HomeMy WebLinkAboutSUMMARY_Rev_0Five Sullivan Brothers CC Kitchen Plmb Improvements 01 10 00
City of Waterloo SUMMARY
INVISION #16021 1 of 2
SECTION 01 10 00
SUMMARY
PART 1 GENERAL
1.01 PROJECT
A. Project Name: 16021 Five Sullivan Brothers Kitchen Improvements
B. Owner's Name: City of Waterloo.
C. Design Professional's Name: INVISION.
D. The Project consists of the construction of the removal of areas of concrete flooring in the Kitchen and
Warewashing areas of the Basement Level of the convention center. Existing sewer and domestic water
systems in that area will be removed and replaced.
1.02 CONTRACT DESCRIPTION
A. Contract Type: A single prime contract based on a Stipulated Price as described in Document 00 72 00 -
General Conditions.
B. Final Completion: January 15th, 2020.
1.03 DESCRIPTION OF ALTERATIONS WORK
A. Scope of demolition and removal work is indicated on drawings.
B. Contractor shall remove and deliver the following to Owner prior to start of work:
1. Existing Dock Leveler and Controler Equipment.
1.04 OWNER OCCUPANCY
A. Owner intends to continue to occupy adjacent portions of the existing building during the entire
construction period.
B. Owner intends to occupy the Project upon Substantial Completion.
C. Cooperate with Owner to minimize conflict and to facilitate Owner's operations.
D. Schedule the Work to accommodate Owner occupancy.
1.05 CONTRACTOR USE OF SITE AND PREMISES
A. Construction Operations: Limited to areas noted on Drawings.
1. Locate and conduct construction activities in ways that will limit disturbance to site.
B. Arrange use of site and premises to allow:
1. Owner occupancy.
2. Work by Others.
3. Work by Owner.
4. Use of site and premises by the public.
C. Provide access to and from site as required by law and by Owner:
1. Emergency Building Exits During Construction: Keep all exits required by code open during
construction period; provide temporary exit signs if exit routes are temporarily altered.
2. Do not obstruct roadways, sidewalks, or other public ways without permit.
D. Time Restrictions: None. Coordinate with the Owner; normal working hours.
E. Utility Outages and Shutdown:
1. Do not disrupt or shut down life safety systems, including but not limited to fire sprinklers and fire
alarm system, without 7 days notice to Owner and authorities having jurisdiction.
2. Prevent accidental disruption of utility services to other facilities.
F. This is a tobacco free project as required by the State of Iowa Law. Use of tobacco is strictly prohibited.
General Contractor shall coordinate enforcement efforts.
G. Clothing worn by workers shall be professional or plain in nature. Any worker wearing clothing
considered to be inappropriate by the Owner or Architect will be asked to change clothing or be removed
from site.
1.06 WORK SEQUENCE
A. Coordinate work of the various Sections of the Specifications to assure efficient and orderly sequence of
installation of construction elements, with provisions for accommodating items installed later.
B. Verify that characteristics of elements of interrelated operating equipment are compatible; coordinate
work of various Sections having interdependent responsibilities for installing, connecting to, and placing
in service, such equipment.
Five Sullivan Brothers CC Kitchen Plmb Improvements 01 10 00
City of Waterloo SUMMARY
INVISION #16021 2 of 2
C. Coordinate space requirements and installation of mechanical and electrical work which are indicated
diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduits, as closely as
practicable; make runs parallel with lines of building. Utilize spaces efficiently to maximize accessibility for
other installations, for maintenance, and for repairs.
D. Execute cutting and patching to integrate elements of Work, uncover ill-timed, defective, and
non-conforming Work, provide openings for penetrations of existing surfaces, and provide samples for
testing if required. Seal penetrations through floors, walls, and roof.
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
END OF SECTION