FAA AIP Project No. 3-19-0094-059 CO-1 Project No – 60789734
1
CHANGE ORDER NO. 1
Owner: Waterloo Regional Airport, City of Waterloo, Iowa Date: September 2, 2026
Project: Runway 18-36 Rehabilitation within Runway 12-30 Safety Area
Owner's Contract No. FAA AIP Project No. 3-19-0094-059
Contractor: Aspro Inc.
Date of Contract Start: March 16, 2026
You are directed to make the following changes in the Contract Documents. Description:
Item
No. Description Unit Unit Price Contract
Quantity Change Percent
Change
Revised
Quantity Amount
5 COLD PROFILE MILLING SYD $ 9.20 28,700.0 250.0 +1% 28,950.0 $ 2,300.00
7 ASPHALT SURFACE COURSE TONS $ 135.00 3,380.0 60.0 +2% 3,440.0 $ 8,100.00
10 PAVEMENT MARKING SF $ 3.00 27,000.0 660.0 +1% 27,250.0 $ 1,980.00
12 GROOVING SYD $ 2.85 25,600.0 250.0 +3% 26,260.0 $ 712.50
Total Change Order $ 13,092.50
Reason for Change Order:
5, 7, 10, & 12 – Quantities adjusted to include a crack repair across Runway 12-30 near Taxiway A intersection.
The asphalt has heaved at this location creating a bump across the runway.