HomeMy WebLinkAboutIDNR - FY17 Wagner Rd Construction Permit Cont No 899-11/7/2016IOWA DEPARTMENT OF NATURAL RESOURCES
Wastewater Disposal System Construction Permit
Application Fee Form
CASHIER'S USE ONLY
0945-542-NPDE-CP-0570
32-3202
Owner
Owner Name: City of Waterloo
Address: 715 Mulberry Street
City, State, Zip: Waterloo, IA 50703
Project Identification: F.Y. 2017 Wagner Road Sanitary Sewer & Grading - Contract No. 899
® $100 Fee enclosed
Please sign and return this form with a check or money order payable to "Iowa Department of Natural Resources".
Place it and the check or money order on top of other Construction Permit Application documents.
Effective beginning July 1, 2006, Applications for Construction Permits for wastewater disposal systems required by
Iowa Code 4556.173 and rules in Iowa Administrative Code 567 IAC 64, must be accompanied by the fee required by
Iowa Code 4558.197 and Iowa Administrative Code 567 IAC 64.16(3)"c".
The fee is $100 for each application, regardless of project size and project type including sanitary sewers, pump
stations, treatment units or a combination thereof. The fee shall be submitted with the certified engineering documents
necessary to apply for a construction permit (plans, specifications and related application schedules A, F, and G as well
as the appropriate schedules indentified on page 2 of Schedule A). The construction permitting process is initiated as
planning for construction begins. Planning coordination and submittal of preliminary engineering reports or facility
plans precedes submittal of technical documents necessary to constitute a construction permit application. The
application fee is not necessary when submitting a planning document but must accompany construction permit
application documents. A fee should accompany each permit application received on or after July 1, 2006.
Failure to submit a fee with the application may delay the processing of a construction permit. If you have any questions
regarding the application fee, please contact Donna Gomm at 515-281-8502 or Donna.Gomm@dnr.iowa.gov
Signature of Owner or Representative:
Printed Name:
, 0, t
su,v7 s. c 6r : A.J<z
Telephone or email contact: 3 (q -- Ze(/- cti12-
Mail to:
Iowa Department of Natural Resources
Wastewater Engineering Section
502 East 9th Street
Des Moines, IA 50319-0034
06/2011 cmz DNR Form 542-1245
Exhibit 11A
Iowa Department of Natural Resources
Wastewater Section
Construction Permit Application
SCHEDULE A, Construction Permit Application
APPLICANT
Owner: City of Waterloo, Iowa
Address: 715 Mulberry Street
Representative: Dennis Gentz, P.E.
Phone Number: 319-291-4312
Email: dennis.gentz@waterloo-ia.org
ENGINEER
Firm: IDE Engineering, PLC
Address: 3731 Pheasant Lane, Suite 201
Project Officer: Jim D. Ellis, P.E.
Phone Number: 319-464-7913
Email: jdeeng@Ipctel.net
Project Identification: F.Y. 2017 Wagner Road Sanitary Sewer Extension and Grading, Contract No. 899
Estimated Start Date*: Dec. 2016 Estimated Completion Date: June 2017
PLEASE RESPOND TO ALL QUESTIONS
1. Has an engineering report, facilities plan or other information previously been submitted for this project?
If Yes: Project Identity: Date Submitted:
2. Does the project and construction permit application, as submitted, follow the recommendations, design loadings,
construction schedule, permit limits, and conclusions of the approved engineering report or facilities plan?
If No: Provide the design basis and technical information justifying all changes.
3. Are there three complete sets of plans and specifications accompanying this application?
For a minor gravity sewer extension within the meaning of 4556.183.3 Code of Iowa and Design Standard 11.1, two complete
sets will be adequate for expeditious approval. For more complex projects, three sets of plans and specifications may be
requested.
4. Are approved standard specifications a part of this application?
If Yes: Approved Standard Specifications of
(municipality or firm): SUDAS Standards Date Approved: 2016 Edition
5. Does each set of plans and specifications or engineering report accompanying this application contain a
Yes No
IZ
® ❑
"professional engineering seal" executed in conformance with 5428.16, Code of Iowa?
If No: Processing will be delayed pending receipt of applicable design schedules and certified plans, specifications or
engineering report.
6. Is this a joint wastewater and water supply project?
® ❑
El El
If Yes: A construction permit application for the water supply project should be submitted separately to the Water Supply
Section. A Water Supply permit fee may be required.
7. Is the applicant to provide treatment of effluent resulting from this construction? ® 0
If No: A Sewage Treatment Agreement executed by the authority providing treatment must accompany this form.
8. Is a new or amended operation permit necessary to use the facilities described in this application?
If Yes: A new or amended permit to operate may be requested prior to the receipt of a construction permit.
9. Is any waterline located within 10 feet; or any private or public well, lake, or public recreation area located within
400 feet of the proposed construction?
If Yes: Identify and locate the facility(ies) relative to the proposed construction.
10. Will construction inspection be conducted by a licensed engineer employed by the applicant?
If No: Name of Engineering Firm Conducting Inspection:
11. Will this project utilize CWSRF loan funds?
0 El
• El
• ❑
CERTIFICATION
O El
APPLICANT
I certify that I am the authorized representative of the owner
and state that the project identified above is approved by the
owner.
Signature I ,&t,(..0 . , ♦ i_.. Date 12-(2-1116'
*Estimated Construction Start Date: Complete applications must
construction in accordance with Rules 567 IAC 60.4 and 64.2
ENGINEER
I certify that all aspects of the design included in this application
conform to applicable standards contained in Chapter 567 IAC
64, or that an explanation and justification for any proposed
variations from such standards is attached. I am familiar with the
information contained in this application and, to the best of my
knowledge, suchlinfor tion is c lete and accurate.
Signature yam,{ C Date a 0 //c.
be submitted east 120 days in advance of the date fo star ing
Please complete the Schedule Checklist on the following page of this form.
04/2016 cmc
DNR Form 542-3129; 28A
DOCUMENT CHECKLIST
Identify all categories included in this project. Also, identify schedules attached to this application.
Schedule Title Attached Included in Project ' Submittal Date
B
C
ID
E
F
G
H1
H2
H3
J
K1
K2
K3
L
M
N
0
P
R1
R2 (A&B)
R3
S
Collection System
Lateral Sewer Extension
Trunk & Interceptor Sewer
Wastewater Pump Station
Treatment Project Site Selection
Treatment Project Design Data
Schematic Flow Diagram
Treatment Process Loading and Removal Efficiency
Mechanical Plant Reliability
Screening, Grit Removal and Flow Measurement
Septic Tank System
Controlled Discharge Pond
Aerated Pond
Anaerobic Lagoon
Setting Tanks
Fixed Film Reactor -Stationary Media
Rotating Biological Contactor
Aeration Tanks or Basins
Gas Chlorination
Sludge Digestion and Holding
Sludge Dewatering and Disposal
Low Rate Land Application of Sludge
Land Application of Sewage Sludge (To be developed)
Land Application of Wastewater (To be developed)
Sewage Treatment Agreement
❑❑❑❑❑❑❑❑❑❑❑❑❑❑❑
Dec. 2016
Dec. 2016
Identify any categories included in this project which are not provided in the above list of schedules.
04/2016 cmc
DNR Form 542-3129; 28A
Iowa Department of Natural Resources
Wastewater Section
Construction Permit Application
SCHEDULE B, Collection System
Date Prepared
12/13/16
Date Revised
Project Identity
F.Y. 2017 Wagner Road Sanitary Sewer Extension & Grading - Contract No. 899
DNR USE ONLY
Project No.
Permit No.
1. Identify proposed construction which is subject to flooding and explain what is proposed to prevent water from entering the
system. If no portion is subject to flooding, state none.
Segment
None
None
Flooding Protection
*2. Indicate hydraulic capacity of: 1) the nearest downstream main or interceptor; 2) the nearest downstream lift station; and 3) all
downstream segments where flow restriction may occur. Indicate the source and accuracy of numerical data.
Location
Design Capacity, MGD
Peak Hourly Dry weather Flow MGD (actual)
Peak Hourly Wet weather Flow MGD (actual)
Segment Segment Segment
12 -inch
None
None
1.03
60+
48,000
0.07
0.17
*3. Identify treatment facility, the design loadings and present raw waste loadings. Indicate source and accuracy of numerical data.
Facility Name and Number Waterloo Wastewater Pollution Control Plant
Facility Loading
Design
Average Wet Weather (actual)
Peak Hourly Wet Weather (actual)
MGD
#BODS/da
34.8
88,000
24.5
31,500
60+
48,000
Provide projected design loading increase, which will be added to this facility as a result of this project.
Design Loading Initial Design Year (2017)
Residential Service Area N/A Acres N/A Acres
Population N/A Persons N/A Persons
Flow (100 GPCD) N/A GPD N/A GPD
BOD5(0.17/#/d/cap) N/A It/day N/A #/day
Industrial Service Area 13.95 Acres 13.95 Acres
Rated Flow 69,750 GPD 69,750 GPD
BODS 118.6 #/day 118.6 #/day
Other N/A N/A Acres N/A Acres
Rated Flow N/A GPD N/A GPD
BOD5 N/A #/day N/A #/day
Total BOD5 118.6 #/day 118.6 #/day
Total Flow 69,750 GPD 69,750 GPD
Peak Hourly Flow 173,678 GPD 173,678 GPD
*Include a written explanation of items 2 and 3 if the sewer system and/or treatment facility are overloaded.
11/2015 cmc
ONR Form 542-3095; 28B
Iowa Department of Natural Resources
Wastewater Section
Construction Permit Application
SCHEDULE C, Lateral Sewer Extension
DNR USE ONLY
Project No.
Permit No.
Date Prepared
12/13/16
Date Revised
Project Identity
F.Y. 2017 Wagner Road Sanitary Sewer Extension & Grading - Contract No. 899
1. Design Basis
Residential Service Area
Population
Flow (100 GPCD)
BODS (0.17/#/d/cap)
Industrial Service Area
Rated How
BODS
Other N/A
Initial
N/A
Design Year (2017)
Acres N/A Acres
N/A Persons N/A Persons
N/A GPD N/A GPD
N/A #/day N/A #/day
13.95 Acres 13.95 Acres
69,750 GPD 69,750 GPD
118.6 #/day 118.6 #/day
N/A Acres N/A Acres
Rated Flow N/A GPD N/A GPD
BODS N/A #/day N/A #/day
Total 1300s 118.6 #/day 118.6 #/day
Total Flow 69,750 GPD 69,750 GPD
Peak Hourly Flow 173,678 GPD 173,678 GPD
2. Pipe Diameter 8 Inch 10 Inch 12 lnch
Material PVC Truss N/A N/A
Joint Elastomeric N/A N/A
Minimum Slope 0.40 % N/A % N/A
Maximum Manhole Space 275 ft. N/A ft. N/A ft.
Total Sewer Length 810 ft. N/A ft. N/A ft.
Maximum Cover 11.6 ft. N/A ft. N/A ft.
Minimum Cover 7.6 ft. N/A ft. N/A ft.
3. Construction specifications (indicate ASTM Number or other standard included in the specifications). A brief description is
required in each part.
A. Bedding class ASTM Class II, 02321-75 except as modified by ASTM D2680-01
B. Pipe laying
C. Compaction
D. Manhole
ASTM Class II, 02321-75 except as modified by ASTM D2680-01
95% Standard Proctor Density
ASTM C4782 - 48 -inch dia.
E. Specified maximum infiltration/exfiltration rate 200 GPDPMPI
F. Infiltration/exfiltration test procedures v -notch weir, televising, or air test
G. Alignment & grade test procedures
(1) During construction Stake & batterboard yes Laser yes
(2) After construction Lamping yes Other televising
H. Deflection test procedures N/A
4. Are detailed manhole drawings included: ® Yes 0 No Typical frame and cover assembly SUDAS SW-306&SW-601TypeA
Are manhole covers nonvented: ® Yes ❑ No Manhole diameter 48 -inch in.
Manhole opening diameter 24 -inch In Material concrete
5. Minimum sewer & water main separation: Horizontal 10 ft. Vertical 18
Are specifications included no
in.
6. Stream, road, or railroad crossing protection N/A
Are specifications included N/A
11/2015 cmc
DNR Form 542-3096; 28C
i CHECK I'JO.
LTV J V 1
atosesta 1,1W
( 11/07/2016 2017-00001063 -" WASTEWATER DISP SYS CONST PERMIT -2017 WAGNER
RD SAN SEW CONT 899
PAY
TO
THE'
ORDER
Or
2
amt —" ado :4P 'E
OF WATERLOO, IOWA
715 MULBERRY ST.
W4TERLOO, IA 50703
319-291-4323
r
L
1
100.00
POS' Reorder* 120.5993
Lam. aEn^v T1.Bi1 1 Ei 1^ -MA Viei it W.
-.
DATE
AMOUNT
One Hundred and 00/100 Dollars
IOWA DEPARTMENT OF NATURAL RESOURCES
WASTEWATER ENGINEERING SECTION
502 EAST 9T111 STREET
DES MOINES, IA50319
$1oo.0o 249907,
VOID AFTER 120 DAYS
By Order of the City Council
Chief Financial Officer
u° 2 5190711° 0:0739004380:000004. 600 ill°
Mayor
r