HomeMy WebLinkAboutEXECUTION AND CLOSEOUT REQUIREMENTS _Rev_0Five Sullivan Brothers CC Kitchen Plmb Improvements 01 70 00 City of Waterloo EXECUTION AND CLOSEOUT REQUIREMENTS INVISION #16021 1 of 4 SECTION 01 70 00 EXECUTION AND CLOSEOUT REQUIREMENTS PART 1 GENERAL 1.01 SECTION INCLUDES A. Examination, preparation, and general installation procedures. B. Pre-installation meetings. C. Cutting and patching. D. Cleaning and protection. E. Closeout procedures, including Contractor's Correction Punch List, except payment procedures. 1.02 RELATED REQUIREMENTS A. Section 01 10 00 - Summary: Limitations on working in existing building; continued occupancy; work sequence; identification of salvaged and relocated materials. B. Section 01 30 00 - Administrative Requirements: Submittals procedures, Electronic document submittal service. C. Section 01 40 00 - Quality Requirements: Testing and inspection procedures. D. Section 01 50 00 - Temporary Facilities and Controls: Temporary interior partitions. E. Section 01 78 00 - Closeout Submittals: Project record documents, operation and maintenance data, warranties . F. Section 02 41 00 - Demolition: Demolition of whole structures and parts thereof; site utility demolition. 1.03 REFERENCE STANDARDS A. NFPA 241 - Standard for Safeguarding Construction, Alteration, and Demolition Operations; 2013. 1.04 SUBMITTALS A. See Section 01 30 00 - Administrative Requirements, for submittal procedures. B. Project Record Documents: Accurately record actual locations of capped and active utilities. 1.05 COORDINATION A. See Section 01 10 00 for occupancy-related requirements. B. Coordinate scheduling, submittals, and work of the various sections of the Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later. C. Notify affected utility companies and comply with their requirements. D. Verify that utility requirements and characteristics of new operating equipment are compatible with building utilities. Coordinate work of various sections having interdependent responsibilities for installing, connecting to, and placing in service, such equipment. E. Coordinate space requirements, supports, and installation of mechanical and electrical work that are indicated diagrammatically on drawings. Follow routing indicated for pipes, ducts, and conduit, as closely as practicable; place runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs. F. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements. G. Coordinate completion and clean-up of work of separate sections. H. After Owner occupancy of premises, coordinate access to site for correction of defective work and work not in accordance with Contract Documents, to minimize disruption of Owner's activities. PART 2 PRODUCTS 2.01 PATCHING MATERIALS A. New Materials: As specified in product sections; match existing products and work for patching and extending work. B. Type and Quality of Existing Products: Determine by inspecting and testing products where necessary, referring to existing work as a standard. C. Product Substitution: For any proposed change in materials, submit request for substitution described in Section 01 60 00 - Product Requirements. Five Sullivan Brothers CC Kitchen Plmb Improvements 01 70 00 City of Waterloo EXECUTION AND CLOSEOUT REQUIREMENTS INVISION #16021 2 of 4 PART 3 EXECUTION 3.01 EXAMINATION A. Verify that existing site conditions and substrate surfaces are acceptable for subsequent work. Start of work means acceptance of existing conditions. B. Verify that existing substrate is capable of structural support or attachment of new work being applied or attached. C. Examine and verify specific conditions described in individual specification sections. D. Take field measurements before confirming product orders or beginning fabrication, to minimize waste due to over-ordering or misfabrication. E. Verify that utility services are available, of the correct characteristics, and in the correct locations. F. Prior to Cutting: Examine existing conditions prior to commencing work, including elements subject to damage or movement during cutting and patching. After uncovering existing work, assess conditions affecting performance of work. Beginning of cutting or patching means acceptance of existing conditions. 3.02 PREPARATION A. Clean substrate surfaces prior to applying next material or substance. B. Seal cracks or openings of substrate prior to applying next material or substance. C. Apply manufacturer required or recommended substrate primer, sealer, or conditioner prior to applying any new material or substance in contact or bond. 3.03 PREINSTALLATION MEETINGS A. When required in individual specification sections, convene a preinstallation meeting at the site prior to commencing work of the section. B. Require attendance of parties directly affecting, or affected by, work of the specific section. C. Notify Design Professional five (5) days in advance of meeting date. D. Prepare agenda and preside at meeting: 1. Review conditions of examination, preparation and installation procedures. 2. Review coordination with related work. E. Record minutes and distribute copies within two days after meeting to participants, with two copies to Design Professional, Owner, participants, and those affected by decisions made. 3.04 LAYING OUT THE WORK A. Verify locations of survey control points prior to starting work. B. Promptly notify Design Professional of any discrepancies discovered. C. Contractor shall locate and protect survey control and reference points. D. Utilize recognized engineering survey practices. E. Establish elevations, lines and levels. Locate and lay out by instrumentation and similar appropriate means: F. Periodically verify layouts by same means. G. Maintain a complete and accurate log of control and survey work as it progresses. 3.05 GENERAL INSTALLATION REQUIREMENTS A. In addition to compliance with regulatory requirements, conduct construction operations in compliance with NFPA 241, including applicable recommendations in Appendix A. B. Install products as specified in individual sections, in accordance with manufacturer's instructions and recommendations, and so as to avoid waste due to necessity for replacement. C. Make vertical elements plumb and horizontal elements level, unless otherwise indicated. D. Install equipment and fittings plumb and level, neatly aligned with adjacent vertical and horizontal lines, unless otherwise indicated. E. Make consistent texture on surfaces, with seamless transitions, unless otherwise indicated. F. Make neat transitions between different surfaces, maintaining texture and appearance. 3.06 CUTTING AND PATCHING A. Whenever possible, execute the work by methods that avoid cutting or patching. B. Perform whatever cutting and patching is necessary to: Five Sullivan Brothers CC Kitchen Plmb Improvements 01 70 00 City of Waterloo EXECUTION AND CLOSEOUT REQUIREMENTS INVISION #16021 3 of 4 1. Complete the work. 2. Fit products together to integrate with other work. 3. Provide openings for penetration of mechanical, electrical, and other services. 4. Match work that has been cut to adjacent work. 5. Repair areas adjacent to cuts to required condition. 6. Repair new work damaged by subsequent work. 7. Remove samples of installed work for testing when requested. 8. Remove and replace defective and non-complying work. C. Execute work by methods that avoid damage to other work and that will provide appropriate surfaces to receive patching and finishing. In existing work, minimize damage and restore to original condition. D. Employ skilled and experienced installer to perform cutting for weather exposed and moisture resistant elements, and sight exposed surfaces. E. Cut rigid materials using masonry saw or core drill. Pneumatic tools not allowed without prior approval. F. Restore work with new products in accordance with requirements of Contract Documents. G. Fit work tightly to pipes, sleeves, ducts, conduit, and other penetrations through surfaces. H. Patching: 1. Finish patched surfaces to match finish that existed prior to patching. On continuous surfaces, refinish to nearest intersection or natural break. For an assembly, refinish entire unit. 2. Match color, texture, and appearance. 3. Repair patched surfaces that are damaged, lifted, discolored, or showing other imperfections due to patching work. If defects are due to condition of substrate, repair substrate prior to repairing finish. 3.07 PROGRESS CLEANING A. Maintain areas free of waste materials, debris, and rubbish. Maintain site in a clean and orderly condition. B. Remove debris and rubbish from pipe chases, plenums, attics, crawl spaces, and other closed or remote spaces, prior to enclosing the space. C. Collect and remove waste materials, debris, and trash/rubbish from site weekly and dispose off-site; do not burn or bury. 3.08 PROTECTION OF EXISTING AND INSTALLED WORK A. Protect installed work from damage by construction operations. B. Provide special protection where specified in individual specification sections. C. Provide temporary and removable protection for installed products. Control activity in immediate work area to prevent damage. D. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings. E. Protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects, by protecting with durable sheet materials. F. Protect work from spilled liquids. If work is exposed to spilled liquids, immediately remove protective coverings, dry out work, and replace protective coverings. G. Remove protective coverings when no longer needed; reuse or recycle coverings if possible. 3.09 FINAL CLEANING A. Execute final cleaning prior to Substantial Completion. 1. Clean areas to be occupied by Owner prior to final completion before Owner occupancy. B. Use cleaning materials that are nonhazardous. C. Clean interior and exterior glass, surfaces exposed to view; remove temporary labels, stains and foreign substances, polish transparent and glossy surfaces, vacuum carpeted and soft surfaces. D. Remove all labels that are not permanent. Do not paint or otherwise cover fire test labels or nameplates on mechanical and electrical equipment. E. Clean equipment and fixtures to a sanitary condition with cleaning materials appropriate to the surface and material being cleaned. F. Replace filters of operating equipment. G. Remove waste, surplus materials, trash/rubbish, and construction facilities from the site; dispose of in legal manner; do not burn or bury. Five Sullivan Brothers CC Kitchen Plmb Improvements 01 70 00 City of Waterloo EXECUTION AND CLOSEOUT REQUIREMENTS INVISION #16021 4 of 4 H. Clean Owner-occupied areas of work. 3.10 CLOSEOUT PROCEDURES A. Make submittals that are required by governing or other authorities. 1. Provide copies to Design Professional and Owner. B. Accompany Contractor and/or Owner on preliminary inspection to determine items to be listed for completion or correction in the Contractor's Correction Punch List for Contractor's Notice of Substantial Completion. C. Notify Design Professional when work is considered ready for Design Professional's Substantial Completion inspection. D. Submit written certification containing Contractor's Correction Punch List, that Contract Documents have been reviewed, work has been inspected, and that work is complete in accordance with Contract Documents and ready for Design Professional's Substantial Completion inspection. E. Conduct Substantial Completion inspection and create Final Correction Punch List containing Design Professional's and Contractor's comprehensive list of items identified to be completed or corrected and submit to Design Professional. F. Correct items of work listed in Final Correction Punch List and comply with requirements for access to Owner-occupied areas. G. Notify Design Professional when work is considered finally complete and ready for Design Professional's Substantial Completion final inspection. H. Complete items of work determined by Design Professional listed in executed Certificate of Substantial Completion. 3.11 MAINTENANCE A. Maintenance Period: As indicated in specification sections or, if not indicated, not less than one year from the Date of Substantial Completion or the length of the specified warranty, whichever is longer. B. Examine system components at a frequency consistent with reliable operation. Clean, adjust, and lubricate as required. C. Include systematic examination, adjustment, and lubrication of components. Repair or replace parts whenever required. Use parts produced by the manufacturer of the original component. END OF SECTION