HomeMy WebLinkAboutEARTHTECH AGREEMENT - RESOLUTION 2007-972 Ear4-0
thTech 501 Sycamore Street p319.232.6531
Suite 222 F319.232.0271
A t14CG International Ltd.Company Waterloo, IA 50703 www.earthtech.com
PROFESSIONAL SERVICES AGREEMENT
PROJECT NAME: FY 2008 Big Rock Road Bridges Replacement with Box Culverts
City Contract No. 739
City of Waterloo,Iowa
This Agreement is by and between
Client
City of Waterloo
715 Mulberry Street
Waterloo, Iowa 50703
and,
Earth Tech
501 Sycamore, Suite 222
P.O. Box 1497
Waterloo, Iowa 50704-1497
Who agree as follows:
Client hereby engages Earth Tech to perform the services described in Part I("Services")and Earth Tech agrees to
perform the Services for the compensation set forth in Part III. Earth Tech shall be authorized to commence the
Services upon execution of this Agreement. Client and Earth Tech agree that this signature page, together with
Parts I-IV and attachments referred to therein,constitute the entire Agreement between them relating to the Project
("Agreement").
APPROVE OR CLIENT APPROVED FOR EARTH TECH
By �� By vZ
Printed Name k..e g it sG h m i-f f Printed N e Joe Becker
Title rhay o c Pra e2 , Title Vice President
Date //-/ 9-6-7 Date November 14,2007
PART I
EARTH TECH'S RESPONSIBILITIES
A. PROJECT DESCRIPTION
The existing timber bridges on Big Rock Road over No Name Creek were constructed in the early 1900s and
are in need of replacement. The easterly bridge(City Structure No.32)has been restricted to a 3-ton posting
based on recommendations from the 2007 bi-annual bridge reviews. The westerly bridge(City Structure No.
31)is also in need of replacement and is beginning to have pile capacity reduction due to deterioration of the
timber piles. The east structure crosses a main branch of No Name Creek(Stream 13 in Waterloo Flood
Insurance Study),and the west structure serves as an overflow structure for No Name Creek.
The City of Waterloo desires to replace these structures in the spring of 2008 due to the above conditions.
Replacement structures for the 20-foot timber bridges are planned to be twin reinforced concrete box culverts
(RCB)for both locations. Preliminary sizes for these culverts are a twin 10'x4'for the west structure and a
twin 10'x6'RCB for the east structure.
This project includes the replacement of both No Name Creek structures along with associated channel work.
B. SCOPE OF SERVICES
Services to be provided under this Agreement include design survey,soil borings,geotechnical engineering
report,preliminary design,final design,permit applications,right-of-way activities and construction-related
services. The scope of services is further defined by the following tasks:
Preliminary Design
Task 1 -Data Collection. This task includes collecting and reviewing existing city utility maps,review of
the existing plan information,and associated as-built drawings.
Task 2-Field Survey and Base Mapping. This task includes field survey and development of base mapping
which will be utilized during the preliminary and final design phases of the project. Survey tasks anticipated
include setting baseline and bench marks in the field,location of features within the project limits,collection
of break lines and spot elevation for a digital terrain model, location of soil borings and selected property
corners. In addition,utilities will be located in the field and appropriate measures taken.
Task 3 -Wetland Boundary Delineation and Project Impact Review. This task includes a field review to
identify and delineate wetland boundaries using currently approved methodology. The wetland delineation
and project impacts will be summarized in a report to be submitted to the Corps of Engineers for the project
404 Permit. This task will be completed by Natural Resources Consulting,Inc., as a subconsultant. This
task does not include developing a wetland mitigation plan, as the need and scope of the plan needs to be
determined first. The wetland mitigation plan may be added as a supplemental agreement, if necessary,
depending on the field wetland delineation.
-2-
Task 4-Geotechnical Engineering. This task includes the field soil borings,lab testing,engineering analysis
and fmal report to provide the fmal soils engineering and recommendations for the culvert design.This task
will be completed by Terracon Consultants,Inc., as a subconsultant.
Task 5 - Conceptual Design of Reinforced Box Culverts. This task includes developing the conceptual
design for both culverts. It is anticipated that alternatives will review both cast-in-place and pre-cast options.
Also included in this task is the hydraulic sizing and required modeling for the proposed box culverts.
The culverts will require Iowa Department of Natural Resources Flood Plain Permits due to the drainage area
of No Name Creek. The existing road grade is not planned to be altered.
Task 6—Structure Inventory and Appraisal Priority Calculation. This task includes calculating the city
bridge priority point system using the Iowa Department of Transportation worksheet. This worksheet is
used to assist the Iowa DOT in determining funding for bridge structures.
Tasks 7-13 - Preliminary Design of Box Culverts. These tasks include the preparation and submittal of
preliminary review drawings for the project. Included are the following plan sheets:
Task 7 Title Sheet
Task 8 Typical Sections
Task 9 General Notes and Estimate Reference Information
Task 10 Tabulations, Quantities and Cost Estimate
Task 11 Big Rock Road Plan and Profile(Replacement Surfacing for Construction of Culvert)
Task 12 Site Plan
Task 13 Miscellaneous Detail Sheets
Task 14 - Type, Size and Location Drawing. This task includes preparation of a type, size and location
drawing for both structures. The fmal hydraulic analyses of the structures will also be completed under this
task.
Final Design
Task 15-Final Design of Culverts. This task includes the fmal design of both Big Rock Road culverts. The
structures are anticipated to be twin barrel box culverts with headwalls.
Tasks 16-22 - Preparation of Final Design Plans. Following Client approval of the preliminary design
drawings, work will proceed on the fmal construction drawings for the project. The preliminary design
drawings will be updated as necessary, and final construction details will be added. Included are the
following plan sheets:
Task 16 Update Title Sheet
Task 17 Update Typical Sections
Task 18 Final General Notes and Estimate Reference Information
Task 19 Update Tabulations, Quantities and Cost Estimate
Task 20 Final Big Rock Road Plan and Profile
Task 21 Situation Plan
Task 22 Structural Details
-3-
Task 23-Quality Control Review. This task includes the quality control review of the plans by senior staff
throughout the course of the project including,but not limited to,the significant milestones in the project
schedule.
Task 24-Final Revisions. This task includes revisions of the final design plans after Client review.
Task 25 - Construction Cost Estimate. This task includes preparation of the estimate of probable
construction cost for the project.
Task 26 - Project Specifications. This task includes preparation of the specifications for the project.
Document will include technical specifications, special provisions,general specifications, etc.
Task 27 - Printing and Submittals. This task includes printing and submittal of intermediate and final
construction plans and other documents.
Meetings and Coordination
Task 28-Project Meetings and Field Review. A total of two(2)project meetings are anticipated to be held
at Waterloo city offices or at the project site. A field review is anticipated with the City prior to completion
of the final construction plans.
Task 29 - Bidding Activities. This task includes providing information and answering questions from
contractors prior to the letting. In addition, this task will include preparing a tabulation of bids after the
contract letting.
Task 30-Project Administration. This task includes project administration and coordination throughout the
project development. The task includes intra-office meetings which will be attended by the project team,as
well as general day-to-day administrative tasks and typing of intra-office memoranda.
Task 31 - Permit Applications and Agency Coordination. Following Client approval of the preliminary
design drawings,permit applications will be submitted to the Iowa Department of Natural Resources(IDNR)
for a flood plain permit application and to the U.S. Army Corps of Engineers for a 404 Permit. This task
also includes coordination with the IDNR and the U.S.Army Corps of Engineers.
Right-of-Way Activities
Tasks 32 - 34. These tasks include preparation of right-of-way documents for construction of the culvert
improvements. These tasks consist of preparing plats and descriptions for the acquisition of permanent and
temporary construction easements. The number of parcels under this task is estimated to be approximately
four(4). These tasks also include staking of approximate new right-of-way lines in the field to assist the
right-of-way acquisition agents in visualizing the proposed lines.
Task 32 Right-of-Way Documents—Permanent Easements
Task 33 Right-of-Way Documents—Temporary Construction Easements
Task 34 Right-of-Way Staking
-4-
Construction-Related Services
The scope of construction-related services will be determined at the time the services are needed and defined
under a future amendment to this Agreement. Construction-related services include construction staking,on-
site field review,materials testing,contract administration during construction and setting new right-of-way
property pins.
PART II
CLIENT'S RESPONSIBILITIES
Client, at its expense, shall do the following in a timely manner so as not to delay the Services.
A. INFORMATION/REPORTS
Furnish Earth Tech necessary information/reports, all of which Earth Tech may rely upon without
independent verification in performing the Services.
B. REPRESENTATIVE
Designate a representative for the Project who shall have the authority to transmit instructions, receive
information, interpret and define Client's policies and make decisions with respect to the Services.
C. DECISIONS
Provide all criteria and full information as to Client requirements for the Project,obtain(with Earth Tech's
assistance,if applicable)necessary approvals and permits,attend Project-related meetings,provide interim
reviews on an agreed-upon schedule,make decisions on Project alternatives,and generally participate in the
Project to the extent necessary to allow Earth Tech to perform the Services.
PART III
COMPENSATION,BILLING,AND PAYMENT
Client shall pay Earth Tech for the Services in accordance with the following:
A. COMPENSATION
Compensation for the Services shall be on an hourly basis in accordance with the hourly fees and other direct
expenses in effect at the time the services are performed. The compensation for the services shall not exceed
Thirty-Eight Thousand Dollars($38,000.00)without authorization from the Owner.
-5-
1
B. BILLING AND PAYMENT
Earth Tech may bill the Client monthly for services completed at the time of billing,with net payment due in
30 days. Unless Client provides Earth Tech with a written statement of any objections to the bill within
15 days of receipt, Client shall be deemed to accept the bill as submitted.
L:\work\ADMIN\AGREE\PROF\W atBigRockBridgesReplace.doc
-6
PART IV
STANDARD TERMS AND CONDITIONS
i. STANDARD OF CARE. Services shall be performed in accordance with the and agrees to defend,indemnify,and save Earth Tech harmless from any claim or liability
standard of professional practice ordinarily exercised by the applicable profession at the for injury or loss arising from Earth Tech's discovery of unanticipated hazardous materials
time and within the locality where the Services are performed. Professional services are or suspected hazardous materials.
not subject to,and Earth Tech can not provide,any warranty or guarantee,express or
implied,including warranties or guarantees contained in any uniform commercial code. 11. INDEMNITY.Earth Tech agrees to defend,indemnify and save harmless the
Any such warranties or guarantees contained in any purchase orders,requisitions or Client,its agencies,agents,employees and assignees from all claims and liabilities due
notices to proceed issued by Client are specifically objected to. to design error, omission or negligent act of Earth Tech, its members, agents,
stockholders or employees in connection with performance of this Agreement.
2. CHANGE OF SCOPE. The scope of Services set forth in this Agreement is based
on facts known at the time of execution of this Agreement,including,if applicable, 12. ACCESS. Client shall provide Earth Tech safe access to any premises necessary
information supplied by Client. For some projects involving conceptual or process for Earth Tech to provide the Services.
development services,scope may not be fully definable during initial phases. As the
Project progresses,facts discovered may indicate that scope must be redefined. 13. REUSE OF PROJECT DELIVERABLES. Reuse of any documents or other
deliverables,including electronic media,pertaining to the Project by Client for any
3. SAFETY. Earth Tech has established and maintains corporate programs and purpose other than that for which such documents or deliverables were originally
procedures for the safety of its employees. Unless specifically included as a service to prepared,or alteration of such documents or deliverables without written verification or
be provided under this Agreement,Earth Tech specifically disclaims any authority or adaptation by Earth Tech for the specific purpose intended,shall be at the Client's risk.
responsibility for general job site safety and safety of persons other than Earth Tech Further,all title blocks and the engineer's seal,if applicable,shall be removed if and
employees. when Client provides deliverables in electronic media to another entity. Client agrees
that relevant analyses,findings and reports provided in electronic media shall also be
4. DELAYS. If events beyond the control of Client or Earth Tech,including,but not provided in"hard copy"and that the hard copy shall govern in the case of a discrepancy
limited to,fire,flood,explosion,riot,strike,war,process shutdown,act of God or the between the two versions,and shall be held as the official set of drawings,as signed and
public enemy,and act or regulation of any government agency,result in delay to any sealed. Client shall be afforded a period of 30 days in which to check the hard copy
schedule established in this Agreement,such schedule shall be amended to the extent against the electronic media. In the event that any error or inconsistency is found as a
necessary to compensate for such delay. In the event such delay exceeds 60 days,Earth result of this process, Earth Tech shall be advised and the inconsistency shall be
Tech shall be entitled to an equitable adjustment in compensation. corrected at no additional cost to Client. Following the expiration of this 30-day period,
Client shall bear all responsibility for the care,custody and control of the electronic
5. TERMINATION/SUSPENSiON. Either party may terminate this Agreement upon media. In addition,Client represents that it shall retain the necessary mechanisms to read
30 days written notice to the other party. Client shall pay Earth Tech for all Services, the electronic media,which Client acknowledges to be of only limited duration. Client
including profit relating thereto,rendered prior to termination,plus any expenses of agrees to defend,indemnify,and hold harmless Earth Tech from all claims,damages,and
termination. expenses,(including reasonable litigation costs),arising out of such reuse or alteration
by Client or others acting through Client.
In the event either party defaults in its obligations under this Agreement(including
Client's obligation to make the payments required hereunder),the non-defaulting party 14. AMENDMENT. This Agreement,upon execution by both parties hereto,can be
may,after 7 days written notice stating its intention to suspend performance under the amended only by a written instrument signed by both parties.
Agreement if cure of such default is not commenced and diligently continued,and failure
of the defaulting party to commence cure within such time limit and diligently continue, 15. ASSIGNMENT. Except for assignments(a)to entities which control,or are
suspend performance under this Agreement controlled by,the parties hereto or(b)resulting from operation of law,the rights and
obligations of this Agreement cannot be assigned by either party without written
6. OPINIONS OF CONSTRUCTION COST. Any opinion of construction costs permission of the other party. This Agreement shall be binding upon and inure to the
prepared by Earth Tech is supplied for the general guidance of the Client only. Since benefit of any permitted assigns.
Earth Tech has no control over competitive bidding or market conditions,Earth Tech
cannot guarantee the accuracy of such opinions as compared to contract bids or actual 16. STATUTES OF LIMITATION. To the fullest extent permitted by law,parties
costs to Client agree that,except for claims for indemnification,the time period for bringing claims
under this Agreement shall expire one year after Project completion.
7. RELATIONSHIP WITH CONTRACTORS. Earth Tech shall serve as Client's
professional representative for the Services,and may make recommendations to Client 17. DISPUTE RESOLUTION. Parties shall attempt to settle disputes arising under
concerning actions relating to Client's contractors,but Earth Tech specifically disclaims this agreement by discussion between the parties senior representatives of management
any authority to direct or supervise the means,methods, techniques, sequences or If any dispute can not be resolved in this manner,within a reasonable length of time,
procedures of construction selected by Client's contractors. parties agree to attempt non-binding mediation or any other method of alternative dispute
resolution prior to filing any legal proceedings. In the event any actions are brought to
8. CONSTRUCTION REVIEW. For projects involving construction, Client enforce this Agreement,the prevailing party shall be entitled to collect its litigation costs
acknowledges that under generally accepted professional practice,interpretations of from the other party.
construction documents in the field are normally required,and that performance of
construction-related services by the design professional for the project permits errors or 18. NO WAIVER. No waiver by either party of any default by the other party in the
omissions to be identified and corrected at comparatively low cost. Client agrees to hold performance of any particular section of this Agreement shall invalidate any other section
Earth Tech harmless from any claims resulting from performance of construction-related of this Agreement or operate as a waiver of any future default,whether like or different
services by persons other than Earth Tech. in character.
9. INSURANCE. Earth Tech will maintain insurance coverage for Professional, 19. NO THIRD-PARTY BENEFICIARY. Nothing contained in this Agreement,nor
Comprehensive General,Automobile,Worker's Compensation,and Employer's Liability the performance of the parties hereunder,is intended to benefit,nor shall inure to the
in amounts in accordance with legal,and Earth Tech's business requirements. Certificates benefit of,any third party,including Client's contractors,if any.
evidencing such coverage will be provided to Client upon request. For projects involving
construction,Client agrees to require its construction contractor,if any,to include Earth 20. SEVERABILITY. The various terms,provisions and covenants herein contained
Tech as an additional insured on its policies relating to the Project. Earth Tech's shall be deemed to be separate and severable,and the invalidity or unenforceability of
coverages referenced above shall,in such case,be excess over contractor's primary any of them shall not affect or impair the validity or enforceability of the remainder.
coverage.
21. AUTHORITY. The persons signing this Agreement warrant that they have the
10. HAZARDOUS MATERIAL. Hazardous materials may exist at a site where there authority to sign as,or on behalf of,the party for whom they are signing.
is no reason to believe they could or should be present. Earth Tech and Client agree that
the discovery of unanticipated hazardous materials constitutes a changed condition L:\WORK\ADMIN\AGREE\SAVE\WaterlooTC.doc July 2001
mandating a renegotiation of the scope of work. Earth Tech agrees to notify Client as -
soon as practically possible should unanticipated hazardous materials or suspected
hazardous materials be encountered. Client acknowledges and agrees that it retains title
to all hazardous material existing on the site and shall report to the appropriate federal,
state or local public agencies,as required,any conditions at the site that may present a
potential danger to the public health,safety or the environment. Client shall execute any
manifests or forms in connection with transportation,storage and disposal of hazardous
materials resulting from the site or work on the site or shall authorize Earth Tech to
execute such documents as Client's agent. Client waives any claim against Earth Tech
1