and certificate of the insurance within ten (10) days after the agreement is presented to him for signature, and start work within ten (10) days after "Notice to Proceed" is issued. 4. Security in the sum of Dollars($ ) in the form of accordance with the INSTRUCTIONS TO BIDDERS. is submitted herewith in 5. Attached hereto is a Non-Collusion Affidavit of Prime Contractor. 6. Attached hereto is a Resident Bidder Certification ). (Mark one.) ), or Non-Resident Bidder Certification 7. The bidder is prepared to submit a financial and experience statement upon request. FORM OF BID FB-1 to 2 AECOM 60336756-2017 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF 8. The Prime Contractor and Subcontractor(s), which have performed an aggregate of $10,000.00 in work for the City in the current calendar year, are prepared to submit an MP or Update and an EOC,within ten (10)days of notification that the bid submitted is lowest and acceptable. 9. The bidder has received the following Addendum or Addenda: '- Addendum No. Date 10. The bidder shall list the MBEIWBE subcontractor(s), amount of subcontracts and bid items on the City of Waterloo Minority and/or Women Business Pre-bid Contact Information Form submitted with this Form of Bid or Proposal. The apparent low Bidder shall submit a list of all other Subcontractor(s) to be used on this Project to the City of Waterloo by 5:00 p.m. the business day following the day Bids on this Project are due along with the Non-Collusion Affidavits of All Subcontractor(s). The Contractor shall submit information on subcontractors on"SUBCONTRACTOR REQUEST AND APPROVAL" Form to be provided by City prior to approval of contract. The subcontractors listed on this proposal and/or submitted to the Contract Compliance Officer cannot be changed except for the following reasons: 1) The City of Waterloo does not approve the subcontractors. 2) The subcontractors submit in writing that they cannot fulfill their subcontracts. 11. The bidder has filled in all blanks on this proposal. Those blanks not applicable are marked "none" or"NA". 12. The bidder has attached all applicable forms. 13. The Owner reserves the right to select alternates, delete line items, and/or to reduce quantities prior to the award of a contract due to budgetary limitations. (Name of Bidder) (Date) BY: Title Official Address: (Including Zip Code): I.R.S. No. FB-2 to 2 Flow Equalization Facility FORM OF BID City Contract No.880 Overflow Connection to Satellite WPCF AECOM 60336756-2017 INFORMATION NEEDED FOR -- IOWA CONSTRUCTION SALES TAX EXEMPTION CERTIFICATE CONTRACTOR NAME: ADDRESS: (Check One) PRIME SUBCONTRACTOR FEDERAL ID#: PROJECT NAME: PROJECT CONTRACT NO.: - DESCRIPTION OF WORK: ❑ Brickwork ❑ Landscaping - ❑ Carpentry ❑ Painting ❑ Concrete ❑ Paving ❑ Drywall-Plaster-Insulation ❑ Plumbing ❑ Electrical ❑ Roofing-Siding-Sheet Metal ❑ Excavation/Grading ❑ Windows �' ❑ Flooring ❑ Wrecking-Demolition ❑ Heavy Construction ❑ Other (Please specify) ❑ Heating-Ventilating-Air Cond. ❑ SALES TAX STE-1 of 1 AECOM 60336756-2017 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF BID BOND KNOW ALL MEN BY THESE PRESENTS, that we, as Principal, and as Surety are held and firmly bound unto the CITY OF WATERLOO , Iowa, hereinafter called "OWNER." in the penal sum Dollars ($ ) lawful money of the United States, for the payment of which sum will and truly be made, we bind ourselves, our heirs, executors, administrators, and successors,jointly and severally, firmly by these presents. The condition of this obligation is such that whereas the Principal has submitted the accompanying bid dated the day of 20 , for NOW, THEREFORE, (a) If said Bid shall be rejected, or in the alternate, (b) If said Bid shall be accepted and the Principal shall execute and deliver a contract in the form specified and shall furnish a bond for his faithful performance of said contract, and for the payment of all persons performing labor or furnishing materials in connection therewith, and shall in all other respects perform the agreement created by the acceptance of said Bid, Then this obligation shall be void, otherwise the same shall remain in force and effect; it being expressly understood and agreed that the liability of the Surety for any and all claims hereunder shall, in no event, exceed the penal amount of this obligation as herein stated. By virtue of statutory authority, the full amount of this bid bond shall be forfeited to the Owner in liquidation of damages sustained in the event that the Principal fails to execute the contract and provide the bond as provided in the specifications or by law. The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its bond shall be in no way impaired or affected by any extension of the time within which the Owner may accept such Bid or execute such contract; and said Surety does hereby waive notice of any such extension. IN WITNESS WHEREOF, the Principal and the Surety, have hereunto set their hands and seals, and such of them as are corporations, have caused their corporate seals to be hereto affixed and these pres- ents to be signed by their proper officers this day of A.D. 20 (Seal) Principal By Title Witness (Seal) Surety Witness By Attorney-in-Fact BID BOND AECOM 60336756-2017 BB-1 of 1 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF NON-COLLUSION AFFIDAVIT OF PRIME BIDDER State of County of )§ being first duly sworn, deposes and says that: 1. He is (Owner, Partner, Officer, Representative, or Agent) , of , the Bidder that has submitted the attached Bid; 2. He is fully informed respecting the preparation and contents of the attached Bid and of all pertinent circumstances respecting such Bid; 3. Such Bid is genuine and is not a collusive or sham Bid; -' 4. Neither the said Bidder nor any of its officers, partners, owners, agents, representatives, employees, or parties in interest, including this affiant, has in any way colluded, conspired, connived or agreed, directly or indirectly, with any other Bidder, firm or person to submit a collusive or sham Bid in connection with the Contract for which the attached Bid has been submitted or to refrain from bidding in connection with such Contract, or has in any manner, directly or indirectly, sought by agreement or collusion or communication or conference with any other Bidder, firm or person to fix the price or prices in the attached Bid or of any other Bidder, or, to fix any overhead, profit or cost element of the bid price or the bid price of any other Bidder, or to secure through any collusion, conspiracy, connivance, or unlawful agreement any advantage against the City of Waterloo, Iowa, or any person interested in the Proposed Contract; and -- 5. The price or prices quoted in the attached Bid are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the Bidder or any of its agents, representatives, owners, employees, or parties in interest, including this affiant. (Signed) Title Subscribed and sworn to before me this day of , 20 Title My commission expires NON-COLLUSION AFFIDAVITS- NCA-1 of 2 AECOM 60336756-2017 flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF NON-COLLUSION AFFIDAVIT OF SUBCONTRACTOR State of )§ County of ) , being first duly sworn, deposes and says that: 1. He is (Owner, Partner, Officer, Representative, or Agent) ofhereinafter referred to as the"Subcontractor;" 2. He is fully informed respecting the preparation and contents of the subcontractor's proposal submitted by the subcontractor to contract pertaining to the Project in (City or County and State) 3. Such subcontractor's proposal is genuine and is not a collusive or sham proposal; 4. Neither the subcontractor nor any of its officers, partners, owners, agents, representatives, employees, or parties in interest, including this affiant, has in any way colluded, conspired, connived, or agreed, directly or indirectly, with any other bidder, firm or person to submit a collusive or sham proposal in connection with such contract or to refrain from submitting a proposal in connection with such contract, or has in any manner, directly or indirectly, sought by unlawful agreement or connivance with any other bidder, firm or person to fix the price or prices in said subcontractor's proposal, or to fix any overhead, profit or cost element of the price of prices in said subcontractor's proposal, or to secure through collusion, conspiracy, connivance or unlawful agreement any advantage against the City of Waterloo, Iowa, or any person interested in the proposed contract; and 5. The price or prices quoted in the subcontractor's proposal are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the bidder or any of its agents, representatives, owners, employees, or parties in interest, including this affiant. (Signed) Title Subscribed and sworn to before me this day of 20 . Title My commission expires Umr NCA-2 of 2 flow Equalization Facility NON-COLLUSION AFFIDAVITS City Contract No.880 Overflow Connection to Satellite WPCF AECOM 60336756-2017 EQUAL OPPORTUNITY CLAUSE (As provided in Executive Order No. 11246) All contractors, subcontractors, vendors and suppliers of goods and services doing and value of said business equals or exceeds ten thousand dollars ($10,000.00) annuallywith as follows: — 1. The contractors, subcontractor, vendor and supplier of goods and services will not discriminate against any employee or applicant for employment because of race, color, creed, sex, national origin, economic status, age, mental or physical handicap, political opinions or affiliations. The contractor, subcontractor, vendor and supplier will develop an Affirmative Action program to ensure that applicants are employed and that employees are treated during employment without regard to their race, creed, color, sex, national origin, religion, economic status, age, mental or physical disability, political opinions or affiliations. Such actions shall include but not be limited to the following: — a. Employment b. Upgrading c. Demotion or Transfer d. Recruitment and Advertising e. Layoff or Termination f. Rates of Pay or Other Forms of Compensation g. Selection for Training Including Apprenticeship 2. The contractor, subcontractor, vendor and supplier of goods and services will, in all solicitations or advertisements for employees, state that all qualified applicants will receive consideration for employment without regard to race, creed, color, sex, national origin, religion, economic status, age, mental or physical disabilities, political opinion or affiliations. 3. The contractor, subcontractor, vendor and supplier or his/her collective bargaining representative will send to each labor union or representative of workers which he/she has a collective bargaining agreement or other contract or understanding, a notice advising said labor union or workers' representative of the contractor's commitment under this section. 4. The contractor, subcontractor, vendor and supplier of goods and services will comply with all published rules, regulations, directives, and order of the City of Waterloo Affirmative Action Program Contract Compliance Provisions. 5. The contractor, subcontractor, vendor and supplier of goods and services will furnish and file — compliance reports within such time and upon such forms as provided by the Affirmative Action Officer. Said forms will elicit information as to the policies, procedures, patterns, and practices of each subcontractor as well as the contractor himself/herself and said contractor, subcontractor, vendor and supplier will permit access to his/her employment books, records and accounts to the City's Affirmative Action Officer, for the purpose of investigation to ascertain compliance with this contract and with rules and regulations of the City's Affirmative Action Program—Contract Compliance Provisions relative to Resolution No. 24664. 6. In the event of the contractor's non-compliance with the non-discrimination clauses of this contract or with any of such rules, regulations and orders, this contract may be canceled, terminated or suspended in whole or in part and the contractor may be declared ineligible for — further contracts in accordance with procedures authorized by the City Council. 7. The contractor, subcontractor, vendor and supplier of goods and services will include, or _ incorporate by reference, the provisions of the non-discrimination clause in every contract, EQUAL OPPORTUNITY CLAUSE — ualization Facility AECOM 60336756-2017 EOC-1 of 2 City Contract No.880 Overflow Con ec onto Satellite WPCF subcontract or purchase order unless exempted by the rules, regulations or orders of the City's Affirmative Action Program, and will provide ins every subcontract, ubcontraractor, or c, on purchase order that said provisions will be binding upon each contractor, r. 8. scr not be We, the undersigned, recognize that we arees for alemployment lywith oure company to non-discrimination ini employment. Any person whopp discriminated against because of race, creed, color, sex, national origin, economic status, age, mental or physical disabilities. (Signed) (Appropriate Official) (Title) (Date) ation Facility EOC-2 of 2 Flow EqualizOverflow Connection to Satellite WPCF EQUAL OPPORTUNITY CLAUSE City Contract No.880 AECOM 60336756-2017 TITLE VI CIVIL RIGHTS During the performance of this contract, the contractor (for itself), its assignees, and successors in interest(hereinafter referred to as the"contractor") agrees as follows: — 1. Compliance with Regulations: The contractor shall comply with the Regulations relative to non- discrimination in Federally assisted programs of the DOT Title 49, Code of Federal Regulations, Part 21, as they may be amended from time to time, (hereinafter referred to as the Regulations), which are herein incorporated by reference and made a part of this contract. 2. Nondiscrimination: The contractor, with regard to the work performed by it during the contract, shall not discriminate on the grounds of race, color, national origin, sex, age, or disability in the selection and retention of subcontractors, including equipment. The contractor shall not participate either directly or indirectly in the discrimination procurement of materials and leases of prohibited by section 21.5 of the Regulations, including employment practices when the contract covers a program set forth in Appendix B of the Regulations. 3. Solicitations for Subcontracts, Including Procurement of Materials and Equipment: In all solicitations either by competitive bidding or negotiation made by the contractor for work to be performed under a subcontract, including procurement of materials or leases of equipment, each potential subcontractor or supplier shall be notified by the contractor of the contractor's obligations under this contract and the Regulations relative to non-discrimination on the grounds of race, color, national origin, sex, age, or disability. 4. Information and Reports: The contractor shall provide all information and reports required by the Regulations or directives issued pursuant there to, and shall allow access to its books, records, accounts, other sources of information, and its facilities as may be determined by the Contracting — Authority, the Iowa DOT, or FHWA to be pertinent to ascertain compliance with such Regulations, orders and instructions. Where any information required of a contractor is in the exclusive possession of another who fails or refuses to furnish this information the contractor shall so certify to the Contracting Authority, the Iowa DOT, or the FHWA as appropriate, and shall set forth what efforts it has made to obtain the information. 5. Sanctions for Noncompliance: In the event of the contractor's noncompliance with the nondiscrimination provisions of this contract, the Contracting Authority, the Iowa DOT, or the FHWA shall impose such contract sanctions as they may determine to be appropriate, including, but not limited to: a. Withholding of payments to the contractor under the contract until the contractor complies, and/or b. Cancellation, termination, or suspension of the contract, in whole or in part. 6. Incorporation of Provisions: The contractor shall include the provisions of paragraphs (1) through (6) in every subcontract, including procurement of materials and leases of equipment, unless — exempt by the Regulations, or directives issued pursuant thereto. The contractor shall take such action with respect to any subcontract or procurement as the Contracting Authority, the Iowa DOT, or the FHWA may direct as a means of enforcing such provisions including sanctions for non-compliance: Provided, however, that, in the event of a contractor becomes involved in, or it threatened with, litigation with a subcontractor or supplier as a result of such direction, the — contractor may request the Contracting Authority or the Iowa DOT to enter into such litigation to protect the interests of the Contracting Authority or the Iowa DOT; and, in addition, the contractor may request the United States to enter into such litigation to protect the interest of the United States. TITLE VI CIVIL RIGHTS TITLEualization Facility 6 56-2017 RIGHTS TVI-1 of 1 City Contract No.880 Overflow Connection ryto Satellite WPCF RESIDENT BIDDER CERTIFICATION — CONTRACT NO: PROJECT NAME: DATE OF LETTING: To be a qualified resident bidder, the bidder shall be a person or entity authorized to transact business in this state and having a business for at least three years prior to the date of the first advertisement for the public improvement. If another state or foreign country has a more stringent definition of a resident bidder, the more stringent definition is applicable as to bidders from that state or foreign country. This qualification as resident bidder shall be maintained by the contractor and his subcontractors at the work site until this project is completed. I hereby certify that I am a resident bidder as defined above. COMPANY NAME CORPORATE OFFICER TITLE DATE RESIDENT BIDDER RB-1 of 3 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connectiont of Satellite WPCF NON-RESIDENT BIDDER CERTIFICATION CONTRACT NO.: PROJECT NAME: DATE OF LETTING: I hereby certify that I am an Iowa non-resident bidder. COMPANY NAME: CORPORATE OFFICER: TITLE: DATE: STATE/COUNTRY OF RESIDENCY: • Stated below are the preference(s)to resident bidders in the state/country of (Preference to bidders, labor force, or other preferential treatment to bidders or laborers, etc. RESIDENT BIDDER RB-2 of 3 Flow Equalization Facility "r AECOM 60336756-2017 City Contract No.880 Overflow Connectiont of Satellite WPCF RESIDENT/NON-RESIDENT BIDDER RESIDENT BIDDER: In accordance with Section 73A.21 of the Iowa Code, all non-federal-aid public improvement projects, which include road construction, shall be performed by a qualified resident bidder. The resident bidder has been further defined as follows: Resident Bidder: A person or entity authorized to transact business in this state and having a business for at least three years prior to the date of the first advertisement for the public improvement. If another state or foreign country has a more stringent definition of a resident bidder, the more stringent definition is applicable as to bidders from that state or foreign country. The contractor shall provide the City with a certification that he is a qualified resident bidder according to the above definition. The Certification shall be submitted with the contractor's bid. A copy of the form of"Resident Bidder Certification" is included in the Contract Documents. If it is determined that the contractor does not meet this qualification after he begins work, a shutdown notice shall be issued and the voiding of the contract shall begin unless the contractor becomes qualified. NON-RESIDENT BIDDER: The contractor shall provide the City with a certification that he is a non-resident bidder according to the above definition. The Certification shall be submitted with the contractor's bid. A copy of the form of"Non-Resident Bidder Certification" is included in the Contract Documents. DJG 01/02/12 IDD B RESIDENT ER AECOM 6IDD6-2017 RB-3 of 3 Flow Equalization Facility City Contract No.880 Overflow Connectiont of Satellite WPCF Revised February 2003 CONTRACTOR'S OR SUBCONTRACTOR'S AFFIRMATIVE ACTION PROGRAM Check box that applies to party completing program: ( ) General Contractor ( ) Subcontractor I. Section A to be completed by GENERAL CONTRACTORS only: A. Name of Company Address of Company Zip Telephone Number( Federal ID Number(if no Federal ID Number, Owner/President's Social Security Number) Name of Project Project Contract Number Estimated Construction Work Dates / Start Finish Section B to be completed by SUBCONTRACTORS only: B. Name of General or Prime Contractor Name of Subcontractor Subcontractor's Address Zip Subcontractor's Telephone Number( Subcontractor's Federal ID Number(if no Federal ID Number Owner/President's Social Security Number) Name of Equal Employment Officer C. Remainder of program to be completed by party completing program, either Prime or Subcontractor. — 1. The Owners and/or Principals of your company: - 1 - Ethnic Name Address Position Sex Origin 2. Other Areas of Interest: If your company has branches or subsidiaries, or if your company is a branch or subsidiary of a parent organization, give the following information: Type of Name Address Affiliation Degree II. EMPLOYER'S POLICY (Please read carefully.) A. We, the undersigned, recognize that we are morally and legally committed to nondiscrimination in employment. Any person who applies for employment with our company will not be discriminated against because of race, color, creed, sex, national origin, economic status, age, mental or physical handicap. B. The employment policies and practices of the undersigned are to recruit and hire employees without discrimination, and to treat them equally with respect to compensation and opportunities for advancement, including training, upgrading, promotion, and transfer. However, we realize the inequities associated with employment training, upgrading, contracting and subcontracting for minorities and women and we will direct our efforts to correcting any deficiencies to the maximum extent possible. The same will be required of our SUBCONTRACTORS and suppliers. C. We submit this program to assure compliance with Executive Order 11246, as amended, and other subsequent orders that may pertain to equal employment opportunity and merit employment policies, fully realizing that our qualification and/or merit system should be evaluated and revised, if necessary. D. We agree to put forth the maximum effort to achieve full employment and utilization of capabilities and productivity of all our citizens without regard to race, creed, color, sex, national origin, economic status, age, and mental or physical handicap. E. will give training (Name of Company) and employment opportunities to local residents of Waterloo, Iowa, to the greatest extent feasible. -2 - III. AFFIRMATIVE ACTION A. recognizes that the (Name of Company) effective application of a policy of merit employment involves more than just a policy statement, and (Name of Company) will, therefore, re-evaluate our Affirmative Action Program to ensure that equal employment opportunities are available on the basis of individual merit, and to actively encourage minorities, women and local residents to seek employment with our company on this basis. B. will undertake the (Name of Company) following six(6) steps to improve our Affirmative Action Program: 1. Minority Recruitment and Employment; 2. Local Recruitment and Employment; 3. Disabled Veteran and Vietnam Era Veteran Recruitment and Employment; 4. Handicapped Recruitment and Employment; 5. Female Recruitment and Employment; and 6. Training, Upgrading and Promotional Opportunities. C. will take (Name of Company) whatever steps are necessary to ensure that our total work force has adequate minority, female, and local representation. We will utilize the following methods in our recruitment attempts: 1. Local advertising media (newspapers, radio, TV); 2. Community organizations (churches, clubs, schools); 3. Public and private institutions in the area (UNI, Hawkeye Community College); 4. Job Service of Iowa; and 5. Other. D. will seek qualified minority, (Name of Company) female, and local group applicants for all job categories and will make asserted efforts to increase minority, female and group representation in occupations at the higher levels or skill and responsibility. E. All sources of employment used shall be aware that we are an Equal Employment Opportunity Employer. Labor organizations representing our employees will be notified of our Equal Employment Opportunity Policy and Affirmative Action Program. F. Training, upgrading, promotion and transfer activities at all levels will be monitored to ensure that full consideration has been given to qualified minority, female, and local group employees. G. will encourage other (Name of Company) companies with whom we are associated and/or do business, to do the same and we will assist them in their efforts. H. has taken the following (Name of Company) -3 - Affirmative Action to ensure that minority, female, local contractors and/or suppliers were provided opportunities to negotiate and/or bid on this project: (if none, write "NONE") 1. 2. As a result of the above efforts, we have involved minority, female, and local contractors and/or suppliers in the following areas of subcontracting: (if none, write"NONE") 1. 2. J. will require approved (Name of Company) Affirmative Action Programs from all nonexempt contractors who propose to work on this project and will take whatever steps are necessary to ensure that non-minority contractors have adequate representation of minority, female and local persons in their total work force. K. In further accordance with rules and guidelines issued pursuant to Executive Order -- 11246 as amended, we establish the goals for our company, based on parity percentages supplied by the City, and we realize these goals will be reviewed on an annual basis. L. will keep records of (Name of Company) specific actions relative to recruitment, employment, training, upgrading and promotion and will provide the City of Waterloo with any information relative to same, including activities of our SUBCONTRACTORS and suppliers as necessary or when requested. M. Parity figures for companies located in Waterloo are as follows: Minority Parity= .08 (8%) N. Affirmative Action (Name of Company) Employment Goals: The definition of Affirmative Action Goals is as follows: "Goals may not be rigid and inflexible quotas which must be met, but must be targets, reasonably attainable by means of applying every good faith effort to make all aspects of the entire Affirmative Action Program work." For the year 201_, please submit percentage targets for employing minorities and women. If you already have reached your target for hiring minorities and women, please submit that percentage. *Goals for Minorities: Goals for Women: *Your affirmative action goals should be between 1% and 10% or more for minorities and 1% and 5% or more for women. -4 - Please be advised that the goals or targets are purely your estimation of how many women and minorities your company can reasonably expect to hire in 201_. Note, that none of the goals are rigid or inflexible. They are targets that your company calculates as reasonably attainable. This will help the City in its monitoring procedures as required by City of Waterloo Resolution No. 1984-142(4). CONTRACTOR'S TOTAL WORK FORCE (WATERLOO) NAME AND ADDRESS JOB CATEGORY RACE SEX WAGE INDICATE: DISABLED VETERAN: DV VIETNAM ERA VETERAN: W HANDICAPPED: H - 5 - We hereby certify that we are in compliance with all City and Federal Affirmative Action Regulations and agree to accept all liability for failure to comply. Respectfully submitted, By: Company Executive Date By: Equal Employment Opportunity Officer Date City of Waterloo Affirmative Action Officer Approved Disapproved Reason: By: Date: -6 - _ DESCRIPTION OF JOB CATEGORIES 1. Officials/Manager: Occupations in which employees set broad policies, exercise overall responsibility for execution of all policies, or direct individual departments or special phases of the agency's operations or provide specialized consultation on a regional, district or area basis. Includes: department heads, bureau chiefs, division chiefs, directors, deputy directors, controllers, examiners, wardens, superintendents, unit supervisors, sheriffs, police and fire chiefs and inspectors and kindred workers. 2. Professionals: Occupations which require specialized and theoretical knowledge which is usually required through college training or thorough work experience and other training which provides comparable knowledge. Includes: personnel and labor relations workers, social workers, doctors, psychologists, registered nurses, economists, dietitians, lawyers, system analysts, accountants, engineers, employment and vocational rehabilitation counselors, teachers or instructors, police and fire captains and lieutenants and kindred workers. 3. Technicians: Occupations which require a combination of basic scientific or technical knowledge and manual skill which can be obtained through specialized post-secondary school education and through equivalent on-the-job training. Includes: computer programmers and operations, draftsmen, surveyors, licensed practical nurses, photographs, radio operators, technical illustrators, police and fire sergeants and kindred workers. 4. Office/Clerical: Workers are responsible for internal and external communication, recording and retrieval of data and/or information and other paper work required in an office. Includes: bookkeepers, messengers, office machine operators, clerk-typists, stenographers, court transcribers, hearing reporters, statistical clerks, dispatchers, license distributors, payroll clerks and kindred workers. 5. Skilled Craft Workers: Workers perform jobs which require special manual skill and a thorough and comprehensive knowledge of the processes involved in the work which is acquired through on-the-job training programs. Includes: Mechanics and repairman, electricians, heavy equipment operators, stationary engineers, skilled machine occupations, carpenters, compositors and typesetters and kindred workers. 6. Sales Workers: Occupations engaging wholly and primarily in direct selling. Includes: advertising agents and salesman, insurance agents and brokers, real estate agents and brokers, _ stock and bond salesmen, demonstrators, salesmen and sales clerks, grocery clerks and cashier checkers, and kindred workers. 7. Operatives (semi-skilled): Workers who operate machine or processing equipment or perform other factory-type duties of intermediate skill level which can be mastered in a few weeks and require only limited training. Includes: apprentices (auto mechanics), plumbers, building trades, metal working trades, bricklayers, carpenters, electricians, machinists, mechanics, printing trades, etc., operatives, attendants (auto service and parking), plasterers, chauffeurs, deliverymen and furnacemen, heaters (metal), laundry and dry cleaning operatives, milliners, mine operatives and laborers, motormen, oilers and greasers, (except auto painters), (except construction and maintenance), photographic process workers, stationary fireman, truck and tractor drivers, weavers, (textile), welders and flame cutters and kindred workers. 8. Laborers (unskilled): Workers in manual occupations which p generally require no special training. Perform elementary duties that may be learned in few days and require the application of little or no independent judgment. Includes: garage laborers, car washers and greasers, gardeners (except farm) and groundskeepers, longshoremen, and stevedores, lumbermen, raftsmen and woodchoppers, laborers performing lifing, digging, mixing, loading and pulling operations and kindred workers. -7 - 9. Apprentices: Persons employed in a program including work training and related instruction to learn a trade or craft which is traditionally an apprenticeship, regardless of whether the program is registered with a Federal or State agency. 10. Trainees (on-the-lob): Production. . . persons in formal training for craftsmen when not trained under apprentice programs--operative laborer, and service occupations. White Collar. . . persons engaged in formal training for clerical, managerial, professional, technical, sales, office and clerical occupations. -8 - ITEMS OF POTENTIAL MBE/WBE PARTICIPATION NOTICE TO PROSPECTIVE BIDDERS: The following are items from the FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF, City Contract No. 880, that have a potential for MBE/WBE Participation. This listing, however, is not intended to be all encompassing; to preclude MBE/WBE Contractors from bidding on any items of the Proposal as a Subcontractor or the entire Proposal as a Prime Contractor. Bid Estimated Unit Bid Total Bid Item Description Unit Quantity Price Price 1 — a MBE/WBE GOALS FOR THIS PROJECT IMPORTANT: Prime Contract Bidders should be aware that ten percent (10%) MBE goal and a two percent (2%) WBE goal is attached to this project. "Certified Return Receipt" letters are no longer needed with the bid showing proof of contacting MBE or WBE Subcontractors, but the Pre-Bid Contact Information Form must be filled out completely. City of Waterloo Contract Compliance Officer: Contract Compliance Officer Community Development Board Carnegie Annex, Suite 202 620 Mulberry Street Waterloo, IA 50703 Phone: (319)291-4429 RESIDENT BIDDER M-1 of 6 Flow Equalization Facility = AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SUBCONTRACTOR'S BID REQUEST FORM PRIME BIDDER'S LETTERHEAD Contract No.: Letting Date: I, (subcontractor's name), hereby attest that I have been solicited for a bid on (project name) in the area of (description of work and bid item no.). (Prime contractor) has informed me that if I am interested in bidding, a subcontracting bid proposal must be submitted to the company office by(date) and (time). Subcontractor's Company Name — Date Subcontractor's Signature Date Prime Bidder's Signature SUBCONTRACTOR BID REQUEST- M-2 of 6 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF LETTER TO BE USED WHEN SOLICITING FOR SUBCONTRACTOR QUOTES Subcontractor Company Name Address RE: Contract No.: Dear • (Prime Contractor's Company Name) is presently soliciting for the following work in connection with the above referenced project. (Insert bid Item Nos. and Description of Work) (Prime Contractor's Company Name) is an Equal Opportunity Employer, and all qualified bidders will not be discriminated against due to race, religion, color, sex, or origin. If interested in bidding your proposal must be turned in to this office by and Date (Time) Sincerely, (Prime Contractor's Representative) Form CCO-3 (11/28/2001) LETTER SOLICITING QUOTES M-3 of 6 AECOM 60336576-2017 CITY CONTRACT NO.880Flow Connection to Equalization Satellite Facility Overflow to Satellite WPCF LETTER OF INTENT TO BID (MBE/WBE LETTER) According to the Current MBE/WBE Contract Compliance Program - 2002, all MBE/WBE Contractors interested in submitting subcontractor quotes on construction projects with goals, MUST submit a LETTER OF INTENT TO BID to the City of Waterloo Contract Compliance Officer at least seven (7) days prior to bid opening. The LETTER OF INTENT TO BID must list the specific items which the MBE/WBE Contractor is interested in bidding. Letter should include the following: Name of Project: Your Company Name: Address: Phone: Date: List of Specific items to be bid: Item No. Description: Item No. Description: Item No. Description: Item No. Description: Item No. Description: (Subcontractor's Company Name and authorized signature) Return this LETTER OF INTENT TO BID to: Contract Compliance Officer Community Development Board 620 Mulberry St. Carnegie Annex, Suite 202 Waterloo, IA 50703 Phone: (319) 291-4429 Form CCO-5 (06-20-2002) LETTER OF INTENT M-4 of 6 Flow Equalization Facility AECOM 60336756-2017 CityContract No.880 Overflow Connection to Satellite WPCF Y o C O C ° a) a) W W = _c o73 ° O O co 'C E N O a) _a) a7 w.. Et a) 'U d L. o- E2 � ° o a CO Cr2 c co cp �o o.w aa) m o c - a,ul C V) °)c .L-' L Z a o o P co c c0 o c d ° a 0 L ° cn 0 W u) U U o 0 'ca Cn C.0 mN o C O m 0 :.-, - u ° Co O as c a w > mo a,, cnOm . o w UUa .o wo E.fl-O EE p v°i ° _. ° Z g o _ m c 0 LL C O a) U C u) u) O fY 0 O w- O (a .L.' T C o 0 p CO C N D O QQ a 'u 0 W N LL U 4 -0 -0 = co W E i cn a) ° O 0" > Z CO 0 C 0 i E O0. w mOWoU p O Ui N m o > o a) F- W a ) > .0 'D v ° E < m a) E C O c O a) m .aa 2 2 N Q aow - (/) > m om o al m aa) >, a O a) oa ° -9 Z O c p U 2.0 +-, _C W w O a )n a O - fn. 2 N Z Q pp U O a) O o .> "a) a) m i- O -o C 0 Cu O c a coco 0 O U U a) a) +' a 0 a)L Q a) 2 T - c > a L m U O > O a) 2 .L.' C a) . co U E C o o O .J O O o .L.., C m 0 O 0 - c Q CC a .E � Qa in.�o O Z aia c°i c _� o a) O u, Cu C w W I- N m � � a) c o U m m � v 0 Ow Cu L• u) C U f0 co =0 � O O C d Z m C °U w a) CO c cn m E E O � mm ID o a° as p o o ccn n as 'c wwCCI �oo y � m c w f6 o c a) .CD ( as �� o 0 ZW g � ui Ea .-,- O L ° Em a cn 1c3 ° aQ W Z .0 m N N O N N m d W 0 m cn . c U o m c) ln0 a) ° c w co al- � 3o � co co () H .S a) u) �a C F- m -2 -a c W a) ui u .Q w o W Q C .u) p cn E Oa a) Z m � m c •o m '= To E m coz ZE cl � w � �� � a) cn• w gw mi� L o,.� �� ° m a) @w Z ° ° m n) O U a) m Ua m "' (/) p O m O1:3 a p DLO �) cn F- O a) w F. m O o a u) W �a mO � � Qc°) m_iu) E Z E c � > Na� cLi T WZ 5 'cm CC .S -�'° a)) > E• co oO oocu a ac) aa) a ° t� �� • m � 2 ° p c E f -c 'E CO a) � 3 � > N En o ev U m a) O E m a) ° E w > ° m .� c a) Q�, c - asy Z �U o Cu m a) C o s ° o .o c = c mQ a3 C w T U O Z O Q C O a) W I-- Y o m U j m 4- -0 W N .� N w a) o 2 c u) m C Z ° i� c (>) H ° E < ai o m O �m � c � L E • ° � c O ' N ° •o Z oU O W •U a 2 W C - a) ) >,C O (0 0) in Q ;n W _a 0- Oa m a) m °' 0 a) a) a3 - u) , coa) m V m o ° m 06 cva 2 a�i 'LO � � � a' - E V) N o 3 o o N2 CI C U N L C O N C- o CL L O T u) a) U ° C CO E `mw - 0 -C C> m o -C '0 Ea) mO ° m W oa_ m 3 U) m � as a) o a N o ��_ m La .E o .g - a' a) ui c LL O i C_ C U u) O +L'.� -O N L ° a) °-C d a) @ a) ca W e ° a) 0 c°o o ° `° rn Q a) a) u) T v a) t. 'L' N C L `O (0 a) .- 0-0 C � UO a '� E -0a � � O m V) o O o O CL Ct N > m U O' c •� U a U > Z a).'L-' 7 O C0 =_ U O) 1 O 0 _ _: w_ _" m CC a) � a `('° E -Q E > co coi Eo 3 a) as vi — >_ Uo . U O a .= H . Q W�a E W c V a) 7 H o-0 L .,- a.) N O)p a) a) co • C a L u) Z ---- '- m a (Da) m O 2. > u) u, Q cn L O a) N •U QJ -° O c o c a) -O L. m 0 l a) >O a N a) , M .N u) C 0 C N a mo c c) = c U 3 a) CCa , o O c � 15 O C C O N M (0 a) m W a) 'Q C Q ° C LO o •N ca O L O N d a L N.'L--' Z O N O O L c w (00 C c Z -ci .@ (- N C o EC.'", '-' Q mi O_ ix LE C O Cu - > C w CO 0 U cis ° Q W F' L m C O N .Q M - 0 -O° N ,_ O c r p u) C O a a) 7 7 '.' (0 CO a T a N m U O °w E W m j W O - O - ° m ct .O O O >, a) O)t Q L Q O E a) 0 0 m 01) N ur N co co 0 o rn W E2 cu o O o .30 0 c c wZ om p C c U vi o c1 u°) < co c C � m � O EO o U N o oQ "_ w mOZ� paQ o mO U) a �M U C0 C wU � � ° o m `0 o ° co � ci 2Uai � cioai rn � ° U � a p m0, U (0 C CO• a cn T Q C .. C CLI)O a) a)oa o � U� E . c 0 o o t a) mm ° m o cLi.`° `° E u) U °°`° L of _ as QC6 "� U f-.c1. U V ma.Qa) O w(5 L N O a) O u) a) >' . L 3 W O O `) _° E O 0.- d Q O)a c- LL 'p CV L U ri 0 v o CC u-i Cl I- Q U) -0 0 0 n u CO MQ _ w� ti m 0 -U o O cca U Fr) a) A a Ca J C C Ca N N .O LL C Q O 0 N O= — O O co — C o r N CO Q CD CO R Q O o MI 0 co =o O_ to "' U O CD ++ W co E ° c 0 a) � a 3° — oa W o mom coo ° o Uo L c � o co Ecn co 1E co N+-• O C Qo @ L a) m S o 0 Cl) o 00 Ea . lit I > N ._ o m m o o v 5 a' I— d � a) o CO TO Q 0 - E 0 C � F— N O o .�ai > Lo m w W Z � Z as Qo a)aoio p0 d o — d O c � � c c — W > 0 V W n 0 TS 5 a) oCO N 'd +r +�.+ FW— Q N 0 O Y-c v Ce d 0 = o WE CZ Et Z Et Ce U co y Q ft o@ o .= oU W mz NLL oo a°iE Sow � m OI— o` Wz " � � o ooN °� -0 2Z CO — � `°• oc wc � moo COW N O 2o 0 0 LL o -0 . -9 co cu Via) Z C ++' z Y, p Q m s 0 0 o W v CO I— o ujoi ai oc 0-'it a) E 1— Z 0 >- mO a 2m �_ oco aS10 No Qc _ o--a �L > > o m� � _ "0 II mm 0)2 � �c 03 0 W0 LLW N +'0 CD _mm a cooEn — Zm � � E � n O C. Z om �ai � W 0) a >, • = CO a) T W � W 'o � o ooc , Q co J2 — ma a) a) 00 o a3 -Om mQoy o m , (jE cE a F— m L rn o ' ° co 3 o -0 _a. W O U W @ �F CO L -o re a) N co L CO ' C m 0 L C.) co U o ' � � -o o 0 W r o ° re o a L o � �, cL CO as o a _ z �l a N � m � E � + a) OE U oa) �`oav W co o C� m m 3 N cc .0 M C L O -0 O mC V a) y N z n O) O O N a) G _a r N r ~ O TS O N N r U W m Q) Q m0 >' m C cn =M CO m (n r_ C C .o Q m co co ,1k, o e�0 C uj O LO Z W C '- l a) > C 0 m i�x\ ° W v m m o a) . ��� �• � o U m � m OU � a mw3 a) E E O — G'qr !Ili c> r� - E >, CO D E = D Ocov m O mill w ��m` o z 3 U co >,0 >- E4- '- 3 �Q CERTIFIED MBE / WBE CONTRACTORS CITY OF WATERLOO, IOWA alg erloo \o CONTRACT COMPLIANCE OFFICE Community Development Board Carnegie Annex, Suite 202 620 Mulberry Street Waterloo,Iowa 50703 City WEB Site: ww�.ci.«aterloo.ia.us Contract Compliance WEB Site for listing updates: http://www.wplwloo.lib.ia.us/contractcompliance/ Contact: Rudy Jones, Community Development Director Email: rude.jonesnwaterloo-ia.org Phone: (319) 291-4429 Fax: (319) 291-4431 MBE/WBE Certified Contractors List Page 1 of 4 CERTIFIED MBE CONTRACTORS CARTER ELECTRIC 725 Adams Street Waterloo,IA 50703 Phone: (319)232-9808 Pager: (319)235-4021 Contact: Derrick Carter Specializing in: ELECTRICAL CONTRACTOR CULPEPPER ELECTRIC 1731 Cottage Grove Avenue Waterloo,IA 50707 Phone: (319)235-0885 Fax: (319)236-8177 Contact: Martin Culpepper Certified: City of Waterloo Certified MBE,Licensed Electrician Specializing in: ELECTRICAL CONTRACTOR DANIELS HOME IMPROVEMENT 339 Albany Street Waterloo,IA 50703 Phone: (319)961-1659 Contact: Sammy Daniels Specializing in: ALL TYPES OF CONCRETE FLATWORK, POURED WALLS ALL TYPES, FOOTINGS, LIGHT DEMOLITION D.C. CORPORATION 426 Beech Street Waterloo,IA 50703 Phone: (319)493-2542 FAX: (319)236-0515 Contact: Terry Phillips Certified: City of Waterloo Certified MBE,Iowa DOT,TSB Certified Specializing in: COMMERCIAL AND RESIDENTIAL DEMOLITION, CONCRETE PAVING, DRIVEWAYS, TRUCKING(ALL TYPES), GENERAL CONSTRUCTION L MBE/WBE Certified Contractors List Page 2 of 4 GREER'S WORKS 2003 Plainview Street Waterloo, IA 50703 Phone: (319)233-4701 Contact: Willie Greer Specializing in: DRIVEWAYS, SIDEWALKS, CARPENTRY, ROOFING, GENERAL CONSTRUCTION OLD GREER'S WORKS 2309 Springview Street Waterloo, IA 50707 Phone: (319)233-2150 Contact: David L. Greer, Sr. Specializing in: ROOFING&GENERAL CONSTRUCTION QUICK CONSTRUCTION 217 Bates Street Waterloo, IA 50703 Phone: (319)215-4166 Contact: Leroy Harrington Specializing in: ALL TYPES OF CONCRETE FLATWORK AND GENERAL CONSTRUCTION D & D CONSTRUCTION 1124 West Donald Street Waterloo,IA 50703 Phone: (319)961-4208 Contact: Darrell E. Caldwell, Sr. Specializing in: ROOFING AND GENERAL CONSTRUCTION E. CASTRO ROOFING 702 Riehl Street Waterloo, IA 50701 Phone: (319)215-5683 Contact: Emillio Castro Specializing in: ROOFING, SIDING, GENERAL CONSTRUCTION 1 MBE/WBE Certified Contractors List Page 3 of 4 CERTIFIED WBE CONTRACTORS �- ATLAS PAINTING, INC.* 911 Sycamore Street P.O. BOX 65 Waterloo,IA 50704 Phone: (319)232-9164 Specializing in: COMMERCIAL AND INDUSTRIAL PAINTING WATCO CONSTRUCTION, INC.* 2920 Texas Street Waterloo,IA 50702 Phone: (319)233-7481 Certified: City of Waterloo WBE Contact: Patricia J.Kimball Specializing in: STORM SEWER, INLETS, DRAIN TILE, WATER MAIN, SANITARY SEWER, INTAKE STRUCTURES PETERMAN & HAES CARPET ONE* 4003 University Waterloo,IA 50701 Phone: (319)233-6131 Fax: (319)233-6133 Certified: City of Waterloo WBE Email: JR11486@cfu.net Contact: Carol Reese Specializing in: FLOOR COVERING *DENOTES WOMEN BUSINESS ENTERPRISE MBE/WBE Certified Contractors List Page 4 of 4 GENERAL SPECIAL PROVISIONS 1. SCOPE OF WORK The work covered by this contract consists of furnishing all labor, equipment, and materials and performing all operations, in connection with the FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF, City Contract No. 880, in accordance with these specifications. The specifications are dated September 2017. They have the general title of FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF, City Contract No. 880. The drawings are numbered and separately entitled as follows: Drawing No. Title 1 -01-G-01 Title Sheet and Location Map 2 -01-G-02 Civil Legend and General Notes -- 3-02-C-1 Overall Site Plan 4-02-C-2 Piping Plan 5-02-C-3 Piping Plan 6 -02-C-4 Piping Plan 7-02-C-5 Piping Profiles 8- 02-CE-1 Electrical Site Plan 9- 110-PP-1 Detailed Information and Layout 10- 117-SME-1 Metering and Control Manhole Details 11 -99-C-1 Civil Details 12 -99-C-2 Civil/Process Details 13 -99-C-3 Civil/Process Details 14 -99-C-4 Civil/Process Details 15- 99-E-1 Electrical Details The standard specifications of the City of Waterloo are to be used along with the special provisions described herein and shall be considered as part of the contract documents. The 2017 Standard Specifications for the Iowa Statewide Urban Design and Specifications Program (as referenced) are to be used along with the special provisions and General Specifications for Construction described herein and shall be considered as part of the contract documents. 2. CONFLICTING SPECIFICATIONS -- All requirements of other specifications contained in the contract documents which conflict with the provisions of the special provisions will be considered void. 3. DUMPING AREAS Excess material resulting from construction operations shall be hauled to the County Landfill or other area secured by the contractor and approved by the City Engineer. Rubble, rubbish, trees, brush, and other unsuitable backfill material, as designated by the City Engineer, shall be hauled to the County Landfill. All Landfill charges are to be considered incidental to the contract and are the responsibility of the contractor. GENERAL SPECIAL PROVISIONS GSP-1 of 4 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 4. CONSTRUCTION DAMAGE The Contractor shall exercise care during construction operations to ensure the safety and protection to existing features located near or within the limits of construction. Damage caused by negligence or poor workmanship, as determined by the Engineer, shall be considered the Contractor's responsibility. 5. REMOVED MATERIALS All materials removed as part of this Contract shall remain the property of the City unless the City determines that the materials are not salvageable and the City does not want to retain ownership of the materials. Materials designated in the field by the Engineer as nonsalvageable shall be hauled and disposed of by the Contractor at no cost to the City. All other materials shall be transported to locations as directed by the Engineer. No separate measurement or payment will be made for hauling or disposing of removed materials and it shall be considered incidental to —" applicable items. 6. OVERHAUL Overhaul will not be paid for "surplus material" obtained from any of the items of construction under this contract. The cost of overhaul will be considered as incidental to the items to which it applies. — 7. MAILBOXES The Contractor shall notify the United States Postal Department of mailboxes, which interfere with any part of the work before removing them, and the Contractor will relocate them as required by the Postmaster. The removal and replacement of mailboxes will not be considered for direct payment but will be considered incidental to the item to which it applies. 8. PAY ITEMS All pay items are listed in the proposal and shall include the purchase of all materials, delivery of these materials, and furnishing all labor, plant, and miscellaneous work needed to make the item complete. All such cost shall be incidental to the proposed item to which it applies and shall not be considered for separate payment. 9. BREAKDOWN OF LUMP SUM CONTRACT PRICE ITEMS The Contractor shall, immediately upon execution and delivery of the contract, before the first estimate for payment is made, deliver to the City Engineer a detailed estimate giving a complete breakdown of the lump sum contract prices. The submitted breakdown shall be approved by the City Engineer prior to any payment of any lump sum price item. 10. PERMISSION TO HAUL OVER STREETS, RAILROADS,AND HIGHWAYS The Contractor will be required to secure, from the proper authorities, permission or permit which may be required to haul over streets, highways, railroads or private property, and any hauling — operations of the Contractor shall be subject to the requirements of such permits, permission, and to all applicable regulations, laws, and ordinances governing hauling and movement of equipment over streets, railroads, highways, and private property. Any costs or inconvenience caused by _ obtaining any necessary permits or permission shall be considered completely covered by the price bid for the items in the proposal. GENERAL SPECIAL PROVISIONS GSP-2 of 4 Flow Equalization Facility — AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 11. CONSTRUCTION SCHEDULING The City Engineer shall approve Contractor's work schedule prior to starting. All revisions shall also be approved. The City Engineer may change the schedule to accommodate changing construction conditions. The Contractor shall coordinate the work under this contract with contractors performing work under other contracts, which may be performed concurrently. The Contractor shall be responsible to notify the Police, Fire, Street, and Engineering Departments of the closing and opening of streets. The Contractor shall commence work within ten (10) days after receipt of the "Notice to Proceed" and diligently execute the work of the contract to completion. 12. PRE-CONSTRUCTION CONFERENCE Before any work is started, the Contractor shall arrange with the City Engineer to hold a pre- construction conference for the purpose of discussing the contract. 13. UNDERGROUND UTILITIES It is the responsibility of the Contractor to obtain the location of gas lines, water lines, electric, telephone, and cable television cables or wires from the various utility companies and the City electrician before starting any excavation. The Contractor shall be responsible for any damage to any underground utilities. The Contractor shall expose those utilities indicated on the plans so that elevations may be determined before beginning construction. This work shall be considered incidental to other items of work. If the Contractor believes that additional costs have been incurred due to a utility being improperly located, the resolution of the additional costs incurred shall be made between the contractor and the respective utility company. 14. TRAFFIC SIGNS AND STREET SIGNS The Contractor shall contact the City of Waterloo Traffic Operations Department to have any street sign that will be affected by construction removed and replaced when the work has been completed. 15. TRAFFIC CONTROL DURING CONSTRUCTION (INCIDENTAL) The Contractor shall provide, erect, and maintain, at all times during the progress and suspension of the work and until completion and final acceptance thereof, suitable and requisite barricades, signs, or other adequate protection, as required by Contract Documents or as may be ordered by the Engineer, to ensure the safety of the public as well as those engaged on the work. All barricading necessary for completion of this project shall be considered incidental to contract bid items. 16. GRADES, LINES, LEVELS,AND SURVEYS The Contractor shall verify all grades, lines, levels, and dimensions as shown on the drawings, and he shall report any errors or inconsistencies in the same to the City Engineer before commencing work. 17. SAFETY OF WORKERS AND PUBLIC GENERAL SPECIAL PROVISIONS GSP-3 of 4 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF The Contractor shall, at all times, take necessary precautions to protect the life and health of all persons employed on this project and the public. He shall provide necessary safety devices and safeguards in accordance with latest and best accident prevention practices. All such protection shall be furnished to employees without cost. No direct measurement of payment shall be made for this protection but shall be considered incidental to other items of work. The public shall be kept outside of any work area. 18. WORKING ON SATURDAYS, SUNDAYS AND LEGAL HOLIDAYS The Contractor shall notify the Engineer in writing forty-eight (48) hours in advance if work on Saturday is planned. By noon the Friday before the planned Saturday work, the Contractor shall confirm the Saturday work schedule with the project inspector. Work on Sunday requires prior approval of the Engineer in accordance with the Waterloo Standard Specifications. The Contractor shall not work the following days in 2013 due to City holidays: _ Veterans Day- Friday, November 10, 2017 Thanksgiving Day-Thursday, November 23 Day After Thanksgiving - Friday, November 24, 2017 Christmas Eve- Friday, December 22, 2017 Christmas Day- Monday, December 25, 2017 New Year's Day- Monday, January 1, 2018 Martin Luther King Day- Monday, January 15, 2018 Memorial Day- Monday, May 28, 2018 *** END OF SECTION ** * GENERAL SPECIAL PROVISIONS GSP-4 of 4 Flow Equalization Facility -- AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF DIVISION I SPECIAL PROVISIONS The Iowa Department of Transportation Standard Specifications for Highway and Bridge Construction, Series of 2015, plus the applicable General Supplemental Specifications and the 2017 Iowa Statewide Urban Specifications, also known as SUDAS, shall apply to construction work on this project. The standard specifications of the City of Waterloo are to be used along with the special provisions described herein and shall be considered as part of the contract documents. Any technicals not covered by SUDAS are listed in the Table of Contents and are made a part of the specification booklet on the following pages. ' END OF SPECIAL PROVISIONS " * " * SPECIAL PROVIDSIONS SP-1 of 1 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 11 00 SUMMARY OF WORK PART 1 GENERAL 1.01 SUMMARY A. This project consists of the installation of a new 24-inch gravity main that would connect the Flow Equalization Basin No. 2 with the Satellite Aeration Basin. A control valve and flow meter will be installed on this line. The project also includes a 12-inch force main that would connect the Satellite Aeration Basin with the Easton Aeration Basins. B. Measurement and Payment: 1. Work specified in this section is considered incidental,and payment shall be included as part of appropriate lump sum included in Bid Form. 1.02 DEFINITIONS A. Standard Specifications: Iowa Statewide Urban Design and Specifications(SUDAS)—2017 edition. 1.03 FORM OF SPECIFICATIONS A. These Specifications are written in imperative and abbreviated form. Imperative language of Specification sections is directed at CONTRACTOR, unless specifically noted otherwise. Incomplete sentences in Specifications shall be completed by inserting "shall," "CONTRACTOR shall,""shall be,"and similar mandatory phrases by inference in same manner as they are applied to notes on Drawings. Words"shall be"shall be supplied by inference where colon(:)is used within sentences or phrases. Except as worded to contrary, fulfill (perform) indicates requirements whether stated imperatively or otherwise. B. Items of Work are specified by section. Specifications or requirements of one or more sections may apply or be referenced in other sections. C. Provide Work described and comply with requirements stated in each Specification section and Drawings unless specifically assigned to other Contractors or OWNER. 1.04 PROJECT INFORMATION A. Owner's Representative: Steve Hoambrecker, Director of Waste Management, steven.hoambrecker(waterloo-ia.orq, 319-291-4553. B. Engineer: Harman Mallhi, Harman.mallhiaecom.com, 319-874-6581. ._ 1.05 CONTRACTS A. Perform Work under lump sum Contract(s)with OWNER. 1.06 MILESTONES (WORK SEQUENCE) A. Construct Work in stages to accommodate use of site during construction period; coordinate Construction Progress Schedule and operations with OWNER. B. Construct Work in stages to provide for public convenience. 1. Minimize periods for which Easton Avenue needs to be closed. 01 11 00-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 1.07 CONTRACTOR'S USE OF PREMISES A. OWNER will occupy Site and existing buildings during entire period of construction for conduct of '— normal operations. Cooperate with OWNER during construction operations to minimize conflict and facilitate OWNER'S operations. B. CONTRACTOR shall, at all times, conduct operations to ensure least inconvenience to OWNER, other CONTRACTORS, general public, and operation of existing wastewater facility. C. Coordinate use of premises under direction of OWNER. _ D. Assume full responsibility for protection and safekeeping of materials and equipment under this contract. E. Obtain and pay for use of additional storage or Work areas needed for operations at no additional cost to OWNER. 1.08 STAKING A. Proposed Work will be staked once, by ENGINEER, at no expense to CONTRACTOR. Should CONTRACTOR request restaking,this Work will be done as ENGINEER'S schedule permits and at expense of CONTRACTOR. Notify ENGINEER at least 3 days prior to start of open-cut work and when making periodic requests for line and grade stakes. 1. ENGINEER will provide one line of survey stakes for utility work and prepare separate cut sheets where multiple pipes are located in common trench. 2. CONTRACTOR shall maintain survey stakes. 1.10 OWNER FURNISHED PRODUCTS A. OWNER will provide 24-inch Tidal Flux flow meter to be installed in the metering manhole. Installation will be by the CONTRACTOR. _ 1.11 CONSTRUCTION SCHEDULE A. The Work under the proposed Contract shall commence within not later than 10 days after the date -- set forth in the Notice to Proceed and shall be substantially completed by April 30,2018,and finally completed by May 31, 2018. PART 2 PRODUCTS "— (Not Used) PART 3 EXECUTION (Not Used) -- *"* END OF SECTION * ** 01 11 00-2 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 29 73 SCHEDULE OF VALUES PART 1 GENERAL 1.01 SUMMARY ... A. Submit Schedule of Values allocated to various portions of Work as required by General Conditions. B. Upon request of ENGINEER, support values with data substantiating their correctness. 1.02 FORM AND CONTENT OF SCHEDULE OF VALUES A. Type schedule on 8-1/2 in. x 11 in.white paper; CONTRACTOR'S standard forms and automated printout will be considered for approval by ENGINEER upon CONTRACTOR'S request. Identify schedule with the following: 1. Project title and location. 2. ENGINEER and ENGINEER'S project number. 3. Name and address of CONTRACTOR. 4. Contract designation. 5. Date of submission. B. Identify installed value of component parts of Work in sufficient detail to serve as basis for computing values for progress payments during construction. C. Use general table of contents of this Project Manual to establish format for listing component items in schedule. 1. Identify each line item with number and title of respective Specification division and section. 2. If Project consists of multiple structures, break down schedule by structure D. Provide separate listing for General Requirements (Division 1) items, such as bonds, insurance premiums, mobilization,field supervision and layout,construction facilities and temporary controls, contingency allowance, construction schedule, O&M data, record drawings, and submittals. "— E. For each Specification division, list subvalues of major materials, equipment or operations under division. F. For various portions of work: 1. Each item shall include direct proportional amount of CONTRACTOR'S overhead and profit. 2. For items on which progress payments will be requested for stored materials, break down value into the following: a. Cost of materials, delivered and unloaded, with taxes paid. b. Total installed value, including CONTRACTOR'S overhead and profit. G. Sum of values listed in schedule shall equal total Contract sum. 01 29 73-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 33 10 SUBMITTALS PART 1 GENERAL 1.01 SUMMARY A. Section specifies procedural requirements for Work-related (non-administrative) submittals, including Shop Drawings, substitutions, product data, samples, test data, operations and maintenance data, and other miscellaneous Work-related submittals. -- 1. Submittals for certification of equipment installation, instructional, and post-startup services are specified in Section 01 60 00. 2. Submittals for record drawings are specified in Section 01 78 39. B. Administrative Submittals: Procedures concerning items such as listing of manufacturers, Suppliers, Subcontractors, Construction Progress Schedule, schedule of Shop Drawing submissions, bonds, payment applications, insurance certificates, and schedule of values are specified elsewhere. C. Work-Related Submittals: 1. Substitutes and "Or Equal" Items: a. Includes material or equipment which CONTRACTOR requests ENGINEER to accept, after Effective Date of the Agreement. Whenever an item of material or equipment is specified or described in the Contract Documents by using the name of a proprietary item or the name of a particular Supplier, the specification or description is intended to establish the type,function,appearance,and quality required. Unless the specification or description contains or is followed by words reading that no like,equivalent,or"or equal" item or no substitution is permitted, other items of material, or equipment, or material or equipment of other Suppliers, may be submitted to ENGINEER for review under the circumstances described below. 2. Shop Drawings: a. Includes technical data and drawings specially prepared for this Project, including fabrication and installation drawings, diagrams, data sheets, schedules, templates, patterns, reports, instructions, design mix formulas, measurements, and similar information not in standard printed form. b. Standard catalog type information prepared without specific reference to Project is not considered as Shop Drawing. 3. Product Data: a. Includes standard catalog type printed information on manufactured materials, equipment and systems that has not been specially prepared for this Project, including manufacturer's product specifications, catalog cuts, standard wiring diagrams, printed performance curves, mill reports, and standard color charts. 01 33 10-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 4. Samples: a. Includes fabricated and manufactured physical examples of materials, products, and units of work, including complete units,partial cuts of manufactured or fabricated work, — swatches showing color, texture and pattern, and units of work to be used for independent inspection and testing. b. Mock-ups are special forms of samples too large or otherwise inconvenient for handling in manner specified for transmittal of sample submittals. 5. Test Results: a. Includes source and field quality inspection and test reports,actual performance curves, and certifications of results prepared specifically for equipment, material, and systems provided for this Project. b. Standard catalog charts or standard test results are considered Product Data. 6. Operations and Maintenance Data: a. Includes information and directions for operating and maintaining equipment provided and installed for this Project. May be standard for equipment or prepared specifically for this Project. 7. Miscellaneous Submittals: a. Work-related submittals that do not fit in previous categories, including schedules, photographs, guarantees, warranties, certifications, maintenance agreements, — workmanship bonds,survey data and reports,physical work records,copies of industry standards, field measurement data, extra materials, keys, and similar information, devices, and materials applicable to Work. 1.02 SUBMITTAL PROCEDURES A. Scheduling: 1. CONTRACTOR is not required to submit preliminary or final schedule of Submittals. B. Coordination: -- 1. Coordinate preparation and processing of submittals with performance of Work. Coordinate each submittal with other submittals and related activities, such as substitution requests, testing, purchasing, fabrication, delivery and similar activities requiring sequential activity. 2. Coordinate submission of different units of interrelated Work so one submittal will not be delayed by ENGINEER'S need to review related submittal. ENGINEER may withhold action on submittal requiring coordination with other submittals until related submittals are provided. 3. Prepare and transmit each submittal sufficiently in advance of scheduled performance of related Work and other applicable activities. 4. Before submitting each Shop Drawing or Sample, CONTRACTOR shall have: a. reviewed and coordinated each Shop Drawing or Sample with other Shop Drawings and Samples and with the requirements of the Work and the Contract Documents; b. determined and verified all field measurements, quantities, dimensions, specified performance and design criteria, installation requirements, materials, catalog numbers, and similar information with respect thereto; c. determined and verified the suitability of all materials offered with respect to the indicated application,fabrication, shipping, handling,storage,assembly,and installation pertaining to the performance of the Work; and 01 33 10-2 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF d. determined and verified all information relative to CONTRACTOR'S responsibilities for —' means, methods, techniques, sequences, and procedures of construction, and safety precautions and programs incident thereto. C. Submittal Preparation: 1. Stamp and sign each submittal certifying to review of submittal, verification of material, and equipment, field measurement, field construction criteria, and coordination of information within submittal with Contract Documents. 2. Transmittal Form: Identify following: a. Date of submittal and dates of previous submittals. b. Project title and number. c. Submittal number. d. Contract identification. e. Names of: 1) CONTRACTOR. 2) Supplier. 3) Manufacturer. f. If submittal is for substitute item of material or equipment, identify as "substitute" on transmittal and include "Contractor's Application for Consideration of Substitute" with -- submittal. g. Identification of equipment and material with equipment identification numbers, motor numbers, and Specification section number. h. Variations from Contract Documents. D. Resubmittal Preparation: 1. Comply with requirements described in Submittal Preparation above, and in addition: a. Identify on transmittal form submittal is resubmission. b. Make corrections or changes in submittals required by ENGINEER'S notations on returned submittal. c. Respond to ENGINEER'S notations. 1) On transmittal or separate page attached to CONTRACTOR'S resubmission transmittal, answer or acknowledge in writing notations or questions indicated by ENGINEER on ENGINEER'S transmittal form returning reviewed submission to CONTRACTOR. 2) Identify each response by question or notation number established by ENGINEER. 3) If CONTRACTOR does not respond to each notation or question, resubmission will be returned without action by ENGINEER until CONTRACTOR provides written response to ENGINEER'S notations or questions. d. CONTRACTOR-initiated revisions or variations. 1) On transmittal form, identify variations or revisions from previously reviewed submittal, other than those called for by ENGINEER. 2) ENGINEER'S responsibility for variations or revisions is established in the Actions on Submittals paragraph of this section. 1.03 SPECIFIC SUBMITTAL REQUIREMENTS A. General: 01 33 10-3 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 1. Specific submittal requirements for individual units of Work are specified in applicable Specification section. Except as otherwise indicated in Specification sections, comply with requirements specified below for each indicated type of submittal. 2. If ENGINEER has responded to Written Clarification/Interpretation/Request submitted by ' CONTRACTOR, CONTRACTOR shall include ENGINEER'S response with applicable submittal. B. Requests for Substitute Items: 1. Collect data for items to be submitted for review as substitute items into one submittal for each item of material or equipment. — 2. Include completed "Contractor's Application for Consideration of Substitution" form as required by Supplementary Conditions. 3. Submit with other scheduled submittals for material or equipment allowing time for ENGINEER to evaluate additional information required to be submitted. 4. If CONTRACTOR requests to substitute for material or equipment specified,but not identified in Specification as requiring submittals, CONTRACTOR shall indicate substitution submittal in Submittal Schedule. _ 5. CONTRACTOR shall submit sufficient information as provided below to allow ENGINEER to determine if the item of material or equipment proposed is essentially equivalent to that named and an acceptable substitute therefore. Requests for review of proposed substitute items of material or equipment will not be accepted by ENGINEER from anyone other than _ CONTRACTOR. 6. CONTRACTOR shall make written application to ENGINEER for review of a proposed substitute item of material or equipment that CONTRACTOR seeks to furnish or use. The application: — a. shall certify that the proposed substitute item will: 1) perform adequately the functions and achieve the results called for by the general design, 2) be similar in substance to that specified, and 3) be suited to the same use as that specified; b will state: 1) the extent, if any, to which the use of the proposed substitute item will prejudice --- CONTRACTOR'S achievement of Substantial Completion on time, 2) whether use of the proposed substitute item in the Work will require a change in any of the Contract Documents (or in the provisions of any other direct contract with OWNER for other work on the Project) to adapt the design to the proposed substitute item, and 3) whether incorporation or use of the proposed substitute item, in connection with the Work, is subject to payment of any license fee or royalty; c will identify: 1) all variations of the proposed substitute item from that specified, and — 2) available engineering, sales, maintenance, repair, and replacement services; and d. shall contain an itemized estimate of all costs or credits that will result directly or indirectly from use of such substitute item, including costs of redesign and claims of "— other contractors affected by any resulting change. C. Shop Drawings: 1. Submit newly prepared information,with graphic information at accurate scale and name of preparer indicated (firm name). Show dimensions and note which are based on field 01 33 10-4 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF measurement, identify materials and equipment included in Work, and revisions on resubmittals. Indicate compliance with standards and notation of coordination requirements with other Work. Encircle, bubble or otherwise indicate selections of products or materials and/or variations from Contract Documents or previous submittals. Highlighting may be used in addition to circling or bubbling of appropriate materials or variations from Contract Documents or previous submittals to direct the attention of the reviewer, but may not be utilized exclusively due to the difficulty in continuity of selections through copying and/or scanning of the submittal. Other acceptable means of selection of materials, products or variations from Contract Documents or previous submittals include striking out selections not included as part of the submittal, providing an arrow pointing directly to the selection or other means that remain after copying and/or scanning. 2. Provide 8 in. x 3 in. blank space for CONTRACTOR and ENGINEER stamps. D. Product Data: 1. Preparation: a. Collect required data into single submittal for each unit of Work or system. Where product data includes information on several similar materials or equipment, some of which are not required for use on Project or not included in submittal, mark copies to show which items are not applicable to Project. b. Where product data must be specially prepared for equipment, materials or systems, because standard printed data is not suitable for use,submit data as Shop Drawing and not as product data. 2. Submittals: a. Submit 6 copies. b. Submittal is final when ENGINEER returns submittal marked"No Exception Taken,"or "Make Corrections Noted." 3. Distribution: a. Maintain one set of product data (for each submittal) at Project site, available for reference by ENGINEER and others. E. Samples: —' 1. Preparation: a. Provide samples physically identical with proposed materials or equipment to be incorporated into Work. Where variations in color, pattern or texture are inherent in material or product represented by sample, submit multiple units (not less than 3) showing approximate limits of variations. b. Provide full set of option samples where selection by ENGINEER is required. c. Include information with each sample to show generic description, source or product name and manufacturer, limitations, and compliance with standards. d. Submit samples for ENGINEER'S visual review of general generic kind, color, pattern, texture, and for final check of coordination of these characteristics with other related elements of Work. e. Mock-ups and similar samples specified in Specification sections are recognized as special type of samples. Comply with samples' submittal requirements to greatest extent possible. 2. Submittals: a. At CONTRACTOR'S option, and depending upon nature of anticipated response from ENGINEER, initial submittal of samples may be preliminary or final submittal. 01 33 10-5 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF b. Preliminary submittal, of single set of samples, required where Specification's indicate ENGINEER'S selection of color, pattern, texture or similar characteristics from manufacturer's range of standard choices is necessary. Preliminary submittals will be reviewed and returned with ENGINEER'S "Action" noted. c. Final Submittals: Submit 3 sets of samples in final submittal, 1 set will be returned. 3. Distribution: a. Maintain returned set of samples at Project site, in suitable condition and available for quality control comparisons throughout course of performing Work. F. Test Results: 1. Preparation: a. Identify each test by Specification section and type of test. 2. Submittals: a. Submit 3 copies. b. Submittal is to confirm that results of tests verify materials, products and systems comply with Contract Documents and are not for approval. 3. Distribution: a. Unless otherwise required in Specifications, test results shall be submitted to ENGINEER'S field office or, if ENGINEER has no field office, to ENGINEER'S office. G. Miscellaneous: 1. Guarantees, Warranties, Maintenance Agreements and Workmanship Bonds: a. Refer to Specification sections for requirements. Submittal is considered final when submittal returned by ENGINEER,marked"No Exceptions Taken"or"Make Corrections Noted." b. In addition to copies desired for CONTRACTOR'S use, furnish 2 executed copies. Provide 2 additional copies where required for maintenance data. 2. Certifications: a. Refer to Specification sections for requirement on submittal of certifications. Submit 6 copies. Certifications are submitted for review of conformance with specified requirements and information. 3. Closeout Submittals: a. Refer to Specification sections and Section 01 78 39 for requirements on submittal of closeout information, materials, tools, and similar items. -- 1) Materials and Tools: Spare parts, extra and overrun stock, maintenance tools and devices, keys, and similar physical units to be submitted. 2) Operating and maintenance data. H. Operating and Maintenance (O&M) Data: 1. Organize operations and maintenance information into suitable sets of manageable size,and bind into individual binders properly identified and indexed (thumb-tabbed). Include emergency instructions, safety precautions, spare parts listing, copies of warranties,wiring 01 33 10-6 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF diagrams, recommended "turn-around" cycles, inspection procedures, Shop Drawings, Product Data, and similar applicable information. a. Manufacturer's printed instructions regarding safety precautions for both(a)protection of personnel operating equipment and systems, and (b) prevention of damage to equipment and systems. b. Shop Drawings and other submittals included in O&M data shall be corrected to include, in same format and style as original submittal, review comments. c. Data may be submitted on CD Rom if approved by ENGINEER. 2. Binders: Commercial quality D-Ring binder with durable and cleanable plastic covers. Paperboard and laminated paperboard covers are not acceptable. a. Do not fill binders to more than 75% of capacity. b. When multiple binders are used for an item of equipment,organize contents into related groupings. Each binder cover shall bear identification of specific contents. 3. Cover Label: Label each binder cover and spine with typed or printed title "OPERATION AND MAINTENANCE INSTRUCTIONS" and following: a. Project title. b. Name(s) of applicable building(s) or structure(s) as shown on Drawings in which equipment located. c. Name of equipment as set forth in Contract Documents. d. Specification section number for equipment as set forth in Contract Documents. 4. Submit after equipment requiring O&M data has been returned "No Exceptions Taken" or "Make Corrections Noted." 5. Submit 6 copies of each manual. General Distribution: 1. Unless required elsewhere, provide distribution of submittals to Subcontractors, suppliers, governing authorities, and others as necessary for proper performance of Work. 2. Provide copies of submittals bearing ENGINEER'S action stamp to: a. Job site file. b. Record documents file. 1.04 ACTION ON SUBMITTALS A. ENGINEER'S Action: 1. General: a. Except for submittals for record and similar purposes, where action and return on submittals is required or requested, ENGINEER will review each submittal, mark with appropriate action, and return. Where submittal must be held for coordination, ENGINEER will so advise CONTRACTOR without delay. b. ENGINEER will stamp each submittal with uniform, self-explanatory action stamp, appropriately marked with submittal action. c. ENGINEER will provide timely review of Shop Drawings and Samples in accordance with the Schedule of Submittals acceptable to ENGINEER. ENGINEER'S review and approval will be only to determine if the items covered by the submittals will, after installation or incorporation in the Work,conform to the information given in the Contract Documents and be compatible with the design concept of the completed Project as a functioning whole as indicated by the Contract Documents. 01 33 10-7 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF d. ENGINEER'S review and approval will not extend to means, methods, techniques, sequences, or procedures of construction (except where a particular means, method, technique, sequence, or procedure of construction is specifically and expressly called for by the Contract Documents) or to safety precautions or programs incident thereto. The review and approval of a separate item as such will not indicate approval of the assembly in which the item functions. e. ENGINEER'S review and approval shall not relieve CONTRACTOR from responsibility for any variation from the requirements of the Contract Documents unless CONTRACTOR has complied with the requirements of request for substitution items and ENGINEER has given written approval of each such variation by specific written notation thereof incorporated in or accompanying the Shop Drawing or Sample. — ENGINEER'S review and approval shall not relieve CONTRACTOR from responsibility for complying with the requirements of submittal procedure coordination. 2. Notification of Insufficient Information: a. If information submitted is not sufficient to complete review of submittal,ENGINEER will send transmittal to CONTRACTOR notifying CONTRACTOR that additional information is required. b. Submittal will be placed in an "On Hold" status and not returned until CONTRACTOR provides additional information. 3. Unsolicited Submittals: ENGINEER will return unsolicited submittals to CONTRACTOR without reviewing. 4. If in ENGINEER'S sole discretion an item of material or equipment proposed by CONTRACTOR is functionally equal to that named and sufficiently similar so that no change in related Work will be required, it may be considered by ENGINEER as an"or equal"item, in which case review and approval of the proposed item may, in ENGINEER'S sole discretion, be accomplished without compliance with some or all of the requirements for approval of proposed substitute items. A proposed item of material or equipment will be considered functionally equal to an item so named if: a. in the exercise of reasonable judgment ENGINEER determines that: 1) it is at least equal in materials of construction, quality, durability, appearance, strength, and design characteristics; 2) it will reliably perform at least equally well the function and achieve the results — imposed by the design concept of the completed Project as a functioning whole;and 3) it has a proven record of performance and availability of responsive service. b. Contractor certifies that, if approved and incorporated into the Work: 1) there will be no increase in cost to the OWNER or increase in Contract Times; and 2) it will conform substantially to the detailed requirements of the item named in the Contract Documents. B. Action Stamp: 1. Marking: No Exceptions Taken. a. Final Unrestricted Release: When submittals are marked as "No Exceptions Taken," Work covered by submittal may proceed,provided it complies with Contract Documents. — Acceptance of Work depends on that compliance. 2. Marking: Make Corrections Noted. — a. Final-But-Restricted Release: When submittals are marked as "Make Corrections Noted"Work covered by submittal may proceed provided it complies with ENGINEER'S 01 33 10-8 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF notations or corrections on submittal and with Contract Documents. Acceptance of Work depends on that compliance. Resubmittal not required. 3. Marking: Rejected; See Remarks. a. Submittal Not Accepted: When submittals are marked as"Rejected;See Remarks,"do not proceed with Work covered by submittal. Work covered by submittal does not comply with Contract Documents. b. Prepare new submittal for different material or equipment supplier or different product line or material of same supplier complying with Contract Documents 4. Marking: Revise and Resubmit. a. Returned for Resubmittal: When submittals are marked as"Revise and Resubmit,"do not proceed with Work covered by submittal. Do not permit Work covered by submittals to be used at Project site or elsewhere where Work is in progress. b. Revise submittal or prepare new submittal in accordance with ENGINEER'S notations in accordance with resubmittal requirements of this section. Resubmit without delay. Repeat, if required, to obtain different action marking. PART 2 PRODUCTS (Not Used) PART 3 EXECUTION (Not Used) * ** END OF SECTION " ** 01 33 10-9 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 43 00 TESTING LABORATORY SERVICES PART 1 GENERAL 1.01 PERFORMANCE REQUIREMENTS A. Employ and pay for services of testing laboratory approved by OWNER to perform specified services and testing as described in Specifications. 1. Employment of laboratory shall, in no way, relieve CONTRACTOR'S obligations to perform Work of Contract. B. Related Requirements in Other Parts of Contract Documents: 1. Inspections and testing required by laws, ordinances, rules, regulations, orders or approvals of public authorities, Conditions of Contract. 1.02 QUALIFICATION OF LABORATORY A. Meet basic requirements of ASTM E329. B. Authorized to operate in state in which Project is located. C. Testing Equipment: 1. Calibrated at reasonable intervals by devices of accuracy traceable to either: a. National Bureau of Standards. b. Accepted values of natural physical constants. 1.03 LABORATORY DUTIES A. Cooperate with ENGINEER and CONTRACTOR; provide qualified personnel to perform Work after due Notice to Proceed. B. Perform specified inspections, secure samples, and test materials. 1. Comply with specified standards. 2. Ascertain compliance of materials with Contract Documents. C. Promptly notify ENGINEER and CONTRACTOR of observed irregularities or deficiencies of Work, equipment or material. D. Promptly submit written report of each test and inspection; one copy each to ENGINEER, OWNER, material supplier and CONTRACTOR, and one copy to record document file. Each report shall include following: 1. Date issued. 2. Project title and number. 3. Testing laboratory name, address and telephone number. 4. Name and signature of laboratory inspector. 5. Date and time of sampling or inspection. 6. Record of temperature and weather conditions if test performed in field. 7. Date of test. 01 43 00-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 8. Identification of product and Specification section. 9. Location of sample or test in Project. 10. Type of inspection or test. 11. Results of tests and compliance with Contract Documents. 12. Interpretation of test results, when requested by ENGINEER. E. Perform additional tests as required by ENGINEER or CONTRACTOR. 1.04 LIMITATIONS OF AUTHORITY OF TESTING LABORATORY A. Laboratory is not authorized to: — 1. Release, revoke, alter or enlarge on requirements of Contract Documents. 2. Approve or accept any portion of Work. 3. Perform duties of CONTRACTOR. 1.05 CONTRACTOR'S RESPONSIBILITIES A. Cooperate with laboratory personnel and provide access to Work. B. Provide to laboratory preliminary design mix proposed to be used for concrete and other material mixes which require control by testing laboratory. — C. Furnish copies of product test reports. D. Furnish incidental labor and facilities. 1. Provide access to Work to be tested. 2. Obtain and handle samples at Project site or at source of product to be tested. 3. Facilitate inspections and tests. 4. Store and cure test samples. E. Notify laboratory and ENGINEER sufficiently in advance of operations to allow for laboratory — assignment of personnel and scheduling of tests. 1. When tests or inspections cannot be performed after such notice, reimburse OWNER for laboratory personnel and travel expenses incurred due to CONTRACTOR'S negligence. F. Make arrangements with laboratory and pay for additional samples and tests required for CONTRACTOR'S convenience. _ G. Employ and pay for services of testing laboratory to perform additional inspections, sampling and testing required when initial tests indicate Work does not comply with Contract Documents. PART 2 PRODUCTS (Not Used) PART 3 EXECUTION (Not Used) ""* END OF SECTION ** * 01 43 00-2 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 43 OOA TESTING PART 1 GENERAL 1.01 SUMMARY A. Measurement and Payment: 1. Testing and furnishing of samples required to be provided by CONTRACTOR will not be paid for separately but shall be considered incidental to unit price of item to which it applies unless called for specifically to be paid separately in the Bid Items. B. CONTRACTOR shall employ services of independent testing laboratory approved by OWNER to perform testing as described in the SUDAS specifications. C. CONTRACTOR shall cooperate with ENGINEER to facilitate execution of assurance testing deemed necessary by ENGINEER. 1.02 SYSTEM DESCRIPTION A. Production Testing: 1. Materials produced off-site and incorporated into Work shall comply with the Contract Documents. -' a. Provide certifications of compliance. 2. On-site testing to confirm that material or equipment comply with Contract Document shall be provided by CONTRACTOR. a. On-site testing to confirm that methods used by CONTRACTOR result in conformance with Contract Documents shall be provided by CONTRACTOR. ENGINEER will not perform production testing (with the exception of nuclear density and moisture meter testing for embankment placement), but CONTRACTOR shall inform ENGINEER of production testing schedule so ENGINEER, at ENGINEER'S option, may observe testing. b. CONTRACTOR is responsible that materials and completed construction comply with Contract Documents. B. Assurance Testing: 1. Testing performed on-site by ENGINEER or an independent testing laboratory to determine if CONTRACTOR'S work or materials comply with Contract Documents. 2. Materials used for assurance testing shall be furnished by CONTRACTOR. CONTRACTOR shall provide labor and equipment needed to provide access to areas for assurance testing. This includes, but is not limited to, excavation of backfill to various depths for testing. 3. Density of subgrades, trench backfill and crushed stone bases/surfaces. a. CONTRACTOR shall employ an independent testing laboratory to gather, test and report on representative earth samples and to provide results of Standard Proctor Density test in accordance with Iowa DOT Materials Laboratory Test Method 103. Samples tested shall be representative of earth materials used for backfilling structures and trenches. b. CONTRACTOR shall employ an independent testing laboratory to gather representative crushed stone base/surface materials and provide the results of Standard Proctor Density test in accordance with Iowa DOT Materials Laboratory Test Method 103. 01 43 00A-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF C. Results of assurance testing or production testing provided by CONTRACTOR shall, in no way, relieve CONTRACTOR of obligations to comply with Contract Documents. PART 2 MATERIALS (Not Used) PART 3 EXECUTION (Not Used) *** END OF SECTION * ** Immo Imoor sop 01 43 OOA-2 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 50 10 TEMPORARY CONSTRUCTION FACILITIES AND UTILITIES PART 1 GENERAL 1.01 QUALITY ASSURANCE A. Items provided under this section shall be listed or labeled by UL or other Nationally Recognized Testing Laboratory(NRTL). 1. Term "RTL" shall be as defined in OSHA Regulation 1910.7. 2. Terms"listed"and"labeled"shall be as defined in National Electrical Code(NEC),Article 100. B. Regulatory Requirements: 1. National Electrical Code (NEC): Components and installation shall comply with National Fire Protection Association (NFPA) 70. C. Comply with federal, state, and local codes and regulations,and with utility company requirements. PART 2 PRODUCTS 2.01 TEMPORARY ELECTRICITY AND LIGHTING A. General: 1. Temporary lighting shall be sufficient to enable CONTRACTOR and Subcontractors to complete Work and enable ENGINEER to observe Work as it is being performed. Illumination shall meet or exceed state code requirements. B. Responsibilities: 1. Provide, maintain, and remove temporary electric service facilities. 2. Facilities exposed to weather shall be weatherproof type and electrical equipment enclosure locked to prevent access by unauthorized personnel. 3. Pay for installation of temporary services, including poles,transformer charges and metering. '- 4. Arrange with local electric utility for temporary electric service subject to their requirements and approval. 5. Register temporary meter in CONTRACTOR'S name. 6. Provide and maintain lamps, wiring, switches, sockets, and similar equipment required for temporary lighting and small power tools. 7. Pay for electrical energy consumed for construction purposes including operation of ventilating equipment for heating of buildings, and for testing and operating of equipment after permanent wiring has been installed, until final acceptance by ENGINEER or until occupancy by OWNER. 8. Provide and pay for service to temporary offices. 2.02 TEMPORARY TELEPHONE SERVICE A. Arrange with local telephone company to provide telephone service throughout duration of Work. B. Locate telephone in Project construction office for local calls. 2.03 WATER FOR CONSTRUCTION 01 50 10-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF A. OWNER will provide on-site source for temporary connection to water. Provide temporary piping required to bring water to point of use and remove piping when no longer needed. 1. Install metering device acceptable to OWNER and pay for water use at current rate. 2.04 WATER FOR TESTING A. CONTRACTOR shall provide water necessary for testing prior to acceptance of Work, unless specifically stated otherwise in Specifications for equipment, system or facility. 2.05 SANITARY FACILITIES A. Do not use existing sanitary facilities. B. Provide temporary sanitary toilet facilities conforming to state and local health and sanitation regulations, in sufficient number for use of ENGINEER'S, CONTRACTOR'S and Subcontractor's employees. C. Maintain in sanitary condition and provide supply of toilet paper. 2.06 TEMPORARY FIRE PROTECTION A. Provide and maintain in working order, minimum of one fire extinguisher at each work location,and such other fire protective equipment and devices as would be reasonably effective in extinguishing fires during early stages by personnel at Project site. 2.07 TEMPORARY SITE AND OTHER ROADS A. Construct and maintain temporary site roadways in snow free,ice free,drivable condition necessary to carry out construction operations. B. Maintain OWNER'S existing on-site roads and public roads used during construction free from accumulations of dirt, mud and construction debris resulting from construction operations. Roads shall be considered "maintained"when material has been removed by sweeper. 2.08 SECURITY A. Security will not be provided by OWNER. B. CONTRACTOR shall be responsible for loss or injury to persons or property where Work is involved,and shall provide security and take precautionary measures to protect CONTRACTOR'S and OWNER'S interests. 2.09 TEMPORARY PARKING A. Designated areas of existing parking facilities may be used for parking of construction personnel's vehicles and of CONTRACTOR'S light-vehicles. B. Do not allow heavy vehicles or construction equipment in parking area. C. Make arrangements with OWNER. 2.10 FIELD OFFICES AND BUILDINGS A. If required by CONTRACTOR,erect where designated by OWNER,and maintain in good condition, temporary field office, tool, and storage building(s) or trailer(s)for CONTRACTOR'S use. 01 50 10-2 Flow Equalization Facility --- 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 1. Tool storage building(s) or trailer(s) shall be of ample size to provide space for tools and equipment. 2. Building(s)or trailer(s)shall be neat and well constructed,surfaced with plywood,drop siding, masonite, or other similar material, well painted and void of advertisements. PART 3 EXECUTION 3.01 GENERAL A. Comply with applicable requirements specified. B. Maintain and operate systems to ensure continuous service. C. Modify and extend systems as Work progress requires. 3.02 REMOVAL AND RESTORATION A. Completely remove temporary materials,equipment,signs and structures when no longer required. B. In unfinished areas,clean and repair damage caused by temporary installations or use of temporary facilities, restore drainage, and evenly grade, seed or plant as necessary to provide appearance equal to or better than original. C. In finished areas, restore existing or permanent facilities used for temporary services to specified or original condition. 3.03 DAMAGE TO EXISTING PROPERTY A. CONTRACTOR is responsible for replacing or repairing damage to existing buildings, structures, sidewalks, roads, parking lot surfacing, and other existing assets. B. CONTRACTOR shall have option of having OWNER contract for such Work and have cost deducted from Contract price. ' '* END OF SECTION * ** 01 50 10-3 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 57 00 TEMPORARY CONTROLS PART 1 GENERAL 1.01 SUMMARY A. CONTRACTOR, in executing Work, shall maintain Work areas on- and off-site free from environmental pollution that would be in violation of federal, state or local regulations. B. Payment: 1. Consider Work specified in this section incidental and include payment as part of appropriate lump sum specified in Bid Form. 1.02 PROTECTION OF STORM SEWERS A. Prevent construction material, pavement, concrete, earth or other debris from entering existing storm sewer or sewer structure. 1.03 PROTECTION OF WATERWAYS A. Observe rules and regulations of State of Iowa and agencies of U.S. government prohibiting pollution of lakes, streams, rivers or wetlands by dumping of refuse, rubbish, dredge material, discharge of wastewater, or debris. 1. Permits obtained by OWNER are contained in Project Forms. 2. Other permits shall be obtained by CONTRACTOR at CONTRACTOR'S cost. B. Provide holding ponds or approved method which will divert flows, including storm flows and flows created by construction activity, to prevent excessive silting of waterways or flooding damage to property. -- C. Comply with Section 9040 of the SUDAS Specifications. D. CONTRACTOR shall comply with Iowa Department of Natural Resources National Pollution Discharge Elimination System, (NPDES)Storm Water Permit for construction site activities. As a minimum, CONTRACTOR is required to prepare, submit, and comply with following. 1. Notice of Intent (NOI). 2. Storm Water Pollution Plan. 1.04 DISPOSAL OF EXCESS EXCAVATED AND OTHER WASTE MATERIALS A. Excess excavated material not required or not suitable for backfill and other waste material shall be disposed of in accordance with local regulatory requirements. B. Provide watertight conveyance for liquid,semi-liquid or saturated solids which tend to bleed during transport. Liquid loss from transported materials is not permitted, whether being delivered to construction site or hauled away for disposal. Fluid materials hauled for disposal must be specifically acceptable at selected disposal site. 1.05 PROTECTION OF AIR QUALITY A. Minimize air pollution by requiring use of properly operating combustion emission control devices on construction vehicles and equipment and encourage shutdown of motorized equipment not in use. 01 57 00-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF B. Do not burn trash on construction site. C. If temporary heating devices are necessary for protection of Work,they shall not cause air pollution. 1.06 THAWING OF FROZEN GROUND A. Obtain permit from appropriate local authority before building fire to thaw frozen ground, and comply with conditions of permit. B. Use fuel which does not create air pollution or inconvenience public. C. ENGINEER reserves right to prohibit fires for thawing whenever deemed undesirable. 1.07 USE OF CHEMICALS A. Chemicals used during project construction or furnished for project operation,whether herbicide, pesticide, disinfectant,polymer, reactant or of other classification,shall be approved by U.S. EPA or U.S. Department of Agriculture or any other applicable regulatory agency. B. Use and disposal of chemicals and residues shall comply with manufacturer's instructions. 1.08 NOISE CONTROL A. Conduct operations to cause least annoyance to residents in vicinity of Work, and comply with applicable local ordinances. B. Equip compressors, hoists, and other apparatus with mechanical devices necessary to minimize noise and dust. Equip compressors with silencers on intake lines. C. Equip gasoline or oil-operated equipment with silencers or mufflers on intake and exhaust lines. D. Line storage bins and hoppers with material that will deaden sounds. E. Conduct operation of dumping rock and of carrying rock away in trucks so as to cause minimum of noise and dust. F. Route vehicles carrying rock, concrete or other material over such streets as will cause least annoyance to public and do not operate on public streets between hours of 6:00 p.m. and 7:00 a.m., or on Saturdays, Sundays or legal holidays unless approved by OWNER. 1.09 DUST CONTROL A. Due to close geographic location of Project to other off-site facilities and residential homes, take special care in providing and maintaining temporary site roadways, OWNER'S existing roads, and _ public roads used during construction operations in clean, dust free condition. B. Comply with local environmental regulations for dust control. If CONTRACTOR'S dust control measures are considered inadequate by ENGINEER, ENGINEER may require CONTRACTOR to _ take additional dust control measures. 1.10 FUELS AND LUBRICANTS A. Comply with local,state and federal regulations concerning transportation and storage of fuels and lubricants. B. Fuel storage area and fuel equipment shall be approved by OWNER prior to installation. Submit containment provisions to OWNER for approval. 01 57 00-2 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF C. Report spills or leaks from fueling equipment or construction equipment to OWNER and cleanup as required. D. OWNER may require CONTRACTOR to remove damaged or leaking equipment from Project site. 1.11 PILE AND SHEATHING DRIVING NOISE A. If piles are required, use only pile driver hammers with mufflers capable of significantly reducing noise and use barriers or shielding techniques, as necessary, to comply with applicable federal, state, and local ordinances. — PART 2 PRODUCTS (Not Used) PART 3 EXECUTION (Not Used) *** END OF SECTION * *" 01 57 00-3 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 60 10 MATERIAL AND EQUIPMENT PART 1 GENERAL 1.01 SUBSTITUTIONS AND "OR EQUAL" ITEMS A. General: 1. When equipment or material is specified by naming one (1) or more equipment manufacturers or material suppliers and followed by words "no substitution permitted" or similar wording, CONTRACTOR shall provide one of named manufacturers or suppliers. B. Substitutions: 1. For material or equipment specified by naming one or more equipment manufacturers or material suppliers and not followed by words"or equal,"CONTRACTOR shall submit request for substitution in accordance with Section 01 33 10 for equipment or manufacturer not specifically named. 2. CONTRACTOR'S requests for changes in equipment and materials from those required by Contract Documents are considered "requests for substitutions" and subject to CONTRACTOR'S representations and review provisions of Contract Documents when one or more of following conditions are satisfied. a. Where required equipment or material cannot be provided within Contract Time,but not as result of CONTRACTOR'S failure to pursue Work promptly or coordinate various activities properly. b. Where packaging of several items of equipment from single source will provide maintenance and coordination advantages to OWNER. c. When CONTRACTOR proposes to provide substitute equipment or material to provide OWNER with cost savings. C. "Or Equal": For material or equipment specified by naming one or more equipment manufacturer followed by the words"or equal",CONTRACTOR shall submit in accordance with Section 01340 for equipment or manufacturer not specifically named. ENGINEER will review submittal in accordance with Section 01340. D. Conditions which are not substitutions: 1. Requirements for substitutions do not apply to CONTRACTOR options on materials and equipment provided for in Specifications. 2. Revisions to Contract Documents, where requested by OWNER or ENGINEER, are "changes" not"substitutions." 3. CONTRACTOR'S determination of and compliance with governing regulations and orders issued by governing authorities do not constitute substitutions or basis for Change Orders, except as provided for in Contract Documents. 1.02 REUSE OF EXISTING MATERIAL A. Except as specifically indicated or specified, do not use materials and equipment removed from existing structure(s) in new Work. B. For material and equipment specifically indicated or specified to be reused in Work: 1. Use special care in removal, handling,storage,and reinstallation to ensure proper function in completed Work. 01 60 10-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 2. Arrange and pay for transportation, storage, and handling of products which require off-site storage, restoration or renovation. 3. Off-site storage areas and buildings shall conform to requirements of this section. 1.03 MANUFACTURER'S INSTRUCTIONS A. Installation of equipment and materials shall comply with manufacturer's instructions. Obtain and distribute printed copies of such instructions to parties involved in installation, including two (2) copies to ENGINEER. 1. Maintain one set of complete instructions at Site during installation and until completion of _ Work. B. Handle,store, install,connect, clean,condition,and adjust materials and equipment in accordance with manufacturer's written instructions and in conformance with Specifications. 1. If Site conditions or specified requirements conflict with manufacturer's instructions,consult ENGINEER for further instructions. Do not proceed with Work without written instructions. 1.04 TRANSPORTATION AND HANDLING A. Arrange deliveries of materials and equipment in accordance with construction Progress Schedule; coordinate to avoid conflict with Work and conditions at site. 1. Deliver materials and equipment in undamaged condition, in manufacturer's original containers or packaging, with identifying labels intact and legible. 2. Protect bright machined surfaces,such as shafts and valve faces,with heavy coat of grease prior to shipment. 3. Upon delivery, inspect shipments to ensure compliance with Contract Documents and approved submittals,and materials and equipment have been protected and are undamaged. B. Provide equipment and personnel to handle materials and equipment by methods recommended by manufacturer to prevent soiling or damage to materials or equipment, or their packaging. 1.05 STORAGE, PROTECTION AND MAINTENANCE A. OWNER assumes no responsibility for damage or loss due to storage of materials and equipment. B. Interior Storage: 1. Store with seals and labels intact and legible. 2. Store materials and equipment subject to damage by elements in weathertight enclosures. 3. Maintain temperature and humidity within ranges required by manufacturer's instructions. C. Exterior Storage: 1. Store fabricated materials and equipment above ground, on blocking or skids, to prevent soiling or staining. Cover materials and equipment subject to deterioration with impervious _ sheet coverings. Provide ventilation to avoid condensation. 2. Store loose granular materials in well-drained area on solid surfaces to prevent mixing with foreign matter. 3. Store materials such as pipe, reinforcing steel, structural steel, and equipment on pallets or racks, off ground. D. Inspection and Maintenance: _ 1. Arrange storage to provide easy access for inspection, maintenance, and inventory. 01 60 10-2 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 2. Make periodic inspections of stored materials and equipment to ensure materials and equipment maintained under specified conditions are free from damage or deterioration,and coverings are in-place and in condition to provide required protection. 3. Perform maintenance on stored material and equipment in accordance with manufacturer's — written instructions and in presence of OWNER or ENGINEER. a. Notify ENGINEER 24 hrs before performance of maintenance. b. Submit report of completed maintenance and condition of coverings to ENGINEER with each Application for Payment. c. Failure to perform maintenance,to notify ENGINEER of intent to perform maintenance or to submit maintenance report may result in rejection of material or equipment. E. Assume responsibility for protection of completed construction and repair and restore damage to completed Work equal to original condition. — F. Wheeling of loads over finished floors,with or without plank protection, is not permitted in anything except rubber-tired wheelbarrows, buggies, trucks or dollies. This applies to finished floors and exposed concrete floors, as well as those covered with composition tile or other applied surfacing. G. Where structural concrete is also finished surface, avoid marking or damaging surface. 1.06 SPECIAL TOOLS, SPARE PARTS AND LUBRICATING EQUIPMENT — A. Furnish, in accordance with manufacturer's recommendations, special tools required for checking, testing, parts replacement, and maintenance. Special tools are those specially designed or adapted for use on parts of equipment, and not customarily and routinely carried by maintenance mechanics. 1. Tools and lubricating equipment shall be of quality compatible to equipment manufacturer has furnished. B. Deliver to OWNER before operating personnel have been instructed in operation, repair and maintenance of equipment and unit is placed in operation. C. Mark spare parts and special tools to identify associated equipment by name, equipment,and part number. Package parts for protection against damage during shipping,handling and storage. Ship spare parts and special tools in boxes marked to indicate contents. 1.07 LUBRICATION A. Where lubrication is required for proper operation of equipment, incorporate necessary and proper provisions in equipment in accordance with manufacturer's requirements. Where possible, lubrication shall be automated and positive. B. Where oil is used, reservoir shall be of sufficient capacity to supply unit for 24-hr period. PART 2 PRODUCTS 2.01 MATERIALS AND EQUIPMENT A. Material and Equipment Incorporated into Work: 1. Conform to applicable specifications and standards. 2. Comply with size, make, type, and quality specified or as approved by Submittal. — B. Manufactured and Fabricated Materials and Equipment: 01 60 10-3 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 1. Design,fabricate,and assemble in accordance with engineering and shop practices standard with industry. 2. Manufacture like parts of duplicate units to standard sizes and gauges, to be interchangeable. 3. Two or more items of same kind shall be identical, by same manufacturer. 4. Material and equipment shall be suitable for service conditions. 5. Equipment capabilities,sizes, and dimensions shown or specified shall be adhered to,unless variations are specifically approved, in writing. 6. Equipment shall be adapted to best economy in power consumption and maintenance. Parts and components shall be proportioned for stresses occurring during continuous or intermittent operation, and for additional stresses occurring during fabrication or installation. _ 7. Design so working parts are readily accessible for inspection and repair, easily duplicated, and replaced. C. Do not use material or equipment for purpose other than for which it is designed or specified. PART 3 EXECUTION 3.01 FIELD QUALITY CONTROL; INSTALLATION, INSTRUCTIONAL, AND POST STARTUP SERVICES A. General: 1. Provide on-site services of Supplier's representatives for equipment provided by CONTRACTOR during construction, installation, equipment startup, and training of OWNER'S personnel for equipment or plant operation as specifically required in Specification section for equipment or system. 2. Include and pay costs for Supplier's services. 3. Work day is defined as 8-hr period during OWNER'S or CONTRACTOR'S typical calendar '- day. Work day for purposes of this section does not include travel to or from Site. 4. Specifications include minimum mandays to provide basis for bidding. If additional time is required to perform services, CONTRACTOR shall include that time in Contract Price. B. Installation Services: 1. Where installation services are called for in Specifications, provide competent and experienced technical representatives of manufacturers of material or equipment and systems to resolve assembly or installation procedures attributable to, or associated with, equipment furnished. 2. After equipment is installed, representatives shall perform initial equipment and system adjustment and calibration to conform to Specifications and manufacturer's requirements and instructions. 3. Provide"Certificate of Installation Services"stating proper adjustments have been made to equipment or system and equipment or system is ready for startup and system demonstration. Use form in Project Forms and furnish two (2) copies to ENGINEER. C. Instructional Services: 1. Do not start Instructional Services until Installation Services have been completed. 2. Where Instructional Services are called for in Specifications, provide competent and experienced technical representative of Supplier to provide detailed instructions to OWNER'S personnel for operation of equipment. Training services shall include operation and maintenance of instrumentation and equipment in classroom and on-site. Training shall include electrical, mechanical, and safety aspects of equipment. 3. Submit documentation identifying name of specific representative,factory authorization,and background of named individual(s)to conduct training. Submit information 30 days before scheduled training period for review and approval by ENGINEER. 01 60 10-4 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 4. Coordinate training periods with ENGINEER and OWNER and Supplier's representatives. a. No training shall be conducted unless instructor has been approved by ENGINEER. b. Notify ENGINEER at least 48 hrs before training sessions are to begin so ENGINEER can make arrangements with OWNER'S operating personnel. c. Reschedule canceled training sessions 48 hrs in advance. d. Failure of Supplier's or manufacturer's representative to appear for scheduled training, failure to notify ENGINEER 24 hrs in advance of need to cancel scheduled training or failure to arrive within 30 min of start of scheduled training shall result in reimbursement to OWNER for time lost by OWNER'S personnel in waiting for arrival of manufacturer's representative. Except in case of failure to arrive on time, time will not exceed 1 hr for each employee scheduled to receive training. Failure to arrive on time will be reimbursed by actual time late, up to 1 hr, after 1 hr training will be rescheduled. e. Failure of Supplier's or manufacturer's representative to appear for scheduled training, failure to notify ENGINEER 24 hrs in advance of need to cancel scheduled training or _ failure to arrive within 30 min of start of scheduled training shall result in reimbursement to OWNER for expenses and time incurred by ENGINEER in traveling and time spent on-site. Minimum time billed shall be 8 hrs. 5. Similar types of equipment differing in model,size or manufacturer shall require equal service time as stated in specific Specification section. 6. O&M data shall constitute basis of instruction. a. Review data contents with personnel in full detail to explain aspects of operations and maintenance. 7. Instructional Services shall be completed before start of system demonstration,as required. 8. Provide "Certificate of Instructional Services", co-signed by OWNER and Supplier's representative, verifying training has been accomplished to satisfaction of each party. Use form in Project Forms and furnish two(2) copies to ENGINEER. *** END OF SECTION * ** 01 60 10-5 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF CERTIFICATE OF INSTALLATION SERVICES (Reference Specification Section 01 60 10) Project Equipment Specification Section -- Contract I hereby certify the equipment supplier/manufacturer has inspected this equipment and that it has been properly installed, adjusted, and calibrated. I further certify this equipment may now be operated for test purposes and/or normal use. MANUFACTURER'S REPRESENTATIVE Signature Date Name (print) Title Representing _ CONTRACTOR Signature Date Name (print) Title This form shall be completed and submitted to ENGINEER prior to training of OWNER'S personnel. 01 60 10-6 Flow Equalization Facility Overflow Connection to Satellite WPCF CERTIFICATE OF INSTRUCTIONAL SERVICES (Reference Specification Section 01 60 10) Project Equipment Specification Section Contract I hereby certify that the equipment supplier/manufacturer has instructed OWNER'S personnel in the startup operation and maintenance of this equipment as required in the Specifications. CONTRACTOR Signature Date Name (print) Title OWNER I hereby certify that my operating personnel received_days instruction from for startup,operation, and maintenance of this equipment. Signature Date Name (print) Title Representing COMMENTS: 01 60 10-7 Flow Equalization Facility Overflow Connection to Satellite WPCF CERTIFICATE OF POST STARTUP SERVICES (Reference Specification Section 01 60 10) Project Equipment Specification Section Contract I hereby certify that the equipment supplier/manufacturer has inspected this equipment, made adjustments and calibrations, and that it is operating in conformance with the design, Specification, and manufacturer's requirements. Notation of improper operation shall be detailed and recommendations made and attached to this form. MANUFACTURER'S REPRESENTATIVE Signature Date Name (print) Title Representing CONTRACTOR Signature Date Name (print) Title OWNER I hereby certify that the equipment supplier/manufacturer has inspected this equipment and made adjustments and calibrations. Signature Date Name (print) Title COMMENTS This form shall be submitted to OWNER upon completion of 1-year reinspection as required by the _ Specifications. 01 60 10-8 Flow Equalization Facility '— Overflow Connection to Satellite WPCF SECTION 01 78 23 OPERATION AND MAINTENANCE (O&M) DATA PART 1 GENERAL 1.01 SUMMARY A. Compile data and related information in manuals appropriate for OWNER'S operation and maintenance (O&M) of each item of equipment identified in other Specification sections. 1.02 QUALITY ASSURANCE A. Preparation of data shall be performed by personnel: 1. Trained and experienced in O&M of described equipment. 2. Familiar with requirements of this section. 3. Skilled as technical writer to extent required to communicate essential data. 4. Skilled as drafter competent to prepare required drawings. 1.03 FORM OF MANUALS A. Components: 1. Size: 8-1/2 in. x 11 in., or 11 in. x 17 in. folded, with standard 3-hole punching. 2. Paper: 20-lb minimum, white, for typed pages. 3. Text: Manufacturer's printed data,or neatly typewritten. Handwritten data is not acceptable. 4. Drawings: a. Bind in with text. b. Fold larger drawings and place in clear plastic pockets punched for inserting into binder. Place identification on outside of each pocket. B. Cover Label: Label each binder cover and spine with typed or printed title "OPERATION AND MAINTENANCE INSTRUCTIONS" and following: 1. Project title. 2. Name(s)of applicable building(s)or structure(s)as shown on Drawings in which equipment located. 3. Name of equipment as set forth in Contract Documents. 4. Specification section number for equipment as set forth in Contract Documents. C. Binders: 1. Commercial quality D-Ring binder with durable and cleanable plastic covers. Paperboard and laminated paperboard covers are not acceptable. 2. Do not fill binders to more than 75% of capacity. 3. When multiple binders are used for an item of equipment, organize contents into related groupings. Each binder cover shall bear identification of specific contents. 1.03 SUBMITTAL SCHEDULE A. Submit 6 copies of complete O&M data, bound in binders bearing identification label, for review within 30 days after time CONTRACTOR receives approved Shop Drawings and other submittals for equipment from ENGINEER. B. ENGINEER'S review and acceptance of O&M data will be only for conformance with requirements of this section, for form of submittal and organization of data and completeness of information 01 78 23-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF provided,but not for technical content or coordination between individual suppliers of equipment or system(s). C. CONTRACTOR shall review O&M submittal and complete Form 1, Contractor Submittal Form, attached to this section indicating requirements of this section have been met before submitting to ENGINEER. ENGINEER will reject submittals without completed Form 1. D. ENGINEER will be sole judge of completeness of data. 1.04 PAYMENTS A. Progress payment for equipment delivered,stored or installed under these Contract Documents will not be made until O&M data is approved by ENGINEER. B. Progress payments for control systems packaged with equipment will not be made until O&M data — incorporated into equipment and control system manual is approved by ENGINEER. PART 2 PRODUCTS — (Not Used) PART 3 EXECUTION 3.01 GENERAL CONTENTS OF DATA — A. Each manual shall contain equipment data pertaining to not more than one Specification section number indicated in Contract Documents. B. Title Sheet: First page in data listing following: 1. Title: "OPERATION AND MAINTENANCE INSTRUCTIONS." 2. Title of Project: As shown on Contract Documents. 3. Name(s) of applicable building(s) or structure(s) in which equipment is located. 4. Name of equipment as described in Contract Documents. 5. Specification section number for equipment. — 6. CONTRACTOR'S name, address, and telephone number. 7. Subcontractor's name, address, and telephone number if equipment is provided by Subcontractor. 8. CONTRACTOR'S or Subcontractor's purchase order number, manufacturer's shop order number or other such numbers required for parts and service ordering. 9. Manufacturer's name, address, and telephone number. 10. Name, address, and telephone number for local source of supply for parts and service. C. Equipment List: Immediately following title sheet containing following: 1. Completed Form 1, Contractor's Submittal Form. — D. Table of Contents: Immediately following equipment list. Arrange in logical, systematic order and shall include as minimum each tabbed divider. Each page shall be numbered. E. Tabbed Dividers: Insert tabbed section dividers between each major section. 1. Provide title of section on each tab. 2. Provide table of contents for each tabbed section, arranged in systematic order. 01 78 23-2 Flow Equalization Facility — 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF F. Equipment Data Sheets: Provide catalog sheets showing configuration, manufacturer's specifications, models, options, and styles of equipment and major components being provided. Product data sheets will show project specific information with inapplicable information deleted by crossing out or removal. Include in tabbed section(s). G. Text: 1. Include only those sheets applicable to Project. 2. Each sheet shall: a. Identify specific equipment or part installed. b. Identify text applicable to equipment or part installed. c. Do not include inapplicable information. H. Drawings: 1. Supplement text with drawings to clearly illustrate following: a. Equipment and components. b. Relations of component parts of equipment and systems. c. Control and flow diagrams. 2. Actual drawings of equipment from manufacturer. "Typical" drawings are not acceptable, unless they accurately illustrate actual installation. Specially written information, as required to supplement text for particular installation. 1. Provide explanation of interrelationships of equipment and components, and effects one component has on another or entire system. 2. Provide overall instructions and procedures for equipment tying in instructions and procedures for separate components into unified instructional package. 3. Provide glossary of special terms used by manufacturer. 4. Organize in consistent format under separate headings for different procedures. 5. Provide logical sequence of instructions for each procedure. J. Copy of each warranty, bond or service contract issued. 1. Provide information sheet for OWNER'S personnel to explain following. a. Proper procedures in event of failure or malfunction to prevent voiding warranty. b. Instances affecting validity of warranties or bonds. 3.02 SPECIFIC DATA FOR EACH EQUIPMENT AND SYSTEMS A. For each item of equipment and system include: 1. Completed Equipment Data Form typewritten on copy of Form 2 to Section 01 78 23. 2. Description of equipment and component parts: a. Function, normal operating characteristics, and limiting conditions. b. Performance curves, engineering data, and tests as applicable. c. Complete nomenclature and commercial number of replaceable parts. d. Complete nameplate data. e. P&ID numbers for equipment as indicated on Drawings. 3. Operating Procedures: a. Startup, break-in, and normal operating instructions. 01 78 23-3 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF b. Regulation, control, stopping, shutdown, and emergency instructions. c. Summer and winter operating instructions, as applicable. d. Special operating instructions. 4. Maintenance Procedures: a. Routine maintenance operations.b. Guide to troubleshooting. c. Disassembly, repair, and reassembly instructions. d. Alignment, adjusting, and checking instructions. 5. Servicing and Lubrication Schedule: a. List of lubricants required and quantity to be applied. b. Schedule of lubrication. c. Schedule for other routine maintenance. 6. Manufacturer's printed instructions regarding safety precautions for both (a) protection of personnel operating equipment and systems and(b) prevention of damage to equipment and systems. 7. Description of sequence of operation of controls. 8. Manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance. a. Predicted life of parts subject to wear. b. Items recommended to be stocked as spare parts and quantities of same. — 9. Approved control diagrams such as ladder diagrams, instrumentation loop diagrams, and electrical schematics as appropriate. 10. Bill of material. 11. Other data as required under applicable Specification sections. B. Each electric and electronic system,as applicable to equipment such as switchgear, motor control centers, panel boards, switchboards, starters, breakers, and relays shall include: 1. Description of System and Component Parts: a. Function, normal operating characteristics, and limiting conditions. b. Performance curves, engineering data, rating tables, and tests as applicable. c. Complete nomenclature and commercial number of replaceable parts. d. Complete nameplate data. — e. P&ID numbers for equipment as set forth on Drawings. 2. Circuit Directories of Panel Boards: a. Electrical service. b. Controls. c. Communications. — 3. Complete instrumentation loop diagrams with tabulated listing of components in each control circuit or loop. 4. Operating Procedures: a. Routine and normal operating instructions. b. Sequences required. _ c. Special operating instructions. 5. Maintenance Procedures: 01 78 23-4 Flow Equalization Facility — 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF -- a. Routine maintenance operations. b. Guide to troubleshooting. c. Disassembly, repair, and reassembly instructions. d. Adjustment and checking instructions. 6. Manufacturer's printed instructions regarding safety precautions for both (a) protection of personnel operating equipment and systems and(b) prevention of damage to equipment and _ systems. 7. List of original manufacturer's spare parts and recommended quantities maintained in storage. 8. Other data as required under pertinent sections of Specifications. C. Prepare and include additional data when need for such data becomes apparent during instruction of OWNER'S personnel or as requested by OWNER. mows 01 78 23-5 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF FORM 1 TO SECTION 01 78 23 Page 1 of 5 CONTRACTOR SUBMITTAL FORM TO: DATE: (Engineer) SPECIFICATION (Address) SECTION TITLE: (City, State, Zip) SECTION NO.: (Attn:) MANUFACTURER/ VENDOR: FROM: NO. OF COPIES (Contractor) SUBMITTED TO (Address) ENGINEER: (City, State, Zip) SIGNATURE OF CONTRACTOR: GENTLEMEN: We have checked the O&M manual submittal dated , 20_, and have found it to be in accordance with the requirements of Specification Section 01785 as noted below. FORMAT Size: 8-1/2 x 11 or 11 x 17 Paper: 20-lb minimum Text: Printed data/neatly typed Drawings:Standard size bound in text; in text-size labeled envelopes Tabbed Section Dividers Cover Label: Title Project name Building/structure ID Equipment name Specification section Binders: Plastic Cover 01 78 23-6 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF FORM 1 TO SECTION 01 78 23 Page 2 of 5 CONTRACTOR SUBMITTAL FORM Provide Not Page d Applicable No. GENERAL CONTENTS One specification only I Title Page -Title - Project title - Building/structure ID - Equipment name - Specification section number -Contractor ID -Subcontractor ID - Purchase order data - Manufacturer ID -Service/parts supplier ID I Product List Table of Contents C Tabbed Sections - Pertinent data sheets -Annotated as needed Text - Pertinent to project -Annotated -- Drawings - Illustrate product and components -Control and flow diagrams 01 78 23-7 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF FORM 1 TO SECTION 01 78 23 Page 3 of 5 CONTRACTOR SUBMITTAL FORM Provide Not Page d Applicable No. GENERAL CONTENTS Special Information - Interrelationships of equipment and components - Instructions and procedures provided - Instructions organized in consistent format - Instructions in logical sequence -Glossary Warranty, Bond, Service Contract SPECIFIC CONTENTS (EQUIPMENT/SYSTEMS ONLY) Description of Unit and Components - Equipment functions - Normal operating characteristics - Limiting conditions - Performance curves - Engineering data -Test data - Replaceable parts list (with numbers) - Nameplate data - P&ID numbers C Operating Procedures -Startup - Routine/normal operation - Regulation and control -Stopping and shutdown - Emergency 01 78 23-8 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF FORM 2 TO SECTION 01 78 23 Page 1 of 4 EQUIPMENT DATA FORM PROJECT NAME CONTRACT NO. CONTRACTOR EQUIPMENT NO. ASSET NO.* DESCRIPTION _ MAINT. NO." LOCATION MANUFACTURER PURCHASED FROM VENDOR ORDER NO. PURCHASE $ DATE OF PURCHASE LOCAL SUPPLIER ADDRESS PHONE NO. MODEL NO. NO. OF UNITS SERIAL NOS. *By Owner 01 78 23-11 Fl )w Equalization Facility 60336756-2017 City Contract No.880 Overflow Conne tion to Satellite WPCF FORM 2 TO SECTION 01 78 23 Page 2 of 4 EQUIPMENT DATA FORM NAMEPLATE DATA ELECTRIC MOTOR PUMP/HVAC UNIT MANUFACTURER MANUFACTURER TYPE [ ]AC [ ] DC TYPE HORSEPOWER SIZE RPM CAPACITY VOLTAGE PRESSURE AMPERAGE ROTATION PHASE IMPELLER SIZE FRAME IMPELLER MATERIAL DRIVE/REDUCER OTHER(I&C) MANUFACTURER MANUFACTURER [ ] GEAR TYPE [ ]V-BELT [ ] CHAIN TYPE [ ]VARIDRIVE SIZE SERVICE FACTOR CAPACITY RATIO RANGE 01 78 23-12 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF FORM 2 TO SECTION 01 78 23 Page 3 of 4 EQUIPMENT DATA FORM MAINTENANCE SUMMARY EQUIPMENT NO. ASSET NO.* DESCRIPTION MAINT. NO.'_ MAINTENANCE OPERATION: FREQUENCY: — List briefly each Maintenance Operation required and refer to specific List required -requency of information in Manufacturer's Manual, if applicable. Refer by symbol each mainter ance operation. to"Lubricant List"for Lubrication Operation. *By Owner 01 78 23-13 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF FORM 2 TO SECTION 01 78 23 Page 4 of 4 EQUIPMENT DATA FORM LUBRICANT/RECOMMENDED SPARE PARTS LIST EQUIPMENT NO. ASSET NO.* DESCRIPTION MAINT. NO.* LUBRICANT LIST REFERENCE LUBRICANT TYPE RECOMMENDED LUBRICANT SYMBOL (MILITARY STANDARD) AND MANUFACTURER List symbols in List general lubricant type. List specific lubricant name, viscosity, and "Maintenance manufacturer. Operation" (Page 3). RECOMMENDED SPARE PARTS LIST PART NO. ** DESCRIPTION UNIT QUANTITY UNIT COST ADDITIONAL DATA AND REMARKS * By Owner ** Identify parts provided by this contract with two asterisks. Note: Attach additional sheets if necessary; identify each sheet at top with equipment number and description. ** * END OF SECTION * ** 01 78 23-14 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 01 78 39 PROJECT RECORD DOCUMENTS PART 1 GENERAL 1.01 SUMMARY A. Maintain at site one record copy of: 1. Drawings. 2. Project Manual. 3. Addenda. 4. Change orders and other modifications to Contract. 5. ENGINEER'S Field Orders,Work Change Directives,Written Amendments,or clarifications. 6. Returned Shop Drawings and other submittals. 7. Field test records. 8. Associated permits. — 1.02 SUBMITTALS A. At Substantial Completion: 1. Deliver 1 marked up set of Drawings to ENGINEER for use in preparation of record drawings. B. Submit with transmittal letter containing following: 1. Date. 2. Project title and number. 3. CONTRACTOR'S name and address. 4. Title of record document. 5. Signature of CONTRACTOR or authorized representative. PART 2 PRODUCTS (Not Used) PART 3 EXECUTION 3.01 MAINTENANCE OF DOCUMENTS AND SAMPLES A. Store record documents and samples on-site apart from documents used for construction. 1. Provide files and racks for storage of documents. 2. Provide secure storage space for storage of samples. B. Maintain record documents in clean, dry, legible condition and in good order. Do not use record -' documents for construction purposes. C. Make record documents and samples available for inspection by ENGINEER or OWNER. D. Failure to properly maintain record documents may be reason to delay portion of progress payments until records comply with Contract Documents. 01 78 39-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 3.02 RECORD DOCUMENTS A. General: _ 1. Maintain 1 complete set of Drawings and Project Manual, including Addenda, legibly annotated to show changes made during construction. 2. Label each document"PROJECT RECORD" in neat, large printed letters. 3. Record information concurrently with construction progress: a. Do not conceal Work until information is recorded. b. Record changes made by Field Order, Change Order or Work Directive Change and identify document number. 4. Give particular attention to concealed equipment and materials that would be difficult to measure and record at later date. B. Drawings: 1. Graphically depict changes by modifying or adding to plans, details, sections, elevations, or schedules. 2. Make changes on each sheet affected by changes. 3. Dimensions: a. Depths of various elements of foundation in relation to finish first floor datum. b. Horizontal and vertical locations of underground utilities and appurtenances,referenced to permanent surface improvements. 4. Location of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of structure. 5. Details not on original Drawings. 6. Location and identification of exposed interior piping, including those shown schematically on Drawings. 7. Size of equipment and location including connections. 8. Electrical and Instrumentation: a. Horizontal and vertical locations and size of underground cable, conduit, and duct runs dimensioned from established building lines. b. Plan location and size of interior concealed and exposed feeders. c. Size and location of access panels. d. Variations from original Drawings. C. Specifications: 1. Mark Specification sections to show substantial variations in actual Work performed in comparison with text of Specifications and modifications. 2. Include variations in products delivered to site and from manufacturer's installation instructions and recommendations. 3. Give particular attention to substitutions and selection of options and similar information. 4. Note related record drawing information and Product Data. **" END OF SECTION *** 01 78 39-2 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 02 66 20 HIGH DENSITY POLYETHYLENE (HDPE) GEOMEMBRANE PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. 60 mil black,smooth, high density polyethylene(HDPE)geomembrane for lining and capping systems. B. References: 1.02 REFERENCES A. American Society for Testing and Materials (ASTM) 1. D 1004 Test Method for Initial Tear Resistance of Plastic Film and Sheeting 2. D 1238 Standard Test Method for Flow Rates of Thermoplastics by Extrusion Plastometer 3. D 1505 Test Method for Density of Plastics by the Density-Gradient Technique 4. D 1603 Test Method for Carbon Black in Olefin Plastics 5. D 3895 Standard Test Method for Oxidative-Induction Time of Polyolefins by Differential Scanning Calorimetry 6. D 4218 Standard Test Method for Determination of Carbon Black in Polyethylene . _ Compounds 7. D 4833 Standard Test Method for Index Puncture Resistance of Geotextiles, Geomembranes, and Related Products 8. D 5199 Standard Test Method for Measuring Nominal Thickness of Geotextiles and Geomembranes 9. D 5397 Standard Test Method for Evaluation of Stress Crack Resistance of Polyolefin Geomembranes Using Notched Constant Tensile Load Test 10. D 5596 Standard Test Method for Microscopic Evaluation of the Dispersion of Carbon Black in Polyolefin Geosynthetics 11. D 5994 Standard Test Method for Measuring Core Thickness of Textured Geomembranes 12. D 6392 Standard Test Method for Determining the Integrity of Nonreinforced Geomembrane Seams Produced Using Thermo-Fusion Methods 13. D 6693 Standard Test Method for Determining Tensile Properties of Nonreinforced Polyethylene and Nonreinforced Flexible Polypropylene Geomembranes 14. D 7240 Standard Practice for Leak Location using Geomembranes with an Insulating Layer in Intimate Contact with a Conductive Layer via Electrical Capacitance Technique(Conductive Geomembrane Spark Test) B. Geosynthetic Research Institute 1. GRI GM 13 Test Properties, Testing Frequency and Recommended Warranty for High Density Polyethylene (HDPE) Smooth and Textured Geomembranes 1.03 DEFINITIONS A. Lot - A quantity of resin (usually the capacity of one rail car) used in the manufacture of geomembranes. Finished roll will be identified by a roll number traceable to the resin lot used. B. ENGINEER- The individual or firm responsible for the design and preparation of the project's Contract Drawings and Specifications. 60336757-2017 02 66 20-1 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF C. Geomembrane Manufacturer(MANUFACTURER) -The party responsible for manufacturing the geomembrane rolls. D. Geosynthetic Quality Assurance Laboratory(TESTING LABORATORY)-Party,independent from —' the OWNER, MANUFACTURER and INSTALLER, responsible for conducting laboratory tests on samples of geosynthetics obtained at the site or during manufacturing. E. INSTALLER- Party responsible for field handling, transporting, storing, deploying, seaming and testing of the geomembrane seams. F. Panel- Unit area of a geomembrane that will be seamed in the field that is larger than 100 ft2. G. Patch - Unit area of a geomembrane that will be seamed in the field that is less than 100 ft2. H. Subgrade Surface-Soil layer surface which immediately underlies the geosynthetic material(s). 1.04 SUBMITTALS POST-AWARD A. Furnish the following product data, in writing, to ENGINEER prior to installation of the geomembrane material: 1. Resin Data shall include the following. a. Certification stating that the resin meets the specification requirements (see Table 2.01.C). 2. Geomembrane Roll a. Statement certifying no recycled polymer and no more than 10%rework of the same type of material is added to the resin (product run may be recycled). B. The INSTALLER shall furnish the following information to the ENGINEER and OWNER prior to installation: 1. Installation layout drawings. a. Must show proposed panel layout including field seams and details. _. b. Must be approved prior to installing the geomembrane. 2. Approved drawings will be for concept only and actual panel placement will be determined by site conditions. —" 3. Installer's Geosynthetic Field Installation Quality Assurance Plan. C. The INSTALLER will submit the following to the ENGINEER upon completion of installation: 1. Certificate stating the geomembrane has been installed in accordance with the Contract Documents. 2. Material and installation warranties. 3. As-built drawings showing actual geomembrane placement and seams, including typical anchor trench detail. D. Submit in accordance with Specification Section 01 33 10. 60336757-2017 02 66 20-2 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF 1.05 QUALITY ASSURANCE A. The OWNER will engage and pay for the services of a Geosynthetic Quality Assurance Consultant (QAC) to monitor geomembrane installation. 1.06 QUALIFICATIONS: A. MANUFACTURER 1. Geomembrane shall be manufactured by the following: a. GSE Lining Technology, LLC. b. Approved equal. 2. MANUFACTURER shall have manufactured a minimum of 10,000,000 square feet of polyethylene geomembrane during the last year. B. Installer: 1. Installer shall have minimum 5 yrs continuous experience in installation of HDPE geomembrane or experience totaling 2,000,000 sq ft of installed HDPE geomembrane for minimum of 10 completed facilities. 2. Personnel performing seaming operations shall be qualified by experience or successfully passing seaming tests. Minimum of one seamer shall have experience seaming minimum 100,000 sq ft of HDPE geomembrane using same type of seaming apparatus in use at site. Most experienced seamer, "master seamer", shall provide direct supervision, as required, --- over less experienced seamers. 1.07 WARRANTY A. Material shall be warranted, on a pro-rata basis against Manufacturer's defects for a period of 5 years from the date of geomembrane installation. 1.08 DELIVERY, STORAGE, AND HANDLING A. Packing and Shipping: 1. Manufacturer shall identify each roll delivered to site with following: a. Manufacturer's name. _ b. Product Identification. c. Thickness. d. Roll number. e. Roll dimensions. 2. Protect geomembrane from excessive heat, cold, puncture, cutting, or other damaging or deleterious conditions during loading, transport, and unloading at site. B. Acceptance at Site: 1. Conduct surface observations of each roll for defects and damage. This examination shall be conducted without unrolling rolls unless defects or damages are found or suspected. 2. Defected or damaged rolls or portions of rolls will be rejected and shall be removed from site and replaced with new rolls. 3. Rolls or portions of rolls without identification labeling will be rejected and shall be removed from site. 60336757-2017 02 66 20-3 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF C. Storage and Protection: 1. OWNER will provide on-site storage area for geomembrane rolls from time of delivery until deployment. 2. CONTRACTOR shall, protect geomembrane from dirt,water,and other sources of damage. 3. Preserve integrity and readability of geomembrane roll labels. 4. Rolls which do not have proper identification at delivery will not be accepted. PART 2 PRODUCTS 2.01 MATERIALS A. Manufacturers: 1. GSE 2. Or equal B. Black Smooth Polyethylene Geomembrane Properties: C. Resin 1. Resin shall be new, first quality, compounded and manufactured specifically for producing geomembrane. 2. Natural resin (without carbon black) shall meet the following recuirements: _ Property, T6st Methbc1 HDPE Density(g/cm3) ASTM D 1505 >0.932 Melt Flow Index (g/10 min) ASTM D 1238 (190/2.16) <1.0 OIT (minutes) ASTM D 3895 (1 atm/200°C) >100 D. Geomembrane manufactured from non-complying resin shall be rejected. E. Geomembrane Characteristics: — 1. Contain maximum of 1% by weight of additives, fillers or extenders (not including carbon black). 2. Contain between 2% and 3% by weight of carbon black for ultraviolet light resistance. 3. No pinholes, bubbles or other surface features that compromise geomembrane integrity. Free of blisters, non-dispersed raw materials, or other signs of contamination by foreign matter. 60336757-2017 02 66 20-4 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF — > O N C C N O)C E - mo _a 4 g _a _6 P. t 0 t 0 N NJ- E a) E 00 O 0000000 a3 0 a) a. a•C O O O O Q' O c:, 0 W 7 W ~ � �a N N vvON � o a) ,_E °) • a)N Cl- `0 a 0 a o) as > U 01 C C 0 -� .0 c • C E E ? cis 50 0 _a - Lo .- C C 0 0 w 7 a 00 !: To • 0 0 a) O0 Z 7 ! _oO - O^ O� 000 0 6 0 O 0 so a% O O N N `.." 0 N CON Z eO etZ 0 E c ,a to 0 O 0 .� U 0 O a) a Eo 0) 0 n .co m 0 m0 0 t E Doo O co ,toM m E E o °� c a G Z7m moor r) � ,� oZ o o `� °o° o } o m aXi O O co fV V Z C a) C > — O L.) CDD a) 1-1 CD N U) C C 0 --� _c _C "� �_ • O) E _c y o000 ��0 0 � � roM � E E 0 0co 0 a � a�OiME S C > 0 Z r' V CO CON O NI- p00 0 0 `) O Q: 0 U w �.O 0 L N CO O �c‘j-- N tf) O Z O O CO LO a) 7 0 0 C — a) 0 N V Z N 2 E N a) 'CO E 1- d U 0 -� a) > N O C O OE E 8 O Q f o c _0 .0 = O �. C C W U c `r 'C C (O O O O - eV 0 C) N E E o 0 o a) Tti> 0.0 C a) CL (� Z °) � � - � M °) co 0 0 0 00 ``ii coo N o c o O N Z V Z N a) C O U O W a) a) .2 N C (1) 4 LU Eca co E U !� N O a 0 0 N 0 C 0 0 - X a) N o m 'C N o o Q O �- C c Ea. N e O N.0 C U � c .. 0 `. o .N 7 U N �O O �` ii E QO 0 O fU w T C O [6 O • c n U ca -0•- U c. o y u N n c 0 o m n O E p 0 0 .Q N O C,) ) E o 0 o a U a)as a)_ca 0 CD~ d O Z '7 m MNt `"' � c'J Lo 0 0 0 o u w rt 0 0 Cam _ �' o 0 CO > CO o COS II) NZ O Ov Z `o cow 12 .w -ow u Cd mN 0Q > N 3 . ca = 0 al G) = w a) 0 @ U O m n.-� > 0) U a0 n�a,m Q L Q7 M V M n M.CO LC) co tf) N a) J [6 a w O '6 O C a) O) p CS) C) Co O) O) Co N O) Co Co Q) CO m-� � 0 a) U a) n a) CO - CO n o Co cn Co CO Co Co (No, Co Co '� m U m E o 0 m O T e- V O) N LU CO LU Ln CO Ln r co co a) O) O N 00H ppcm p p Opp 0 00 p a) all C�2O ns -- cn as H p p 0 0 CO H a)0 o U 0 0 O)N a) c o a) r _2 c mz O c6 (D L 'D 'O a1 X •7 Co a) 0'O N- Ca — ma Li) O c a o cD E a) cca ,0 O a`Oi cC m as o dap moo mw a) po _� Eoo` rna`) >, 00c U (9 aJ U a) (o 0) < < a a7 a) U c6.'' co > - > 45 aai -o cU '- mU a)p � a) _ -� C t� O- E U n Q a3-iz •f6 U c c6 w mc L co.. c6 > aa) a) N ?.o c N co ON E a) C Q' c O O a) N w n CD a) 0 0 y �N ' O C aJQL C U) O O ca C) C O 'O _ ` a) a) - - u a) Uo Ta > t 0 N > o > > CY co O O OL _c n CI CO 'C er > > - F co a) ca o p c 0 m a) o >o c a) c oai c 0. c pm 2 m.° y000ica Cs_ E m E c .-.0 E m m E a) n o a) c c C 'w m o c o ca C I- `. 0 H c 1- c t > > a e)L. a n > ,4w N c o E c :w QC OO E O � E 0 i) .c y N =o = E oc .N a ,n N 'c " O a) ,n O N 0 N N H O M N O Y a) U O O a) � p m m � rn rd � c 'y Y 00 w o0 N a) O w a � 0_c mC n• " E a) _ y c E �j .0 cc c m m * m mo rn_.c o a) E C a, c° o 'v) C a) 7 a) a N a N °) U C mC .-'C ' -C .c so a) - L .() C t . U 'CI) a) C la a) y a) c N c ass •D - o > o c } Nb } m m c co Q o(n �2 cfn �2�' �fn o202 � HOUI- =F- ZD C 0 a) v a) cu 'X > co> O H • u. I- • • • • H d CO U U 0 m O m .D p p m ID (ID ��� -al') � wOwi 2.02 SEAMING AND TESTING EQUIPMENT A. Welding: 1. Maintain on-site minimum of 2 spare operable seaming apparatus, unless otherwise agreed upon at pre-construction meeting.2. Seaming equipment shall not damage geomembrane. 3. Use extrusion welding apparatus equipped with gauges giving temperature of extrudate at nozzle of apparatus, or utilize hand-held gauges to measure extrudate temperatures. 4. Use fusion-welding apparatus which are self-propelled devices equipped with following: a. Gauge indicating temperature of heating element. b. Method of monitoring relative pressure applied to geomembrane. 5. Place electric generator on smooth base such that no damage occurs to geomembrane. B. Vacuum Testing Equipment: — 1. Vacuum box assembly consisting of: rigid housing, transparent viewing window, soft neoprene gasket attached to bottom of housing, porthole or valve assembly, and vacuum gauge. 2. Pump assembly equipped with pressure controller and pipe connections. 3. Pressure/vacuum rubber hose with fittings and connections. 4. Soapy solution to wet test area.5. Means of applying soapy solution. C. Air Pressure Testing Equipment: 1. Air pump (manual or motor driven), equipped with pressure gauge, capable of generating, sustaining, and measuring pressure between 24 and 35 psi(160 and 240 kPa),and mounted on cushion to protect geomembrane. 2. Rubber hose with fittings and connections. 3. Sharp hollow needle, or other approved pressure feed device. 4. Air pressure monitoring device. D. Tensiometer Testing Equipment: 1. Tensiometer shall be capable of maintaining constant jaw separation rate of 2 in. per min, and shall be calibrated, with certificate of calibration less than 1 year old kept with tensiometer. 2.03 SOURCE QUALITY CONTROL-GRI TEST METHOD GM13 A. Comply with GRI Test Method GM13 PART 3 EXECUTION 3.01 QUALITY CONTROL SAMPLING -GRI TEST METHOD GM13 A. Comply with GRI Test Method GM13. 02 66 20-6 Belle Plaine UV&FEQ-60442742 3.02 PREPARATION A. Surface Preparation: 1. CONTRACTOR is responsible for preparing supporting surface for geomembrane placement. 2. After prepared surface has been accepted by QAC, report to OWNER ana ENGINEER any change in supporting surface condition that may require repair work. Maintain prepared surface. 3. Do not place geomembrane onto area which has become softened by precipitation or cracked due to desiccation. Observe and report surface condition daily to evaluate degree of softening and desiccation cracking. 4. Repair damage to prepared surface caused by installation activities at CONTRACTOR'S expense. 3.03 INSTALLATION A. Panel Nomenclature: 1. Field panel is defined as a roll or portion of roll cut and seamed in field, excluding patches and cap strips. 2. Identify each field panel with identification code (number or letter-number) consistent with CONTRACTOR'S layout plan. This identification code shall be agreed upon by OWNER, CONTRACTOR, and ENGINEER. 3. Writing on liner with colored markers shall be as follows: a. CONTRACTOR-white marker. b. QAC -yellow marker. Only authorized personnel shall be permitted to write on liner. B. Protection: 1. Do not use equipment which damages geomembrane. 2. Ensure prepared surface underlying geomembrane has not deteriorated since previous acceptance, and remains acceptable immediately prior to geomembrane deployment. 3. Keep Geosynthetic elements immediately underlying geomembrane clean and free of debris. 4. Do not permit personnel to smoke or wear shoes that can damage geomembrane while working on geomembrane. Personnel shall not bring glass bottles on geomembrane. 5. Unroll panels in manner which does not cause excessive scratches or crimps in geomembrane and does not damage supporting soil. 6. Place panels in manner which minimizes wrinkles (especially differential wrinkles between adjacent panels). 7. Prevent wind uplift by providing adequate temporary loading and/or anchoring (e.g., sandbags, tires) that shall not damage geomembrane. In case of high winds, continuous loading is recommended along panel edges. 8. Protect geomembrane in areas where excessive traffic is expected with geotextiles, extra geomembrane, or other suitable materials. C. Field Panel Deployment: 1. Install field panels at locations indicated on CONTRACTOR'S layout plan. 2. Replace seriously damaged(torn,twisted or crimped)field panels,or portions thereof,at no cost to OWNER. Repair less serious damage as specified. QAC shall determine if material shall be repaired or replaced. 3. Remove damaged panels or portions of damaged panels which have been rejected from work area. 02 66 20-7 Belle Plaine L V&FEQ-60442742 4. Do not proceed with deployment at ambient temperature below 32°F (0°C) or above 104°F (40°C) unless otherwise authorized, in writing, by OWNER and ENGINEER. 5. Do not deploy during precipitation, in presence of excessive moisture, fog, dew, in area of ponded water or in presence of excessive winds. 6. Do not undertake deployment if weather conditions will preclude material seaming on same day as deployment. 7. Do not deploy more geomembrane field panels in one day than can be seamed during that day. D. Seam Layout: 1. When possible, orient seams parallel to line of maximum slope, i.e., oriented along, not across, slope. 2. When possible, no horizontal seam shall be less than 5 ft(1.5 m)from toe of slope. 3. In general, maximize lengths of field panels and minimize number of field seams. 4. Align geomembrane panels to have nominal overlap of 3 in. (75 mm)for extrusion welding and 4 to 6 in. (100 mm to 150 mm) for fusion welding. Final overlap shall be sufficient to allow peel tests to be performed on seam.E. Temporary Bonding: 1. Hot air device (Leister) may be used to temporarily bond geomembrane panels to be extrusion welded. 2. Do not damage geomembrane when temporarily bonding adjacent panels. Apply minimal amount of heat to lightly tack geomembrane panels together. Control temperature of hot air at nozzle of any temporary welding apparatus to prevent damage to geomembrane. 3. Do not use solvent or adhesive. F. Seaming Methods: 1. Approved processes for field seaming are extrusion fillet welding and fusion welding. Proposed alternate processes shall be documented and submitted to OWNER and ENGINEER for approval. Alternate procedures shall be used only after being approved in writing by OWNER and ENGINEER. 2. Seams shall meet following requirements: POLYETHYLENE SEAM PROPERTIES PROPERTY METHOD SPECIFIED VALUE MATERIAL THICKNESS 40 60 80 Bonded Seam Strength ASTM D4437, ppi min 80 120 160 Peel Adhesion: ASTM D4437, ppi min. 60 91 121 Fusion ASTM D4437, ppi min. 52 78 104 Extrusion Modifications to ASTM D4437: For shear tests, sheet shall yield before failure of seam. For peel adhesion, seam separation shall not extend more than 50 percent of seam width into seam. For either test, testing shall be discontinued when sample has visually yielded. For peel adhesion all tests //4//of 5 samples shall pass 5th sample can be as low as 80% of listed value for seam to qualify and all shall have a strength value. 3. Use double-fusion welding as primary method of seaming adjacent field panels. a. For cross seam tees, associated with fusion welding, extrusion weld to minimum distance of 4 in. (100 mm) on each side of tee. b. Place welder on protective pad to prevent geomembrane damage between seaming. c. When sub-grade conditions dictate, use movable protective layer(e.g. extra piece of geomembrane)directly below each overlap of geomembrane that is to be seamed to _ 02 66 20-8 Belle Plaine UV&FEQ-60442742 prevent buildup of moisture between sheets and prevent debris from collecting around pressure rollers. 4. Use extrusion fillet welding as secondary method for seaming between adjacent panels and as primary method of welding for detail and repair work. a. Purge heat-degraded extrudate from barrel of extruder under following conditions: 1) Prior to beginning seam. — 2) Whenever extruder has been inactive. b. Place smooth insulating plate or fabric beneath hot welding apparatus after usage. c. Use clean and dry welding rods or extrudate pellets. d. Complete grinding process without damaging geomembrane within 1 hr of seaming operation. e. Minimize exposed grinding marks adjacent to extrusion weld. Do not allow exposed grinding marks to extend more than 1/4 in. outside finished seam area. f. Grind perpendicular to seam. G. Seaming Procedures: 1. General Seaming Procedures: (Ambient temperature between 32°F (0°C) and 104°F (40°C)). a. Do not field seam without master seamer being present. b. Dry conditions, i.e., no precipitation nor other excessive moisture,such as fog or dew. c. No excessive winds. d. If required, provide firm substrate by using extra piece of geomembrane, or similar hard surface directly under seam overlap to achieve proper support for seaming apparatus. e. Align seams with fewest possible number of wrinkles and fish mouths. —' f. Extend seams to outside edge of panels placed in anchor trench. g. Prior to seaming, ensure that seam area is clean and free of moisture, dust,dirt,debris or foreign material. h. Fish mouths or wrinkles at seam overlaps shall be cut along ridge of wrinkle in order to achieve flat overlap. Cut fish mouths or wrinkles shall be seamed and any portion where overlap is inadequate shall be patched with an oval or round patch of same geomembrane extending minimum of 6 in. (150 mm) beyond cut in each direction. i. Deploy and seam geomembrane to minimize bridging due to temperature changes that could result in failure of liner. 2. Cold Weather Seaming Procedures (ambient temperature is below 32°F (0°C)). a. No seaming of geomembrane is permitted unless demonstrated to ENGINEER that geomembrane seam quality will not be compromised. b. ENGINEER shall determine geomembrane surface temperatures at intervals of at least once per 100 ft of seam length to determine if preheating is required. For extrusion welding, preheating is required if surface temperature of geomembrane below 32°F (0°C). c. Preheating may be waived by OWNER based on recommendation from ENGINEER, if demonstrated to ENGINEER'S satisfaction that welds of equivalent quality may be obtained without preheating at expected temperature of installation. d. If preheating is required, ENGINEER shall observe areas of geomembrane that have — been preheated by hot air device prior to seaming, to ensure they have not been subjected to excessive melting. e. ENGINEER shall confirm that surface temperatures not lowered below minimum surface temperatures specified for welding due to winds or other adverse conditions. It may be necessary to provide wind protection for seam area. f. Preheating devices used shall be pre-approved by ENGINEER prior to use. 02 66 20-9 Belle Plaine UV&FEQ-60442742 g. Additional destructive seam tests may be taken at interval between 500 ft and 250 ft of seam length, at ENGINEER'S discretion. h. Sheet grinding may be performed before preheating, if applicable. i. Trial seaming shall be conducted under same ambient temperature and preheating conditions as actual seams. New trial seams shall be conducted if ambient temperature drops by more than 10°F(3°C)from initial trial seam test conditions. New trial seams shall be conducted upon completion of seams in progress during temperature drop. 3. Warm Weather Procedures (ambient temperature is above 104°F (40°C)). a. No seaming of geomembrane is permitted unless demonstrated to ENGINEER that geomembrane seam quality will not be compromised. b. Trial seaming shall be conducted under same ambient temperature conditions as actual seams. New trial seams shall be conducted if ambient temperature rises by more than 5°F(3°C)from initial trial seam test conditions. Such new trial seams shall be conducted upon completion of seams in progress during temperature rise. c. At option of ENGINEER, additional destructive seam tests may be required for any .� suspect areas. H. Repair Procedures: 1. Repair portions of geomembrane exhibiting flaw,or failing destructive or nondestructive test. 2. Final decision as to repair procedure shall be agreed upon between CONTRACTOR and ENGINEER. -- 3. Acceptable repair procedures include following: a. Patching: Piece of same geomembrane material extrusion welded into place. Use to repair large holes, tears, non-dispersed raw materials, and contamination by foreign -- matter. b. Spot welding or seaming: Bead of molten extrudate placed on flaw. Use to repair, pinholes, or other minor, localized flaws. .� c. Capping: Strip of same geomembrane material extrusion welded into place over inadequate seam. Use to repair large lengths of failed seams. d. Extrusion welding flap: Bead of molten extrudate placed on exposed flap of fusion weld. Use to repair areas of inadequate fusion seams, which have exposed edge. Repairs of this type shall be approved by ENGINEER and shall not exceed 100 ft (30 m) in length. e. Removal and replacement: Remove bad seam and replace with strip of same geomembrane material welded into place. Use to repair large lengths of failed seams. .. 4. For each repair method: a. Ensure surfaces are clean, dry, and prepared in accordance with specified seaming process. b. Ensure seaming equipment used in repairing procedures meet requirements of this Specification. c. Extend patches or caps at least 6 in. (150 mm)beyond edge of defect. Round corners of patches with radius of approximately 3 in. (75 mm). 5. Do not place overlying layers over locations which have been repaired until appropriate acceptable nondestructive and destructive (laboratory)test results are obtained. 3.04 FIELD QUALITY CONTROL A. Costs: 1. All testing, destructive and non-destructive, are the responsibility of the CONTRACTOR. 02 66 20-10 Belle Plaine UV&FEQ-60442742 B. Visual Inspection: 1. ENGINEER will examine seam and non-seam areas of geomembrane for identification of defects, holes, blisters, non-dispersed raw materials, and any sign of contamination by foreign matter. 2. Clean and wash geomembrane surface if ENGINEER determines that amount of dust or mud inhibits examination. 3. Do not seam any geomembrane panels that have not been examined for flaws by ENGINEER. 4. Nondestructively test seams and any non-seam areas identified by ENGINEER. C. Trial Seams: 1. Make trial seams on fragment pieces of geomembrane liner to verify that conditions are adequate for production seaming. 2. Make trial seams at beginning of each seaming period,and at least once each 5 hrs,for each production seaming apparatus used that day. Each seamer shall make at least one trial seam each day. 3. Make trial seams under same conditions as actual seams. 4. Make trial seams only under observation of ENGINEER. 5. Seam overlap shall be as indicated for finished seam. 6. Make trial seam sample shall be at least 5 ft(1.6 m)long by 1 ft(0.3 m)wide(after seaming) with seam centered lengthwise. 7. Cut 3 specimens from sample with 1 in. (25 mm)wide die. These specimen locations shall be selected randomly along trial seam sample by ENGINEER. Test specimens in peel using field tensiometer. Samples shall fail in sheet or exceed the specified peel criteria stated in this Specification. 8. If specimen fails, entire trial seam operation shall be repeated. If additional specimen fails, do not use seaming apparatus and seamer until deficiencies are corrected and 2 consecutive successful trial welds are achieved. 9. Cut remainder of successful trial seam into three pieces; one to be retained in OWNER'S archives, one to be retained by CONTRACTOR, and one to be retained by ENGINEER for possible laboratory destructive seam testing. If required by ENGINEER, remaining portion of trial seam sample may be subjected to destructive testing. C. Nondestructive Seam Testing: 1. General: a. Purpose of nondestructive tests is to check continuity of seams. It will not provide quantitative information on seam strength. b. Nondestructively test field seams over their full length using vacuum test for extrusion seams, air pressure for double-fusion seams or other OWNER approved method. c. Perform nondestructive testing as seaming work progresses. 2. Vacuum Testing for extrusion seam: a. Energize vacuum pump and reduce tank pressure to approximately 5 psi(10 in.of Hg) (35 kPa) gauge pressure. b. Wet strip of geomembrane approximately 12 in. by 48 in. (0.3 m by 1.2 m)with soapy solution. c. Place box over wetted area. d. Close bleed valve and open vacuum valve. e. Ensure that leak-tight seal is created. f. For minimum of 10 sec, apply vacuum and examine geomembrane through viewing window for presence of soap bubbles. 02 66 20-1 1 Belle Plaine 1:V&FEQ-60442742 g. If no bubbles appear within 10 sec, close vacuum valve and open bleed valve, move box over to next adjoining area with minimum 3 in. (75 mm) overlap and repeat process. h. Mark and repair areas where soap bubbles appear. 3. Air Pressure Testing for double-fusion seam: a. Seal both ends of seam to be tested. b. Insert needle or other approved pressure feed device into air channel created by fusion weld. c. Insert protective cushion between air pump and geomembrane. d. Pressurize air channel to pressure of approximately 30 psi(200 kPa). Close valve and allow pressure to stabilize for approximately 2 min. e. Observe air pressure 5 min after initial 2 min stabilization period ends. If pressure loss exceeds Maximum Permissible Pressure Differential or pressure does not stabilize, locate faulty area and repair. MAXIMUM PERMISSIBLE PRESSURE DIFFERENTIAL AFTER 5 MINUTES Material (mil) Pressure Diff. (psi) 40 4 60 3 80 2 �. 100 2 f. Cut opposite end of tested seam area once testing is completed to verify continuity of air channel. If air does not escape, locate blockage and retest un-pressurized area. Repair cut end of air channel. g. Remove needle or other approved pressure feed device and repair hole in geomembrane. 4. Inaccessible Seams: a. Cap-strip seams that cannot be nondestructively tested. ' b. Cap-strip material shall be composed of same type and thickness geomembrane as geomembrane to be capped. c. Examine cap-stripping operations with ENGINEER for uniformity and completeness. d. In accordance with ASTM D4437 mechanical point stress non-destructive test may be used as qualitative measure of edge bonding. D. Destructive Seam Testing: 1. General: a. Purpose of destructive seam testing to evaluate seam strength. b. Perform destructive seam test as seaming progresses. c. Failed destructive seam sample shall result if grips of testing machine cannot be closed on sample test flap (available flap is 1/2 in. long or less) due to excessive temporary welding. 2. Location and frequency: a. Test at minimum frequency of one test location per 500 ft (150 m) of seam length performed by each welding machine. b. Test locations shall be determined during seaming, at ENGINEER'S discretion. c. CONTRACTOR will not be informed in advance of locations where seam samples will -- be taken. d. ENGINEER reserves right to increase frequency of testing in accordance with performance results of samples previously tested. ._ 02 66 20-12 Belle Plaine UV&FEQ-60442742 3. Sampling Procedures: a. Cut samples at locations chosen by ENGINEER. b. ENGINEER shall number each sample and record sample number and location in panel layout drawing. c. Repair holes in geomembrane resulting from destructive seam sampling immediately in accordance with repair procedures described in this Specification. d. Continuity of repair and seams shall be tested in accordance with vacuum testing -- requirements. 4. Sample Dimensions: Take two 1 in. wide samples for field testing prior to cutting full laboratory sample. a. Field Testing: Cut 1 in. (25 mm)wide samples, 8 in. long with seam centered parallel to width. Distance between these 2 samples shall be 42 in. (1.1 m). Test both samples on field tensiometer in peel. If both samples pass field test, take sample for laboratory testing. b. Laboratory Testing: Take laboratory test sample from between samples taken for field testing. Cut sample for laboratory testing 12 in. (0.3 m)wide by 42 in. (1.1 m)long with -- seam centered lengthwise. Cut this sample into three parts. ENGINEER shall distribute parts as follows: 1) One part to CONTRACTOR for optional laboratory testing, 12 in.by 12 in. (0.3 m by 0.3 m). 2) One part to Geosynthetic Quality Assurance Laboratory for testing, 12 in. by 18 in. (0.3 m by 0.5 m). 3) One part to OWNER for archive storage, 12 in. by 12 in. (0.3 m by 0.3 m). c. Final determination of sample sizes shall be agreed upon at pre-construction meeting. d. Submit laboratory sample for quantitative testing. CONTRACTOR shall bear the cost for this testing. 5. Destructive Test Failure Procedures: When sample fails destructive testing,whether test is conducted by Geosynthetic QAL or by field tensiometer, CONTRACTOR has following options: a. Repair seam between any 2 passing destructive test locations. b. Trace welding path to intermediate point(10 ft(3 m)minimum from point of failed test in each direction)and take small sample with 1 in. (25 mm)wide die for an additional field test at each location. If these additional samples pass test, then take full laboratory samples. If these laboratory samples pass tests, repair seam between these locations. If either sample fails, repeat process to establish zone in which seam should be repaired. c. Acceptable repaired seams shall be bound by 2 locations from which samples passing laboratory destructive tests have been taken. In cases exceeding 150 ft (50 m) of repaired seam, Geosynthetic QAC may have CONTRACTOR destructive test repair seam. d. When sample fails, OWNER may require additional testing of seams that were welded by same welder and/or welding apparatus during same time shift. e. Passing laboratory destructive tests of trail seam samples taken as indicated in Section 3.04, B, may be used as boundary for failing seam. E. Repair Verification: 1. ENGINEER shall observe number and log each repair. 2. Nondestructively test each repair. 3. Nondestructive test results that pass shall indicate adequate repair. 02 66 20-13 Belle Plaine 1 V&FEQ-60442742 4. Repairs more than 150 ft long, may require destructive test sampling. 5. Failed destructive or nondestructive tests indicate that repair shall be redone and retested until passing test results. F. Large Wrinkles: Wrinkle is considered to be large when geomembrane can be folded over onto itself. 1. When seaming of geomembrane is completed, and prior to placing overlying materials, — GEOSYNTHETIC QAC shall identify large geomembrane wrinkles which should be cut and reseamed. 2. Cut and reseam wrinkles identified by GEOSYNTHETIC QAC. Seams produced while — repairing wrinkles shall be nondestructively tested. 3. Repair wrinkles identified by GEOSYNTHETIC QAC. Repair during coldest part of installation period. *** END OF SECTION* ** 02 66 20-14 Belle Plaine UV&FEQ-60442742 SECTION 09 96 10 COATINGS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Painting and finishing of piping, pipe supports fittings and other items as detailed here in or on the plans. B. Following categories of work are not included as part of field applied finish work. 1. Pre-Finished Items: Unless otherwise indicated,do not include painting when factory finishing or installer finishing is specified. 2. Finished Metal Surfaces: Unless otherwise indicated, metal surfaces of anodized aluminum, stainless steel,chromium plate,copper, bronze,and similar finished materials will not require finish painting. 4. Operating Parts: Unless otherwise indicated,moving parts of operating units, mechanical and electrical parts such as valve and damper operators, linkages, sinkages, sensing devices, motor, and fan shafts will not require finish painting. C. Following categories of work are included under other sections of these Specifications. 1. Equipment manufacturer is responsible for surface preparation and coatings of equipment, motors and appurtenances. 2. Do not paint over any code-required labels such as UL and Factory Mutual or any equipment identification, performance rating, name or nomenclature plates. D. Mechanical and Electrical Work: 1. Mechanical items to be painted include, but are not limited to: a. Piping, pipe hangers, pipe insulation, and supports. b. Accessory items. 2. Electrical items to be painted include, but not limited to: a. Conduit and fittings. 1.02 SUBMITTALS A. Product Data: Manufacturer's technical information, including paint label analysis and application instructions, for each material proposed for use. B. Submit in accordance with Division 1. C. Certification by the manufacturer that the products supplied comply with local regulations controlling use of Volatile Organic Compounds (VOCs) 1.03 QUALITY ASSURANCE A. Single Source Responsibility: Provide primers and other undercoat paint produced by same manufacturer as finish coats. Use only thinners approved by paint manufacturer within 09 96 10-1 Flow Equalization Facility 60336757-2017 City Contract No.880 Overflow Connection to Satellite WPCF recommended limits. B. Coordination of Work: Review other Specification sections in which prime paints are provided to ensure compatibility of total coatings system for various substrates. Upon request from other trades, furnish information or characteristics of finish materials provided for use to ensure compatible prime coats used. C. Engage an experienced applicator who has successfully completed coating system applications similar in material and extent to those indicated for project. 1.04 DELIVERY, STORAGE, AND HANDLING A. Deliver materials to Project site in original, new, and unopened packages and containers bearing manufacturer's name, label, and following information: 1. Name or title of material. 2. Manufacturer's stock number and date of manufacture. 3. Manufacturer's name. 4. Contents by volume for major pigment and vehicle constituents. 5. Thinning instructions. 6. Application instructions. 7. Color name and number. 8. VOC content. B. Store materials not in actual use in tightly covered containers. Maintain containers used in storage of paint in clean condition, free of foreign materials and residue. 1. Protect from freezing where necessary. Keep storage area neat and orderly. Remove oily rags and waste daily. Take precautions to ensure workers and work areas are adequately protected from fire and health hazards resulting from handling, mixing, and application of paints. 1.05 PROJECT/SITE CONDITIONS -^ A. Apply water base paints only when surface temperatures to be painted and surrounding air temperatures are between 50°F and 90°F, unless otherwise permitted by paint manufacturer's printed instructions. B. Apply solvent thinned paints only when surface temperature to be painted and surrounding air temperatures are between 45°F and 95°F, unless otherwise permitted by paint manufacturer's printed instructions. C. Do not apply paint in snow, rain,fog,or mist;when relative humidity exceeds 85%;or to damp or wet surfaces unless otherwise permitted by paint manufacturer's printed instructions. Do not apply in conditions that are dusty. PART 2 PRODUCTS 2.01 MANUFACTURERS A. Tenemec B. Carboline C. Sherwin-Williams Company(S-W). 09 96 10-2 Flow Equalization Facility ^- 60336757-2017 City Contract No.880 Overflow Connection to Satellite WPCF • D. Pittsburgh Paints (PPG). G. Or equal. 2.02 MATERIALS A. Material Quality: Provide best quality grade of various types of coatings as regularly manufactured by paint materials manufacturers. Materials not displaying manufacturer's identification as standard, best grade product are not acceptable. B. Color Pigments: Pure, non-fading, applicable types to suit substrates and service indicated. 1. Colors shall be chosen by the Owner. 2. Lead content in pigment, if any, limited to contain not more than 0.06% (or statutory limit) lead, as lead metal based on total non-volatile (dry film) of paint by weight. PART 3 EXECUTION 3.01 EXAMINATION A. Examine areas and conditions under which painting work to be applied and notify CONTRACTOR in writing of conditions detrimental to proper and timely completion of work. Do not proceed with work until unsatisfactory conditions have been corrected in manner acceptable to applicator. B. Start of painting work will be construed as applicator's acceptance of surfaces and conditions within any particular area. C. Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces or conditions otherwise detrimental to formation of durable paint film. 3.02 SURFACE PREPARATION A. Prepare and clean in accordance with paint manufacturer's instructions and as specified for each particular substrate condition. 1. Provide barrier coats over incompatible primers or remove and reprime as required. Notify ARCHITECT in writing of any anticipated problems using specified coating systems with substrates primed by others. 2. Remove hardware, hardware accessories, machined surfaces, plates, lighting fixtures, and similar items in-place and not to be finish painted or provide surface applied protection prior to surface preparation and painting operations. Remove, if necessary,for complete painting of items and adjacent surfaces. Following completion of painting of each space or area,reinstall removed items. 3. Clean surfaces to be painted before applying paint or surface treatments. Remove oil and grease prior to mechanical cleaning. Program cleaning and painting so contaminants from cleaning process will not fall onto wet, newly painted surfaces. B. Cementitious Materials: Prepare cementitious surfaces of concrete and concrete block to be painted by removing efflorescence, chalk, dust, dirt, grease, oils, and roughening as required to remove glaze. 1. Determine alkalinity and moisture content of surfaces to be painted by performing appropriate tests. If surfaces found to be sufficiently alkaline to cause blistering and burning of finish paint,correct condition before application of paint. Do not paint over surfaces where moisture content exceeds that permitted in manufacturer's printed directions. 09 96 10-3 Flow Equalization Facility 60336757-2017 City Contract No.880 Overflow Connection to Satellite WPCF 2. Clean concrete floor surfaces scheduled to be painted with commercial solution of muriatic acid or other etching cleaner. Flush floor with clean water to neutralize acid and allow to dry before painting. C. Ferrous Metals: Clean ferrous surfaces not galvanized or shop coated of oil,grease, dirt, loose mill scale, and other foreign substances by solvent or mechanical cleaning. 1. Touch-up shop applied prime coats wherever damaged or bare. 2. Clean and touch-up with same type shop primer. D. Galvanized Surfaces: Clean free of oil and surface contaminants with non-petroleum based solvent. E. Workmanship for surface preparation, as specified, shall conform with SSPC specifications. 1) SP-1: Solvent Cleaning 2) SP-2: Hand Tool Cleaning 3) SP-3: Power Tool Cleaning 4) SP-5: White Metal Blast Cleaning 5) SP-6: Commercial Blast Cleaning 6) SP-7: Brush-Off Blast Cleaning 7) SP-8: Pickling 8) SP-10: Near-White Blast Cleaning 9) SP-11: Power Tool Cleaning to Bare Metal 10) SP 12: Cleaning of Metals by Waterjetting Prior to Recoating 11) SP 13: Surface Preparation of Concrete 12) SP16: Brush-Off Blast Cleaning of Coated and Uncoated Galvanized Steel, Stainless Steel and Non-Ferrous Metals Wherever"solvent cleaning," "hand tool cleaning," "wire brushing" or"blast cleaning," or similar words of equal intent used in Specifications or coating manufacturer's specifications, they shall be understood to refer to applicable SSPC specifications listed above. Use hand tools to clean areas that cannot be cleaned by power tools. 3.03 MATERIALS PREPARATION A. Mix and prepare painting materials in accordance with manufacturer's directions. B. Maintain containers used in mixing and application of paint in clean condition, free of foreign materials and residue. C. Stir materials before application to produce mixture of uniform density and stir as required during application. Do not stir surface film into material. Remove film and, if necessary, strain material before using. 3.04 APPLICATION A. Apply paint in accordance with manufacturer's directions. Use applicators and techniques best suited for substrate and type of material being applied. '— 1. Paint, surface treatments, and finishes are as indicated in Drawings. 2. Provide finish coats compatible with prime paints used. 3. Apply additional coats when undercoats, other conditions show through final coat of paint, until paint film is of uniform finish, color, and appearance. Give special attention to ensure surfaces, including edges, corners, crevices,welds, and exposed fasteners, receive dry film thickness equivalent to flat surfaces. 5. Sand lightly between each succeeding enamel coat. 09 96 10-4 Flow Equalization Facility — 60336757-2017 City Contract No.880 Overflow Connection to Satellite WPCF 6. Omit first coat(primer)on metal surfaces which have been shop primed and touch-up painted unless otherwise indicated. B. Surfaces to be Painted: Except where natural finish of material is specifically noted as surface not to be painted, paint exposed surfaces whether or not colors are designated in schedules. Where items or surfaces are not specifically mentioned, paint same as similar adjacent materials or areas. If color or finish is not designated, ENGINEER AND/OR OWNER will select these from standard colors or finishes available. Paint exposed piping, conduit, and ducts to match adjacent or near surfaces, except for color coding. C. Scheduling Painting: Apply first coat material to surfaces that have been cleaned, pretreated or otherwise prepared for painting as soon as practicable after preparation and before subsequent surface deterioration. 1. Allow sufficient time between successive coatings to permit proper drying. Do not recoat until paint has dried to feel firm, does not deform or feel sticky under moderate thumb pressure, and application of another coat of paint does not cause lifting or loss of adhesion of undercoat. _ D. Minimum Coating Thickness: Apply materials at not less than manufacturer's recommended spreading rate to establish total dry film thickness as indicated or, if not indicated,recommended by coating manufacturer. — E. Prime Coats: Apply prime coat of material required to be painted or finished, not prime coated by others. 1. Recoat primed and sealed surfaces where evidence of suction spots or unsealed areas in first coat to ensure finish coat with no burn through or other defects due to insufficient sealing. F. Pigmented (Opaque) Finishes: Completely cover to provide opaque, smooth surface of uniform finish, color, appearance, and coverage. Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness or other surface imperfections not acceptable. G. Completed Work: Match approved samples for color, texture, and coverage. Remove, refinish or repaint work not in compliance with specified requirements. 3.05 CLEANING A. Clean Up: During progress of work, remove discarded paint materials, rubbish, cans, and rags at end of each work day from site. 3.06 PROTECTION A. Protect work of other trades,whether to be painted or not, against damage by painting and finishing work. Correct any damage by cleaning, repairing or replacing, and repainting as acceptable to ARCHITECT. 3.07 FIELD QUALITY CONTROL A. Sampling of Materials: 1. ENGINEER reserves right to select unopened containers of materials furnished for project and have materials tested at an independent testing laboratory. OWNER will pay for first tests. 2. Retests of rejected materials and tests of replacement materials shall be paid for By CONTRACTOR. 09 96 10-5 Flow Equalization Facility 60336757-2017 City Contract No.880 Overflow Connection to Satellite WPCF 3. Remainder of contents of containers not required for testing will be returned to CONTRACTOR. B. Coverage: 1. If coverage is not acceptable to ENGINEER, ENGINEER reserves right to require extra application of paint at no extra cost to OWNER. ... 2. Work at site where coat of material is applied will be inspected by ENGINEER before application of succeeding specified coat, otherwise no credit for coat applied will be given and CONTRACTOR automatically assumes responsibility to recoat Work in question. Furnish ENGINEER report of particular coat applied and when completed for inspection to comply with above. 3.08 PAINT SCHEDULE A. Concrete Masonry Units: 1. Ferrous metals, submerged ductile iron NP, ductile iron pipe and all ferrous supports. a. Surface Preparation: Ferrous Metal SSPC SP10. b. First Coat: 4.0 to 6.0 DFT"Series 66HS Hi-Build Epoxoline" polyamine epoxy. c. Second Coat: 6.0 to 8.0 DFT"Series 66HS Hi-Build Epoxoline" polyamine epoxy. d. Third Coat: 6.0 to 8.0 DFT"Series 66HS Hi-Build Epoxoline" polyamine epoxy. 2. Galvanized metal (not shop primed), interior splash, for conduits. a. Surface preparation: Sweep blast or mechanically abraid followed by SSPC—SP1. b. First Coat: 3.0 to 5.0 DFT"Series N69 Hi—Build Epoxoline" polyamidoamine epoxy. *** END OF SECTION *", 09 96 10-6 Flow Equalization Facility 60336757-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 26 05 02 BASIC MATERIALS AND METHODS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Raceway Systems 2. Wire, Cables and Connectors 3. Wiring Devices 4. Motor and Circuit Disconnects 5. Fuses 1.02 SUBMITTALS A. Approval of equipment supplied in this section is contingent upon CONTRACTOR verification of available fault current from electric utility. 1. Notify ENGINEER if available fault current is higher than specified equipment. B. Product Data: 1. Submit for disconnects and circuit breakers. 2. Product data sheets with printed installation instructions. C. Shop Drawings: 1. Show enclosure dimensions, nameplate nomenclature, electrical ratings, and thermal unit schedule. 2. Wiring diagrams and schematics. D. Operation and Maintenance(O&M) Data: 1. Maintenance data for materials and products for inclusion in Operating and Maintenance Manual. 1.03 QUALITY ASSURANCE A. Items provided under this section shall be listed or labeled by UL or other Nationally Recognized Testing Laboratory(NRTL). 1. Term "NRTL" shall be as defined in OSHA Regulation 1910.7. -- 2. Terms "listed" and "labeled" shall be as defined in National Electrical Code (NEC), Article 100. B. Regulatory Requirements: 1. National Electrical Code(NEC): Components and installation shall comply with National Fire Protection Association (NFPA) 70. PART 2 PRODUCTS 2.01 METAL CONDUIT AND TUBING 26 05 02-1 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF A. Galvanized Rigid Steel Conduit: NEMA C80.1. B. Plastic-Coated Steel Conduit and Fittings: NEMA RN 1. C. Electrical Metallic Tubing and Fittings: NEMA C80.3 with compression-type fittings. D. Flexible Metal Conduit: Zinc-coated steel. E. Liquid Tight Flexible Metal Conduit: Flexible steel conduit with PVC jacket. 2.02 NONMETALLIC CONDUIT —' A. Rigid Nonmetallic Polyvinyl Chloride (PVC) Conduit: NEMA TC 2, Schedule 40 or 80 PVC. 2.03 FITTINGS A. Fittings for steel conduits: 1. Steel or malleable iron, zinc galvanized or cadmium plated. 2. Do not use set screw or indentor type fittings. 3. Do not use aluminum or die cast fittings. 4. EMT and GRS Connectors and Couplings: a. Threaded. b. Insulated throat. c. Gland compression type. d. Rain and concrete type. 5. Comply with ANSI C80.4. 6. Comply with NEMA FB 1, compatible with conduit materials. B. Conduit bodies: 1. Malleable iron with galvanized finish. C. Fittings for flexible metal conduit. 1. Insulated throat type. 2. Threaded. 3. Grounding type. 4. Liquidtight: 1 piece sealing"0" rings with connectors when entering boxes or enclosures. D. PVC Conduit Fittings: 1. NEMA TC 3; match to conduit type and material. E. Expansion Joints: 1. Conduit expansion fittings complete with copper bonding jumper, Cooper Crouse-Hinds Type XJ. 2. Conduit expansion/deflection fittings with copper bonding jumper, Cooper Crouse-Hinds Type XD. F. Seals: 1. Wall entrance, OZ/Gedney Type FSK or FSC. 26 05 02-2 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF G. Drain Fittings: 1. Automatic Drain Breather: a. Explosionproof. 1) Safe for Class I, Groups C and D. b. Capable of passing minimum 25 cc water/min and minimum 0.05 cu ft air/min at atmospheric pressure. 2. Condensate Drain: a. Conduit outlet body, Type T. b. Threaded, galvanized plug with 3/16 in. drilled hole through plug. H. Hazardous Areas: 1. Explosionproof. 2. Horizontal seal fittings, Cooper Crouse-Hinds Type EYS. 3. Vertical seal fittings, Cooper Crouse-Hinds Type EYD. 4. Vertical seal fittings shall have drain plug. — 2.04 WIREWAYS A. Material: Sheet metal sized and shaped as indicated. —' B. Fittings and Accessories: Include couplings,offsets,elbows,expansion joints,adapters, hold-down straps, end caps, and other fittings to match and mate with wireway as required for complete system. C. Select features where not otherwise indicated,as required to complete wiring system and to comply with NEC. D. Wireway Covers: 1. Hinged type for dry locations. 2. Bolted cover with gasket for wet locations. E. Finish: Manufacturer's standard enamel finish unless otherwise noted. 2.05 BOXES A. Of indicated types, sizes and NEMA enclosure classes. Where not indicated, provide units of types, sizes,and classes appropriate for use and location. Provide items complete with covers and accessories required for intended use. Provide gaskets for units in damp or wet locations. B. Fasteners: 1. General Use: Corrosion resistant screws and hardware, including cadmium and zinc-plated items. 2. Damp or Wet Locations: Stainless steel screws and hardware. C. Pull and Junction Boxes: 1. Boxes shall have screwed or bolted-on covers of material same as box and shall be of size and shape to suit application. 26 05 02-3 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 2. Galvanized Steel Boxes: Flat rolled, code gauge, sheet steel with welded seams. Hot-dip galvanized after fabrication. Cover shall be gasketed. 3. Stainless-Steel Boxes: Fabricate of stainless steel conforming to Type 304 of ASTM A167. Cover shall be gasketed. 4. Galvanized Cast-Iron Boxes: Molded of cast iron alloy, with gasketed cover and integral threaded conduit entrances. 5. Boxes Approved for Classified Locations: Cast metal or cast nonmetallic boxes conforming to UL 886 listed and labeled for use in specific location classification, and with specific hazardous material encountered. Conduit entrances shall be integral threaded type. 2.06 WIRES, CABLES, AND CONNECTORS A. Building wires and cables with insulation type, cable construction, and rating as required to meet application and NEC requirements. B. Manufacturers: 1. Wire and Cable: a. Southwire b. Houston Wire and Cable c. Belden '- d. American Insulated Wire Corp e. Republic Wire f. Superior Essex 2. Connectors: a. FCI-Burndy b. Thomas and Betts c. Blackburn, Thomas and Betts C. Copper wire only. D. 600v insulation(ASTM standard compounds)and color code conductors for low voltage(secondary feeders and branch circuits) as required by NEC. 1. Type THWN Stranded: Single conductor No. 12 AWG minimum for branch circuit and feeder conductors size No. 8 AWG and smaller. 2. Type XHHW Stranded: Single conductor for branch circuits,feeders and service conductors larger than No. 8 AWG. 3. Provide grounding conductor when run with circuit conductors with same insulation as circuit conductors. 4. Type USE Stranded: Single conductor for underground direct burial. 5. Type THWN Stranded: Single conductor No. 12 AWG minimum for 120v control wiring and No. 14 AWG minimum for graphic indication, nonshielded instrumentation and other control wiring operating at less than 120v unless otherwise noted on Drawings. a. Provide high density polyethylene jacketed multi-wire cable assemblies in underground conduit or duct. 6. PVC insulation, tinned copper (19 by 27) stranded, No. 16 AWG, twisted pair cabled with — aluminum mylar shielding, stranded,tinned,No. 18 AWG copper drain wire,and overall black FR-PVC, 90°C, 600 volt jacket for interference sensitive instrumentation wiring. a. Provide high density polyethylene jacket on cables installed below ground and in duct encasements. 26 05 02-4 Flow Equalization Facility — 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF E. Joints, Taps and Splices: 1. Joints, Taps and Splices in Conductors No. 10 AWG and Smaller: UL listed preinsulated compression spring-type solderless connectors. 2. Joints, Taps and Splices in Conductors No. 8 AWG and Larger: Solderless 2 - r 4-bolt compression type connectors of type that will not loosen under vibration or normal strains. F. Terminations: 1. Power Conductors: Compression crimp type lugs. 2. Control and Instrumentation Conductors: Compression crimp type fork tongue, insulated support type lugs on terminal strips. Do not splice. 2.07 WIRING DEVICES A. Manufacturers: 1. Hubbell Wiring Device Division 2. Pass and Seymour/Legrand 3. Appleton Electric Company 4. Cooper Crouse-Hinds Company B. Color: Ivory unless otherwise indicated or required by NEC. C. Switches: 1. General Use Lighting Switches: 20 amp toggle, equal to Hubbell No. 1221-I series. 2. Switches controlling equipment, operation of which is not evident from switch position, shall include flush neon pilot light in conjunction with proper switch. Each switch shall be complete with engraved plate to identify equipment being controlled(white letters on black, 1/8 in. high minimum). D. Receptacles: 1. General use duplex receptacles: NEMA 5-20R, grounding type, 20 amp Hubbell No. 5362 Specification Grade. 2. Special purpose receptacles as shown on Drawings and schedules. E. Ground-Fault Circuit Interrupter Receptacles (GFCI). 1. Ratings: 120 vac., 20 amp. 2. Tripping Requirement: UL Class A. 3. Construction: a. Shallow depth. b. Line and load terminal screws. c. Noise suppression. d. Feed through. e. Standard duplex wall plates shall fit. f. NEMA 5-20R configuration. 4. Meet requirements of UL 943 ground-fault circuit interrupters. F. Wiring Device Plates and Covers: 1. Wall plates for wiring devices with ganging and cut-outs as indicated, provided with metal — screws for securing plates to devices, screw heads colored to match finish of plate. 2. Plates for Flush-Mounted Devices: 26 05 02-5 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF InMk a. Hubbell 302/304 stainless steel. 3. Device plates for surface mounted Type FS or FD boxes to be Type FSK galvanized steel. 5. Device plates for surface mounted,4 in. sq boxes to be 1/2 in.raised galvanized steel covers. 6. Weatherproof plates and covers for exterior devices or devices in damp locations to be galvanized gray cast malleable with gasketed, lift cover plate. 7. Weatherproof plates and covers suitable for wet locations while in use. a. Hinged and gasketed cover/enclosure to maintain weather tight seal while the equipment is plugged into it. TayMac or equal. G. Explosionproof Devices: 1. Wiring devices for use in hazardous areas shall be explosionproof approved for Class I, — Division 1, Group D areas. 2. Receptacles: Appleton Cat. No. EFS B175-2023M, Cooper Crouse-Hinds Cat. No. ENR 21201 or equal NEMA 5-20R. 3. Plugs: Match receptacles. Furnish 1 plug for each receptacle installed. 4. Switches: Appleton EFS series, Cooper Crouse-Hinds EDS series or equal. 2.08 MOTOR AND CIRCUIT DISCONNECTS A. Manufacturers: 1. Eaton Electrical 2. Square D, Schneider Electric B. Enclosed Circuit Breaker Construction: 1. Dual cover interlock. 2. External trip indication. 3. Provisions for control circuit interlock. 4. Padlock provisions for padlock in Off position. 5. Handle attached to box, not cover. 6. Handle position indicates On, Off or Tripped. 7. Provisions for insulated or groundable neutral. — C. Permanent Trip Circuit Breakers: 1. Thermal and magnetic protection. 2. Magnetic protection only in combination with motor starters and motor circuit protectors (MCP). 3. Single magnetic trip adjustment. 4. Single-handle common trip, 2 and 3 poles (handle ties not acceptable). 5. Push-to-trip test button. 6. Bolt-on type. 7. Quick make and break toggle action. 8. Handle trip indication. 9. Handle position indication, On, Off, and Tripped centered. 10. UL listed for type of wire specified. 11. UL listed short circuit rating (integrated equipment rating). a. Up to 240v: 10,000 RMS symmetrical amp minimum. b. Up to 480v: 14,000 RMS symmetrical amp minimum. — 26 05 02-6 Flow Equalization Facility — 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF D. Safety Switches: 1. NEMA heavy duty Type HD. 2. Dual cover interlock. 3. Visible blades. 4. Provisions for control circuit interlock. 5. Pin type hinges. 6. Tin-plated current carrying parts. 7. Quick make and break operator mechanism. 8. Handle attached to box, not cover. 9. Handle position indication, On in up position and Off in down position. 10. Padlock provisions for up to 3 padlocks in Off position. 11. UL listed lugs for type and size of wire specified. 12. Spring reinforced fuse clips for Class R fuses. 13. Provisions for insulated or groundable neutral. 14. UL listed short circuit rating 200,000 RMS amp with Class R fuses. E. Enclosures: 1. NEMA 1 in electrical equipment rooms. 2. NEMA 12 in other indoor locations. 3. NEMA 4X stainless steel with watertight hubs for outdoor and wet locations. 4. NEMA 7 in hazardous classified locations. 5. As otherwise indicated and as required by NEC. 2.09 FUSES '— A. Manufacturers: 1. Cooper Bussmann 2. Ferraz Shawmut 3. Littelfuse B. 600v Fuses: 1. Class RK 1, 1-end rejection or to fit mountings specified, 1/10 to 600 amps, 200,000 amp interrupting rating. a. Bussmann Low-Peak. LPS-R, dual element,time delay with short circuit protection for motor, transformer, welder, feeder and main service protection. 2. Class L, bolt-in, 601 to 6,000 amps, 200,000 amp interrupting rating. a. Bussmann HI-CAP. KRP-C, time delay for overload and short circuit protection for motor, transformer, feeder and main service protection. 3. Class CC, fast acting, single element, 1/10 to 30 amps, 200,000 amp interrupting rating. a. Bussmann Limitron. KTK-R, UL listed for motor control circuits, lighting ballasts,control transformers, and street lighting fixtures. C. Spare Fuses: 1. 10%, minimum of 3, of each type and rating of installed fuses. 26 05 02-7 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 2.10 PANELBOARDS A. Panelboard Circuit Breakers: 1. Thermal and magnetic protection. 2. Single-handle common trip, 2 and 3 poles(handle ties not acceptable). 3. Bolt-on type unless otherwise noted on Drawings. 4. Quick make and break toggle action. 5. Handle trip indication. 6 Handle position indication, On, Off, and Tripped centered. 7. UL listed for type of wire specified. '- 8. UL listed short circuit rating (integrated equipment rating). a. Up to 240v: 10,000 RMS symmetrical amp minimum. b. Up to 480v: 14,000 RMS symmetrical amp minimum. 9. HACR breakers for air conditioning units. 10. UL SWDL switching duty on 120v circuits for switched circuits. 11. Switch neutral common trip per NEC 514-5 for fuel pumps. PART 3 EXECUTION 3.01 RACEWAY SYSTEMS A. Outdoors, Damp or Wet Locations: Use following wiring methods unless otherwise noted on Drawings: 1. Exposed: Galvanized rigid steel. 2. Concealed: Galvanized rigid steel. 3. Underground Power: Rigid nonmetallic(PVC) schedule 40 conduit. 4. Underground Shielded Instrumentation Cables: PVC-coated steel conduit. 5. Connection to Vibrating Equipment (including transformers and hydraulic, pneumatic, or electric solenoid or motor-driven equipment): Liquidtight flexible metal conduit. B. Indoor Dry Locations: Use following wiring methods unless otherwise noted on Drawings. 1. Connection to Vibrating Equipment (including transformers and hydraulic, pneumatic, or electric solenoid or motor-driven equipment): Flexible metal conduit. 2. Exposed: Galvanized rigid steel conduit. 3. Concealed: Electrical metallic tubing. C. Hazardous Classified Locations: Use following wiring methods unless otherwise noted on Drawings. 1. Exposed and Concealed: Galvanized rigid steel conduit. D. Use 3/4 in. minimum trade size conduit unless otherwise noted, except conduit runs to room light switches may be 1/2 in. E. Encase galvanized rigid steel conduits installed underground in at least 3 in. of concrete. PVC coated galvanized rigid steel conduits may be used underground without concrete encasement. PVC conduit may be used without concrete encasement for underfloor conduit or where specifically indicated on Drawings. 1. Underground conduit shall be minimum of 1 in., buried at depth of not less than 24 in.below grade. 26 05 02-8 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 2. Provide conduits or ducts terminating below grade with means to prevent entry of dirt and moisture. 3. When using PVC conduit, provide PVC coated galvanized rigid steel elbows. F. In pre-cast areas, run conduits in insulation space or in floor topping without crossing conduits, using 3/4 in. maximum conduit size. G. Raceways Embedded in Slabs: Following restrictions shall be adhered to, unless otherwise noted. 1. Use galvanized rigid steel conduit. 2. No conduit placed vertically shall be larger in cross-sectional area than 4% of column into which it is placed. 3. Conduits,when placed within slab and walls,shall not be larger than 1/3 thickness of slab or wall nor placed closer than 3 outside diameter clear from each other. 4. Reinforcing steel shall be in-place before embedded items placed and reinforcing cut or removed shall be replaced with additional reinforcing as indicated on Drawings or approved by ENGINEER. 5. Do not pass sleeves through columns without ENGINEER'S approval. 6. Do not place conduits in slabs on grade. Place minimum 4 in. under bottom of slab. 7. Secure raceways to reinforcing rods to prevent sagging or shifting during concrete placement. 8. Space raceways laterally to prevent voids in concrete. 9. Install in middle third of slab thickness where practical, and leave at least 1 in. (25 mm) concrete cover. 10. Run conduit larger than 1 in. trade size parallel to or at right angles to main reinforcement and spaced on center of at least 3 times conduit trade diameter with minimum 2 in.concrete covering. Conduits over 1 in. may not be installed in slab without approval of ENGINEER. 11. When at right angles to reinforcement, place conduit close to slab support. 12. Conduits embedded in concrete frame shall comply with applicable provisions of ACI 318/318R. H. Examine surfaces to receive raceways, wireways and fittings for compliance with installation tolerances and other conditions affecting performance of raceway system. I. Coordinate layout and installation of raceway and boxes with other construction elements to ensure adequate headroom, working clearance, and access. J. Complete conduit installation prior to installing cables. K. Raceway systems shall be continuous from outlet to outlet and from outlets to cabinets,junction or pull boxes. L. Enter and secure to boxes, ensuring electrical continuity from point of service to outlets. M. Conduit shall be run concealed, except exposed surface conduit may be installed where noted on Drawings or where concealment found to be impractical or impossible, and only with approval of ENGINEER. N. Provide watertight conduit system where installed in wet places, underground or where buried in masonry or concrete. 1. Use threaded hubs when entering top of enclosures. 2. Use sealing type locknuts when entering sides or bottom of enclosures. O. Conduit runs extending through areas of different temperature or atmospheric conditions or partly indoors and partly outdoors shall be sealed,drained and installed in manner preventing drainage of condensed or entrapped moisture into cabinets, motors or equipment enclosures. 26 05 02-9 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF P. Route conduit runs above suspended acoustical ceilings not interfering with tile panel removals. Q. Cap conduits after installation to prevent entry of debris. R. Connections to motors and equipment subject to vibration shall be maximum of 3 ft long. Locate where least subject to physical abuse. S. Install conduit expansion fittings complete with bonding jumper in following locations. 1. Conduit runs crossing structural expansion joint. 2. Conduit runs attached to 2 separate structures. — 3. Conduit runs where movement perpendicular to axis of conduit may be encountered. T. Keep raceways at least 6 in. away from parallel runs of flues and steam or hot water pipes. Install horizontal raceway runs above water and steam piping.U. Install separate ground conductor inside flexible conduit connections. V. Use approved flexible connections in hazardous locations. W. Use explosionproof fittings and seals in hazardous areas in accordance with NEC. X. PVC Coated Galvanized Rigid Steel Conduit: Use only fittings approved for use with that material. Patch nicks and scrapes in PVC coating after installing conduit. 3.02 WIRE AND CABLE A. Install wires and cables as indicated, according to manufacturer's written instructions and NECA "Standard of Installation". B. Run wire and cable in conduit unless otherwise indicated on Drawings. C. On branch circuits, use standard colors. D. Run ground wire with power circuits; conduit shall not be grounding path. E. Provide separate conduit systems for following. — 1. Line voltage control. 2. Low voltage control. — 3. Shielded instrumentation. 4. As required by NEC. F. Where power cables and instrument/signal cables enter and pass through same handhole or distribution box, steel barrier or steel conduit separation shall be maintained to avoid magnetic interaction between power cables and instrumentation conductors. In handholes, provide Type C conduit outlet body with 3/16 in. holes drilled in bottom for drainage. G. Run instrumentation cable into control cabinets or MCC only if terminated therein. H. Terminate control, instrumentation, and communication cables on terminal strips in separate terminal cabinets located near conduit entrances of buildings or as shown on Drawings. —' Color Coding: Conductors for lighting and power wiring as indicated below. 26 05 02-10 Flow Equalization Facility — 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF Phase 208/120v 480/277v A Black Brown B Red Orange C Blue Yellow Travelers Pink Purple Neutral White White With Non-Green Stripe Ground Green Green J. Color coding for intrinsically safe systems shall be light blue. 3.03 JOINTS, TAPS, AND SPLICES A. Where pre-insulated spring connectors are used for motor and equipment connections, tape connector to wire to prevent loosening under vibration. B. Each tap,joint or splice in conductors No. 8 AWG and larger shall be taped with 2 half-lap layers of vinyl plastic electrical tape and finish wrap of color coding tape where required by code. C. Cable splices shall be made only in handholes,wireways, distribution boxes and junction boxes. 3.04 WIRING DEVICES A. Do not install devices until wiring is complete. B. Do not use terminals on wiring devices (hot or neutral) for feed-through connections, looped or otherwise. Make circuit connections by using wire connectors and pigtails. C. Install gasket plates for devices or system components having light emitting features such as switch with pilot light and dome lights. Where installed on rough textured surfaces, seal with black self-adhesive polyfoam. 3.05 MOTOR AND CIRCUIT DISCONNECTS A. Locate disconnect switches as shown on Drawings or specifications and required by NEC. B. Provide control circuit interlock as required by NEC. C. Overcurrent protective devices. 1. Install fuses just prior to energizing equipment. 2. Locate circuit breakers as shown on Drawings. D. Install on equipment rack or anchor firmly to wall or structural surface. 3.06 FIELD QUALITY CONTROL A. Control Circuits, Branch Circuits, Feeders, Motor Circuits and Transformers: 1. Megger check of phase-to-phase and phase-to-ground insulation levels. a. Do not megger check solid state equipment. 2. Continuity. 3. Short circuit. 4. Operational check. 26 05 02-11 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF B. Wiring Devices: 1. Test receptacles with Hubbell 5200, Woodhead 1750 or equal tester for correct polarity, proper ground connection, and wiring faults. 3.07 ADJUSTMENT AND CLEANING A. Motor Starters and Disconnects: 1. Adjust covers and operating mechanisms for free mechanical movement. 2. Tighten wire and cable connections. —' 3. Verify over-current protection thermal unit size with motor nameplate to provide proper operation and compliance with NEC. 4. Clean interior of enclosures. 5. Touch up scratched or marred surfaces to match original finish. B. Circuit Breakers: 1. Adjustable settings shall be set to provide selective coordination, proper operation, and compliance with NEC. *** END OF SECTION * ** 26 05 02-12 Flow Equalization Facility 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION 33 05 13 MANHOLES AND INLETS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: 1. Precast Concrete Manholes 1.02 SYSTEM DESCRIPTION A. Design Requirements: 1. Precast concrete manhole structures shall be designed to resist buoyancy forces with a factor of safety of 1.10. Groundwater shall be assumed to be at-grade. 2. Structure top slab shall be designed to support AASHTO H-20 wheel loads. 1.03 SUBMITTALS A. Include one copy of results of tests and certification reports with each shipment of materials. B. If manufacturer's test data is inadequate or unavailable, ENGINEER reserves right to require cores drilled for compressive strength tests. C. Submit in accordance with Section 01 33 10. D. Shop Drawings: 1. Technical data for manhole and cover indicating materials of construction. 2. Drawings of manhole and cover. 3. Certification that manholes have been designed in accordance with the requirements specified in Paragraph 1.02.A above. Certifications shall be stamped by Professional Engineer registered in the State of Iowa. E. Written statement detailing that top slabs of structures are designed to withstand loads exerted by slide gate (where applicable). F. Written statement detailing that structures were evaluated for buoyance and will withstand field buoyant forces. See Section 1.02.A.1 of this specification. PART 2 MATERIALS 2.01 PRECAST CONCRETE MANHOLES A. ASTM C478. B. Provide eccentric or concentric cone type precast tops as shown on Drawings. Flat top slabs shall be used only with approval of ENGINEER. C. Reinforced integral base shall be as shown on Drawings. 60336756-2017 33 05 13-1 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF D. Incorporate cast-in adaptors and boots to accommodate connection of pipe. Provide for sewer grade differential between center of manhole and manhole wall for each sewer pipe entering manhole. E. Wall Thickness: Wall thickness shown on the plans is representative; actual thickness shall be by the precast designer. F. Joint precast section of sanitary sewer manhole with watertight rubber gaskets. Provide butyl joint wrap by Strong Seal MS-2C, or equivalent. G. Flexible Plastic Gaskets: 1. Manufacturers: a. K.T. Snyder Company, Inc. b. Hamilton-Kent, Inc. c. Cretex. d. Forterra e. Engineer Approved Equivalent 2. Comply with physical requirements for Type B gaskets in AASHTO M198. H. Manufacturer shall install steps as specified herein. Embed steps into riser or conical top section wall a minimum of 3 in. I. Mark each precast section with name or trademark of manufacturer and date of manufacture. Marking shall be indented into manhole section or shall be painted thereon with waterproof paint. J. Construct manhole and cover of reinforced concrete. 1. Concrete Strength: Minimum 5,000 psi at 28 Days 2. Reinforcing Steel: ASTM A615 GR 60 3. Minimum Concrete Cover for Reinforcing Steel: 1 in 4. Lap Reinforcement at Splices: Minimum of 2 Cross Wires for Wire Mesh 5. Joints shall have bell and spigot connections in conformance with ASTM C478. K. Cast each piece from 1 piece mold. Do not use connecting form ties, which may result in corrosion or leakage points. 2.02 MANHOLE STEPS A. Steel Reinforced Plastic: 1. Approved plastic, such as copolymer polypropylene, meeting with requirements of ASTM D4101, Type II, Grade 49108, reinforced with deformed 3/8-in. diameter reinforcing bar which conforms to requirements of ASTM A616/A615M, Grade 60. B. Embedded portion of steps shall be deformed and grouted to withstand specified live loading. 2.03 CASTINGS A. ASTM A48/A48M, Class 30-B, and dimensions shown on Drawings. B. Free from cracks, holes, swells, and cold shuts. —' 60336756-2017 33 05 13-2 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF C. Types as shown on Drawings. 2.04 FLEXIBLE SEAL _ A. Physical Requirements: ASTM C443. B. Performance Requirements: ASTM C425 and C443. 2.05 CEMENT MORTAR A. ASTM C270, Type M. PART 3 EXECUTION 3.01 EXCAVATION AND PREPARATION OF SUBGRADE A. Excavate and prepare subgrade in accordance with Drawings. B. Elevations indicated on Drawings designate sewer elevations at location of center of manholes. 3.02 BASES A. Cast-in-Place Base for Precast Manhole (if required): 1. Set precast manhole bottom barrel section on concrete brick or solid block so bottom of section is below spring line of outlet pipe and plumbed. 2. Pour in accordance with above. B. Precast Manhole with Integral Base: 1. Excavate deep enough so bottom manhole barrel section with integral base rests on 4-in. minimum of bedding material. 3.03 BACKFILL A. Backfill with pipe bedding and cover material to spring line of incoming pipe in accordance with the drawings. 3.04 MANHOLE INVERT -- A. Do not pour until manhole is built and backfilled. B. Invert shall be same diameter as larger of adjoining sewers and shall be shaped as shown on Drawings. 3.05 PIPE TO MANHOLE CONNECTION A. Flexible Connection of Pipe: 1. Connect plastic sanitary sewer pipe to precast manholes by means of flexible watertight pipe to manhole seal. 2. Lay pipe entering manhole through this seal and do not rigidly support. 3. To maintain seal flexibility, plug portion of annular space between pipe and manhole wall which falls within area of poured invert with flexible plastic gasket prior to pouring manhole invert. 60336756-2017 33 05 13-3 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF 3.06 SETTING OF PRECAST CONCRETE MANHOLES A. Set manholes plumb with orientation of cast-in items as shown on Drawings. B. Joint precast sections of storm sewer manholes and inlets with cement mortar, preformed flexible plastic gaskets or rubber type gaskets. _ C. Joint precast sections of sanitary sewer manholes with rubber gaskets or preformed flexible plastic gaskets. 0-ring or profile gaskets are acceptable. 3.07 MANHOLE STEPS A. Equally space vertically to form continuous ladder at distance of 16 in. oc. B. Place steps within allowable tolerance of±1 in. 3.08 CONSTRUCTION OF WALLS, CORBEL AND CHIMNEY _. A. Construct manhole wall at specified diameter up to beginning of corbel section. B. Construct corbel at approximately 1/2 in. horizontal to 1 in. vertical slope to diameter of manhole frame. C. Keep face of manhole in which steps are installed vertical. _ D. Construct chimney having minimum height of 6 in. on top of corbel section or flat slab to elevation at which frame is set. 3.09 SETTING CASTINGS A. Set at elevation shown on Drawings. B. Adjust castings to grade with brick or concrete rings, 3 in.to 6 in.thick. C. Sealing: _ 1. Standard Manhole(Storm): a. Joint: Mortar. 2. Standard Manhole (Sanitary): Bituminous sealing material, approved by ENGINEER, which affects watertight seal between frame and manhole. 3. Sealed Manhole(Sanitary). a. Joint: Mortar or mortar and external elastomeric seal. 4. Anchored Manhole(Sanitary): a. Joint: Bolted down frame and cover with mortar and butyl rubber seal. 3.10 INSTALLATION A. Install in accordance with manufacturer's written instructions and approved submittals. B. Set manholes plumb with orientation of cast-in items as shown on Drawings. 60336756-2017 33 05 13-4 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF C. Joint precast sections of sanitary sewer manholes with rubber gaskets or preformed flexible plastic gaskets. 0-ring or profile gaskets are acceptable. 3.11 FIELD QUALITY CONTROL A. Precast concrete risers and tops shall be subject to rejection on account of failure to conform to any specification requirements. In addition, individual sections of risers and tops may be rejected because of any of following reasons: 1. Fractures or cracks passing through shell, except for single-end crack not exceeding depth of joint. — 2. Defects indicating imperfect proportioning, mixing and molding. 3. Surface defects indicating honeycombed or open texture. 4. Damaged ends where such damage would prevent making satisfactory joint. 5. Infiltration into structure exceeding 0.0758 gal/vertical ft/hr. 6. Internal diameter of section varying more than 1%from nominal diameter. 7. Any continuous crack having surface width of 0.01 in. or more and extending for length of 12 in. or more, regardless of position. * * * END OF SECTION "* * 60336756-2017 33 05 13-5 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF SECTION 40 05 05 PROCESS-MECHANICAL PIPING SYSTEMS -- PART 1 GENERAL 1.01 SUMMARY A. This section identifies process-mechanical piping systems to be provided, specifies unique requirements for each system identified, and references other sections where detailed requirements of piping components are specified. B. Process-mechanical piping systems are shown on Process-Mechanical Drawings and on Civil Site Piping Drawings. Civil Site Piping Drawings may also show site utility. plumbing, fire protection, and HVAC piping systems which are specified in other sections. C. Schedule 1 to Section 40 05 05 includes piping schedule which identifies process-mechanical piping systems to be provided. Piping schedule includes application information and specifies unique system requirements. 1.02 SUBMITTALS -- A. Shop Drawings: 1. Layout drawings for each process-mechanical piping system drawn to scale. Identify each piping system with same flow stream identifier as shown on Drawings. a. Double-line layout for each piping system 3 in. pipe size and larger. Minimum scale: 1/4 in. = 1 ft. b. Single-line or double-line layout for each piping system smaller than 3 in. pipe size. Minimum scale: 1/4 in. = 1 ft. c. For each piping system include: -- 1) Size for each pipe and fitting. 2) Material, lining type, and system number for coating to be provided for each pipe and fitting. _ 3) Pipe class, thickness or schedule for each pipe and fitting. 4) Pipe end connections (joint type)and couplings. 5) Location and type of supports, hangers, anchors and expansion joints. 6) Pipe couplings, saddles, sleeves, clamps, adapters and other piping products. 7) Pipe mounted equipment and instrumentation identified by tag number assigned on Drawings. 8) Insulation to be provided. A. Submit in accordance with Section 01 33 10. B. Submit results of all testing as detailed in SUDAS Section 4060. 60336756-2017 40 05 05-1 Flow Equalization Facility -- City Contract No.880 Overflow Connection to Satellite WPCF PART 2 PRODUCTS 2.01 PIPE AND FITTINGS A. Provide pipe and fittings as shown on Drawings and as specified in sections identified in Schedule 1 to Section 40 05 05, Process-Mechanical Piping Schedule, presented at end of this section. 2.02 PRODUCTS FOR PIPING SUPPORT, FLEXIBILITY, THERMAL EXPANSION, ANCHORAGE AND VIBRATION ISOLATION A. Provide support system for each non-buried process-mechanical piping system in accordance with the plans. B. Provide anchors, restraints, and concrete blocks as required to resist hydraulic thrust and forces due to thermal expansion. C. Piping system, including support and anchorage system, shall allow for thermal expansion and _ contraction due to differences in operating temperatures and temperatures piping is exposed to during construction. Provide piping system products to allow for and control movement of piping due to thermal expansion and contraction. D. No attempt has been made to show all pipe supports, hangers, anchors, expansion joints, and other piping products required for piping support, thermal expansion, and anchorage. Absence of these products on Drawings does not relieve Contractor of his responsibility for providing them in accordance with these Specifications. E. Provide joints, couplings, and expansion joints as shown on Drawings and as required for piping flexibility and vibration isolation. No attempt has been made to show all joints, couplings, --� expansion joints,and other piping products required for piping flexibility and vibration isolation. 2.03 OTHER PIPING PRODUCTS A. For buried piping, furnish and install pipe per SUDAS. Polyethylene wrap is required for all ductile iron pipe, valves and fittings. 2.04 COATINGS A. Coat exterior surfaces of non-insulated piping products with coating system numbers specified in this Section and in accordance with Section 09 96 10. PART 3 EXECUTION 3.01 PREPARATION A. Use implements, tools, and facilities for handling and protection of piping products to avoid damage prior to installation. B. Inspect piping products before installation. Provide new, repair or recondition damaged piping products. Repair or reconditioning is subject to ENGINEER'S approval. Patch damaged interior linings and exterior coatings or replace damaged product with new product. Patching is subject to ENGINEER'S approval. 60336756-2017 40 05 05-2 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF C. Clean ends of piping product before installation. Remove foreign matter and dirt from inside of piping product and keep product clean until Work has been accepted. 3.02 INSTALLATION A. Location: 1. Install piping parallel to structure lines unless shown otherwise on Drawings. — 2. Do not install piping through beams, columns or other structural members unless shown on Drawings. 3. Locate valves in piping system in accordance with manufacturer's instructions. In horizontal piping runs,do not orient valves so operating stem is below horizontal centerline unless specifically noted on Drawings to do so. B. Assembly: 1. Install piping without springing or forcing in manner which would cause stress in piping, valves or connected equipment. 2. Set pipe flanges level, plumb and aligned. Set flanged fittings so flange is true and perpendicular to pipe axis. Set flanges so bolt holes straddle vertical centerline of pipes. 3. For flanged connections, match bolt holes and obtain uniform contact over entire flange area prior to installation of flange bolts. Tighten bolts to uniformly compress gaskets and minimize flange stress. Tighten bolts to torque recommended by gasket manufacturer. Coat nuts and bolts with anti-seize thread compound. 4. Machine off raised-face of steel flange when mating with flat-faced flange. C. Pump and Equipment Connections: 1. Align pipe, equipment, and pumps so stresses are not transmitted to connections. Support piping independently from pumps and other equipment. Do not support piping from equipment and pumps. Anchor piping to prevent transmission of hydraulic thrust load to pumps and other equipment. 2. Install couplings, adapters, expansion joints, flanges and unions so pumps, equipment, valves and in-line instruments can be removed from service without disruption to other portions of piping system. 3. Install couplings, expansion joints and other vibration isolation components to isolate piping from pump, blower and equipment vibration. 4. For welded nozzle connections, allow for shrinkage during welding to prevent excessive stresses on pumps and equipment. 5. Provide piping from pump and equipment drains and overflows to floor drain system. — 6. Provide control lines such as air and bubbler level system piping necessary for operation of pumps, equipment, valves and in-line instruments. D. Install insulating flange, insulating coupling or dielectric union at each connection between ferrous and non-ferrous metal piping. 3.03 FIELD QUALITY CONTROL A. Inspect installed piping products for dents, kinks, abrupt changes of curvature, damage to lining, and other damage. Repair or recondition damaged products as approved by ENGINEER or replace damaged products with new products. B. Inspect installed, unlined piping products for corrosion and scale on interior surfaces. Clean products to remove corrosion and scale or replace with new products. 60336756-2017 40 05 05-3 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF C. Test system in as detailed in Schedule 1 to Section 40 05 05. 3.04 CLEANING A. After installation and before testing,remove dirt, rocks,debris and other foreign matter from interior of each piping system. B. Water flush each hydrostatically tested piping system unless specified otherwise. 1. Flushing velocities of 2.5 ft per sec shall be maintained until accumulated debris has been removed. — 2. Insert cone strainers at equipment connections prior to flushing. Remove cone strainers after flushing is complete. 3. Remove accumulated debris through drains not less than 2 in. in diameter or by temporarily removing pipe spools, fittings or valves. 4. Drain piping after flushing and immediately dry piping with compressed air. C. Blow clean each pneumatically tested piping system with compressed air unless specified — otherwise. 3.05 PROCESS MECHANICAL PIPING SCHEDULE A. SERVICE Column: Presents Flow Stream Identifiers for process-mechanical piping systems shown on Process-Mechanical Drawings and on Civil Drawings. 1. Civil Drawings may also show site utility, plumbing,fire protection, and HVAC piping systems which are not included in Process-Mechanical Piping Schedule. B. SIZE Column: Presents nominal pipe diameter(s) for each piping system shown on Process- Mechanical Drawings and continuation of piping system on Civil Drawings. C. LOCATION Column: Identifies installation location of piping system. Piping system components shall be suitable for condition specified. D. REMARKS Column: Provides further description of piping system and specifies additional requirements. E. If process mechanical piping shown on Drawings is not listed in schedule, CONTRACTOR shall provide piping. 1. Provide type of pipe used in similar services on project. 2. Provide piping suitable for pressure,temperature and other service conditions. 3. Submit type of pipe proposed for review by ENGINEER. F. Bolts shall meet SUDAS 5010 2.02.A for restrained and mechanical joints; i.e., ceramic filled, baked on, fluorocarbon resin coating for bolts and nuts for buried piping; in tank piping shall have all 316 SS nuts and bolts. 60336756-2017 40 05 05-4 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF SCHEDULE 1 TO SECTION 40 05 05 PROCESS MECHANICAL PIPING SCHEDULE ALL PIPING SHALL FOLLOW SUDAS SPECIFICATIONS AS INDICATED Size Pipe Service (in.) Material Location Remarks SUDAS 5010 2.01 B. Bedding and backfill per SUDAS 24 in RWW from FEQ 3010. Bedding per SUDAS 3010 Class F3, Figure Class 52 3010.103. Push-on joints, restrained joints AND thrust to Satellite Basin- <_24 Buried DIP blocks at fittings at changes in direction and elevation. Buried Test per SUDAS 4060. exterior asphalt coat, interior coat per SUDAS 4010 2.01 G.2. AWWA C115. Gaskets shall be full face 1/8-inch and 24 in RWW in Tank conform to appendices to AWWA C110 and C115. All Pipe in Satellite Basin— <24 Class 53 In Tank, 316 SS nuts and bolts. Nuts and bolts to comply with In Tank DIP Submerged AWWA C110 and C115. Test per SUDAS 4060. Interior coat per SUDAS 4010 2.01 G.2. Exterior coat per 09 96 10 SUDAS 5010 2.01 B. Bedding and backfill per SUDAS 3010. Bedding per SUDAS 3010 Class F3, Figure 12 in RWW from 3010.103. Push-on joints, restrained joints AND thrust Satellite to Easton _<12 Class 52 Buried blocks at fittings at changes in direction and elevation. Aeration Basins DIP Test per SUDAS 4060.exterior asphalt coat, interior coat per SUDAS 4010 2.01 G.2. PVC from Metering and Sch 80 Control Manholes to 4 PVC Buried Solvent Weld Joints. Test per SUDAS 4060 Area Drain 1. Pipe within structures shown as flanged is to be Class 53 AWWA C115 flanged pipe. Coat flanged pipe per Division 9 specifications. '** END OF SECTION ** * 60336756-2017 40 05 05-5 Flow Equalization Facility City Contract No.880 Overflow Connection to Satellite WPCF _ GENERAL SPECIFICATIONS FOR CONSTRUCTION CITY OF WATERLOO, IOWA Department of Engineering SECTION A- Definitions of Terms SECTION B -Scope of work -- SECTION C -Control of Materials and Work SECTION D - Procedure and Progress SECTION E -Measurements and Payments SECTION F -Legal Relations and Responsibility SECTION A- DEFINITIONS OF TERMS 1. CITY. The City of Waterloo, Iowa, which is the Party of the First Part of the accompanying contract, acting through its authorized representative. 2. COUNCIL. The duly elected Council of the City of Waterloo, Iowa. 3. ENGINEER. The City Engineer of Waterloo, Iowa, or his authorized representative. 4. INSPECTOR. The authorized representative of the Engineer, assigned to the detailed inspection of the work or materials therefor and to such other duties as may be delegated to him in these specifications. 5. CONTRACTOR. The Party of the Second Part in the accompanying contract for the improvement covered by these specifications, or his authorized representative. -- 6. SUBCONTRACTOR. Any person, firm, or corporation who has, with the approval of the Council, contracted with the Contractor to execute and perform in his stead all or any part of the contract. 7. BIDDER. Any individual, firm, or corporation submitting a proposal for all or a part of the work provided for in these specifications. 8. PROPOSAL GUARANTEE. The security designed in the Notice of Bidders or Proposal to be furnished by the bidder as a guarantee of good faith to enter into a contract and furnish an acceptable bond for the work contemplated if it be awarded him. 9. SURETY. The corporate body bound with and for the Contractor for the acceptable performance of the contract. 10. PROPOSAL. The written Proposal, submitted by the bidder in the prescribed manner and on the standard form, for the improvements covered by these specifications. 11. SPECIFICATIONS. The documents that set forth the manner in which the proposed work is to be accomplished which have been prepared by the Engineer and approved by the City Council, official copies of which are now on file with the City Clerk. 12. SPECIAL PROVISIONS. Clauses or memoranda not contained herein, applying to the contract of which these specifications are a part, which change or supplement these specifications. 13. CONTRACT. The agreement entered into between the City and the Contractor, setting forth the terms under which the work covered by the plans and specifications is to be performed. The contract includes all conditions, definitions, and instructions set forth in the official publications relating to GENERAL SPECS GS-1 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF the work, the official contract and specifications, the Proposal, official plans, and all supplemental agreements entered into by the parties to the contract. 14. NOTICE TO BIDDERS. The notice called attention of bidders to the time and place for '— receiving bids, containing a brief description of the work, and briefly setting forth the requirements and conditions for submission of Proposals. 15. INSTRUCTIONS TO BIDDERS. The clauses setting forth in detail the information relative to the proposed work and requirements for the submission of Proposals. 16. PLANS. The plans for the improvement covered by the specifications and approved by the Council, official copies of which are on file with the City Clerk. 17. CONTRACT BOND. The bond executed by the Contractor and his surety in favor of the City of Waterloo, Iowa, guaranteeing the complete execution of the contract in accordance with the plans and specifications, the payment of all debts pertaining to the work, and maintenance of the work as provided by law or by the specifications. 18. CONTRACT PERIOD. The period from the specified date for beginning the work to the specified date of completion, both dates inclusive. The contract period may be extended by the Council, as provided in these specifications, in which event the contract period includes the new date of completion. 19. OFFICIAL PUBLICATIONS. The official publications are the formal resolutions and notices relative to the proposed improvement that are required by law to be published in a prescribed manner and that have actually been published in accordance with the statutes relating thereto. Attention is directed to the fact that these official publications are by statute vested with all of the force and effect of contract obligations. 20. A.S.T.M. Abbreviation for American Society for Testing Materials. 21. WORK. The term "Work" of the Contractor and Subcontractor includes labor or materials or both, equipment, transportation, or other facilities necessary to complete the contract. -- 22. TIME. All time limits stated in the contract documents are of the essence in the contract. SECTION B -SCOPE OF WORK 1. CORRELATION AND INTENT OF DOCUMENTS. The Contract documents are complementary, and what is called for by any one shall be as binding as if called for by all. The intention of the documents is to include all labor, materials, equipment, and transportation necessary for the proper execution of the work. Materials or work described in words which, so applied, have a well-known technical or trade meaning shall be held to refer to such recognized standard. — 2. DRAWINGS AND SPECIFICATIONS. Unless otherwise provided in the contract documents, the engineer shall furnish to the Contractor, free of charge, all copies of drawings and specifications reasonably necessary for the execution of the work. — The Contractor shall keep one (1) copy of all drawings and specifications on the work available to the Engineer and to his representatives. 3. CONTRACTOR'S UNDERSTANDING. It is understood and agreed that the Contractor has, by careful examination, satisfied himself as to the nature, character and location of the work, the conformance to the ground, the character, quality, and quantity of the materials to be encountered, the character of the equipment and facilities needed preliminary to and during the prosecution of the work, — the general and local conditions, and all other matters which can, in any way, affect the work under this GENERAL SPECS GS-2 of 13 Flow Equalization Facility — AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF contract. No verbal agreement or conversation with any officer, agent, or employee of the City, either before or after the execution of the Contract, shall affect or modify any of the terms or obligations herein contained. 4. REPORTING ERRORS AND DISCREPANCIES. If the Contractor, in the course of the work, finds any discrepancies between the plans and the physical conditions of the locality or any errors of omission in plans or in the layout as given by said stakes and instructions, it shall be his duty to inform the Engineer immediately, in writing, and the Engineer shall promptly correct the same. 5. ALTERATION OR CORRECTION OF PLANS. The plans are made up from surveys that are presumably correct and represent the foreseen construction requirements. Any modification of the plans which may be required by the exigencies of the construction or any corrections made necessary because of errors in the original surveys, will be made by the Engineer. Should corrections or modifications of the plans or specifications require a different quality or class of work than that upon which the unit prices in the Proposal are based, or if the modifications or corrections are required in parts of the work partially completed and such modifications result in an increased cost to the Contractor, the amount to be paid for work resulting from such changes shall be agreed upon in writing at the time the changes are ordered and before the work is begun by the Contractor. No allowance will be made for anticipated profits on work not performed. 6. CHANGES IN THE WORK. The City, without invalidating the contract, may order extra work or make changes by altering, adding to, or deducting from the work, the contract sum being adjusted by agreement or arbitration before such changed work is undertaken. All such work shall be executed under the conditions of the original contract, except that any claim for extension of time caused thereby shall be adjusted at the time of ordering such change. 7. INCREASED OR DECREASED QUANTITIES. The right is reserved without impairing the contract, to order the performance of such work of a class not contemplated in the Proposal or to increase or decrease the quantities as may be considered necessary to complete fully and satisfactorily the work included in the contract. However, when the work is completed without change in the plans, and the measured quantity of any item of work varies by more than twenty percent (20%) from the estimated quantity specified in the contract, an adjustment in price may be made for such item of work by agreement between the Engineer and the Contractor, subject to the approval of the City Council. Either party to the contract may request such an adjustment. 8. LANDS AND RIGHT OF WAY. The City shall provide the lands upon which the work under this contract is to be done, except that the Contractor shall provide land required for the erection of temporary construction facilities and storage of his material, together with the right of access to same. 9. CITY WATER. The Contractor shall be allowed to use City Water but before any water is used, he shall make application to the Waterloo Water Works for a temporary water connection from a fire hydrant or by some other connection method. Water usage will be charged at the rate for temporary water service. The rules, regulations, and water rates are available at the Waterloo Water Works offices at 325 Sycamore Street or their telephone number is 319-232-6280. 10. RIGHTS OF VARIOUS INTERESTS. Whenever work being done by the City's forces or by other Contractors is contiguous to work covered by this contract, the respective rights of the various interests involved shall be established by the Engineer to secure the completion of the various portions of the work in general harmony. 11. CLOSING STREETS TO TRAFFIC. The Engineer shall be the judge of how many streets or parts of streets it is necessary for the Contractor to close at any time and may refuse to permit the closing of additional streets until such of the work is finished and opened to traffic as he may direct. GENERAL SPECS GS-3 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 12. OBSTRUCTION OF STREETS. The work is to be carried on in such manner as to obstruct the streets, highways, and alleys as little as possible. The Contractor shall carry on the different parts of the work so as to complete the whole, as nearly as practicable, at the same time. In doing the work, the Contractor shall follow the directions of the Engineer as to the place or places where work shall be started or be carried on and the direction in which it shall be done. 13. SHANTIES AND BUILDINGS. Shanties or other buildings shall not be erected in or upon any street, highway, or alley without permission of the Engineer. If such permission be granted, it may be upon any reasonable terms prescribed by the person or body granting such permission. 14. SANITARY CONVENIENCES. The Contractor shall furnish the necessary sanitary — conveniences, properly secluded, for the laborers on the work, and these shall be maintained in a manner that will be inoffensive to the public. 15. CLEANING UP. The Contractor shall, as directed by the Engineer, remove from the City's property and from all public and private property, at his own expense, all temporary structures, rubbish, and waste materials resulting from his operations before work can be considered completed. The Contractor shall also renew or replace any and all fences, sidewalks, or other property damaged or disturbed by his work. 16. OMISSION OF PARTS OF GENERAL SPECIFICATIONS. Parts of the General Specifications deemed not to apply to some particular work may be omitted by special reference in other - parts of the contract documents. SECTION C -CONTROL OF MATERIALS AND WORK 1. SUPERVISION AND INSPECTION. The Engineer shall have supervision of the construction provided for in this Contract and shall decide any and all questions which may arise as to the quality and acceptability of materials furnished, work performed, manner of performance, rate of progress on the work, and all questions regarding the acceptable fulfillment of the terms of the Contract. Materials and construction work shall, at all times, be subject to the inspection of the Engineer or his representatives. The Contractor shall be held strictly to the true intent of these specifications as regards — the quality of materials, workmanship, and the diligent prosecution of the work. The Engineer and his representatives shall, at all times, have access to the work wherever it is in preparation of progress, and the Contractor shall provide proper facilities for such access and for inspection. If the specifications, the Engineer's instructions, law ordinances, or any public authority require — any work and/or materials to be especially tested or approved, the Contractor shall give the Engineer timely notice of readiness for inspection. If the inspection is to be made by authority other than the Engineer, the Contractor shall notify the engineer of the date fixed for inspection. Inspections by the Engineer will be promptly made and, where practicable, at the source of supply. If any work should be covered up without the approval or consent of the Engineer, it must, if required by the Engineer, be uncovered for examination at the Contractor's expense. Re-examination of questioned work may be ordered by the Engineer, and, if so ordered, the work — must be uncovered by the Contractor. If such work be found in accordance with the Contract, the City shall pay the cost of re-examination and replacement. If such work be found not in accordance with the Contract, the Contractor shall pay such cost unless he shall show that the defect in the work was caused by another Contractor, and, in that event, the City shall pay the cost. 2. AUTHORITIES AND DUTIES OF INSPECTORS. Inspectors may be stationed on the work to report to the Engineer as to the progress of the work and the manner in which it is being — performed; also, to report whenever it appears that materials furnished and work performed by the GENERAL SPECS GS-4 of 13 Flow Equalization Facility — AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF Contractor fail to fulfill the requirements of the specifications and Contract, and to direct the attention of the Contractor to such failure or infringement; but such inspection shall not relieve the Contractor from any obligations to furnish acceptable materials or to provide completed construction that is satisfactory in every particular. In case of any dispute arising between the Inspector and the Contractor as to materials furnished or the manner of performing the work, the Inspector shall have the authority to reject materials or suspend the work until the question at issue can be referred to and decided by the Engineer. Inspectors are not authorized to revoke, alter, enlarge, relax, or release any requirements of these specifications. The Inspector shall, in no case, act as foreman or perform other duties for the Contractor, or interfere with the management of the work by the latter. 3. STATUS OF THE ENGINEER. The Engineer shall have general supervision and direction of the work. He has authority to stop the work whenever such stoppage may be necessary to insure the proper execution of the Contract. He shall also have authority to reject any work and/or materials which do not conform to the specifications, to direct the application of forces to any portion of the work as, in his judgment, is required, and to order the force increased or diminished, and to decide questions which arise in the execution of the work. 4. ENGINEER'S DECISIONS. The Engineer shall, within a reasonable time, make decisions on all claims of the Contractor and on all other matters relating to the execution and progress of the work or the interpretation of the contract documents. — All such decisions of the Engineer shall be final except as to the element of time and financial consideration involved, which, if no agreement in regard thereto is reached, shall be subject to arbitration. 5. STAKES AND INSTRUCTIONS. The Contractor shall provide reasonable and necessary opportunities and facilities for setting stakes and making measurements. The Contractor shall not furnish stakes or men to set them. He shall not proceed until he has received from the Engineer such stakes and instructions as may be necessary to the progress of the work. The Contractor shall carefully preserve bench marks, reference points, and stakes, and in case of willful or careless destruction, he shall be charged with the resulting extra expense and shall be responsible for any mistakes that may be caused, by their loss or disturbance. 6. SUPERINTENDENCE. The Contractor shall keep on his work during its progress a competent superintendent and any necessary assistants, all satisfactory to the Engineer. The Superintendent shall not be changed except with the consent of the Engineer, unless the Superintendent proves to be unsatisfactory to the Contractor and ceases to be in his employ. The Superintendent shall represent the Contractor in his absence, and all directions given to him shall be as binding as if given to the Contractor. Important decisions shall be confirmed in writing to the Contractor. Other directions shall be so confirmed on written request in each case. The Contractor shall give efficient supervision to the work using his best skill and attention. He shall carefully study and compare all drawings, specifications, and other instructions, and shall report at once to the Engineer any error, inconsistency, or omission which he may discover. 7. REMOVAL OF UNAUTHORIZED WORK. Work done without lines and grade being give, work done beyond lines shown on the plans or as given, except as herein provided, or any extra or additional work done without authority, will be considered as unauthorized and at the expense of the Contractor and will not be paid for under the provisions of the Contract. Work so done may be ordered removed and replaced at the Contractor's expense. 8. REMOVAL OF DEFECTIVE MATERIALS OR WORK. The Contractor shall promptly remove from the premises all materials condemned by the engineer as failing to conform to the Contract; whether incorporated in the work or not, and the Contractor shall promptly replace and re-execute his GENERAL SPECS GS-5 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF own work in accordance with the contract and without expense to the City, and shall bear the expense of making good all work of other Contractors destroyed or damaged by such removal or replacement. If the Contractor does not remove such condemned work and materials within a reasonable time, fixed by written notice, the City may remove them and may store the material at the expense of the Contractor. If the Contractor does not pay the expense of such removal within a reasonable time thereafter, the City may, upon ten (10) days'written notice, sell such materials at auction or at private sale and shall account for the net proceeds thereof, after deducting all the costs and expense that should have been borne by the Contractor; or, if the net proceeds of such sale are insufficient to pay the expenses of removal, the City may deduct the balance from any amounts due the Contractor. 9. MATERIALS, EQUIPMENT, APPLIANCES, AND FACILITIES. Unless otherwise stipulated, the Contractor shall provide and pay for all materials, labor, water, tools, equipment, light, power, transportation, and other facilities necessary for the execution and completion of the work. Materials shall be of the quality specified for each particular part of the work. Whenever, in construction of the work or in the manufacture of any article of appliance necessary for the construction or operation of the work, it is necessary to use any material that is not fully specified in these specifications, it shall be of good quality and shall meet with the approval of the Engineer. Any appliance that is necessary for the construction or operation of the work and is commonly recognized as a part of the work, shall be furnished by the Contractor as part of the work, whether or not it is specifically called for in the plans and specifications, and such appliance shall be of good quality and standard make and shall meet with the approval of the Engineer. 10. MATERIAL SAMPLES. Before the contract is awarded, the bidder may be required to furnish a statement of the origin, composition, and manufacture of any and all materials proposed for use in the performance of the Contract, together with samples of the material. These samples will be considered as representative and typical of the material to be obtained from any particular source. 11. CHARACTER OF WORKMEN AND EQUIPMENT. The Contractor shall employ competent and efficient workmen for every kind of work. Any person employed on the work who shall refuse or neglect to obey the directions of the engineer or Inspector, or who shall be deemed incompetent or disorderly, or who shall commit trespass upon public or private property in the vicinity of the work, shall be dismissed when the Engineer so orders, and shall not be re-employed unless express permission be given by the Engineer. The Contractor shall, at all times, enforce discipline and good order among his employees. The methods, equipment, and appliances used on the work, and the labor employed, shall be such as will produce a satisfactory quality of work and shall be adequate to complete the contract within — the specified time limit. 12. HIRING CITY EMPLOYEES. The Contractor shall not employ and hire any of the City's employees without the permission of the Engineer. -- 13. LABOR. Local labor shall be given preferences so far as practicable. 14. THE CITY'S RIGHT TO DO WORK. If the Contractor should — neglect to prosecute the work properly or fail to perform any provision of this Contract, the City of Waterloo, after three (3) days' written notice to the Contractor may, without prejudice to any other remedy he may have, make good such deficiencies and may deduct the cost thereof from the payment then or thereafter due the Contractor, provided, however, that the Engineer shall approve both such action and the amount charged to the Contractor. GENERAL SPECS GS-6 of 13 Flow Equalization Facility — AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SECTION D- PROCEDURE AND PROGRESS 1. ORDER OF COMPLETION - USE OF COMPLETED PORTIONS. The Contractor shall complete any portion or portions of the work in such order or time as the Engineer may require. The City shall have the right to take possession of an use completed or partially completed portion of the work at any time, but such taking possession and use shall not be deemed an acceptance of work so taken or used, or any part thereof. If such prior use increases the cost of or delays the work, the Contractor shall be entitled to such extra compensation or extension of time, or both, as the Engineer may determine. 2. WEATHER. During stormy or inclement weather, all work shall be suspended, except such as can be done in an acceptable manner. Permission to work during freezing, stormy, or inclement weather shall in no way be construed as a release of the Contractor's responsibility regarding the quality of the finished work at such time. 3. SUNDAYS AND LEGAL HOLIDAYS. Except for such work as may be required to properly maintain or protect completed or partially completed construction or to maintain lights and barricades, no work will be permitted on Sundays or legal holidays without specific permission of the Engineer. 4. DELAYS AND EXTENSION OF TIME. If the Contractor be delayed in the completion of the work by an act of neglect of the City, or its employees; or by any other Contractor employed by the City; or by changes ordered in the work; or by strikes, lockouts, fire, unusual delays in transportation, unavoidable casualties, or any cause beyond the Contractor's control; or by delay authorized by the Engineer pending arbitration; or by any cause which the Engineer shall decide justifies the delay, then the time of completion shall be extended for such reasonable time as the Engineer may decide will compensate for such delay. No such extension shall be made for delay occurring more than thirty (30) days before claim therefor is made in writing to the Engineer. In the case of a continuing cause of delay, only one claim is necessary. This article does not exclude the recovery of damages for delay by either party under provisions in the contract documents. 5. TEMPORARY SUSPENSION OF WORK. The Engineer shall have authority to suspend the work, wholly or in part, for such period or periods of time as he may deem necessary, due to unsuitable weather or such other conditions as are considered unfavorable for the suitable prosecution of the work, or for such time as is necessary due to the failure to the Contractor to carry out orders given or to perform any or all provisions of the Contract. 6. NOTICES - HOW SERVED. Any notice to be given by the City to the Contractor under this contract shall be deemed to be served if the same be delivered to the man in charge of any office used by the Contractor or his foreman or agent at or near the work, or deposited in the post office, postpaid, addressed to the Contractor at his last known place of business. 7. PROGRESS OF WORK. The progress of the work shall be such that, at the expiration of one-fourth (1/4) of the contract period, one-eighth (1/8) of the work shall be completed; at the expiration of one-half(1/2) of the contract period, three-eighths (3/8) of the work shall be completed; at the expiration of three-fourths (3/4) of the contract period, the work shall be three-fourths (3/4) completed, and the whole work shall be completed at the expiration of the contract period. If, at any time the above schedule is not being maintained, the Council may give written notice to the Contractor and his sureties that the specifications are not being complied with. Such notice shall state what action on the part of the Contractor is required to bring the work within the requirements of the specifications. If the Contractor fails, within ten (10) days, to proceed as directed in the said notice, then the Council shall have authority to annul this contract without process or action at law and take over the GENERAL SPECS GS-7 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF prosecution and completion of the work, as provided under the article covering City's right to terminate contract. 8. CITY'S RIGHT TO TERMINATE CONTRACT. If the Contractor should be adjudged a bankrupt; or if he should make a general assignment for the benefit of this creditor; or if a Receiver should be appointed on account of his insolvency; or if he should persistently or repeatedly refuse or should fail, except in cases for which extension of time is provided, to supply enough skilled workmen or proper materials; or if he should fail to make prompt payment to Subcontractors or for materials or labor; or if he should persistently disregard laws, ordinances, or the instructions of the Engineer; or if he should otherwise be guilty of a substantial violation of any provision of the contract, then the City, upon the certificate of the Engineer that sufficient cause exists to justify such action, may, without prejudice to any _.. other rights or remedy, and after giving the Contractor seven (7) days' written notice, terminate the employment of the Contractor and take possession of the premises and of all materials, tools and appliances thereon and finish the work by whatever method he may deem expedient. In such cases, the Contractor shall not be entitled to receive any further payment until the work is finished.If the unpaid balance of the contract price shall exceed the expenses of finishing the work, including compensation for additional managerial and administration services, such excess shall be paid to the Contractor. If such expense shall exceed such unpaid balance, the Contractor shall pay the difference to the City. The expense incurred by the City as herein provided and the damage incurred through the Contractor's default shall be certified by the Engineer. 9. REMOVAL OF EQUIPMENT. In the case of annulment of this contract before completion, from any cause whatsoever, the Contractor, if notified to do so by the City; shall promptly remove any part or all of his equipment and supplies from the property of the City, failing which, the City shall have the right to remove such equipment and supplies at the expense of the Contractor. -" SECTION E -MEASUREMENTS AND PAYMENT , 1. STANDARD OF MEASUREMENT. All work completed under the contract shall be measured by the Engineer according to the United States standard measures. 2. SCOPE OF PAYMENTS. The Engineer's measurements of quantities shall be the basis for final payment for the work performed under this Contract. After the work is completed, the Engineer will make measurements and computations of the number of units of each of the various items of work completed, and the Contractor will be paid for the actual amount of work performed at the rates specified in his Proposal. Before final settlement is made, the Council may require the Contractor to submit a list of all persons furnishing labor or materials, with evidence that such persons have been paid in full. Payment shall be made in the manner set forth in official publications and Council Proceedings relative thereto. 3. PAYMENT FOR EXTRA WORK. Such extra work as may have been ordered by the Engineer and performed by the Contractor shall be compensated for as provided herein. If work is to be done or materials are to be furnished by the Contractor which cannot properly be classified under unit -.- prices included in the Proposal, the Contractor shall be paid therefor the actual reasonable cost of the labor and materials entering permanently in such work, plus fifteen percent (15%) of the cost thereof. In computing the labor cost on such extra work, the following items shall be included: (a) Actual payroll expenditures for labor at the current rate therefor, and cost of materials. (b) Pay of foreman and timekeepers for actual time required on the extra work. (c) Liability insurance, prorated, for the extra work. GENERAL SPECS GS-8 of 13 Flow Equalization Facility -- AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF Labor cost items on extra work shall be furnished in duplicate by the Contractor to the Inspector daily. The Inspector shall check the items, and if he finds them to be correct, he shall so certify on the statement of cost, returning one copy to the Contractor and filing one copy with the Engineer. The Engineer shall determine the cost of materials entering into extra work from the materials and receipted freight bills for the same. For any special machine, power tools, or equipment, including fuel and lubricants, but not including small hand tools, which may be deemed necessary or desirable to use, the Contractor shall be allowed a reasonable rental thereon, to be agreed upon in writing by the Engineer before such work is begun, and to which sum no percentage is to be added. The item of cost shall not include repairs or replacement of equipment or overhead expenses of any character. The fifteen percent (15%) allowed is considered to cover the use of hand tools and all overhead expenses except liability insurance. In no case will a claim for extra compensation be allowed unless the work upon which the claim is based has been ordered in writing, except as provided hereinafter. 4. CLAIMS FOR EXTRA COST. If the Contractor claims that any instructions, by drawings or otherwise, involved extra cost under this contract, he shall give the Engineer written notice thereof within ten (10) days after completion of the work. — No such claim shall be valid unless so made. 5. CLAIMS FOR EXTRA COMPENSATION. If the Contractor deems that extra compensation is due him for work and/or materials that he considered is not clearly covered in the items for which he submitted unit prices in his bid and that were not ordered in writing by the Engineer as an extra s heretofore provided, the Contractor shall notify the Engineer, in writing, of his intention to make claim for extra compensation for work and/or material before starting construction. If such written notification is not given or the Engineer is not afforded proper facilities by the Contractor for keeping strict account of actual cost as defined herein, then the Contractor hereby agrees to waive the claim for extra compensation. Such notice to the engineer and the fact that the Engineer has kept account of cost as aforesaid, shall not in any way be construed as proving the validity of the claim, which must be passed upon by the Council. In the event that the Council finds the claim to be just, it shall be allowed and paid for as extra work as provided herein. 6. COMPLETION REPORT AND OBJECTIONS THERETO. Within ten (10) days after the full completion of the work to be done under this contract, the Engineer shall make a written statement of all the work done by the Contractor hereunder, stating the quantity of each item as found by him and including a statement of all credits for extra work and all credits or debits for changes, alterations, omissions, and defects, and shall forthwith deliver a copy of such statement to the Contractor. The Contractor shall compare such statement with his own records and shall then, in writing, either approve such statement or point out any claimed errors or omissions. If any of such claims are found correct, the Engineer shall, within ten (10) days, prepare a new statement, a copy of which shall in like manner be delivered unto the Contractor. The Engineer will not file a formal completion report with the City until the Contractor has approved the same. If the figures of the Engineer and the Contractor cannot be reconciled, or there is a difference of opinion regarding some item or items, then such difference of opinion shall be submitted to arbitration as hereinafter provided, and the decision of the arbitrator or arbitrators shall be final, and the Engineer shall, within a period of five(5) days, file his completion report. Before action by the City Council upon such completion report, the Contractor shall also file a written statement of any claims he may have against the City, other than those shown by such completion report, growing out of this contract or the work done hereunder. The City shall retain ten percent (10%) of GENERAL SPECS GS-9 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF the amount due the Contractor on the completion report for a period of thirty (30) days. If no claims are filed against the Contractor within thirty (30) days, the final ten percent (10%) shall then be paid to the Contractor. 7. WAIVER. By the execution of this contract ,the Contractor agrees that any objections he may have to the statement of the amount of work done hereunder included by the Engineer in this completion report, and any claims of the Contractor against the City growing out of this contract and the _ work done hereunder which are not stated in writing in the manner and within the time provided in Article 6, Section E hereof, shall be waived, and no such claim shall thereafter be asserted against the City. SECTION F -LEGAL RELATIONS AND RESPONSIBILITIES 1. LAWS RELATING TO WORK. The Contractor is presumed to be familiar with all laws, ordinances, and regulations which may, in any manner, affect those engaged or employed upon the work or the materials or equipment used in or upon the work, and shall conduct the work so as not to conflict with such laws, ordinances, and regulations. 2. PROTECTION OF WORK AND PROPERTY. The Contractor for any part of the improvement shall be held responsible for the care of materials and of partially completed and completed work until final acceptance of the same by the Council. He will be required to make good at his own expense any damage which the work may sustain from any cause prior to the filing of the engineer's certificate of completion. He shall take all risk from floods and casualties of every description and make no charge for delay due to such cause. He may, however, be allowed a reasonable extension of time on account of such delays. He shall correct or make good at his own expense all damages to adjacent property due to the acts or negligence of his employees of the prosecution of his work, and save the City harmless therefor. The Contractor shall be held liable and responsible for all damages done to water, sewer, drain, _ or other underground pipes and structures, and to sidewalks and private property. 3. RESPONSIBILITY FOR ACCIDENTS. The Contractor shall assume full responsibility for all damages sustained by persons or property due to the carrying on of his work until final acceptance thereof, or until released by the Engineer in writing. 4. LIABILITY INSURANCE. The Contractor shall carry liability insurance which shall save the City harmless and protect the public and any person from injury sustained by the reason of the '— prosecution of the work or the handling or storing of materials therefor, and said Contractor shall also carry liability insurance which shall meet the requirements of the Iowa Worker's Compensation Law. Before work shall be started on this contract, the Contractor shall furnish the City Clerk with proper affidavit or Affidavits executed by representatives of duly qualified insurance companies, evidencing that said insurance company or companies have issued liability insurance policies, effective during the life of the contract, or for a period of a least ten (10) days following the filing of written notice of �. cancellation, protecting the public and any person from injuries or damages sustained by reason of carrying on the work involved in the Contract. The affidavit shall specifically evidence the following forms of insurance protection: (a) Public liability insurance covering all operations performed by persons directly employed by the Contractor. (b) Public liability insurance covering all operations performed by any Subcontractor to whom a portion of the work may have been assigned. GENERAL SPECS GS-10 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF (c) Public liability insurance covering all work upon the project performed by any independent Contractor working under the direction of either the principal Contractor or a Subcontractor. (d) Motor vehicle bodily injury liability insurance and property damage liability insurance on all motor vehicles employed on the work, whether owned by the Contractor or by other persons, firms, or corporations. (e) The minimum protection shall be as follows: Comprehensive General Liability Insurance General Aggregate Limit $ 2,000,000.00 Products—Completed Operations Aggregate Limit $2,000,000.00 Each Occurrence Limit $ 2,000,000.00 Comprehensive Automobile Liability Insurance $ 1,000,000.00 The Contractor shall have the City of Waterloo, Iowa, named as an "Additional Named Insured". A certificate, or a policy if requested, shall be filed with the Owner. All certificates and/or policies of insurance furnished by the Contractor to be filed with the City Clerk shall include the name and address of the agency issuing the same. It shall also be required that the City Clerk be notified by registered mail of the cancellation or expiration of the above insurance. 5. BARRICADES AND SIGNS. The Contractor shall, at his own expense and without further or other order, provide, erect, and maintain, at all times during the progress and suspension of the work and until completion and final acceptance thereof, suitable and requisite barricades, signs, or other adequate protection, as required by the latest edition of the "Iowa Manual on Uniform Traffic Control Devices for Streets and Highways" and shall provide, keep, and maintain such barricades, signs, etc., as -- may be required or as may be ordered by the City Engineer, to insure the safety of the public as well as those engaged on the work. All barricading plans shall be approved by the City Engineer. 6. ROYALTIES AND PATENTS. The Contractor shall pay all royalties and license fees. He shall defend all suits or claims for infringement of any patent rights and shall save the City harmless from loss on account thereof, except that the City shall be responsible for all such loss when a particular process or the product of a particular manufacturer is specified. 7. PERMITS AND REGULATIONS. Permits and licenses of a temporary nature for the prosecution of the work shall be secured and paid for by the Contractor. Permits, license, and easements for permanent changes in existing facilities shall be secured and paid for by the City. 8. CLAIMS FOR DAMAGES. Any claim for damages arising under this Contract shall be made in writing to the party liable within a reasonable time of the first observance of such damage and no later than the time of final payment, except as expressly stipulated otherwise in the case of faulty work or materials, and shall be adjusted by agreement or arbitration. The Contractor shall be held for the payment of all just claims against him arising out of the prosecution of this contract, and his bond will not be released until such claims are paid for dismissed. 9. ASSIGNMENT OF CONTRACT. The Contractor shall not sell or assign the contract or sublet any portion of the work provided for therein without the written consent of the City Council. GENERAL SPECS GS-11 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF 10. SUBCONTRACTORS. The Contractor shall, as soon as practicable after the signature of the contract, notify the Engineer in writing of the names of the Subcontractors proposed for the work and shall not employ any that the Engineer may, within a reasonable time, object to as incompetent or unfit. The Contractor agrees that he is as fully responsible to the City for the acts and omission of his Subcontractors and of persons either directly or indirectly employed by them as he is for the acts and omissions of persons directly employed by him. Nothing contained in the contract documents shall create any contractual relation between any _ Subcontractor and the City. 11. ARBITRATION. All questions subject to arbitration under this Contract shall be submitted to arbitration at the choice of either party to the dispute. The Contractor shall not cause a delay of the work during any arbitration proceedings, except by agreement with the Engineer. The demand for arbitration shall be filed in writing with the Engineer, in the case of an appeal from his decision, within ten (10) days of its receipt, and in any other case, within a reasonable time after cause thereof, and in no case later than the time of final payment, except as otherwise expressly stipulated in the contract. If the Engineer fails to make a decision within a reasonable time, an appeal to arbitration may be taken as if his decision had been rendered against the part appealing. No one shall be nominated or act as an arbitrator who is in any way financially interested in the contract or in the business affairs of either the City or the Contractor. The general procedure shall conform to the laws of the State of Iowa. Unless otherwise provided by such laws, the parties may agree upon one arbitrator; otherwise, there shall be three--one named in writing by each party to this contract to the other party, and the third chosen by these two arbitrators, or, if they fail to select a third within ten (10) days, then he shall be chosen by the Comptroller of the State of Iowa. Should either party refuse or neglect to supply the arbitrators with any papers or information demanded in writing, the arbitrators are empowered by both parties to proceed ex parte. If there be one arbitrator, his decision shall be binding; if three, the decision of any two shall be binding. Such decision shall be a condition precedent to any right of legal action, and, wherever '— permitted by law, it may be filed in Court to carry it into effect. The arbitrators, if they deem that the case demands it, are authorized to award to the party whose contention is sustained such sums as they shall deem proper for the time, expense, and trouble incident to the appeal, and, if the appeal was taken without reasonable cause, damages for delay, the arbitrators shall fix their own compensation unless otherwise provided by agreement, and shall assess the costs and charges of the arbitration upon either or both parties. The award of the arbitrators must be in writing, and it shall not be open to objections on account of the form of proceeding or the award, unless otherwise provided by the laws of Iowa. In the event of such laws providing on any matter covered by this article otherwise than as hereinbefore specified, the method of procedure throughout and the legal effect of the award shall be wholly in accordance with the laws of the State of Iowa, it being intended hereby to lay down a principle of _ action to be followed, leaving its local application to be adopted to the legal requirements of the place in which the work is to be done. 12. PERFORMANCE AND PAYMENT BONDS. The Contractor shall, at the time of _. execution and delivery of this contract and before the taking effect of same, furnish and deliver to the City GENERAL SPECS GS-12 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF written bonds of indemnity to the amount required by law in form and substance, and with surety thereon satisfactory and acceptable to the City, to insure the faithful performance and payment by the Contractor of all the covenants and agreements on the part of the Contractor contained in this contract. These bonds shall remain in force and effect for the full amount of the Contract. 13. PERSONAL LIABILITY OF PUBLIC OFFICIALS. In carrying out any of the provisions of the Contract or in exercising any power or authority granted him thereby, there shall be no liability upon the Engineer or his authorized assistants, either personally or as an official of the City, it being understood that in such matters he acts as the agent and representative of the City. 14. JURISDICTION. Any action in Court against the Contractor or sureties on his bond because of damages to property or individuals by said Contractor or his workmen, or because of the violation of any provisions of the specifications, or on account of the failure of said Contractor to comply fully with these provisions, shall be brought in the District Court of the State of Iowa in and for Black Hawk County. 15. TERMINATION OF RESPONSIBILITY. The Contract shall be considered as completed and the Contractor released from further obligations except as to the requirements of his bond, after the work has been completed and finally accepted and final estimates have been allowed and the completion report of the engineer has been filed and approved by the Council. 16. CITY'S LEGAL RIGHTS. The City shall not be precluded by any measurements, estimate, or certificate made, either before or after the completion and acceptance of the work and — payment therefor, from showing the true amount and character of the work performed and materials furnished by the Contractor, or from showing that any such measurement, estimate, or certificate is untrue or incorrectly made, or the work or materials do not, in fact, conform to the Contract. The City shall not be precluded, notwithstanding any such measurements, estimate, or certificate and payment in accordance therewith, from recovering from the Contractor and his surety such damages as it may sustain by reason of his failure to comply with the terms of the Contract. Neither the acceptance by the City or any of its representatives, nor any payment for or acceptance of the whole or any part of the work, nor any extension of time, nor any possession taken by the City, shall operate as a waiver on any portion of the contract or of any power herein reserved, or any right to damages herein provided. A waiver of any breach of the contract shall not be held to be a waiver of any other or subsequent breach. * * * END OF GENERAL SPECIFICATIONS FOR CONSTRUCTION * * " GENERAL SPECS GS-13 of 13 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF SUPPLEMENTAL GENERAL SPECIFICATIONS FOR CONSTRUCTION 1. SUBCONTRACTS The contractor shall cause appropriate provisions to be inserted in all subcontracts relative to the work to require compliance by each subcontractor with the applicable provisions of the contract for the improvements embraced in this contract. 2. REVIEW BY THE CITY OF WATERLOO The City of Waterloo, its authorized representatives and agents, shall at all times have access to and be permitted to observe and review all work, materials, equipment, payrolls, personnel records, employment conditions, material invoices, and other relevant data and records pertaining to this contract, provided, however, that all instructions and approval with respect to the work will be given to the contractor only by the City of Waterloo through its authorized representative or agents. 3. INSPECTION a. The contractor shall furnish promptly all materials reasonably necessary for any tests, which may be required. All tests by the City of Waterloo will be performed in such manner as not to delay the work unnecessarily and will be made in accordance with the provisions of the Technical Specifications. b. Inspection of materials and appurtenances to be incorporated in the improvements _ embraced in this contract may be made at the place of production, manufacture or shipment, whenever the quantity justifies it, and such inspection and acceptance, unless otherwise stated in the Technical Specifications, shall be final, except as regards (1) latent defects, (2) departures from specific requirements of the contract, (3) damage or loss in transit, or (4) fraud or such gross mistakes as amount to fraud. Subject to the requirements contained in the preceding sentence, the inspection of materials as a whole or in part will be made at the project site. 4. WARRANTY OF TITLE No material, supplies, or equipment to be installed or furnished under this contract shall be purchased subject to any chattel mortgage or under a conditional sale, lease-purchase or other agreement by which an interest therein or in any part thereof is retained by the seller or supplier. The contractor shall warrant good title to all materials, supplies, and equipment installed or incorporated in the work and upon completion of all work, shall deliver the same together with all improvements and appurtenances constructed or placed thereon by him to the City of Waterloo free from any claims, liens, or charges. Neither the contractor nor any person, firm or corporation furnishing any material or labor for any work covered by this contract shall have any right to a lien upon any improvement or appurtenance thereon. Nothing contained in this paragraph, however, shall defeat or impair the right of persons furnishing materials or labor to recover under any bond given by the contractor for their protection or any rights under any law permitting such persons to look to funds due the contractor in the hands of the City of Waterloo. The provisions of this paragraph shall be inserted in all subcontracts and material contracts and notice of its provisions shall be given to all persons furnishing materials for the work when no formal contract is entered into for such materials. *** END OF SUPPLEMENTAL GENERAL SPECIFICATIONS ' SUPPLEMENTAL GENERAL SPECIFICATIONS SGS-1 of 1 Flow Equalization Facility — AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF FORM OF CONTRACT CONTRACT FOR THE CONSTRUCTION OF FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF CITY OF WATERLOO, IOWA CONTRACT NO.880 This contract made and entered into this day of , 20_, by and between the City of Waterloo, Iowa, a Municipal Corporation , (hereinafter referred to as City), and of , (hereinafter referred to as Contractor), WITNESSETH: PAR. 1 Contractor agrees to build and construct the and furnish all necessary tools, equipment, materials, and labor necessary to do all the work called for in the plans and specifications in a workmanshiplike manner and for the prices set forth in Contractor's proposal, which was accepted by the City, and which is understood and agreed to be a part of this contract. PAR. 2 It is understood and agreed that the resolution adopted by the City Council ordering the construction of the improvement, the Notice to Contractors as published, the Instruction to Bidders, the Form of Proposal, the Construction and Maintenance Bonds, the Council Proceedings relating to this matter, and the Plans and Specifications shall all be considered as forming a part of the contract the same as though they were each set out in said contract. PAR. 3 The Contractor agrees to furnish at its own cost and expense, all necessary materials and labor for said work and to construct said improvements in a thorough, substantial, and workmanlike manner, and in strict accordance with the requirements of this contract, and of the plans and specifications made a part hereof by reference, and to the satisfaction and approval of the City and its engineer. PAR. 4 The Contractor agrees to perform said work and install said improvements on the terms set out in bid or proposal to the City which has been accepted by the City and which is by reference made a part of this contract. PAR. 5 The Contractor agrees to commence said work within ten (10) working days after receipt of "Notice to Proceed" and complete it on or before , 20_, unless an extension of time is granted in writing by the Council of the City. PAR. 6 Should the Contractor fail to complete said improvements in strict accordance with the terms and conditions of this contract, or the plans and specifications therefor promptly by the date herein specified, the City may pay such additional sums as it may be required to pay by reason of the failure of said contractor and deduct any and all such sums from any amount then due the Contractor. FORM OF CONTRACT C-1 of 4 Flow Eugalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF PAR. 7 The Contractor agrees to comply with and obey all ordinances of the City of Waterloo, Iowa, relating to the obstruction of streets and alleys, keeping open passage ways for water, traffic, and protecting any excavations in any street or alley, and maintaining proper and sufficient barricades with lights and signals during all hours of darkness, to see that the backfilling is properly done, and agrees to keep the City whole and defend any and all suits that may be brought against the City by reason of any injuries that may be sustained by any person or property allegedly caused by the Contractor, or his agents, while work is done pursuant to this agreement. PAR. 8 The Contractor agrees that in the event a law suit is brought against the City for damages allegedly sustained by reason of any act, omission or negligence of the Contractor or its — agents, or on account of any injuries allegedly sustained by reason of any obstruction, hole, depression or barrier placed or dug by the defendant or its agents, in the doing of the work herein contracted for, that it will defend said suit and save the City harmless therein, and in case judgment is rendered against the City, the Contractor agrees to pay the same promptly. The Contractor agrees to carry public liability insurance in a solvent company in a sufficient amount to protect the City and those who use the streets of the City. PAR. 9 The City shall have the right to appoint one or more construction reviewers who shall review the progress of the work in detail; also, to make any test or any material to be used in such work. No material shall be used in any work until the same has first been approved by the construction reviewer. Such construction reviewer shall have full authority to pass judgment — upon all materials and upon the manner of doing the work, and their judgment on rejecting any materials, substance, or manner of work shall be final unless it is revoked or modified by the City Engineer. PAR. 10 Any material, which has been rejected by the construction reviewer, shall be at once removed from the line of work and shall not be again taken thereon or placed with the material proposed to be used without the written consent of the City Engineer. — PAR. 11 The Contractor shall maintain no cause of action against the City on account of delays and prosecution of work, but if said work is delayed by the City, the Contractor shall have such extra time for completion of the job as was lost by reason of the delay caused by the City. PAR. 12 The Contractor agrees to pay punctually all just claims of labor, material, men, or subcontractors who shall perform labor or furnish materials entering into this improvement. It is agreed that the City need not pay the Contractor until all such claims are paid by the Contractor. It is agreed that the City shall not be liable for said labor, material, or men under this contract. PAR. 13 The Contractor agrees to furnish the City, simultaneously with this contract, a bond on a form to be provided by the City in the amount provided by law as stated in the Notice to Bidders, which shall be for the benefit of the City, and any and all persons injured by the breach of any of the terms of this contract. Said bond shall be filed with the City Clerk and — shall be subject to the approval of the City Council, and is by reference made a part of this contract. PAR. 14 The Contractor agrees that should it abandon work under this contract or cease the prosecution thereof for a period of thirty (30) consecutive days without reasonable cause, and should it fail to proceed with said work within ten (10) days after a notice to continue or carry it on has been mailed to it at the address given herein by the City, or after such notice has been served on it, then the City may proceed to complete said work, using any material, FORM OF CONTRACT C-2 of 4 Flow Euqalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF tools, or machinery found along said line of work, doing the work either by contract or as it may elect, and the Contractor and the sureties on its bond shall be liable to the City for the costs and expenses so paid out. Said costs shall be retained by the City from any compensation due, or to become due the Contractor, and may be recovered by the City in an action upon Contractor's bond. PAR. 15 In consideration of the full compliance on the part of the Contractor with all the provisions, stipulations, and conditions hereof, or contained in the various instruments made a part of this contract by reference, and upon completion and acceptance of said work, the City agrees to pay to the Contractor, in the manner set out in the Notice to Contractors, the amount of money due the Contractor for work performed and accepted, at the unit prices set out in the Contractor's proposal, which has been accepted by the City. PAR. 16 The total amount of the contract, based on the Engineer's estimates of quantities and the Contractor's unit bid prices, and for which 100% surety bond is required is PAR. 17 After the completion of said work, the Contractor agrees to remove all debris and clean up said streets, and to save the City harmless from any damage allegedly resulting from a failure to clean up and remove the debris or put the street back in a proper condition for travel. PAR. 18 This contract is not divisible, but in the event of a conflict between this contract and the various instruments incorporated by reference, this contract shall govern. PAR. 19 Before the Contractor shall be entitled to receive final payment for work done under this contract, it shall execute and file a bond in the penal sum of not less than 100% of the total amount of the contract, same to be known as"Maintenance Bond,"and which bond must be approved by the City Council, and which bond is in addition to the bond given by the Contractor to guarantee the completion of the work. PAR. 20 The Contractor shall maintain all work done hereunder in good order for the period of two(2) years from and after the date it is accepted by the Council of the City of Waterloo, Iowa. _ Said maintenance shall be made without expense to the City or the abutting property. In the event of the failure or default of the Contractor to remedy any or all defects appearing in said work within a period of two (2) years from the date of its acceptance by said Council, and after having been given ten (10) days notice so to do by registered letter deposited in the _ United States Post Office in said town, addressed to said contractor at the address herein given, then the City may proceed to remedy such defects. The costs and expenses thereof to be recovered from the Contractor and the sureties on its maintenance bond by an action brought in any court of competent jurisdiction. PAR. 21 The Contractor shall give notice to said City by registered letter directed to the Mayor or City Clerk/Auditor thereof not more than four (4) and not less than three (3) months prior to the expiration of the term during which the Contractor is required to maintain said improvements, in good repair by the terms of its Contract. The liability of the Contractor and of the sureties on its bond for maintenance of the said improvements shall continue until three (3) months after such notice has been given to the City, and, in any event, until two (2) years after the acceptance of the work. FORM OF CONTRACT C-3 of 4 Flow Euqalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF CITY OF WATERLOO, IOWA Mayor City Clerk Contractor BY: Title: Approved by the City Council of the City of Waterloo, Iowa,this day of , 20_. ATTEST: , City Clerk Waterloo, Iowa FORM OF CONTRACT C-4 of 4 Flow Euqalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF PERFORMANCE BOND KNOW ALL MEN BY THESE PRESENTS: That we, _ of (the"Principal"), and of (the"Surety"), are held and firmly bound unto the City of Waterloo, Iowa(the "Obligee"), in the penal sum of Dollars ($ ), lawful money of the United States,for the payment of said sum in connection with a contract(the"Contract")dated on or about for the purpose of . The Contract is incorporated herein by reference as though fully set forth herein. _ Whenever the Principal shall be and is declared by the Obligee to be in default under the Contract, with the Obligee having performed its obligations in the Contract, then the Surety, acknowledging that time is of the essence, may promptly remedy the default, or shall promptly undertake to: 1. Complete the Contract in accordance with its terms and conditions; or 2. Obtain one or more bids for completing the Contract in accordance with its terms and conditions, and upon determination by the Surety of the lowest responsible bidder, or negotiated proposal, or, if the Obligee elects, upon determination by the Obligee and the Surety jointly of the lowest responsible bidder, or negotiated proposal, arrange for a contract between such party and the Obligee. The Surety will make available as work progresses sufficient funds to pay the cost of completion less the balance of the Contract price. The cost of completion includes responsibilities of the Principal for correction of defective work and completion of the Contract, the Obligee's legal and design professional costs resulting directly from the Principal's default, and liquidated damages or actual damages if no liquidated damages are specified in the Contract. The term "balance of the Contract price" - - means the total amount payable by the Obligee to the Principal under the Contract and any amendments thereto, less the amount properly paid by the Obligee to the Principal; or 3. Determine the amount for which it is liable to the Obligee and pay the Obligee that amount as soon as practicable. In the event this bond is enforced, Principal and Surety agree to indemnify Obligee and hold Obligee harmless from and against any and all costs of enforcement, including but not limited to reasonable attorneys' fees and expenses. Every Surety on this bond shall be deemed and held, any contract to the contrary notwithstanding, to consent to each and all of the following matters,without notice: 1. To any extension of time to the Contract in which to perform the Contract. 2. To any change in the plans, specifications, or Contract when such change does not involve an increase of more than twenty percent (20%) of the total Contract price, and shall then be released only as to such excess increase. 3. That no provision of this bond or of any other contract shall be valid which limits to less than one (1) year from the time of the acceptance of the work the right to sue on this bond for defect in workmanship or material not discovered or known to the Obligee at the time such work was accepted. If the Principal performs the Contract, then this bond shall be null and void; otherwise it shall remain in full force and effect. In no event shall the Surety's total obligation exceed the penal amount of this bond. Performance Bond PFB-1 of 2 Flow Equalization Facility — AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF Terms used herein shall include, as appropriate, the singular or plural number, or the masculine, feminine or neuter gender. IN WITNESS WHEREOF,the undersigned Principal and Surety have executed this Performance Bond as of_ PRINCIPAL SURETY Name Name By: By: Title: Title: [attach Power of Attorney] NOTE: Date of BOND must not be prior to date of Contract.If CONTRACTOR is Partnership, all partners should execute BOND. If this project includes Federal Funds the following applies to the payment bond: IMPORTANT: Surety companies executing bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State where the project is located. Performance Bond PFB-2 of 2 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF PAYMENT BOND KNOW ALL MEN BY THESE PRESENTS: that (Name of Contractor) (Address of Contractor) a , hereinafter called Principal, (Corporation, Partnership or Individual) and, (Name of Surety) (Address of Surety) hereinafter called Surety, are held and firmly bound unto — (Name of Owner) (Address of Owner) hereinafter called OWNER, in the penal sum of Dollars,($ ) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, successors, and assigns, jointly and severally, firmly by these presents. THE CONDITION OF THIS OBLIGATION is such that whereas, the Principal entered into a certain contract with the OWNER, dated the day of , 20 _, a copy of which is hereto attached and made a part hereof for the construction of: FLOW EQUALIZATION FACILITY OVERFLOW CONNECTION TO SATELLITE WPCF CITY OF WATERLOO, IOWA CITY CONTRACT NO. 880 NOW, THEREFORE, if the Principal shall promptly make payment to all persons, firms, SUBCONTRACTORS, and corporations furnishing materials for or performing labor in the prosecution of the WORK provided for in such contract, and any authorized extension or modification thereof, including all amounts due for materials, lubricants, oil, gasoline, coal and coke, repairs on machinery, equipment and tools, consumed or used in connection with the construction of such WORK, and all insurance premiums on said WORK, and for all labor, performed in such WORK whether by SUBCONTRACTOR or otherwise, then this obligation shall be void; otherwise to remain in full force and effect. PROVIDED, FURTHER, that the said Surety for value received hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the contract or to the WORK to be performed thereunder or the SPECIFICATIONS accompanying the same shall in any wise affect its obligation on this BOND, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the contract or to the WORK or to the SPECIFICATIONS. PAYMENT BOND PB-1 of 2 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF PROVIDED, FURTHER, that no final settlement between the OWNER and the CONTRACTOR shall abridge the right of any beneficiary hereunder, whose claim may be unsatisfied. IN WITNESS HEREOF, this instrument is executed in counterparts, each one of which — (number) shall be deemed an original, this the day of , 20_. _ ATTEST: Principal (Principal) Secretary (SEAL) By (s) _ (Address) Witness as to Principal (Address) Surety ATTEST: Attorney-in-Fact Witness as to Surety (Address) (Address) (Address) NOTE: Date of BOND must not be prior to date of Contract. If CONTRACTOR is Partnership, all partners should execute BOND. If this project includes.Federal Funds,the following applies to the payment bond: "- IMPORTANT: Surety companies executing bonds must appear on the Treasury Department's most current list (Circular 570 as amended) and be authorized to transact business in the State where the project is located. PAYMENT BOND PB-2 of 2 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF APPENDIX 1. CHANGE ORDER FORM 2. DAVIS-BACON WAGE RATES AND FORMS A. Davis-Bacon Wage Rates B. Form WH-347 Payroll and Certification C. Form SF-1444 Request for Authorization of Addi.ional Classification and Rate D. Form WH-321 Notice Poster CHANGE ORDER NO. Owner Date Project Owner's Contract No. Contractor Date of Contract Start $ You are directed to make the following changes in the Contract Documents. Description: Reason for Change Order: CONTRACT PRICE CONTRACT TIMES (Calendar Days) To substantial To final completion completion Original: $ Original Completion Date: Previous C.O.'s(ADD/DEDUCT): $ Previous CIO's(ADD/DEDUCT): This C.O.(ADD/DEDUCT): $ This C.O. (ADD/DEDUCT): Contract Price with all REVISED: approved Change Orders: $ Revised Completion Date: It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s)ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. APPROVED: By: OWNER(Authorized Signature) Date ACCEPTED: By: CONTRACTOR(Authorized Signature) Date AECOM 60336756 / Project Change Number Order No CHANGE ORDER FORM CO-1 Flow Equalization Facility AECOM 60336756-2017 City Contract No.880 Overflow Connection to Satellite WPCF General Decision Number: IA170004 07/28/2017 IA4 Superseded General Decision Number: IA20160004 State: Iowa Construction Type: Heavy Sewer/Water Treating Plant .. Counties: Iowa Statewide. EXCEPT SCOTT COUNTY 06.0 SEWER AND WATER TREATMENT PLANTS ONLY Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.20 for calendar year 2017 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.20 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2017. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts. Modification Number Publication Date 0 01/06/2017 1 06/30/2017 2 07/28/2017 * SUTA2002-004 12/01/2014 .{ Rates Fringes Carpenters (ALL OF THE STATE OF IOWA, except the named cities and counties listed below: ) $ 24 .05 14.29 Carpenters (BURLINGTON AND KEOKUK) $ 27 . 83 16.29 Carpenters (CLINTON COUNTY, City of Clinton) $ 27.83 16.29 Carpenters (CLINTON, DUBUQUE, ,,,y JOHNSON, LOUISA, MUSCATNE, DES MOINES, CEDAR and LEE COUNTIES, Except any of the previously named cities) $ 24.05 14.29 Carpenters (COUNCIL BLUFFS) $ 31.98 12.13 11 Carpenters (DUBUQUE COUNTY (City of Dubuque) ) $ 27.83 16.29 Carpenters (FORT MADISON) $ 27.83 16.29 Carpenters (IOWA CITY) $ 27.83 16.29 Carpenters (LINN COUNTY) $ 31.68 16.29 Carpenters (MUSCATINE COUNTY, City of Muscatine) $ 27.83 16.29 Carpenters (POLK COUNTY) $ 35.84 12.13 Carpenters (SIOUX CITY) $ 31.98 12.13 Carpenters (WATERLOO/CEDAR FALLS) $ 27.83 16.29 Cement mason (ALL OF THE L. STATE OF IOWA, except for the named cities and couties listed below: ) $ 25.66 9.05 Cement mason (BURLINGTON AND KEOKUK) $ 34 .02 10.05 Cement mason (CLINTON COUNTY, City of Clinton) $ 34.02 10.05 Cement mason (CLINTON, DUBUQUE, JOHNSON, LOUISA, MUSCATINE, DES MOINES, CEDAR and LEE COUNTIES, Except any of the previously named cities) $ 27.01 10.05 Cement mason (COUNCIL BLUFFS) $ 31.98 10.05 L. Cement mason (DUBUQUE COUNTY (City of Dubuque) ) $ 34.02 10.05 L. Cement mason (FORT MADISON) $ 32.58 10.05 Cement mason (IOWA CITY) $ 34.02 10.05 Cement mason (LINN COUNTY) $ 34.02 10.05 Cement mason (MUSCATINE COUNTY) $ 34.02 10.05 Cement mason (POLK COUNTY) $ 32.58 10.05 i Cement mason (SIOUX CITY) $ 31.31 10.05 Cement mason (WATERLOO/CEDAR FALLS) $ 28.81 10.05 tom IRONWORKER (ALL OF THE STATE OF IOWA, except for the named cities or counties listed below: ) $ 23.75 16.37 IRONWORKER (BURLINGTON AND KEOKUK) $ 28 .58 16.37 IRONWORKER (CLINTON COUNTY, City of Clinton) $ 35.04 16.37 IRONWORKER (CLINTON, DUBUQUE, .-k JOHNSON, LOUISA, MUSCATINE, DES MOINES, CEDAR and LEE COUNTIES, Except any of the previously named cities) $ 23.75 16.37 IRONWORKER (COUNCIL BLUFFS) $ 24.15 16.37 IRONWORKER (DUBUQUE COUNTY '7 (City of Dubuque) ) $ 27.53 16.37 IRONWORKER (FORT MADISON) $ 28.58 16.37 IRONWORKER (IOWA CITY) $ 27.53 16.37 IRONWORKER (LINN COUNTY) $ 27.53 16.37 IRONWORKER (MUSCATINE COUNTY) $ 35.04 16.37 IRONWORKER (POLK COUNTY) $ 27.37 16.37 IRONWORKER (SIOUX CITY) $ 18.57 16.37 .-r IRONWORKER (WATERLOO/CEDAR FALLS) $ 27.53 16.37 LABORERS (ALL OF THE STATE OF .., IOWA, except for the named cities and counties listed below: ) $ 23.28 8.60 LABORERS (BURLINGTON AND KEOKUK) $ 28.85 8.60 LABORERS (CLINTON COUNTY, rAl City of Clinton) $ 28.49 8.60 LABORERS (CLINTON, DUUQUE, JOHNSON, LOUISA, MUSCATINE, DES MOINES, CEDAR and LEE COUNTIES, Except any of the previously named cities) $ 25.27 8.60 LABORERS (COUNCIL BLUFFS) $ 25.51 8.60 LABORERS (DUBUQUE COUNTY (City of Dubuque) ) $ 25.41 8. 60 LABORERS (FORT MADISON) $ 28.85 8. 60 LABORERS (IOWA CITY) $ 27.98 8. 60 LABORERS (LINN COUNTY) $ 29. 61 8. 60 LABORERS (MUSCATINE COUNTY (City of Muscatine) ) $ 28.98 8.60 LABORERS (POLK COUNTY) $ 29.45 8. 60 LABORERS (SIOUX CITY) $ 25.63 8. 60 LABORERS (WATERLOO/CEDAR FALLS) $ 25.63 8. 60 OPERATOR: Power Equipment (POLK, WARREN, DALLAS, STORY & JASPER COUNTIES) SEWER L Class A $ 34.20 13.80 Class B $ 32.50 13.80 Class C $ 30.31 13.80 WATER Class A $ 33.93 13.80 Class B $ 32.23 13.80 Class C $ 29.85 13.80 Power Equipment Operator (ALL OF THE STATE OF IOWA, except for the named cities and 6. counties listed below: ) Class A $ 34.20 13.80 Class B $ 32.50 13.80 j Class C $ 30.31 13.80 L Power Equipment Operator (BURLINGTON AND KEOKUK) Class A $ 32.50 29.95 L. Class B $ 29.75 29.95 Power Equipment Operator (CLINTON COUNTY, City of ~" Clinton) Class A $ 32.50 29.95 Class B $ 29.75 29.95 Power Equipment Operator (CLINTON, LOUISA, MUSCATINE, ! DES MOINES, CEDAR and LEE COUNTIES, Except any of the previously named cities) Class A $ 32.50 29.95 L Class B $ 29.75 29.95 L '1 Power Equipment Operator +1 (COUNCIL BLUFFS) SEWER Class A $ 34.20 13.80 Class B $ 32.50 13.80 Class C $ 30.31 13.80 WATER Class A $ 33.93 13.80 Class B $ 32.23 13.80 Class C $ 29.85 13.80 Power Equipment Operator (DUBUQUE COUNTY (Including City of Dubuque) and JOHNSON COUNTY) SEWER -1 Class A $ 34.20 13.80 Class B $ 32.50 13.80 Class C $ 30.31 13.80 WATER Class A $ 33.93 13.80 Class B $ 32.23 13.80 Class C $ 29.85 13.80 Power Equipment Operator (FORT MADISON) Class A $ 32.50 29.95 .1 Class B $ 29.75 29.95 Power Equipment Operator (IOWA CITY) SEWER Class A $ 34.20 13.80 Class B $ 32.50 13.80 Class C $ 30.31 13.80 .1 WATER Class A $ 33.93 13.80 Class B $ 32.23 13.80 ,.., Class C $ 29.85 13.80 Power Equipment Operator (LINN COUNTY) SEWER Class A $ 34.20 13.80 Class B $ 32.50 13.80 Class C $ 30.31 13.80 r1 WATER Class B $ 32.23 13.80 Class C $ 29.85 13.80 .1 Power Equipment Operator (MUSCATINE COUNTY) Class A $ 32.50 29.95 .., Class B $ 29.75 29.95 Power Equipment Operator (SIOUX CITY) L L. SEWER Class A $ 34.20 13.80 Class B $ 32.50 13.80 Class C $ 30.31 13.80Lw WATER Class A $ 33.93 13.80 Class B $ 32.23 13.80 Class C $ 29.85 13.80 Power Equipment Operator (WATERLOO/CEDAR FALLS) V. SEWER Class A $ 34.20 13.80 Class B $ 32.50 13.80 L. Class C $ 30.31 13.80 WATER Class A $ 33.93 13.80 Class B $ 32.23 13.80 L. Class C $ 29.85 13.80 Truck drivers (ALL OF THE STATE OF IOWA, except for the 6. named cities and counties listed below: ) $ 21.66 10.50 Truck drivers (BURLINGTON AND KEOKUK) $ 24.59 10.50 Truck drivers (CLINTON COUNTY, City of Clinton) $ 25.03 10.50 Truck drivers (CLINTON, DUBUQUE, JOHNSON, LOUISA, MUSCATINE, DES MOINES, CEDAR6. and LEE COUNTIES, Except any of the previously named cities) $ 22.76 10.50 Truck drivers (COUNCIL BLUFFS) $ 25.68 10.50 Truck drivers (DUBUQUE COUNTY `,,, (City of Dubuque) ) $ 24.06 10.50 Truck drivers (FORT MADISON) $ 24.59 10.50 L Truck drivers (IOWA CITY) $ 26.34 10.50 Truck drivers (LINN COUNTY) $ 27.10 10.50 L Truck drivers (MUSCATINE COUNTY) $ 24.59 10.50 Truck drivers (POLK COUNTY) $ 25. 68 10.50 Truck drivers (SIOUX CITY) $ 23.28 10.50 L L Truck drivers (WATERLOO/CEDAR L L. FALLS) $ 24.21 10.50 AA POWER EQUIPMENT OPERATOR CLASSIFICATIONS CLASS A: Asphalt laydown machine, Asphalt Plant Operator, Asphalt heater-planer unit, Backhoe, Bulldozer, Central Mix Plant, Concrete Pump, Crawler Tractor Pulling Scraper, Dredge Engineer, Dredge Leverman, Front-end Loader (over 2 yds) , Group Equipment Greaser (unsupervised) , Horizontal AA boring machine, Master Mechanic, Milling Machine, Motor Patrol, Porland Concrete Paver, Power Shovel, Crane & Dragline, Pushcat, Scraper (10 yards & over or finish) , Self-propelled Elevation Grader or Similar Machine, Sideboom Tractor, Subgrader (or equivalent) , Tow Push Boat or Work Boat, Trenching Machine (Cleveland 80 or similar capacity) . Al CLASS B: Asphalt Distributor, Asphalt Finish Roller, Asphalt Screed, Belt Loader or Similar Machine, Bullfloat, Churn or Rotary Drill, Concrete Widening Machine, Concrete Curbing Al Machine, Conveyor, Crawler Tractor - Pulling ripper, Disc, Sheepsfoot or Roller, Deckhand/Oiler, Finishing Machine (on concrete) , Flex-plane, forklift, Form Grader, Front-end Loader (under 2 yeards) , Group greaser (supervised) , Haiss loader or similar, Mechanic-welder, Offroad articulated hauler, Paving breaker pumps (over 3") , Screening & wash plant, Skid loader, Spreader Operator, Self-propell Roller AA (other than asphalt) , Self-propelled vibrating compactor, shoulder machine, Trenching Machine (other than above) , Water wagon on compaction. CLASS C: Asphalt Roller (other than finish) , Boiler, Boom & Winch Truck, Compressor, Concrete Spreader, Belt Placer, Farm Type or Utility Tractor with attachments (under 50 hp) , Group Greaser Light plant, Mechanical Broom, Mechanical Heater, Oiler, Pile Hammer Power Unit, Pump (Other than Dredge) , Pumps (3" and under) , Pumps on well points & deep wells for dewatering, Safety Boat, Truck Crane combination Driver Oiler, Welding Machine. FOOTNOTE: ""1 IRONWORKERS: (Setting of all structural steel and reinforcing steel installation) Al WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental. Note: Executive Order (EO) 13706, Establishing Paid Sick Leave .•, for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide "1 AA employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year. Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a familymember6. (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the SO is available at www.dol.gov/whd/govcontracts. �.. Unlisted classifications needed for work not included within the scope of the classifications listed may be added after 6. award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii) ) . 6. The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type (s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical 6. order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local) , a survey rate (weighted average rate) or a union average rate (weighted union average rate) . Union Rate Identifiers A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or "UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example: PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number `,. where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, L. 2014 . Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate. Survey Rate Identifiers Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average 6. rate based on all the rates reported in the survey for that 6. L s'S classification. As this weighted average rate includes all �-, rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier. Survey wage rates are not updated and remain in effect until a ..7 new survey is conducted. Union Average Rate Identifiers "1 Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 .1 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier. A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based. WAGE DETERMINATION APPEALS PROCESS 1. ) Has there been an initial decision in the matter? This can ..., b e: * an existing published wage determination * a survey underlying a wage determination -n * a Wage and Hour Division letter setting forth a position on a wage determination matter * a conformance (additional classification and rate) ruling On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2. ) and 3. ) should be followed. With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to: 1 6. 66 Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 6. 200 Constitution Avenue, N.W. Washington, DC 20210 `. 2. ) If the answer to the question in 1. ) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7) . Write to: r.. Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W. L Washington, DC 20210 The request should be accompanied by a full statement of the 4 interested party's (w age y position and by any information (wa e payment data, project description, area practice material, etc. ) that the requestor considers relevant to the issue. 3. ) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board) . Write to: 6. Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W. Washington, DC 20210 bm 4. ) All decisions by the Administrative Review Board are final. END OF GENERAL DECISION 1 6. L 6. n LLi 6. 7 cs),—� . Y N �O 0 w "l0 CVEll W u7' � wp w rn w7Q� i a da — Z Qa ooco 0 Qo � ci r�. 0.) O „, o z m._ a) c n OW p rJ_. ZQ Z JO ~U O O ~zpw m a• c o-:,- c 0 UOo Nc)N—0 nt I--` Eaoa ,n w 'o 3 N O C7 N U T wo z oC= O C O H 0 Wes,N O d C = O o— O m d m LL0 m > m o 1 0 W U - oU cn a,7 O 2 0 NW Z N N Y O • N = aL Na ce co_ a 0 c3 'J § E _ p _ p c rn m m ai w c o▪ T > E 0 o oo a,n m o O c N E c cc O• d o,U a o U O m c c a L s • N J _- c O C 113 C O M o =z_.x o.c m E o " 1— E E rc `d Ua co m I c o a sE _ mp — So E °c m o qO <w U a oE c0 S w .o m TO o a la i a,w- Z \\:\ 2 a- L s c �p o� . 0 H �zw y�m'>15 E_ '> 2 g - \\\\\ -,0 >,. E O ., 0 Q w O" a 0 E _ co • N z c m E a -o - 'G• a O w E 'rn y OJ o ~aCL LL • o • �_O i Z 0 m F.` Q m E dm . RJ U) O Ww J 0 mo o_m 1 _ 0 = m Q� � 0 Ho � p a o o cpo 1—= a -, Q 0 2 0 a sVQ S - c c co c 'o d o c3 ° c ma a ' E a+ T N Q m K, • E rs m t _ ci a `oE 0c co) ma O r O m= c_ o a IF., a Q Q LLO cc m O w (.0 N 0 0 OP, wa co 0o z Y N `O ...2 U y y.2 ce 3 0 o c a co a __ D a a O mo m J a 2 f�- 0 U E o u Op o, N u) O« N C t O O O ac § E 1a w = w o 3 m G. 'O 5O 6'ot > o p U, a, E d m D b C 0 p- '1S ao-lO 0 w 0 . 0 V) 0 V, 0 w 0 CO 0 N O N "'�' m s O O a0+ `. z a o v 3 E m u= c.) C co cu Z Z 'o i c'a y c y IL-O vcoi d 9 m o c w a O o c o - M U >O Li `T & C CC >cn 'E' O` o O _OLL Q °m 3?3 m0 C LL 0 Li' = ; 73 o .-. c ` g _ 0 o y CC SNOI1dWOX3 o o 5 O � ON!OlOHH11M 30 n o U 'ON m3 E . ~ o m a o m m ap_ c O w H E a 2 = 1— O 0 E .00 a s c oQ m Ti m o �N .Q U j U Z w m,° o a ,n m CO w C7 c 0 o J •E O ZQ - a 3 o m E LLUw H mt`0. m - Q Q ❑ Z O v� o ) E _ 'NO .O 0 O g c a, = o m o co E > O a H 0 flit fl d N - ca (n O m p0g `o c..n v, no wQ = Z Z Z o M m e U W N c 8 O z H N ci a « ,n p >, LL _, as n w,c m m c O O w U U o E - � W a z O zd °'▪otiE m81E a7-1--N `o c m CC al a. .15 a)- 0 F a_0N K cL C U I-O a)— 0 ) a) am ¢c., L n N N c0... H Z o a).� Oz O 'wow — w a) OU 0 0-0 z w N bp 0 a c P z N c Z 0a N y p w m C 2 3 J mw Wi= gn w ~ Qw N a)U gO NY V U)o_ a C a3 CC• ° O Li, w z a) --c. '5 U m O y 0 0 a) H W F 0 Q 1-0 • E EmE z <vwi U a a3 a) 0 co w • Cr a) Ww as Z %n as 0 >N N c 0z 0 U-_= Q O Tn c6 QO H 0- 2 c% Q w 7 W n U CC O a) " U I—co < E -- 0)ax) 0 ... W cc co O O >i .) °a J CC a)-o T 2 H Z Q LLJ O a w...) 5. Q Z W v_C00 O� • U U ID w 0'C N.L. Z Z a=00 a.. 0 W m_a.E 00U Z V) d ¢_>w LPL 0 w LO¢ 0 X ,°v~i d W Q x 0 w w j "OW 2 0 I- 0z al I- J C W o CC <Y Z 5o,- Q w Uw 2 wm0 �, W < =W C) CC Z F-0 M a); _ — a) a) a) 4- T c V 2 a) a) N a) C .0 S 0 L L. @ C N 0 O 2 a) N o Co E 2- O Y.0 C N ul OU O O N O 7.X C 2 n0 -CD CO 0 0 U a).. o 0 c Y a) 2'm'0 > a) 2 a) co_c c 5 _c C C �� E O 2 2'�C N O 00 6 .0~ m a) cG a)_ 4 _ O >,a t O E o 0 _ o C_ -0 CD a a) E.L rl a)'N a) 0 0 H � L C c4 O N L Co.N O)❑ z a3 O .� n C a) a) - -0 N Y O)m 0 to 2 .0 0 Co o U o -2 E O` `7 O N 2 LL m!= 0 O a) 'O 0 Q 0 U co >, O Co co N-0 N N U a) >,N L(n cn L C m CO ,, a) E N L 4.c NL. -O T O-O Z c0_o 0) co 0) C O-U _ a U 0�) N O Co �'� an Boa a) � o'E a o 003 .� -0 �,-0 L'Q V U 4 U 0 >i co w 2 0 -0.E a) O O C a) a' aS�,L...� UJ O C C O O no 0 0-O Q9O. '6 3 0 •-• L N U CoCC L W. 0o o Y vC m 0) a) aLi o.N E.� a) :0: Q a) E m oo c r5n c S) v Ea) o °)o O mTojIf o a o o -o Qam ` 0 L a n, H 3 a N a)n U a) a) JO 0 C J(0) a) a) Oa) a) 0 >.=0 c a) sn a no = Co cit0E a) E Q oL C c O U) OC•L.. OV °UOa) L N N a) d O T E a) Co N �., O cq @ ° .� O n W L a3 O '5 O - 4 a)L Y9 2 y a3 .E c� a) (DC 2' U 0-a) C C U 0 .L.O 2 C) 0 0 co❑ o_ < .,-O-0 0 O O > 0 -0 U V N 0 >,L — 0 n co c6 c8— a3 ✓ >, ` L• @ as O co I� �.0. a3 O.`L'@•Q ~ a) N LO Co Co c U 0 C a)y CO 0 (D C 0 0- cn ° f .2 a) O O O 0 - a) () N n a) m'— U E-0-0 ca z O N a) Z` L.. U Y O,,. >,>,C .0 0)-0 0 N y N W c w .... Coo Co 0 O_� no-D cn N �.@ O N N2 COm .O > N C o C > 6'D C.0 7n �'L"'C'N a) 0 -0 L O CD m Y Z -0 Co a) •Ci CD a 0) C L >,a)'—c0 Co Co U Y a) 'C L rt a) co E o m c o" ac 'm o� OL nET W .Er. U) E > 77 5 >,-0 c °�co -- coa) �o Toaa) w I co a) co m o n E a�4i N C E o)Co CD `° o. of 0 . — >, E a) Co Co3 CO a) 0 as Co n n.m _ @ a)L a)— aD U 2 C ca L L V) L N-_ 0)— O ca-0 O L cc) 0 a) c6 .0 F 00 3 3 LL H N co H U U N F- a- a) L U ca a) O >«(� a) N U aj M C N V N N O c Y a) 0,- Co a) a) L no a) ENco Con 0-0-16 0 -- '°0 Co a) > co coM U N 0 N<CO REQUEST FOR AUTHORIZATION OF CHECK APPROPRIATE BOX SERVICE CONTRACT OMB No.: 9000-0089 ADDITIONAL CLASSIFICATION AND RATE Expires: 02/28/96 El CONSTRUCTION CONTRACT Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data — sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the FAR Secretariat (VRS),Office of Federal Acquisition Policy, GSA,Washington, DC 20405; and to the Office of Management and Budget, Paperwork Reduction Project (9000-0089), Washington, DC 20503. NOTE: THE CONTRACTOR SHALL COMPLETE ITEMS 3 THROUGH 16 AND SUBMIT THE REQUEST,IN QUADRUPLICATE,TO THE CONTRACTING OFFICER - 1.TO: 2. FROM: (REPORTING OFFICE) ADMINISTRATOR, Employment Standards Administration WAGE AND HOUR DIVISION U.S. DEPARTMENT OF LABOR WASHINGTON,D.C. 20210 — 3. CONTRACTOR 4. DATE OF REQUEST 5. CONTRACT NUMBER 6. DATE BID OPENED(SEALED 7. DATE OF AWARD 8. DATE CONTRACT WORK 9. DATE OPTION EXERCISED(IF BIDDING) STARTED APPLICABLE)(SCA ONLY) - 10. SUBCONTRACTOR(IF ANY) 11. PROJECT AND DESCRIPTION OF WORK (ATTACH ADDITIONAL SHEET IF NEEDED) 12. LOCATION(CITY, COUNTY AND STATE) 13. IN ORDER TO COMPLE IE THE WORK PROVIDED FOR UNDER THE ABOVE CONTRACT,IT IS NECESSARY TO ES IABLISH THE FOLLOWING RATE(S)FOR THE INDICATED CLASSIFICATION(S)NOT INCLUDED IN THE DEPARTMENT OF LABOR DETERMINATION - NUMBER: DATED: a.LIST IN ORDER: PROPOSED CLASSIFICATION TITLES(S);JOB DESCRIPTION(S);DUTIES; b.WAGE RATE(S) c.FRINGE BENEFITS PAYMENTS AND RATIONALE FOR PROPOSED CLASSIFICATIONS(SCA ONLY) (Use reverse or attach additional sheets,if necessary) 14. SIGNATURE AND TITLE OF SUBCONTRACTOR REPRESENTATIVE(IF ANY) 15. SIGNATURE AND TITLE OF PRIME CONTRACTOR REPRESENTATIVE 16. SIGNATURE OF EMPLOYEE OR REPRESENTATIVE TITLE CHECK APPROPR ATE BOX-REFERENCING BLOCK 13. 0 AGREE ❑ DISAGREE TO BE COMPLETED BY CONTRACTING OFFICER (CHECK AS APPROPRIATE- SEE FAR 22.1019 (SCA) OR FAR 22.406-3 (DBA)) 1-1 THE INTERESTED PARTIES AGREE AND THE CONTRACTING OFFICER RECOMMENDS APPROVAL BY THE WAGE AND HOUR DIVISION. AVAILABLE INFORMATION Li AND RECOMMENDATIONS ARE ATTACHED. - El THE INTERESTED PARTIES CANNOT AGREE ON THE PROPOSED CLASSIFICATION AND WAGE RATE. A DETERMINATION OF THE QUESTION BY THE WAGE AND HOUR DIVISION IS THEREFORE REQUESTED. AVAILABLE INFORMATION AND RECOMMENDATIONS ARE ATTACHED. (Send copies 1,2,and 3 to Department of Labor) SIGNATURE OF CONTRACTING OFFICER OR REPRESENTATIVE TITLE AND COMMERCIAL TELEPHONE DATE SUBMITED NO. NSN 7s edition is usable DEPARTMENT OF LABOR STANDARD FORM 1444 (REV. 12-90) Previous ed tion is usable Prescribed by GSA-FAR(48 CFR) 53.222(f) REQUEST FOR AUTHORIZATION OF CHECK APPROPRIATE BOX El SERVICE CONTRACT OMB No.: 9000-0089 ADDITIONAL CLASSIFICATION AND RATE Expires: 02/28/96 _ CONSTRUCTION CONTRACT Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden,to the FAR Secretariat (VRS),Office of Federal Acquisition Policy, GSA,Washington, DC 20405; and to the Office of Management and Budget, Paperwork Reduction Project (9000-0089), Washington, DC 20503. NOTE: THE CONTRACTOR SHALL COMPLETE ITEMS 3 THROUGH 16 AND SUBMIT THE REQUEST,IN QUADRUPLICATE,TO THE CONTRACTING OFFICER 1. TO: 2. FROM: (REPORTING OFFICE) ADMINISTRATOR, Employment Standards Administration WAGE AND HOUR DIVISION U.S. DEPARTMENT OF LABOR WASHINGTON,D.C. 20210 3. CONTRACTOR 4. DATE OF REQUEST 5. CONTRACT NUMBER 6. DATE BID OPENED(SEALED 7. DATE OF AWARD 8. DATE CONTRACT WORK 9. DATE OPTION EXERCISED(IF BIDDING) STARTED APPLICABLE)(SCA ONLY) 10. SUBCONTRACTOR(IF ANY) 11. PROJECT AND DESCRIPTION OF WORK (ATTACH ADDITIONAL SHEET IF NEEDED) 12. LOCATION(CITY, COUNTY AND STATE) 13. IN ORDER—TO COMPLETE 1 HE WORK PROVIDED FOR UNDER 1 HE ABOVE CONTRACT,IT IS NECESSARY TO ESTABLISH THE FOLLOWING RATE(S)FOR 1 HE INDICATED CLASSIFICATION(S)NOT INCLUDED IN THE DEPARTMENT OF LABOR DETERMINATION NUMBER: DATED: a.LIST IN ORDER: PROPOSED CLASSIFICATION TITLES(S);JOB DESCRIPTION(S);DUTIES; b.WAGE RATE(S) c.FRINGE BENEFITS PAYMENTS AND RATIONALE FOR PROPOSED CLASSIFICATIONS(SCA ONLY) (Use reverse or attach additional sheets,if necessary) 14. SIGNATURE AND TITLE OF SUBCONTRACTOR REPRESENTATIVE(IF ANY) 15. SIGNATURE AND TITLE OF PRIME CONTRACTOR REPRESENTATIVE 16. SIGNATURE OF EMPLOYEE OR REPRESENTATIVE TITLE CHECK APPROPRIATE BOX-REFERENCING BLOCK 13. ❑ AGREE ❑ DISAGREE TO BE COMPLETED BY CONTRACTING OFFICER (CHECK AS APPROPRIATE- SEE FAR 22.1019 (SCA) OR FAR 22.406-3 (DBA)) 1-1 THE INTERESTED PARTIES AGREE AND THE CONTRACTING OFFICER RECOMMENDS APPROVAL BY THE WAGE AND HOUR DIVISION. AVAILABLE INFORMATION AND RECOMMENDATIONS ARE ATTACHED. ElTHE INTERESTED PARTIES CANNOT AGREE ON THE PROPOSED CLASSIFICATION AND WAGE RATE. A DETERMINATION OF THE QUESTION BY THE WAGE AND HOUR DIVISION IS THEREFORE REQUESTED. AVAILABLE INFORMATION AND RECOMMENDATIONS ARE ATTACHED. (Send copies 1,2,and 3 to Department of Labor) SIGNATURE OF CONTRACTING OFFICER OR REPRESENTATIVE TITLE AND COMMERCIAL TELEPHONE DATE SUBMITED NO. NSN 7540-01-268-0631 RETURN TO CONTRACTING OFFICER - RECORD COPY STANDARD FORM 1444 (REV. 12-90) Previous edition is usable Prescribed by GSA-FAR(48 CFR) 53.222(f) CHECK APPROPRIATE BOX - REQUEST FOR AUTHORIZATION OF El SERVICE CONTRACT OMB No.: 9000-0089 ADDITIONAL CLASSIFICATION AND RATE Expires: 02/28/96 El CONSTRUCTION CONTRACT Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data - sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden,to the FAR Secretariat (VRS),Office of Federal Acquisition Policy, GSA,Washington, DC 20405; and to the Office of Management and Budget, Paperwork Reduction Project (9000-0089), Washington, DC 20503. NOTE: THE CONTRACTOR SHALL COMPLETE ITEMS 3 THROUGH 16 AND SUBMIT THE REQUEST,IN QUADRUPLICATE,TO THE CONTRACTING OFFICER - 1.TO: 2. FROM: (REPORTING OFFICE) ADMINISTRATOR, Employment Standards Administration WAGE AND HOUR DIVISION U.S. DEPARTMENT OF LABOR WASHINGTON,D.C. 20210 — 3. CONTRACTOR 4. DATE OF REQUEST 5. CONTRACT NUMBER 6. DATE BID OPENED(SEALED 7. DATE OF AWARD 8. DATE CONTRACT WORK 5 DATE OPTION EXERCISED(IF BIDDING) STARTED APPLICABLE)(SCA ONLY) - 10. SUBCONTRACTOR(IF ANY) 11. PROJECT AND DESCRIPTION OF WORK (ATTACH ADDITIONAL SHEET IF NEEDED) 12. LOCATION(CITY, COUNTY AND STATE) 13. IN ORDER TO COMPLETE THE WORK PROVIDED FOR UNDER THE ABOVE CONTRACT,IT IS NECESSARY TO ESTABLISH 1 HE FOLLOWING RATE(S)FOR THE INDICATED CLASSIFICATION(S)NOT INCLUDED IN THE DEPARTMENT OF LABOR DETERMINATION - NUMBER: DATED: a.LIST IN ORDER: PROPOSED CLASSIFICATION TITLES(S);JOB DESCRIPTION(S);DUTIES; b.WAGE RATE(S) c. FRINGE BENEFITS PAYMENTS AND RATIONALE FOR PROPOSED CLASSIFICATIONS(SCA ONLY) (Use reverse or attach additional sheets,if necessary) 14. SIGNATURE AND TITLE OF SUBCONTRACTOR REPRESENTATIVE(IF ANY) 15. SIGNATURE AND TITLE OF PRIME CONTRACTOR REPRESENTATIVE 16. SIGNATURE OF EMPLOYEE OR REPRESENTATIVE TITLE CHECK APPROPRIATE BOX-REFERENCING BLOCK 13. — AGREE ❑ DISAGREE TO BE COMPLETED BY CONTRACTING OFFICER (CHECK AS APPROPRIATE- SEE FAR 22.1019 (SCA) OR FAR 22.406-3 (DBA)) 1-1 THE INTERESTED PARTIES AGREE AND THE CONTRACTING OFFICER RECOMMENDS APPROVAL BY THE WAGE AND HOUR DIVISION. AVAILABLE INFORMATION LI AND RECOMMENDATIONS ARE ATTACHED. THE INTERESTED PARTIES CANNOT AGREE ON THE PROPOSED CLASSIFICATION AND WAGE RATE. A DETERMINATION OF THE QUESTION BY THE WAGE AND HOUR DIVISION IS THEREFORE REQUESTED. AVAILABLE INFORMATION AND RECOMMENDATIONS ARE ATTACHED. (Send copies 1,2,and 3 to Department of Labor) SIGNATURE OF CONTRACTING OFFICER OR REPRESENTATIVE TITLE AND COMMERCIAL TELEPHONE 'DATE SUBMITED — NO. NSN 7540-01-268-0631 L{.`` n r c,V STANDARD FORM 1444 (REV. 12-90) Previous edition is usable Prescribed by GSA-FAR(48 CFR) 53.222(f) REQUEST FOR AUTHORIZATION OF CHECK APPROPRIATE BOX OMB No.: 9000-0089 SERVICE CONTRACT ADDITIONAL CLASSIFICATION AND RATE Expires: 02/28/96 El CONSTRUCTION CONTRACT •••••, Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden,to the FAR Secretariat (VRS),Office of Federal Acquisition Policy, GSA,Washington, DC 20405; and to the Office of Management and Budget, Paperwork Reduction Project (9000-0089), Washington, DC 20503. NOTE: THE CONTRACTOR SHALL COMPLETE ITEMS 3 THROUGH 16 AND SUBMIT THE REQUEST,IN QUADRUPLICATE,TO THE CONTRACTING OFFICER 1.TO: 2. FROM: (REPORTING OFFICE) ADMINISTRATOR, Employment Standards Administration WAGE AND HOUR DIVISION U.S. DEPARTMENT OF LABOR WASHINGTON,D.C. 20210 3. CONTRACTOR 4. DATE OF REQUEST 5. CONTRACT NUMBER 6. DATE BID OPENED(SEALED 7. DATE OF AWARD 8. DATE CONTRACT WORK 9. DATE OPTION EXERCISED(IF BIDDING) STARTED APPLICABLE)(SCA ONLY) 10. SUBCONTRACTOR(IF ANY) 11. PROJECT AND DESCRIPTION OF WORK (ATTACH ADDITIONAL SHEET IF NEEDED) 12. LOCATION(CITY, COUNTY AND STATE) 13. IN ORDER TO COMPLE I E 1 HE WORK PROVIDED FOR UNDER THE ABOVE CON I RACT,I I IS NECESSARY TO ESTABLISH-1 HE FOLLOWING RATE(S)FOR THE INDICATED CLASSIFICATION(S)NOT INCLUDED IN THE DEPARTMENT OF LABOR DETERMINATION NUMBER: DATED: a.LIST IN ORDER: PROPOSED CLASSIFICATION TITLES(S);JOB DESCRIPTION(S);DUTIES; b.WAGE RATE(S) c. FRINGE BENEFITS PAYMENTS AND RATIONALE FOR PROPOSED CLASSIFICATIONS(SCA ONLY) (Use reverse or attach additional sheets,if necessary) 14. SIGNATURE AND TITLE OF SUBCONTRACTOR REPRESENTATIVE(IF ANY) 15. SIGNATURE AND TITLE OF PRIME CONTRACTOR REPRESENTATIVE 16. SIGNATURE OF EMPLOYEE OR REPRESENTATIVE TITLE CHECK APPROPRIATE BOX-REFERENCING BLOCK 13. ❑ AGREE ❑ DISAGREE TO BE COMPLETED BY CONTRACTING OFFICER (CHECK AS APPROPRIATE- SEE FAR 22.1019 (SCA) OR FAR 22.406-3 (DBA)) 1-1 THE INTERESTED PARTIES AGREE AND THE CONTRACTING OFFICER RECOMMENDS APPROVAL BY THE WAGE AND HOUR DIVISION. AVAILABLE INFORMATION "'" LI AND RECOMMENDATIONS ARE ATTACHED. ElTHE INTERESTED PARTIES CANNOT AGREE ON THE PROPOSED CLASSIFICATION AND WAGE RATE. A DETERMINATION OF THE QUESTION BY THE WAGE AND HOUR DIVISION IS THEREFORE REQUESTED. AVAILABLE INFORMATION AND RECOMMENDATIONS ARE ATTACHED. (Send copies 1,2,and 3 to Department of Labor) SIGNATURE OF CONTRACTING OFFICER OR REPRESENTATIVE TITLE AND COMMERCIAL TELEPHONE DATE SUBMITED NO. NSN 7540-01-268-0631 STANDARD FORM 1444 (REV. 12-90) Previous edition is usable Prescribed by GSA-FAR(48 CFR) 53.222(f) CHECK APPROPRIATE BOX REQUEST FOR AUTHORIZATION OF ❑ SERVICE CONTRACT OMB No.: 9000-0089 ADDITIONAL CLASSIFICATION AND RATE Expires: 02/28/96 CONSTRUCTION CONTRACT Public reporting burden for this collection of information is estimated to average 15 minutes per response, including the time for reviewing instructions, searching existing data — sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the FAR Secretariat (VRS),Office of Federal Acquisition Policy, GSA,Washington, DC 20405; and to the Office of Management and Budget, Paperwork Reduction Project (9000-0089), Washington, DC 20503. NOTE: THE CONTRACTOR SHALL COMPLETE ITEMS 3 THROUGH 16 AND SUBMIT THE REQUEST,IN QUADRUPLICATE,TO THE CONTRACTING OFFICER - 1.TO: 2. FROM: (REPORTING OFFICE) ADMINISTRATOR, Employment Standards Administration WAGE AND HOUR DIVISION U.S. DEPARTMENT OF LABOR WASHINGTON,D.C. 20210 3. CONTRACTOR 4. DATE OF REQUEST 5. CONTRACT NUMBER 6. DATE BID OPENED(SEALED 7. DATE OF AWARD 8. DATE CONTRACT WORK I. DATE OPTION EXERCISED(IF BIDDING) STARTED APPLICABLE)(SCA ONLY) - 10. SUBCONTRACTOR(IF ANY) 11. PROJECT AND DESCRIPTION OF WORK (ATTACH ADDITIONAL SHEET IF NEEDED) 12. LOCATION(CITY, COUNTY AND STATE) 13. IN ORDER TO COMPLETE THE WORK PROVIDED FOR UNDER THE ABOVE CON I RACT,IT IS NECESSARY TO ESTABLISH THE I-OLL.OWING RATE(S)FOR THE INDICATED CLASSIFICATION(S)NOT INCLUDED IN THE DEPARTMENT OF LABOR DETERMINATION - NUMBER: DATED: a.LIST IN ORDER: PROPOSED CLASSIFICATION TITLES(S);JOB DESCRIPTIONIS);DUTIES; b. WAGE RATE(S) c. FRINGE BENEFITS PAYMENTS AND RATIONALE FOR PROPOSED CLASSIFICATIONS(SCA ONLY) (Use reverse or attach additional sheets,if necessary) 14. SIGNATURE AND TITLE OF SUBCONTRACTOR REPRESENTATIVE(IF ANY) 15. SIGNATURE AND TITLE OF PRIME CONTRACTOR REPRESENTATIVE 16. SIGNATURE OF EMPLOYEE OR REPRESENTATIVE TITLE CHECK APPROPRIATE BOX-REFERENCING BLOCK 13. ❑ AGREE ❑ DISAGREE TO BE COMPLETED BY CONTRACTING OFFICER (CHECK AS APPROPRIATE- SEE FAR 22.1019 (SCA) OR FAR 22.406-3 (DBA)) 1-1 THE INTERESTED PARTIES AGREE AND THE CONTRACTING OFFICER RECOMMENDS APPROVAL BY THE WAGE AND HOUR DIVISION. AVAILABLE INFORMATION LI AND RECOMMENDATIONS ARE ATTACHED. THE INTERESTED PARTIES CANNOT AGREE ON THE PROPOSED CLASSIFICATION AND WAGE RATE. A DETERMINATION OF THE QUESTION BY THE WAGE AND HOUR DIVISION IS THEREFORE REQUESTED. AVAILABLE INFORMATION AND RECOMMENDATIONS ARE ATTACHED. (Send copies 1,2,and 3 to Department of Labor) SIGNATURE OF CONTRACTING OFFICER OR REPRESENTATIVE TITLE AND COMMERCIAL TELEPHONE DATE SUBMITED NO. NSN 7540-01-268-0631 STANDARD FORM 1444 (REV. 12-90) Previous edition is usable Prescribed by GSA-FAR(48 CFR) 53.222(f) DAVIS-BACON ACT EMPLOYEE RIGHTS UNDER THE FOR LABORERS AND MECHANICS EMPLOYED ON FEDERAL OR FEDERALLY ASSISTED CONSTRUCTION PROJECTS THE UNITED STATES DEPARTMENT OF LABOR WAGE AND HOUR DIVISION -� PREVAILING You must be paid not less than the wage rate listed in the Davis-Bacon WAGES Wage Decision posted with this Notice for the work you perform. OVERTIME You must be paid not less than one and one-half times your basic rate of pay for all hours worked over 40 in a work week.There are few exceptions. ENFORCEMENT Contract payments can be withheld to ensure workers receive wages and overtime pay due,and liquidated damages may apply if overtime pay requirements are not met. Davis-Bacon contract clauses allow contract termination and debarment of contractors from future federal contracts for up to three years. A contractor who falsifies certified payroll records or induces wage kickbacks may be subject to civil or criminal prosecution,fines and/or imprisonment. APPRENTICES Apprentice rates apply only to apprentices properly registered under approved Federal or State apprenticeship programs. PROPER PAY If you do not receive proper pay, or require further information on the applicable wages, contact the Contracting Officer listed below: or contact the U.S. Department of Labor's Wage and Hour Division. For additional information: 1 -866-4-USWAGE MIND U.S.Wage and Hour Division (1-866-487-9243) 1 1 Y: 1-877-889-5627 S TATLS p4 l" VVWW.WAGEHOUR.DOL.GOV U.S.Department of Labor I Employment Standards Administration I Wage and Hour Division WH 1321 Revised,Aprii 2202)