HomeMy WebLinkAboutModern Builders - CO#3(2) Hangar 4 Wall Repairs-11/21/2016CHANGE ORDER NO. 2
Owner Waterloo Regional Airport, City of Waterloo, Iowa Date November 29 2016
Project Hangar No. 4 Wall Repairs
Owner's Contract No. State Contract No. 17448 Contractor Modern Builders, Inc.
Date of Contract Start September 19, 2016
You are directed to make the following changes in the Contract Documents. Description:
ITEM
NO.
DESCRIPTION
UNIT
UNIT
PRICE
QUANTITY
AMOUNT
102
Replace Electrical Box
LS
$ 250.00
1
$ 250.00
103
Paint Interior Doors
LS
$ 725.00
1
$ 725.00
TOTALS
$ 975.00
Reason for Change Order:
Item 102 — During wall cleaning activities at Hangar #4, an electrical junction box on the interior wall was found to
be corroded extensively and in need of replacement. This item will replace the electrical junction.
Item 103 — This item adds painting to the interior doors on the south wall of the hangar bay. Both sides of these
doors will be painted. The south wall was identified in the contract documents to be cleaned and painted but the
doors were not part of the original contract.
Hangar #4 Wall Repairs
CO -2
1
Project No — 60482850
CONTRACT PRICE
Original: $ 72,168.00
Previous C.O.s (ADD): $ 4,500.00
This C.O. (ADD): $ 975.00
Contract Price with all
approved Change Orders: $ 77,643.00
CONTRACT TIMES (Calendar Date)
Substantial Final
completion completion
Original: _ 11/18/2016
Previous C.O.s (ADD): 0
This C.O. (ADD): 0
REVISED: 11/18/2016
It is agreed by the Contractor that this Change Order includes any and all costs associated with or resulting from the
change(s) ordered herein, including all impact, delays, and acceleration costs. Other than the dollar amount and time
allowance listed above, there shall be no further time or dollar compensation as a result of this Change Order.
THIS DOCUMENT SHALL BECOME AN AMENDMENT TO THE CONTRACT AND ALL
STIPULATIONS AND COVENANTS OF THE CONTRACT SHALL APPLY HERETO.
RECOMMENDED:
Engineer (Authorized nature)
APPROVED:
By:
Owner (Authorized Signature)
ACCEPTED:
By:
Co
a— !�•
actor (Authorized Signature)
November 29, 2016
Date
Date Co vki1c C Awls„ as s. 11)241%,
Date
Hangar #4 Wall Repairs CO -2 Project No — 60482850
2
Nancy Higby
From: Keith Kaspari
Sent: Monday, December 12, 2016 1:17 PM
To: Nancy Higby
Subject: FW: Final Inspection / Punch List
Importance: High
Nancy:
FYI, a little clarification from David Hughes from AECOM.
So, technically, the resolution can still be correct, as it was Change Order No: 3 (overall) for Modern, but for this project
at Hangar 4, Change Order No: 2.
Thanks, K
From: Hughes, David (Des Moines) [mailto:David.Hughes@aecom.com]
Sent: Monday, December 12, 2016 1:09 PM
To: Keith Kaspari
Subject: FW: Final Inspection / Punch List
Importance: High
Keith,
3'd Change Order for Modern — Change Order No. 2 for Hangar #4.
David B. Hughes, P.E.
Department Manager
515-323-7919
From: Hughes, David (Des Moines)
Sent: Tuesday, November 15, 2016 3:00 PM
To: Keith Kaspari
Subject: FW: Final Inspection / Punch List
Importance: High
Keith,
The 2016 CSVI Grant was set to fund the Bag Claim Doors and Hangar 4 Walls. Bottom line is that there is about $41,000
remaining in the grant.
Since local procedures allow you to do work for less than $1,000, which is a requirement of the grant, why don't we
include the $960.00 in this project for Overhead Doors?
The grant breakdown is as follows:
Item
Funds Required
Funds Remaining
Grant
$101,196.00
1
Hangar No. 4 (Bid)
$0.00
$101,196.00
Terminal Doors (Bid)
$34,677.66
$ 66,518.34
A/E Services
$16,900.00
$ 49,618.34
Terminal Doors - Bag Makeup Interlock (CO 1)
$ 2,600.00
$ 47,018.34
Hangar No. 4 Wall (CO 1)
$ 4,500.00
$ 42,518.34
Hangar No. 4 Interior Doors (CO 2)
$ 725.00
$ 41,793.34
Hangar No. 4 Electrical Box (CO 2)
$ 250.00
$ 41,543.34
David B. Hughes, P.E.
Department Manager
515-323-7919
From: Kevin McConnell [mailto:kevin.mcconnell@moderniowa.com]
Sent: Tuesday, November 15, 2016 1:19 PM
To: Keith Kaspari; Hughes, David (Des Moines)
Subject: Re: Final Inspection / Punch List
Importance: High
Keith, David,
See my response below.
Kevin
From: Keith Kaspari <Keith.Kaspari@WATERLOO-IA.ORG>
Date: Tuesday, November 15, 2016 at 2:00 PM
To: Kevin McConnell <kevin.mcconnell@moderniowa.com>, "Hughes, David (Des Moines)"
<David. H ughes@a eco m.co m>
Subject: RE: Final Inspection / Punch List
Kevin and David:
See my responses, below.
Keith
From: Kevin McConnell [mailto:kevin.mcconnell@moderniowa.com]
Sent: Tuesday, November 15, 2016 10:38 AM
To: Keith Kaspari; Hughes, David (Des Moines)
Subject: Re: Final Inspection / Punch List
Good Morning Keith, David,
I now have several issues that we're chasing that are causing us concern for Fridays walk through.
1.