Council Communication
City Council Meeting: March 22, 2010
Prepared: March 16, 2010
Dept. Head Signature: Eric Thorson, PE., City Engineer
# of Attachments:
SUBJECT: CHANGE ORDER NO. 1 -$6,497.85 DECREASE
F.Y. 2009 BIG ROCK ROAD BRIDGES REPLACEMENT WITH
BOX CULVERTS
HELMKAMP CONSTRUCTION OF IOWA
CONTRACT 739
Submitted by: Dennis Gentz, P.E.,Assistant City Engineer
Recommended City Council Action:
Staff has reviewed this Change Order and recommends that the Mayor be authorized to sign it on
behalf of the City.
Please execute all three (3) copies and return two (2) to our office for further processing.
Summary Statement
Transmitted herewith is Change Order No. 1 in the amount of($6,497.85). This is the
accumulated amount of adjustments from original to final quantities that were determined
necessary during the construction of the project, which results in a decrease to the total project
cost.
Expenditure Required N/A
Source of Funds G.O. Bonds
Policy Issue N/A
Alternative None
Background Information: