HomeMy WebLinkAboutPLUMBING SCHEDULE OF VALUES_Rev_0Five Sullivan Brothers CC Kitchen Plmb Improvements 22 00 80City of Waterloo PLUMBING SCHEDULE OF VALUES
INVISION #16021 1 of 1
SECTION 22 00 80
PLUMBING SCHEDULE OF VALUES
PART 1 GENERAL
1.01 FORM COMPLETION
A. The successful mechanical contractor shall complete this form in its entirety within 30 days ofreceipt of the signed contract from the general contractor, and submit directly to MODUS.
B. This information is confidential and will not be disclosed to any individual outside of MODUS. Data collected will be used in evaluating pay applications.
1.02 OVERALL CONTRACT
Basic Plumbing Bid $Add or deduct accepted alternates, negotiated changes, or
other modifications to the contract
$
Total Plumbing Bid $
1.03 SCHEDULE OF VALUES
Domestic Plumbing Insulation - Material $
Domestic Plumbing Piping - Material $Domestic Plumbing Specialties - Material $Plumbing Equipment - Material $
Plumbing Fixtures - Material $Plumbing Installation - Labor $
Plumbing Insulation - Material and Labor $Total Plumbing Bid (Sum of Schedule of Values) $
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
NOT USED
END OF SECTION