HomeMy WebLinkAboutPR #1 Grease Interceptor RelocationPROPOSAL REQUEST
Please submit itemized pricing for the work associated with each item/option described below. Within
seven (7) days submit this proposal to INVISION. Proposal to include purchase, delivery and installation.
Power will be provided at each installation location by a separate contract.
DESCRIPTION
The contractor shall provide a price or no cost change for the following:
1. Relocate the grease interceptor to the dock as indicated on the supplemental drawing.
2. Provide 2 layers of 2” rigid insulation on all sides of the grease interceptor.
3. Coordinate all flow lines and proper depths prior to installing the grease interceptor.
RFI’S/ASI’S None
ATTACHMENTS (1) Drawing
CONTRACTOR RESPONSE
Provide the following information with back up documentation for review by the Architect and Owner.
Net amount of this proposal: Add $
(Provide pricing breakdown on separate sheet(s)-include material and labor costs with sub-contractor and
supplier costs)
CONTRACTOR SIGNATURE
PROJECT 5 Sullivan Brother Kitchen Renovation PROJECT #16021
OWNER City of Waterloo DATE 1.8.2020
CONTRACTOR Henkel PR #1
ARCHITECT INVISION
By
Name
Date
ARCHITECT REVIEW OWNER APPROVAL
Recommend Acceptance Approve
Do Not Recommend Acceptance Reject
Other Other
By By
Name Name
Date Date
GI-1
6
4" SS
4" SS
3" V UP
4" SS
CO
3" V
SAMPLE PORT
EX 4" SS
3" V TRASH 011
30
LOADING DOCK
29
STORAGE 006
23
LOADING DOCK
29
6
GI-1
3" V DN
3" V
3" V
REFERENCED NOTES:
6. INSTALL NEW GREASE INTERCEPTOR. COORDINATE EXACT LOCATION WITH
DESIGN TEAM. INSTALL 2 LAYERS OF INSULATION AROUND THE GREASE
INTERCEPTOR.
#
01/06/2020 1/8" = 1'-0"SHEET:DATE:SCALE:
TITLE:
P101R2
PLUMBING NEW WORK PLAN
5 SULLIVAN BROTHER CONVENTION CENTER KITCHEN REMODEL
1/8" = 1'-0"1 UNDERFLOOR PLUMBING PLAN
1/8" = 1'-0"2 ABOVE FLOOR PLUMBING PLAN