HomeMy WebLinkAboutModern Builders - CO#3(2) Hangar 4 Wall Repairs-11/21/2016CHANGE ORDER NO. 2 Owner Waterloo Regional Airport, City of Waterloo, Iowa Date November 29 2016 Project Hangar No. 4 Wall Repairs Owner's Contract No. State Contract No. 17448 Contractor Modern Builders, Inc. Date of Contract Start September 19, 2016 You are directed to make the following changes in the Contract Documents. Description: ITEM NO. DESCRIPTION UNIT UNIT PRICE QUANTITY AMOUNT 102 Replace Electrical Box LS $ 250.00 1 $ 250.00 103 Paint Interior Doors LS $ 725.00 1 $ 725.00 TOTALS $ 975.00 Reason for Change Order: Item 102 — During wall cleaning activities at Hangar #4, an electrical junction box on the interior wall was found to be corroded extensively and in need of replacement. This item will replace the electrical junction. Item 103 — This item adds painting to the interior doors on the south wall of the hangar bay. Both sides of these doors will be painted. The south wall was identified in the contract documents to be cleaned and painted but the doors were not part of the original contract. Hangar #4 Wall Repairs CO -2 1 Project No — 60482850 CONTRACT PRICE Original: $ 72,168.00 Previous C.O.s (ADD): $ 4,500.00 This C.O. (ADD): $ 975.00 Contract Price with all approved Change Orders: $ 77,643.00 CONTRACT TIMES (Calendar Date) Substantial Final completion completion Original: _ 11/18/2016 Previous C.O.s (ADD): 0 This C.O. (ADD): 0 REVISED: 11/18/2016 It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order. THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO. RECOMMENDED: Engineer (Authorized nature) APPROVED: By: Owner (Authorized Signature) ACCEPTED: By: Co a— !�• actor (Authorized Signature) November 29, 2016 Date Date Co vki1c C Awls„ as s. 11)241%, Date Hangar #4 Wall Repairs CO -2 Project No — 60482850 2 Nancy Higby From: Keith Kaspari Sent: Monday, December 12, 2016 1:17 PM To: Nancy Higby Subject: FW: Final Inspection / Punch List Importance: High Nancy: FYI, a little clarification from David Hughes from AECOM. So, technically, the resolution can still be correct, as it was Change Order No: 3 (overall) for Modern, but for this project at Hangar 4, Change Order No: 2. Thanks, K From: Hughes, David (Des Moines) [mailto:David.Hughes@aecom.com] Sent: Monday, December 12, 2016 1:09 PM To: Keith Kaspari Subject: FW: Final Inspection / Punch List Importance: High Keith, 3'd Change Order for Modern — Change Order No. 2 for Hangar #4. David B. Hughes, P.E. Department Manager 515-323-7919 From: Hughes, David (Des Moines) Sent: Tuesday, November 15, 2016 3:00 PM To: Keith Kaspari Subject: FW: Final Inspection / Punch List Importance: High Keith, The 2016 CSVI Grant was set to fund the Bag Claim Doors and Hangar 4 Walls. Bottom line is that there is about $41,000 remaining in the grant. Since local procedures allow you to do work for less than $1,000, which is a requirement of the grant, why don't we include the $960.00 in this project for Overhead Doors? The grant breakdown is as follows: Item Funds Required Funds Remaining Grant $101,196.00 1 Hangar No. 4 (Bid) $0.00 $101,196.00 Terminal Doors (Bid) $34,677.66 $ 66,518.34 A/E Services $16,900.00 $ 49,618.34 Terminal Doors - Bag Makeup Interlock (CO 1) $ 2,600.00 $ 47,018.34 Hangar No. 4 Wall (CO 1) $ 4,500.00 $ 42,518.34 Hangar No. 4 Interior Doors (CO 2) $ 725.00 $ 41,793.34 Hangar No. 4 Electrical Box (CO 2) $ 250.00 $ 41,543.34 David B. Hughes, P.E. Department Manager 515-323-7919 From: Kevin McConnell [mailto:kevin.mcconnell@moderniowa.com] Sent: Tuesday, November 15, 2016 1:19 PM To: Keith Kaspari; Hughes, David (Des Moines) Subject: Re: Final Inspection / Punch List Importance: High Keith, David, See my response below. Kevin From: Keith Kaspari <Keith.Kaspari@WATERLOO-IA.ORG> Date: Tuesday, November 15, 2016 at 2:00 PM To: Kevin McConnell <kevin.mcconnell@moderniowa.com>, "Hughes, David (Des Moines)" <David. H ughes@a eco m.co m> Subject: RE: Final Inspection / Punch List Kevin and David: See my responses, below. Keith From: Kevin McConnell [mailto:kevin.mcconnell@moderniowa.com] Sent: Tuesday, November 15, 2016 10:38 AM To: Keith Kaspari; Hughes, David (Des Moines) Subject: Re: Final Inspection / Punch List Good Morning Keith, David, I now have several issues that we're chasing that are causing us concern for Fridays walk through. 1.