U.S.HIGHWAY 63 IMPROVEMENTS
U.S.HIGHWAY 63—WESTFIELD AVENUE CONNECTION
WATERLOO,IOWA
SUPPLEMENTAL AGREEMENT NO.2
WHEREAS,a Professional Services Agreement was entered into by the City of Waterloo,Iowa("City"),and Earth
Tech, Inc. ("Consultant"), of Waterloo, Iowa, dated April 3, 2006, for the alternative evaluation, traffic analysis,
environmental documentation,preliminary design,final design and construction review for improvements on U.S.
Highway 63 between the U.S. 218 Interchange and Donald Street in Waterloo,Iowa; and
WHEREAS,Preliminary Engineering(NHSX-63-6(69)--3H-07)was defined and authorized in said agreement dated
April 3,2006; and
WHEREAS, the City and Consultant entered into Supplemental Agreement No. 1 dated July 27, 2007, for
engineering services during the construction phase of the U.S.Highway 63—Westfield Avenue Connection Project;
and
WHEREAS,the Estimated Actual Costs for Task 15—Management of Contaminated Subsurface Soil provided by
Weston Solutions, Inc., needs to be increased due to delay in construction progress related to inclement weather
conditions and management/disposal for excess spoil.
NOW THERI;,FORE, it is mutually agreed to amend the original Professional Services Agreement as follows:
I. SCOPE OF SERVICES
Services to be provided under this supplemental agreement shall be consistent with those provided under
Supplemental Agreement No. 1 dated July 27, 2007.
II. COMPENSATION
The Consultant shall be reimbursed for the actual costs incurred in accordance with Article 3 of the original
Agreement with the exception that all parties agree that Weston Solutions will exceed their Total Estimated
Costs prior to the approval of this Supplemental Agreement No.2 to allow construction activities to continue
at the construction site. Weston's Total Estimated Costs shall be increased by Fifty-Three Thousand Five
Hundred Dollars ($53,500.00) which is further defined in Attachment B. Weston's assumptions and
clarifications for this budget estimate are noted in Attachment C.
The Estimated Actual Costs,Fixed Fee,Contingency and Maximum Amount Payable for this supplemental
agreement as stated below and as shown in Attachment A, replace those previously provided in
Supplemental Agreement No. 1.
.
•
Estimated Actual Costs $194,000.00
Fixed Fee 11,000.00
Contingency 9,500.00
Maximum Amount Payable $214,500.00
III. In all other aspects,the obligations of the City and Consultant shall remain as specified in the Professional
Services Agreement dated April 3,2006, and subsequent amendments.
IN WITNESS WHEREOF, the parties hereto have executed this Supplemental Agreement No. 2 as of the dates
shown below:
EARTH TECH,
By Date November 13,2007
Joe A.Becker
Vice President
CITY OF WATERLOO,IOWA
By Date �—/ 3 - 0 7
T y . urley
ayor
IOWA DEPARTMENT OF TRANSPORTATION
ACCEPTED FOR AUTHORIZATION
y / Date
J es C. emberger,P.E.
Local Systems Engineer
District 2-
L:\work\ADMIN\AGREE\SUPPLE\SA2Hwy63.doc
-2-
Attachment A
U.S. Highway 63 -Westfield Avenue Connection
City of Waterloo, Iowa
Construction Related Services
Cost Analysis
I. Direct Labor Cost (Earth Tech)
Category Hours Rate/Hour Amount
Senior Professional 0 $71.00 $0.00
Project Professional 130 $45.25 $5,882.50
Staff Professional 30 $33.00 $990.00
CADD Operator I 40 $18.00 $720.00
Senior Technician 640 $27.00 $17,280.00
Technician 270 $20.00 $5,400.00
Project Support 60 $22.25 $1,335.00 $31,607.50
1170
II. Payroll Burden and Overhead Provisional Costs 160.00% $50,572.00
Ill. Direct Project Expenses
Category Units Rate/Unit Amount
Mileage 3500 0.485 1,697.50
Per Diem 0 30.00 0.00
Lodging 0 50.00 0.00
Copier 1000 0.06 60.00
Blueprinting 60 0.50 30.00
GPS 10 25.00 250.00
Geodimeter 40 12.50 500.00
Testing 1,000.00
Miscellaneous, Other 300.00 $3,837.50
IV. Earth Tech Estimated Actual Costs $86,017.00
Rounded $86,000.00
V. Subcontract Expense
Weston Solutions SA No. 1 $54,500.00
Weston Solutions SA No. 2 (See Attachment B) $53,500.00 $108,000.00
VI. Estimated Actual Costs $194,000.00
VII. Fixed Fee $11,000.00
VIII. Contingency
Earth Tech $4,000.00
Weston Solutions $5,500.00 $9,500.00
IX. Maximum Amount Payable $214,500.00
ATTACHMENT C
Weston Solutions, Inc. — Change Order Request
City of Waterloo/Iowa Department of Transportation
Iowa DOT Project HDP-8155(698)--71-07
Assumptions and Clarifications for the Budget Estimate
• Performance or other bonds are not required;
• The estimate assumes that field oversight activities are required for five
consecutive weeks at 50 hours per week (Monday through Friday). This will
extend Weston's scope of services through November of 2007. Construction
oversight costs are subject to change based on weather, contractor schedule
and other field conditions.
• Construction oversight costs include travel time and expenses for WESTON
personnel to mobilize/demobilize between the work site and our office in
Vernon Hills, Illinois. The estimate assumes that one WESTON employee
will demobilize from and remobilize back to the work site on a bi-weekly
basis(i.e. every other weekend).
• It is assumed that Modified Level D personal protection equipment is
adequate for conducting field oversight activities (Refer to SSHASP). Higher
levels of personal protection will trigger additional costs.