HomeMy WebLinkAboutAECOM Change Order No. 3 - FY15 Phase II CIP Pipe Lining-10/24/2016AXOM
October 14, 2016
Mr. Steven Hoambrecker
Waste Management Services
City of Waterloo
3505 Easton Avenue
Waterloo, Iowa 50702
AECOM 319-232-6531 tel
501 Sycamore Street 319-232-0271 fax
Suite 222
Waterloo, Iowa 50703
www.aecom.com
Subject: Sanitary Sewer Improvements FY 2015 Phase II CIP Pipe Lining Project
Change Order No. 3
City of Waterloo, Iowa
City Contract No. 876
AECOM #60339160
Dear Mr. Hoambrecker:
Attached is Change Order No. 3 for the Sanitary Sewer Improvements FY 2015 Phase II CIP Pipe Lining
project. The following is included in this Change Order:
1. Deductions for CIPP segment removals due to damaged pipe. These segments could not be lined.
2. Addition for pipe cleaning associated with the damage pipe deductions. The contractor must clean the
pipe segments prior to completing the Pre -Televising work. The contractor spent time cleaning the pipe
before the damage was discovered. Cleaning is incidental to the CIPP lining and the contractor would
not be paid for this work. The contractor requested to be paid for this work that is no longer covered
under the CIPP bid items.
3. Reconciliation of the Bid Quantities and Change Order No. 1 and 2 Quantities to match quantities
installed.
AECOM recommends that the City of Waterloo authorize Change Order No. 3 for the deduction amount of -
$30,388.65 decreasing the total project cost to $1,734,590.95.
Yours sincerely,
Christopher G. Oelkers, P. E.
Attachment: Change Order No. 3 Authorization form
Change Order No. 3 Tabulation
Pipe Cleaning Tabulation
c: Ms. Suzy Schares — City of Waterloo (w/attachment)
P 003391601600_Construction_SupporV665 Change ONera= No. 3@0161014 CIP Phase II - CO No 3 Ll Aocx
Owner.
CHANGE ORDER NO. 3
Date: Octobe
Project: Sanitary Sewer Improvements FY 2015 Phase U CIP Pipe Lining Project
Owner's ContmctNo.: 876 Contractor: Municipal Pipe Tool Company, LLC
Date of Contract Start: February 2, 2015
You are directed to make the following. changes in the Contract Documents. Description: See attached Change Order No. 3 spread sheet.
• 10 segments are removed from the project for the following reasons
o Existing Pipe is too damaged to install the CIPP.
o Time constraints due to the onset of winter.
• Removed Segment Cleaning
o Recommend that the contract be paid on a time basis for cleaning of the existing pipes that were removed from the project due to existing pipe damage.
• Quantity Reconciliation
o Pipe quantity changes are due to differences in the planned quantity and the actual installed quantity.
o Manhole quantity changes are due to over estimation and change of installed product.
• Change Order No. I manhole quantity correction reconciles quantities added to the contract in Change Order No, 1.
Reason for Change Order: Segment removals and final quantity reconciliation.
CONTRACT PRICE
Original:
Previous C.O.s (ADD/DEDUCT):
This C.O. (ADB/DEDUCT):
Contract Price With All Approved
Change Orders:
$ 1,734,590.95 REVISED:
Original Completion Date:
Revised Completion Date:
June24,2016 June30 2016
September 25, 2015 October 9, 2015
June24 2016 June 30,2016
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays,
and acceleration costs. Other than the dollar amount and time allowance listed above, them shallbeno furthertime or dollarcompensation as a result ofthis Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
APPROVE ,�(/
By. 4Z`1/(
Owner (Authorized Signature) Date:
ACCEPTED:
By: I , ',
L &A ZJ" coniQ (l/ (� 10/14/16
Contractor (Authorized Signature) Date:
AECOM
60339160 3
Project No. Change Order No.
P:Wm391M600_Comx cfion_Suppon1665CM ge OrdmXMNo.3120161014PHHCm'ChengeONer No-3dm
CONTRACT TIMES (Calendar Days)
To Substantial To Final
Completion Completion
$ 1,471,353.90
Original:
September 25, 2015 October 9, 2015
$ 293,625.70
Previous C.O.s(ADD/DEDUCT):
3 Months 3 Months
$ (30,388.65)
This C.O. (ADD/DEDUCT):
6 Months 6 Months
$ 1,734,590.95 REVISED:
Original Completion Date:
Revised Completion Date:
June24,2016 June30 2016
September 25, 2015 October 9, 2015
June24 2016 June 30,2016
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays,
and acceleration costs. Other than the dollar amount and time allowance listed above, them shallbeno furthertime or dollarcompensation as a result ofthis Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO
APPROVE ,�(/
By. 4Z`1/(
Owner (Authorized Signature) Date:
ACCEPTED:
By: I , ',
L &A ZJ" coniQ (l/ (� 10/14/16
Contractor (Authorized Signature) Date:
AECOM
60339160 3
Project No. Change Order No.
P:Wm391M600_Comx cfion_Suppon1665CM ge OrdmXMNo.3120161014PHHCm'ChengeONer No-3dm
<�,,,.�
��.�,.,w
Pipe Cleaning for Segments Removed from the Project
San Sewer Improvements- M5 CIPP lining Project
City of Waterloo
City Contract No. 876
AECOM Pryed No:00339160
Wadnesday,Augusl31,2016
DWG CO SA
MH
MH
Roue
U"
1W 12'
Bid CostV$2�7055'
otai
Hours
Cost TOTAL Desvi Son
13
14
16
18
12-07
1015
12-N
10-18
Moods Steel
Carlotta He Road
233
200
$ 19.35500.55
S 19.35$0]0.00
5.2
4.2
2]5.00 1,430.00 Collapsed 9,,o 6&ft south of MH 12-M
5275.00 $1,155.00 Servke Pmtnrsions
29
2
15 05-0508 0505.07
Coatltman Ddve
160
$ 19.3596.0)
3.33
$2]5.00 f 915.75 CollapsedlOHset Pie 96R
35
2
17 2011&0120L&02
Whiston RDA.e WSTAIIey
330
$ 19.3585.50
6.66
$2]5.00 S1,88650 Collapsed Mpe 12-R West of MH 200002
4
2
11
1007
10.08
Sooner Street
59
$28.50986.50)
4.4
$2]5.00 $1,210.0 Cdlapsetl We20 and 83fl from MH 1008
4
2
11
1008
10.09
Sunnerstreet
200
$ 28.5070D.0)
42
$2]5.00 $1,155.00 CNlapsetl❑na Y4 and122-R1mm MH16O9
13
3
16
12-01
12-08
Aacill Street
16
$ 19.35309.60)
QuarMyenWsdas2301fin C01. Bid Leng0ris249-If
26
3
19
1018
10.15
Pmspecl Boulevard
300
$ 21.50A5o.00)
6.24
$2]5.00 $1,T16.00 ffimo U547-11460 Colla ed Pipe l4RSotlh of MH 10.15
26
3
19
1016
10.19
Presped Boulevard
398
$ 21.50557.00)
8.28
$2]5.00 $2,tn.GD Colla sed Pipe 21&R SOuth of MH 10.18
32
3
19 301&03 301&02
Winn Strad
301
E 28.506]6.50)
6.26
$275.00 $1,72150 NOMH ontheend. CenTllne
29
3
16
12-21
12-20
Valley Drive,
280
$ 19.35031.00)
5.41
$95.00 51.487]5 Colla setl at63'mM 207
3p
3
18
10.11
1011-01
Carriage Po8 Road
24]
E 19.35179.45)
11.81
$275.00 f 3,247.]5 Transition tram e" to 6"
15
3
16
10.01
1001-03
Hickory -tee,
144
$ 19.35786.40)
3
$2]5.Us f 825.OD Service Promwons
TOTALDEDUCT $(62,018.60) CLEANINGTOTAL $19,027.25
GHANGEORDERN0.1 5 (8,378.55) $ 2,685.00
CHANGEORDERN0.2 $(17,148.00) $ 51167.25
CNANGEORDERNO.. $(36,491.06) $11,275.00